IR 05000373/2025001

From kanterella
Jump to navigation Jump to search
County Station Integrated Inspection Report 05000373/2025001 and 05000374/2025001
ML25128A115
Person / Time
Site: LaSalle  Constellation icon.png
Issue date: 05/08/2025
From: Robert Ruiz
NRC/RGN-III/DORS/RPB1
To: Rhoades D
Constellation Energy Generation
References
IR 2025001
Download: ML25128A115 (1)


Text

SUBJECT:

LASALLE COUNTY STATION - INTEGRATED INSPECTION REPORT 05000373/2025001 AND 05000374/2025001

Dear David Rhoades:

On March 31, 2025, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at LaSalle County Station. On April 9, 2025, the NRC inspectors discussed the results of this inspection with John VanFleet, Site Vice President, and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Robert Ruiz, Chief Reactor Projects Branch 1 Division of Operating Reactor Safety Docket Nos. 05000373 and 05000374 License Nos. NPF-11 and NPF-18

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000373 and 05000374

License Numbers:

NPF-11 and NPF-18

Report Numbers:

05000373/2025001 and 05000374/2025001

Enterprise Identifier:

I-2025-001-0065

Licensee:

Constellation Nuclear

Facility:

LaSalle County Station

Location:

Marseilles, IL

Inspection Dates:

January 01, 2025, to March 31, 2025

Inspectors:

J. Benjamin, Senior Resident Inspector

M. Domke, Senior Reactor Inspector

R. Farmer, Health Physicist

T. Hooker, Health Physicist

J. Kutlesa, Senior Emergency Preparedness Inspector

T. McGowan, Emergency Preparedness Inspector

J. Meszaros, Resident Inspector

P. Smagacz, Acting Senior Resident Inspector

R. Zuffa, Illinois Emergency Management Agency

Approved By:

Robert Ruiz, Chief

Reactor Projects Branch 1

Division of Operating Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at LaSalle County Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

Type Issue Number Title Report Section Status LER 05000373/2024-004-00 LER 2024-004-00 for LaSalle County Station,

Unit 1, Emergency Diesel Generator Auto-Start and Load due to Loss of Station Auxiliary Transformer 71153 Closed

PLANT STATUS

Unit 1 operated at rated thermal power for the entire inspection period.

Unit 2 began the inspection period at rated thermal power. On February 9, 2025, the unit coasted down to approximately 91 percent power and commenced refueling outage (RFO)

L2R20. On March 1, 2025, the unit started up and reached rated thermal power on March 4, 2025. The unit remained at rated thermal power for the remainder of the inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed activities described in IMC 2515, Appendix D, Plant Status, observed risk significant activities, and completed on-site portions of IPs. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.01 - Adverse Weather Protection

Impending Severe Weather Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated the adequacy of the overall preparations to protect risk-significant systems from impending high winds and severe thunderstorms on March 14, 2025.

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (4 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1)fuel pool cooling while protected for alternate decay heat removal during RFO L2R20 division 1 and 2 residual heat removal (RHR) maintenance on February 20, 2025 (2)train 'A' and 'B' RHR service water while protected for shutdown cooling during RFO L2R20 on February 11, 2025

(3) Unit 1A train standby liquid control system with Unit 1B train standby liquid control system inoperable due to a failed check valve on March 12, 2025
(4) Common 'B' train main control room ventilation system when 'A' train main control room ventilation train was out of service for planned maintenance on March 24, 2025

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (9 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1) Fire Zone (FZ) 312, reactor building, elevation 673'-4", Unit 2 high pressure core spray cubicle on January 8, 2025
(2) FZ 314, reactor building, elevation 673'-4", Unit 2 low pressure core spray and reactor coolant isolation cooling system cubicle on January 8, 2025
(3) FZ 2H2, reactor building, elevation 694'-6", Unit 1 high pressure core spray cubicle on January 8, 2025
(4) FZ 211, reactor building, elevation 673'-4", Unit 1 general area on January 10, 2025
(5) FZ 2F, reactor building, elevation 740'-0", Unit 1 general area and control rod drive repair room on January 10, 2025
(6) FZ FA1 (North), elevation 843'-6", Unit 2 refuel floor on February 12, 2025
(7) FZ 3D, reactor building, elevation 786'-0", Unit 2 general area on February 23, 2025
(8) FZ 3E, reactor building, elevation 761'-0", Unit 2 general area on February 23, 2025
(9) FZ 2H3, reactor building, elevation 694'-6", Unit 1 RHR heat exchanger 'B' cubicle on February 12, 2025

71111.08G - Inservice Inspection Activities (BWR)

