Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in IE Insp Repts 50-373/79-11 & 50-374/79-08
ML19289F350
Person / Time
Site: LaSalle  Constellation icon.png
Issue date: 05/01/1979
From: Fiorelli G
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Brian Lee
COMMONWEALTH EDISON CO.
Shared Package
ML19289F351 List:
References
NUDOCS 7906070266
Download: ML19289F350 (1)


Text

Mdb i

TIGG UNITED STATES f(g* "80 I.

NUCLEAR REGULATORY COMMISSION

'

r ( [,S

[ (

REGloN lli 3'

j ss noosevrLv nono f

cLEN ELLYN, ILUNOIS 60 8 M

.....

I N

Docket No. 50-373 Docket No. 50-374 Commonwealth Edison Company ATTN:

Mr. Byron Lee, Jr.

Vice President P. O. Box 767 Chicago, IL 60690 i

Gent.emen:

Thank you for your letter dated April 18, 1979, informing us of the steps you have taken to correct the noncompliance identified in our letter dated March 15, 1979. Regarding Item 1, the CECO Director of QA stated during a phone conversation on April 25, 1979, that a reinspection program will be implemented covering all of the previously identified raceway locations which contained debris and that the cables in these locations will be inrpected for damage and appropriate corrective action will be taken where necessary.

We will examine your corrective action during a future inspection.

Your cooperation with us is appreciated.

Sincerely, G. Fiorelli, Chief Reactor Construction and Engineering Support Branch cc:

Mr. Cordell Reed, Assistant Vice-President Mr. L. J. Burke, Site Project Superintendent Mr. T. E. Quaka, QA Supervisor 2232 145

-

Mr. R. H. Holyoak, Station Superintendent cc w/ltr dtd 4/18/79:

Central Files Reproduction Unit NRC 20b PDR Local PDR NSIC TIC Mr. Dean Hansell, Office of 79060701Q Assistant Attorney General