IR 05000346/2025003

From kanterella
Jump to navigation Jump to search
Integrated Inspection Report 05000346/2025003 07200014/2025001 and Exercise of Enforcement Discretion
ML25351A112
Person / Time
Site: Davis Besse  
Issue date: 12/22/2025
From: Sanchez-Santiago E
NRC/RGN-III/DORS/RPB2
To: Craven R
Vistra Operations Company
References
EAF-RIII-2025-0160 IR 2025001, IR 2025003
Download: ML25351A112 (0)


Text

SUBJECT:

DAVIS-BESSE NUCLEAR POWER STATION - INTEGRATED INSPECTION REPORT 05000346/2025003; 07200014/2025001 AND EXERCISE OF ENFORCEMENT DISCRETION

Dear Robert Craven:

On September 30, 2025, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Davis-Besse Nuclear Power Station. On December 2, 2025, the NRC inspectors discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.

Due to the temporary cessation of government operations, which commenced on October 01, 2025, the NRC began operating under its Office of Management and Budget-approved plan for operations during a lapse in appropriations. Consistent with that plan, the NRC operated at reduced staffing levels throughout the duration of the shutdown. However, the NRC continued to perform critical health and safety functions and make progress on other high-priority activities associated with the ADVANCE Act and Executive Order 14300. On November 13, 2025, following the passage of a continuing resolution, the NRC resumed normal operations. However, due to the 43-day lapse in normal operations, the Office of Nuclear Reactor Regulation granted the regional offices an extension on the issuance of the calendar year 2025, third quarter integrated inspection reports normally issued by November 15, 2025, to December 31, 2025. The NRC will resume the routine cycle of issuing inspection reports on a quarterly basis beginning with the calendar year 2025, fourth quarter integrated inspection reports, which will be issued 45 days after the fourth quarter ends on December 31, 2025.

One finding of very low safety significance (Green) is documented in this report. This finding involved a violation of NRC requirements. We are treating this violation as a non-cited violation (NCV) consistent with Section 2.3.2 of the Enforcement Policy.

December 22, 2025 If you contest the violation or the significance or severity of the violation documented in this inspection report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN:

Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region III; the Director, Office of Enforcement; and the NRC Resident Inspector at Davis-Besse Nuclear Power Station.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Elba M. Sanchez Santiago, Chief Reactor Projects Branch 2 Division of Operating Reactor Safety Docket No. 05000346; 07200014 License No. NPF-3

Enclosure:

As stated

Inspection Report

Docket Number:

05000346; 07200014

License Number:

NPF-3

Report Number:

05000346/2025003; 07200014/2025001

Enterprise Identifier:

I2025003-0052; I2025001-0111

Licensee:

Vistra Operations Company, LLC

Facility:

Davis-Besse Nuclear Power Station

Location:

Oak Harbor, OH

Inspection Dates:

July 01, 2025 to September 30, 2025

Inspectors:

B. Towne, Senior Resident Inspector

N. Audia, Reactor Inspector

K. Fay, Senior Reactor Inspector

A. Guieb, Resident Inspector

I. Hafeez, Senior Reactor Inspector

T. Hooker, Health Physicist

C. Padilla, Senior Resident Inspector

A. Rowe, Transport & Storage Safety Inspector

J. Tapp, Senior Trans & Storage Safety Insp

Approved By:

Elba M. Sanchez Santiago, Chief

Reactor Projects Branch 2

Division of Operating Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Davis-Besse Nuclear Power Staion, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

Failure to Incorporate Strategies from FAQ070040 to Reduce Fire Risk During Non-Power Operation High Risk Evolutions Cornerstone Significance Cross-Cutting Aspect Report Section Initiating Events Green NCV 05000346/202500301 Open/Closed None (NPP)71111.21N.05 The inspection team identified a Green finding and associated non-cited violation (NCV) of the Davis-Besse Operating License Condition 2.C(4), Transition License Condition step 3, for failing to revise procedures to implement Non-Power Operation requirements for National Fire Protection Association (NFPA) 805. Specifically, Davis-Besse failed to incorporate strategies committed by the licensee in response to Frequently Asked Question (FAQ) 070040 to reduce fire risk during Non-Power Operation (NPO) high risk evolutions (HREs) into their procedures.