BWR Inservice Inspection Activities Sample - Nondestructive Examination and Welding

Activities (IP Section 03.01)

The inspector evaluated boiling water reactor non-destructive testing by reviewing the following examinations from February 10, 2025 to February 21, 2025:

(1)

1. Volumetric, phased array nondestructive examination of American Society of

Mechanical Engineers (ASME) R1.11-2 category B dissimilar metal Feedwater safe end to nozzle weld 1FW-2001-20A on containment drywell elevation 796'

2. Volumetric, phased array nondestructive examination of ASME R1.11-2

category B dissimilar metal Feedwater safe end to nozzle weld 1FW-2002-20A on containment drywell elevation 796'

3. Volumetic convential ultrasonic nondestructive examination of ASME

R-A/R1.16-2 stainless steel weld IRH-2001-21A on containment drywell elevation 740'

4. Visual VT-3 examination on seismic component MS04-2876X on containment

drywell elevation 740'

5. Visual VT-1 examination on lug component MS04-2876X (IWA) on

containment drywell elevation 740'

6. Pressure boundary ASME class 1 weld review for bottom head drain

replacement work order number 05237886 task 19 specifically replacement welds 1R3, 4A, 17R1, 18R1

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)

(1) The inspectors observed and evaluated licensed operator performance in the control room during shutdown operations for RFO L2R20 on February 9, 2025.

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) The inspectors observed and evaluated simulator-based training on January 22, 2025.

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (1 Sample)

The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components (SSCs) remain capable of performing their intended function:

(1)evaluation of the Unit 1B train emergency diesel generator fuel oil leak that occurred on October 21, 2024

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (4 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:

(1)elevated risk during grid cold weather alert on January 7, 2025

(2) Unit 1 risk evaluation due to emergent work associated with the standby liquid control system during the week ending March 15, 2025 (3)elevated risk during control room ventilation 'A' train work window week of March 24, 2025 (4)elevated risk during Unit Common 'B' train emergency diesel generator 24-hour run surveillance test on March 31, 2025

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (5 Samples)

The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:

(1)operability of the reactor core isolation cooling system after mechanical backseating of the outboard steam isolation valve on January 17, 2025 (2)operability of Unit 2 division 2 RHR service water pumps given inservice test results falling in alert range and no increased testing frequency established, as documented in Action Request (AR) 4828295

(3) AR 4831047, UMCRA-1H13-P601-A501, 1B DG Engine Trouble Alarm Received Unexpectedly (4)control rod operability after scram time testing on February 26, 2025, given scram times documented in ARs 4840680, 4840783, 4840671, 4840797, 4840717,

===4840682, and 4840751 (5)operability of Unit 1A train standby liquid control due to observed chattering of 'B' check valve and reduced flow during surveillance as documented in AR 4844688 on March 12, 2025

71111.18 - Plant Modifications

Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02)

=

The inspectors evaluated the following temporary or permanent modifications:

(1) Engineering Change (EC) 640788, Diesel Fire Pump 'B' Engine Replacement, during the week ending February 8, 2025
(2) EC 625078, Remove Bonnet Vent Valves on Unit 2 Reactor Recirculation Discharge Isolation Valves, during the week ending March 14, 2025
(3) EC 631743, Shutdown Cooling Trip Bypass Keylock, during the weeks ending March 8 through March 15, 2025
(4) EC 640577, Unit 2 - Adding a Time Delay to Load Reject Circuit, during the week ending March 15, 2025

71111.20 - Refueling and Other Outage Activities

Refueling/Other Outage Sample (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated Unit 2 RFO L2R20 from February 10 through March 1, 2025.

71111.24 - Testing and Maintenance of Equipment Important to Risk

The inspectors evaluated the following testing and maintenance activities to verify system operability and/or functionality:

Post-Maintenance Testing (PMT) (IP Section 03.01) (10 Samples 1 Partial)

(1)

(Partial)

Unit Common 'B' diesel fire pump after upgrade during the week of February 3, 2025

(2) Unit 2 division 1 125 Vdc battery testing after electrical maintenance during RFO L2R20 on February 18, 2025 (3)performance of LOS-MS-R7 after safety relief valve replacement during RFO L2R20 on February 20 and 21, 2025 (4)performance of reactor vessel leakage test per LOS-NB-R2 after RFO L2R20 on February 26, 2025
(5) Unit 2 division 2 125 Vdc battery testing after electrical maintenance during RFO L2R20 on February 22, 2025
(6) Unit 2B train residual heat removal pump run after RFO L2R20 work window on February 20, 2025
(7) Unit 2C train residual heat removal pump run after RFO L2R20 work window on February 18, 2025
(8) WO 5625872, "2E12-F050A Failed LLRT [local leak rate test]," on February 24, 2025 (9)verification of core loading after refueling on February 22, 2025
(10) Unit 2A train residual heat removal pump discharge relief valve on February 23, 2025
(11) Unit 1 standby liquid control 'A' and 'B' trains pump runs after emergent work on the

