IE Insp Repts 50-373/79-28 & 50-374/79-19 on 790710-11.No Noncompliance Noted.Major Areas Inspected:Part 21 Rept Followup of 4-inch Pipe Fittings W/Potential for Abnormally High Content of Carbon
ML19208B376
Person / Time
Site: LaSalle  
Issue date: 08/01/1979
From: Clint Jones, Williams C
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML19208B373 List:
References
50-373-79-28, 50-374-79-19, NUDOCS 7909200116
Download: ML19208B376 (3)


Text

.

U.S. NUCLEAR REGULATORY COMMISSION

'

0FFICE OF INSPECTION AND ENFORCEMENT

REGION III

Report No. 50-373/79-28; 50-374/79-19

~

Docket No. 50-373; 50-374 License No. CPPR-99; CPPR-100 Licensee: Commonwealth Edison Company P. O. Box 767 Chicago, IL 60690 Facility Name:

La Salle County Station, Units 1 and 2 Inspection At: La Salle County Station, Marseilles, Illinois Inspection Conducted: July 10-11, 1979 Ob wu Inspector:

C.

E'. Jones h-/-79

.%

)

Approved By:

. C.

I lams, Acting

/

Projects Section 2

'/ /

Inspection Summary Inspection on July 10-11, 1979 (Report No. 50-373/79-28; 50-374/79-19)

Areas Inspected: Part 21 report followup of 4" pipe fittings identified to have the potential for containing an abnormally high content of carbon.

Activities relative to the installation of the heating, ventilating and air conditioning system and a spot check of the mill certifications for this material. The inspeciton involved 12 inspector-hours on site by one NRC inspector.

Results:

In the two areas inspected, no items of noncompliance or deviations were identified.

.

,t oln

.

't 900 2 00lllo f,

,

.

DETAILS

.

Persons Contacted Principal Licensee Personnel

.

  • L. J. Burke, Site Project Superintendent
  • G. E. Groth, Engineer, Station Construction
  • G. F. Marcus, Director Quality Assurance
  • B. J. McAndrew, Engineer, Station Construction
  • L. J. Tapella, Quality Assurance Engineer
  • L. H. Lauderback, Quality Assurance Engineer J. D. Diebeck, Engineer, Station Construction Contractor Personnel
  • R. L. Wilson, Supervisor, Quality Control, Zack Company C. Baumgardner, Zack Company
  • Denotes personnel attending exit interview.

Licensee Action on Previously Identified Items (Closed) Part 21 report concerning the potential for certain 4-inch steel elbows to exceed the specified carbon content. The Benjamin F. Shaw Company informed the licensee by letter dated April 17, 1979, that certain fittings with heat code W6719 might have abnormally high carbon content.

The material supplier arranged for a representative from U. S. Steel to examine the fittings at the site and reject those fittings with high carbon content.

The examination indicated a total of 26 fittings on site from heat code W6719. Tests indicated one of these 4" fittings, control No. HG2020, Fab. Mark No. 2HG02A-4"-10, exceeded the specified carbon content by a small amount.

This elbow was removed from the line and replaced with a fitting that met material specifications.

.

Program or Functional Areas Inspected Heating, Ventilating and Air Conditioning 1.

Control Room HVAC System The inspector observed this system as well as others that are designated as safety related. The system is being insulated with difficulty since the insulation fails to adhere to the duct. The licensee stated that new procedures and different fire resistant materials were being tested.

~

~

o l a,

~

i

.

2.

Certified Mill Test Reports (HTR)

,

Approximately 20 MTRs were reviewed and checked for traceability.

The retrievability and traceability covered material in all systems and was considered acceptable.

3.

Material Flow

~

The Supervisor of Quality Control for the Zack Company summarized

-

the flow of material from its receipt in the shop through final erection. The summary covered the essential points of material receipt and inspection in the shop, shop fabrication, shipment to the field, field receipt inspection, storage in the field and then final erection.

The initial field inspection is for shipping damage, piece accountability and documentation.

No items of noncompliance were identified.

Exit Interview The inspector met with the site represectatives (denoted under Persons Contacted) at the conclusion of the inspection. The inspector summarized the purpose and findings of the inspection. The licensee acknowledged the findings reported herein.

.