Additional Tracking Items

Type Issue Number Title Report Section Status URI 05000346/20240 1002 Failure to Correctly Implement 10 CFR 50.59 Administrative Procedures 71111.21M Closed URI 05000346/20220 1101 Multiple NFPA 805 Non-Power Operation Transition Issues 71111.21N

.05 Closed EDG EAF-RIII20250160 Enforcement Action EAF-RIII20250160:

Failure to Comply with 10 CFR Part 37 71124.08 Closed LER 05000346/2021 001-02 LER 2021001-02 for Davis-Besse Nuclear Power Station, Unit 1, Emergency Diesel Generator Speed Switch Failure due to Direct Current System Ground 71153 Closed LER 05000346/2021 001-01 LER 2021001-00 for Davis-Besse Nuclear Power Station, Unit 1, Emergency Diesel Generator Speed Switch Failure due to Direct Current System Ground 71153 Closed LER 05000346/2021 001-01 LER 2021001-01 for Davis-Besse Nuclear Power Station, Unit 1, Emergency Diesel Generator Speed Switch Failure due to Direct Current System Ground 71153 Closed

PLANT STATUS

Unit 1 began the inspection period at rated thermal power. On August 12, 2025, the unit was shut down to conduct repairs to the steam generator 1 (SG1) level instrument reference leg.

The unit was returned to rated thermal power on August 19, 2025, and remained at or near rated thermal power for the remainder of the inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed activities described in IMC 2515, Appendix D, Plant Status, observed risk significant activities, and completed onsite portions of IPs. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (1 Sample)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1) Emergency diesel generator (EDG) train 2 after EDG train 2 monthly surveillance on August 28, 2025

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (5 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1) Cable spreading room, room 422A, fire area CC, on July 14, 2025
(2) Main steam line area and control room heating ventilation and cooling equipment room, room 601, 602, and 603, fire area DH on July 28, 2025
(3) Component cooling water heat exchanger and pump room, room 328, fire area T on August 27, 2025
(4) Service building 6, laydown area, station blackout diesel on September 4, 2025
(5) High voltage switchgear room A, room 325, fire area S on September 30, 2025

Fire Brigade Drill Performance Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated the onsite fire brigade training and performance during a simulated fire in the high voltage switchgear room A, breaker AC202 on August 8, 2025

71111.07A - Heat Exchanger/Sink Performance

Annual Review (IP Section 03.01) (1 Sample)

The inspectors evaluated readiness and performance of:

(1) Service water cold water forebay flow verification during the week ending September 6, 2025

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (2 Samples)

(1) The inspectors observed and evaluated licensed operator performance in the control room during plant shutdown and transition to mode 4 due to steam generator level instrument reference leg leak on August 12, 2025
(2) The inspectors observed and evaluated licensed operator performance in the control room during transition to mode 2 and reactor startup following a maintenance outage on August 17, 2025

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) The inspectors observed and evaluated operator performance in the simulator during rapid shutdown scenario validation on August 14, 2025

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (3 Samples)

The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components (SSCs) remain capable of performing their intended function:

(1) Service water pump 1 strainer drain valve asfound diagnostic inservice testing on July 8, 2025
(2) Makeup and purification system demineralizer 3 inlet isolation valve troubleshooting following failure to establish flow during the week ending September 6, 2025
(3) Negative battery charger 2 (DBC2N) load testing on September 26, 2025

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (2 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:

(1) Assessment of elevated risk and mitigating actions due to PJM electrical grid hot weather and max generation alerts during the week ending July 26, 2025
(2) Assessment of elevated risk and mitigating actions due to station air compressor (SAC) 2 maintenance outage during the week ending August 2, 2025

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (3 Samples 1 Partial)

The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:

(1) Operability determination of temperature instruments TIRC3A5 and TIRC3B5 due to discovery of missed surveillance for SR 3.3.17.3 on July 31, 2025
(2) Operability determination of high pressure injection (HPI) pump 2 due to recirculation flow outside of acceptance criteria band on August 5, 2025 (3)

(Partial)

Operability determination of steam feed rupture control system due to diverging steam generator 2 level instrumentation on August 11, 2025

(4) Operability determination of source range nuclear instrument 2 due to start up rate (SUR) and counts per second (CPS) reading erratically on August 17, 2025

71111.20 - Refueling and Other Outage Activities

Refueling/Other Outage Sample (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated Unit 1 maintenance outage activities from August 12 to August 18, 2025

71111.24 - Testing and Maintenance of Equipment Important to Risk

The inspectors evaluated the following testing and maintenance activities to verify system operability and/or functionality:

Post-Maintenance Testing (PMT) (IP Section 03.01) (3 Samples)

(1) Post-maintenance test of station air compressor (SAC) 2 following troubleshooting after second trip of SAC 2 on August 5, 2025
(2) Post-maintenance test following HPI train 1 scheduled maintenance on September 10, 2025
(3) Post-maintenance test following motor-driven feed pump maintenance outage on September 17, 2025

Surveillance Testing (IP Section 03.01) (4 Samples)