'B' check valve and system rotameter replacement on March 14, 2025

Surveillance Testing (IP Section 03.01) (3 Samples)

(1) LOS-RP-SA3, Unit 2, reactor manual scram functional test, instrument channels A and B on February 9, 2025
(2) LOS-DG-201, Unit common emergency diesel generator start and load acceptance surveillance, February 14, 2025
(3) LOS-DG-R0, Unit common emergency diesel generator 24-hour surveillance test on March 31, 2025

Inservice Testing (IST) (IP Section 03.01) (1 Sample)

(1) LOS-RH-Q1 Unit 2C train residual heat removal pump attachment 2 on January 6, 2025

Containment Isolation Valve (CIV) Testing (IP Section 03.01) (1 Sample)

(1)primary containment vent and purge outlet valves on February 17, 2025

71114.02 - Alert and Notification System Testing

Inspection Review (IP Section 02.01-02.04) (1 Sample)

(1) The inspectors evaluated the following maintenance and testing of the alert and notification system:

annual siren inspection and maintenance records for the period of February 2023 - February 2025

71114.03 - Emergency Response Organization Staffing and Augmentation System

Inspection Review (IP Section 02.01-02.02) (1 Sample)

(1) The inspectors evaluated the readiness of the emergency preparedness organization.

71114.05 - Maintenance of Emergency Preparedness

Inspection Review (IP Section 02.01 - 02.11) (1 Sample)

(1) The inspectors evaluated the maintenance of the emergency preparedness program.

RADIATION SAFETY

71124.01 - Radiological Hazard Assessment and Exposure Controls

Radiological Hazard Assessment (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated how the licensee identifies the magnitude and extent of radiation levels and the concentrations and quantities of radioactive materials and how the licensee assesses radiological hazards.

Instructions to Workers (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated how the licensee instructs workers on plant-related radiological hazards and the radiation protection requirements intended to protect workers from those hazards.

Contamination and Radioactive Material Control (IP Section 03.03) (2 Samples)

The inspectors observed/evaluated the following licensee processes for monitoring and controlling contamination and radioactive material:

(1)licensee surveys of potentially contaminated workers and material leaving the radiologically controlled area (RCA) at the north service building exit (2)licensee surveys of potentially contaminated workers and material leaving the RCA at the main RCA exit

Radiological Hazards Control and Work Coverage (IP Section 03.04) (4 Samples)

The inspectors evaluated the licensee's control of radiological hazards for the following radiological work:

(1)removal of insulation from valve 2G33-F393A (2)inner pipe preparation within a glove bag on 2A RT pump (3)ultrasonic testing of 2RA001A piping elbow (4)addition of shielding on pipes connected to valve 2G33-F393A High Radiation Area and Very High Radiation Area Controls (IP Section 03.05) (3 Samples)

The inspectors evaluated licensee controls of the following high radiation areas (HRAs) and very high radiation areas (VHRAs):

(1) Unit 2 694 elevation shutdown cooling line raceway
(2) Unit 2 B/C residual heat removal suction pump room
(3) Unit 2 reactor water cleanup pump room Radiation Worker Performance and Radiation Protection Technician Proficiency (IP Section 03.06) (1 Sample)
(1) The inspectors evaluated radiation worker and radiation protection technician performance as it pertains to radiation protection requirements.

71124.04 - Occupational Dose Assessment

Special Dosimetric Situations (IP Section 03.04) (1 Sample)

The inspectors evaluated the following special dosimetric situations:

(1)use of finger rings for measurement of extremity dose for removal of insulation on valve 2G33-F393A

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:

IE01: Unplanned Scrams per 7000 Critical Hours Sample (IP Section 02.01)===

(1) Unit 1 (January 1 through December 31, 2024)
(2) Unit 2 (January 1 through December 31, 2024)

IE03: Unplanned Power Changes per 7000 Critical Hours Sample (IP Section 02.02) (2 Samples)

(1) Unit 1 (January 1 through December 31, 2024)
(2) Unit 2 (January 1 through December 31, 2024)

IE04: Unplanned Scrams with Complications (USwC) Sample (IP Section 02.03) (2 Samples)

(1) Unit 1 (January 1 through December 31, 2024)
(2) Unit 2 (January 1 through December 31, 2024)

EP01: Drill/Exercise Performance (DEP) Sample (IP Section 02.12) (1 Sample)

(1) January 2023 through December 2024 EP02: Emergency Response Organization (ERO) Drill Participation (IP Section 02.13) (1 Sample)
(1) January 2023 through December 2024 EP04: Emergency Response Facility and Equipment Readiness (ERFER) (IP Section 02.14) (1 Sample)
(1) January 2025 through February 2025

71153 - Follow Up of Events and Notices of Enforcement Discretion Event Report (IP Section 03.02)

The inspectors evaluated the following licensee event reports (LERs):

(1) LER 05000373/2024-004-00, Emergency Diesel Generator Auto-Start and Load due to Loss of Station Auxiliary Transformer (Agencywide Documents Access and Management System [ADAMS] Accession No. ML24171A003). The inspectors determined that the cause of the condition described in the LER was not reasonably within the licensee's ability to foresee and correct and therefore was not reasonably preventable. No performance deficiency nor violation of NRC requirements was identified. This LER is closed.

INSPECTION RESULTS

No findings were identified.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified that no proprietary information was retained or documented in this report.

  • On April 9, 2025, the inspectors presented the integrated inspection results to John VanFleet, Site Vice President, and other members of the licensee staff.
  • On February 14, 2025, the inspectors presented the radiation protection inspection results to John VanFleet, Site Vice President, and other members of the licensee staff.
  • On February 21, 2025, the inspectors presented the inservice inspection results to John Van Fleet, Site Vice President, and other members of the licensee staff.
  • On February 28, 2025, the inspectors presented the emergency preparedness inspection results to Deb McBreen, Operations Director, and other members of the licensee staff.

THIRD PARTY REVIEWS Inspectors reviewed Institute on Nuclear Power Operations reports that were issued during the inspection period.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