(1) Auxiliary feedwater pump (AFP) 1 quarterly test on July 9, 2025
(2) Decay heat train 1 pump and valve test on July 19, 2025
(3) EDG 1 monthly test on July 20, 2025
(4) Emergency feedwater pump monthly test on September 20, 2025

Inservice Testing (IST) (IP Section 03.01) (1 Sample)

(1) Asfound testing of MV1379 service water pump strainer 1 drain valve in accordance with DBSV09302 testing motor operated valves on July 8, 2025

71114.06 - Drill Evaluation

Additional Drill and/or Training Evolution (1 Sample)

The inspectors evaluated:

(1) The inspectors evaluated an emergency plan training exercise simulating a fuel leak and radiological release followed by containment failure resulting in a general emergency declaration on September 18,

RADIATION SAFETY

71124.08 - Radioactive Solid Waste Processing & Radioactive Material Handling, Storage,

& Transportation

Radioactive Material Storage (IP Section 03.01)

The inspectors evaluated the licensees performance in controlling, labeling and securing the following radioactive materials:

(1)10 CFR Part 37 material storage location

Radioactive Waste System Walkdown (IP Section 03.02) (1 Sample)

The inspectors walked down the following accessible portions of the solid radioactive waste systems and evaluated system configuration and functionality:

(1) Spent resin processing systems

Waste Characterization and Classification (IP Section 03.03) (2 Samples)

The inspectors evaluated the following characterization and classification of radioactive waste:

(1) Primary and secondary resin waste streams
(2) Dry active waste stream

Shipping Records (IP Section 03.05) (3 Samples)

The inspectors evaluated the following non-excepted radioactive material shipments through a record review:

(1) Shipment 20231001; Filter; UN3321 Radioactive Material, low specific activity (LSA-II)
(2) Shipment 20231002; Secondary Resin Liners; UN2910, Radioactive Material, excepted package - limited quantity of material
(3) Shipment 20251001; Primary Resin Liner; UN3321, Radioactive Material, low specific activity (LSA-II)

OTHER ACTIVITIES

BASELINE

71152S - Semiannual Trend Problem Identification and Resolution Semiannual Trend Review (Section 03.02)

(1) The inspectors reviewed the licensees corrective action program to identify potential trends in jockey fire pump volumetric flow that might be indicative of a more significant safety issue.

71153 - Follow-Up of Events and Notices of Enforcement Discretion Event Report (IP Section 03.02)

The inspectors evaluated the following licensee event reports (LERs):

(1) LER 2021001-00 for Davis-Besse Power Station, Unit 1, Emergency Diesel Generator Speed Switch Failure due to Direct Current System Ground, (ML21105A489). The inspection conclusions associated with this LER are documented in, 05000346/2021092 (ML21356A058), 05000346/2022040 (ML22314A225), 05000346/2022090 (ML22109A157) and 05000346/2025002 (ML25216A272). This LER is Closed.
(2) LER 2021-00101 for Davis-Besse Power Station, Unit 1, Emergency Diesel Generator Speed Switch Failure due to Direct Current System Ground, (ML24263A236). This LER updated LER 2021001-00 with the cause and corrective actions taken since the initial report submittal. The updated information was reviewed and there were no changes to our inspection conclusions as indicated in our review of LER 2021001-00 above. This LER is Closed.
(3) LER 2021001-02 for Davis-Besse Power Station, Unit 1, Emergency Diesel Generator Speed Switch Failure due to Direct Current System Ground, (ML24344A257). This LER revision added additional reporting requirement. There were no changes in our inspection conclusions as indicated in our review of LER

===2021001-00 above. This LER is Closed.

OTHER ACTIVITIES

TEMPORARY INSTRUCTIONS, INFREQUENT AND ABNORMAL 60855 - Operation of an Independent Spent Fuel Storage Installation Operation of an Independent Spent Fuel Storage Installation===

(1) The inspectors evaluated the licensees activities related to long-term operation and monitoring of their independent spent fuel storage installation (ISFSI). The inspectors were onsite from August 18 through August 21, 2025. During the onsite walkdown, the inspectors toured the ISFSI and evaluated the material and radiological conditions of the ISFSI pad and storage system. The inspectors verified that the ISFSI pads radiological conditions were as expected during the walkdown.

Since the last inspection, the inspectors evaluated corrective action documents. The inspectors also reviewed procedures and interviewed staff regarding daily temperature monitoring of the casks. The site did not perform any screenings or evaluations under 10 CFR 72.48, Changes, Tests, and Experiments, since the last inspection.