LAP-100-44

Inclement Weather Guidance

LOA-TORN-001

High Winds - Tornado

OP-AA-108-111-

1001

Severe Weather and Natural Disaster Guidelines

71111.01

Procedures

SY-AA-101-146

Severe Weather Preparation and Response

AR 4839094

NRC Question Related to FC ADHR WS Flow

2/20/2025

Corrective Action

Documents

Resulting from

Inspection

AR 4848380

NRC Follow up to Question Related to FC ADHR WS Flow

03/24/2025

M-134, Sheet 1

P & ID CSCS Equipment Cooling Water System

BH

M-134, Sheet 2

P & ID Core Standby Cooling System Equipment Cooling

Water System

AT

M-144, Sheet 1

P & ID Fuel Pool Cooling Filter & Demineralizing System

AS

M-144, Sheet 2

P & ID Fuel Pool Cooling Filter & Demineralizing System

Y

Drawings

M-99

P & ID Standby Liquid Control System

AD

Engineering

Changes

EC 643002

L2R20 ADHR Evaluation

000

LOP-FC-03

Fuel Pool Cooling System Startup, Operation, Shutdown,

Level Changes, and Flushing

LOP-RH-07

Shutdown Cooling System Startup, Shutdown, Operation

and Transfer

LOP-SC-01M

Standby Liquid Control System Mechanical Checklist

71111.04

Procedures

LOP-VC-01

Control Room HVAC Operation

PFP RX BLDG

673-3, Fire Zone

211

Pre-Fire Plan Unit 1 General Area

PFP RX BLDG

673-3, Fire Zone

2

Pre-Fire Plan Unit 2 HPCS Cubicle

71111.05

Fire Plans

PFP RX BLDG

673-3, Fire Zone

3E

Pre-Fire Plan Unit 2 General Area and RWCU Pump

Cubicles

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

PFP RX BLDG

673-4, Fire Zone

314

Pre-Fire Plan Unit 2 LPCS/RCIC Pump Room

PFP RX BLDG

694-6 Elevation,

Fire Zone 2H3

Pre-Fire Plan Unit 1 RHR Heat Exchanger B Cubicle

PFP RX BLDG

694-6, Fire Zone

2H2

Pre-Fire Plan Unit 1 HPCS Cubicle

PFP RX BLDG

740-0, Fire Zone

2F

Pre-Fire Plan Unit 1 General Area and CRD Repair Room

PFP RX BLDG

786-6, Fire Zone

3D

Pre-Fire Plan Unit 2 Reactor Building General Area

PFP RX BLDG

843-6, Fire Zone

FA1

Pre-Fire Plan Elevation U1 and U2 Refuel Floor Area

004

ER-AA-600-1069

High Risk Fire Area Identification

MA-AA-716-008-

1008

Reactor Services Refuel Floor FME Plan

OP-AA-201-004

Fire Prevention for Hot Work

OP-AA-201-009

Control of Transient Combustible Material

Procedures

OP-LA-201-012-

001

LaSalle On-Line Fire Risk Management

AR 4557455

UT PA Exam Results for 2RR28B-3" Weld 1

2/26/2023

AR 4557459

L2R19 VT-3 IWF Class 1 Support Indication Reactor Water

Cleanup

2/26/2023

AR 4557639

UT PA Exam Results for 2RH03CB-12" Weld 1

2/27/2023

AR 4557711

IR 04557459 Written with the Wrong Component Listed

2/27/2023

AR 4557817

UT PA Exam Results for 2RH03CB-12" Weld 2

2/27/2023

AR 4557912

UT PA Exam Results for 2RT01B-6" Weld 17

2/28/2023

AR 4558003

UTPA for 2RT01B-6" Weld 18

2/28/2023

71111.08G

Corrective Action

Documents

AR 4558217

UT PA Exam Results for 2RR28B-3" Weld 1R

03/01/2023

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

AR 4558634

UT PA Exam Results for 2RR28B-3" Weld 1 Repair 2

03/02/2023

AR 4721674

Internal Corrosion in 2A RHR Pump Seal Cooler Outlet Pipe

2/05/2023

Engineering

Changes

EC 636268

Unit 2 Bottom Head Drain Reroute

03/16/2023

Engineering

Evaluations

DDR 2690

Deviation Disposition Request for minimum corrosion

allowance for carbon steel forgings

11/04/2022

L2R20-MT-002

Magnetic Particle Examination

2/18/2025

L2R20-UT-008

1RH-2001-21A Ultrasonic Examination Report

2/20/2025

L2R20-VEN-001

1FW-2001-20A Safe End to Nozzle Examination Report

2/20/2025

L2R20-VEN-002

1FW-2002-20A Safe End to Nozzle Examination Report

2/18/2025

L2R20-VT-001

Visual Examination of Pipe Hanger, Support or Restraint

(VT-3)

2/11/2025

L2R20-VT-002

Visual Examination of Pipe Hanger, Support or Restraint

(VT-3)

2/11/2025

L2R20-VT-005

Visual Examination of Pipe Hanger, Support or Restraint

(VT-3)

2/12/2025

L2R20-VT-006

Visual Examination of Welds (VT-1)

2/12/2025

L2R20-VT-022

Visual Examination of Pipe Hanger, Support or Restraint

(VT-3)

2/18/2025

NDE Reports

L2R20-VT-023

Visual Examination of Pipe Hanger, Support or Restraint

(VT-3)

2/18/2025

ER-AA-335-014

VT-1 Visual Examination

ER-AA-335-016

VT-3 Visual Examination of Component Supports,

Attachments and Interiors of Reactor Vessels

Procedures

GEH-PDI-UT-1

PDI Generic Procedure for the Ultrasonic Examination of

Ferritic Welds

2.1

Work Orders

WO 5237886-19

Unit 2 Bottom Head Drain Reroute (EC636268) Task 19

03/03/2023

ReMA Plan

  1. L2C20-02

L2C20 Standing Shutdown ReMA

03/17/2023

71111.11Q

Miscellaneous

Sequence ID:

SAr9.1

L2C20 December 2024 Shutdown Sequence

2/18/2024

LGP-2-1

Normal Unit Shutdown

133

LGP-3-2

Reactor Scram

71111.11Q

Procedures

OP-LA-101-111-

1002

LaSalle Operations Philosophy Handbook

Engineering

Changes

EC 642941

Ability of 1B Diesel Generator to Have Performed Required

Function with Fuel Oil Leak

ER-AA-320

Maintenance Rule Implementation Per NEI 18-10

71111.12

Procedures

ER-AA-320-1004

Maintenance Rule - (a)(1) and (a)(2) Requirements

AR 4844688

1B SBLC Pump Discharge Check Valve Chattering

03/12/2025

AR 4845280

1B SBLC Pump Run Indicated Low Flow

03/13/2025

Corrective Action

Documents

AR 4845342

Leak on 1B SBLC Plungers Packing

03/14/2025

ER-AA-600

Risk Management

OP-AA-107

Integrated Risk Management

71111.13

Procedures

WC-AA-101-1006

On-Line Risk Management and Assessment

AR 4764916

Unit 2 Div 2 RHRWS Pumps in Alert Range

04/10/2024

AR 4828295

Unknown Cause in Change in the IST Dp for 2C & 2D

RHRWS pps

01/08/2025

AR 4840671

CRD 18-35 Scram Time Exceeded 90% TS limit

2/26/2025

AR 4840680

L2R20 LL - CRD 22-31 Scram Time Exceeded TS Limit

2/26/2025

AR 4840682

CRD 26-31-Scram Time Within 90% of TS Limits

2/26/2025

AR 4840717

CRD 50-19 Scram Time Exceeded 90% TS Limit

2/26/2025

AR 4840751

CRD 58-27 Scram Time Exceeded 90% TS Limit

2/26/2025

AR 4840783

CRD 38-43 Scram Time Within 90% of TS Limits

2/26/2025

AR 4840797

CRD 30-55 Scram Time Exceeded 90% TS Limit

2/26/2025

Corrective Action

Documents

AR 4844688

1B SBLC Pump Discharge Check Valve Chattering

03/12/2025

71111.15

Engineering

Changes

EC EVAL 643386

Backseating Evaluation for Valve 1E51-F008

Procedures

OP-AA-103-105

Limitorque Motor-Operated and Chainwheel Operated Valve

Operations

WO 4758055

EM Perform EQ Inspection and Votes Test 1E51-F008

2/27/2024

WO 5214768

2B RHR WS Biennial Comprehensive IST Pump Test

04/10/2024

71111.15

Work Orders

WO 5355489

Scram Time Rods per LOS-RD_SR12 & Flush Rods at 00 or

2/28/2025

WO 5527728

IM -EWP-LIS-RH-207 U2 RHR B Service Water Flow Ind

Cal

04/12/2024

71111.15

Work Orders

WO 5527960

2B RHR WS Biennial Comprehensive IST Pump Test

05/14/2024

EC 625078

Remove Bonnet Vent Valves on Unit 2 RR Discharge

Isolation Valves (2B33-F067A/F067B)

04/23/2019

EC 631743

Shutdown Cooling Trip Bypass Keylock Switches

EC 640577

Unit 2 - Adding a Time Delay to Load Reject Circuit

Engineering

Changes

EC 640788

DFP 'B' Engine Replacement

71111.18

Work Orders

WO 4816800

Remove Bonnet Vent Valves on 2B33-F067A

2/21/2023

AR 4840816

Drywell Closeout Upper Elevation Walkdown with NRC

2/26/2025

WO 4839094

NRC Question Related to FC ADHR WS Flow

2/20/2025

Corrective Action

Documents

WO 4842502

Drywell Closeout 740 Elevation Walkdown with NRC

2/27/2025

L2C20-02

Shutdown Reactivity Maneuver Plan

03/17/2023

71111.20

Miscellaneous

PORC 25-02

L2R20 Shutdown Safety Plan

AR 4844688

1B SBLC Pump Discharge Check Valve Chattering

03/12/2025

AR 4845280

1B SBLC Pump Run Indicated Low Flow

03/14/2025

Corrective Action

Documents

AR 4845342

Leak on 1B SBLC Plungers Packing

03/14/2025

Drawings

M-92

P&ID Primary Containment Vent & Purge

AU

LOS-DG-201

Diesel Generator, 0DG01K, Start and Load Acceptance

Surveillance

LOS-DG-R0

Diesel Generator 0DG01K Twenty-Four Hour Run

Surveillance

Procedures

LTS-900-6

RHR Shutdown Cooling Return Pressure Isolation Valve

Water Leak Test 1(2)E12-F050A/B, 1(2)E12-F053A/B, and

1(2)E12-F099A/B

WO 5344917

OP LOP-NB-R2 Reactor Vessel Leakage Test

2/27/2025

WO 5344917

Reactor Vessel Leakage Test

2/27/2025

WO 5344926

U2 Core Verification (BOC Startup)

2/23/2025

WO 5344968

2C RHR PMTs

2/18/2025

WO 5344969

2B RHR PMTs

2/24/2025

WO 5344994

Unit 2 Div 1 DC Restoration PMT JBR

2/18/2025

WO 5355489

Scram Time Rods per LOS-RD-SR12 & Flush Rods at 00 or

2/28/2025

WO 5393175

LLRT 2VQ034, 35, 36, 38

2/17/2025

71111.24

Work Orders

WO 5393180

PC VQ Valves LLRT 2VQ029/30/42

2/17/2025

WO 5393242

OP LOS-MS-R7 U2 Main Steam Safety Relief Valve

Operability Test

2/24/2025

WO 5529697

OP LOS-RP-SA3 U2 Rx Manual Scram Func Att 2A

2/09/2025

WO 5530430

OP LOS-RP-SA3 U2 Rx Manual Scram Func Att 2B

2/09/2025

WO 5554037

Unit 2 Div 2 DC Restoration PMT JBR

2/22/2025

WO 5557889

LOS-RD-SR4 Rod Movement Log

2/25/2025

WO 5566272

2E12-F025A Perform 'As Found' LLRT LTS-100-15

2/23/2025

WO 5601138

OP LOS-SC-Q1 1A SBLC Pump Quarterly Att 1A

03/14/2025

WO 5602167

OP LOS-SC-Q1 1B SBLC Pump Quarterly Att 1B

03/14/2025

WO 5625872

2E12-F050A Failed LLRT

2/24/2025

Corrective Action

Documents

Resulting from

Inspection

AR 4841181

NRC ID: E-Plan IPAWS Testing Records not Available

2/25/2025

Miscellaneous

N/A

PNS System Maintenance Reports

January

23 through

December

24

71114.02

Procedures

EP-MW-121-1006

Contracted Siren Maintenance Oversight

001

Miscellaneous

N/A

ERO Personnel Qualifications

Various

EP-AA-1000

Exelon Nuclear Standardized Radiological Emergency Plan

71114.03

Procedures

TQ-AA-113

ERO Training and Qualification

EP-AA-120-F-06

Evacuation Time Estimate Review Checklist

05/05/2024

KLD TR - 1408

LaSalle County Generating Station 2024 Population Update

Analysis

06/13/2024

N/A

24 Letters of Agreement: Seneca Fire Dept.; LaSalle

County Sheriff; Marseilles Area Ambulance Service;

Marseilles Fire Protection District; Seneca Ambulance

Service; Morris Hospital

Various

71114.05

Miscellaneous

N/A

EP Inventories 2023 & 2024

Various

LA-02-25-00518

L2R20 DW ISI, FAC, LROT Inspection Activities

01/31/2025

LA-02-25-00901

L2R20 RFF Reactor Disassembly and Reassembly Activities

01/29/2025

ALARA Plans

LA-2-25-00304

2A RT Pump Project

01/27/2025

AR 4761497

Gas Leak in the Unit 1 Hydrogen Analyzer Room

03/27/2024

71124.01

Corrective Action

Documents

AR 4797099

Radwaste Impacts Due to CCW (2TBCCW) Sent to Floor

Drains

08/27/2024

AR 4810702

RP Knowledge and Skills, Self-Assessment Findings

10/20/2024

AR 4811146

Dose Outside Performance Criteria for August SAC

10/22/2024

AR 4816117

NOS ID: Rad Boundaries/Signage did not Follow Procedure

11/08/2024

AR 4816122

NOS ID: Radiological Surveys Were Missing Required Data

11/08/2024

AR 4816155

NOS ID: Alpha Eval Incorrectly Tracked

11/08/2024

AR 4816170

Unit 1 Hydrogen Analyzer Room High Radioactive Gas

Content

11/08/2024

AR 4823593

Unit 1 OG Pretreat Room Radioactive Leak

2/13/2024

AR 4824042

Technician "Gassed Up" After U1 Pre Treat Sampling

2/16/2024

AR 4824995

Rad Risk Assess. Approvals Not Documented for High-Risk

Job

2/19/2024

RP-AA-401-1002

Radiological Risk Management

RP-AA-403

Administration of the Radiation Work Permit Program

Procedures

RP-AA-503-F-01

Unconditional Release Instructions Using the Tool and

Equipment Monitor (TEM) for Personal Items Used in the

Radiologically Controlled Area (RCA) and in a Contaminated

Area

25-233152

4-valve Room Prior to 2G33-F393A Insulation Removal

2/05/2025

Radiation

Surveys

25-233666

RT Pump Room Prior to Piping End Prep

2/12/2025

L-02-25-0642

L2R20 RB High Risk Valves-2G33-F393-394 Cut Out and

Replacement

LA-02-25-00518

L2R20 DW ISI, FAC, LROT Inspection Activities

LA-02-25-00901

L2R20 RFF Reactor Disassembly and Reassembly Activities

LA-2-25-00304

RWCU System Maintenance

Radiation Work

Permits (RWPs)

LA-2-25-00304

L2R20 RB RXB High Risk Valves-2G33-F393A

04716436

24 In Field Work Controls

10/10/2024

04716437

24 - Radworker Performance

10/28/2024

Self-Assessments

04716440-08-02

24 Rad Pro Knowledge and Skills

10/31/2024

71124.04

Procedures

RP-AA-210

Dosimetry Issue, Usage, and Control

71151

Miscellaneous

LS-AA-2110

Monthly Data Elements for NRC ROP Indicator - Emergency

Response Organization Drill Participation

January

23 through

December

24

LS-AA-2130

Monthly Data Elements for NRC ROP Indicator - Alert and

Notification System (ANS) Reliability

January

23 through

December

24

71151

Miscellaneous

LS-AA-2135

Monthly Data Elements for NRC ROP Indicator - Emergency

Response Facility and Equipment Readiness (ERFER)

January

25 through

February

25

Calculations

L-004330 (EC 630084)

Curtiss Wright Seismic Report NUS-A056QA for Controller

Module Model CON2000-701-03/N

AR 4485554

RCIC Controller Not Stable During RCIC Low Press Run

03/17/2022

AR 4681919

U2 RCIC Broke

06/01/2023

AR 4684795

Unit RCIC Work Window 4.0 Critique

06/14/2023

AR 4684797

U2 RCIC Critique (DUP)

06/14/2023

AR 4704146

U2 RCIC Pump Flow Controller Not Working in Manual

09/21/2023

AR 4800683

U2 RCIC INPO Nuclear Safety Concern

09/10/2024

AR 4800685

U2 RCIC INPO Nuclear Safety Concern Follow On

09/10/2024

AR 4810348

Unit 2 RCIC Identified Issues, Troubleshooting Results

10/18/2024

Corrective Action

Documents

AR 4811828

U2 RCIC Flow Controller Improperly Calibrated

10/24/2024

Engineering

Changes

EC 630084

Curtiss Wright Seismic Report NUS-A056QA for Controller

Module Model Con2000-701-03/N

3002010628

Nuclear Maintenance Applications Center: Terry Turbine

Maintenance Guide, RCIC Application

10/01/2017

Miscellaneous

LS-MSPI-001

LaSalle MSPI Basis Document

AD-AA-101-1002

Writers Guide for Procedures and T&RM

AD-LA-1000

LaSalle Procedure Writers Guide

CC-AA-103-2001

Setpoint Change Control

ER-AA-10

Equipment Reliability Process Description

ER-AA-200

Preventive Maintenance Program

ER-AA-2003

System Performance Monitoring and Analysis

LIS-RI-202

Unit 2 RCIC Pump Discharge Flow Indication Calibration

LIS-RI-215

Unit 2 RCIC Control System Calibration

LMP-RI-02

Reactor Core Isolation Cooling Turbine Maintenance

71152A

Procedures

LOP-RI-06

Controlled Start of the Reactor Core Isolation Cooling

System in the CST Test Mode

LOS RI-Q3

Reactor Core Isolation Colling (RCIC) System Pump

Operability and Valve Inservice Tests in Conditions 1,2, and

MA-AA-716-010

Maintenance Planning

Procedures

MA-AA-716-010-

20

Writer's Guide for Maintenance Work Order Instructions

WO 4704314

RCIC Pump Discharge Flow IND

04/30/2020

WO 4932662

RCIC Control Sys

11/02/2021

WO 4980430

U2 RCIC Replace the EGM Module and RGSC

11/27/2023

WO 5030345

RCIC Pump Discharge Flow IND

09/30/2022

WO 5103995

LRA Turbine Inspection/Rebuild

2/25/2023

WO 5145550

U2 RCIC S/P Check Valves TST LOS-RI-R4, ATT 1A/LOS-

RI-Q3

03/10/2023

WO 5204910

RCIC Control Sys

06/11/2023

WO 5240282

RCIC Controller Not Stable During RCIC Low Press Run

2/11/2023

WO 5241758

U1 RCIC S/P Check Valve TST LOS-RI-R4, ATT 1A/LOS-

RI-Q3 ATT

03/09/2024

WO 5300925

RCIC Pump Discharge Flow IND

05/31/2023

WO 5343171

RCIC Pump Flow Controller not Working in Manual

06/08/2023

WO 5371708

U2 RCIC Broke

06/05/2023

WO 5403690

U2 RCIC Troubleshooting/Repair

11/29/2023

WO 5482486

LOS-RI-01 U2 RCIC Valves ATT 2A

05/01/2024

71152A

Work Orders

WO 5538711

LOS-RI-Q1 U2 RCIC Valves ATT 2A

07/31/2024

AR 4767915

Loss of Unit 1 SAT Due to OCB 1-13 Tripped on Diff Current

04/20/2024

AR 4767916

Loss of Division 1 Gross Gamma

04/20/2024

AR 4767918

Loss of 'A' MSL Rad Monitor

04/20/2024

AR 4767919

Loss of 1B CW Pump

04/20/2024

AR 4767921

VR No Air Flow Supply Isolation Damper Closed Alarm

04/20/2024

71153

Corrective Action

Documents

AR 4767922

VR Isolation Dampers Shut on Loss of the SAT

04/20/2024