60859 - ISFSI License Renewal Inspection ISFSI License Renewal Inspection

(1) The inspectors conducted a License Renewal Inspection for the Transnuclear Standardized NUHOMS at the site. The inspectors were onsite from August 18 through August 21, 2025 to verify that:
  • Age-related degradation is identified and adequately managed or corrected, as applicable.

The inspectors conducted the inspection through a combination of document reviews and onsite walkdowns. Specifically, the inspectors reviewed:

  • All applicable TLAAs including Dry Shielded Canister (DSC) Fatigue, Transfer Cask Fatigue, and Thermal Performance of Horizontal Storage Modules (HSMs) for the Period of Extended Operation.

Additionally, the inspectors observed the site perform visual examinations of a DSC external surface as well as the internal and external surfaces of an HSM.

INSPECTION RESULTS

Unresolved Item (Closed)

Failure to Correctly Implement 10 CFR 50.59 Administrative Procedures URI 05000346/202401002 71111.21M

Description:

In September 2024, as part of the Comprehensive Engineering Team Inspection, the inspectors reviewed the licensee's 10 CFR 50.59 implementation process and eleven 50.59 screenings. The inspectors determined 50.59 screenings 1500776, Switchyard 345kV Breaker Replacement, Revision 15 and 2300791, "Limiting Differential Pressure for Auxiliary Feedwater Pump Discharge Valves," Revision 0 did not contain sufficient information to justify the conclusions reached, which was contrary to procedure NOBP-LP4003A, "10 CFR 50.59 User Guidelines," Revision 12. NOBP-LP4003A, Attachment 2, "10 CFR 50.59 Screen,"

requires, in part, that the technical basis for response to each of the questions be addressed and documented, and for the justification to be complete enough to permit an independent reviewer with similar expertise to understand the judgment and develop concurrence with the technical basis without recourse to the preparer.

The licensee entered the issues into the corrective action program and generated CR202407558, "2024 CETI: Insufficient Detail Contained in 10 CFR 50.59 Screen 1500776," CR202407619, "2024 CETI: AF599 and AF608 Not Evaluated for Worst Case Differential Pressure," and CR202407625, "2024 CETI: AFW Discharge MOV Calculations Credit Operator Actions," to capture the inspectors' concerns. For screening 2300791, the licensee prepared two new screenings: 2401449, "Calculation CME050.03122, 111 &

112," and 2401590, "Calculation CME050.03117, 120, 121, 130," and updated the associated calculations. For screening 1500776, the licensee updated the screening to include more thorough justifications, including the vendor determination that existing relay settings are acceptable and would not adversely impact the main transformer's differential protection to detect abnormal condition originating in the main generation system and respond accordingly. The inspectors reviewed the updated 50.59 screenings and calculations and determined 50.59 evaluations and prior NRC approval was not required.

The ROPs significance determination process does not specifically consider the regulatory process impact in its assessment of licensee performance. Therefore, it was necessary to address this violation, which impeded the NRCs ability to regulate using traditional enforcement to adequately deter non-compliance. The inspectors determined the licensees failure to correctly implement 10 CFR 50.59 administrative procedures to prepare adequate written evaluations that provided the bases for the determination that the changes did not require a license amendment was contrary to 10 CFR 50.59(d)(1). Specifically, the inspectors determined screenings 1500776 and 2300791 did not provide the bases that changes made to offsite power circuit breakers and auxiliary feedwater (AFW) valves, respectively, were not adverse and did not require a license amendment. The inspectors assessed the violation in accordance with the NRC Enforcement Policy dated August 12, 2025, and the NRC Enforcement Manual, Revision 11, to determine the significance of the violation. They noted Section 2.1.3.D.5.a of the manual indicated failures to implement 10 CFR 50.59 administrative procedures that resulted in non-isolated (i.e., repetitive) failures to prepare adequate written evaluations would be categorized as Severity Level (SL) IV violations.

Following consultation with Enforcement & Investigations Coordination Staff, the inspectors have determined that two out of eleven insufficient 50.59 screenings does not meet the criteria of non-isolated failures and, as such, does not rise to the level for a Severity Level IV violation and will be treated as a minor violation, consistent with Section 2.3.1 of the Enforcement Policy.

Corrective Action Reference(s): CR202407558, CR202407619, CR202407625 Failure to Incorporate Strategies from FAQ070040 to Reduce Fire Risk During Non-Power Operation High Risk Evolutions Cornerstone Significance Cross-Cutting Aspect Report Section Initiating Events Green NCV 05000346/202500301 Open/Closed None (NPP)71111.21N.05 The inspection team identified a Green finding and associated non-cited violation (NCV) of the Davis-Besse Operating License Condition 2.C(4), Transition License Condition step 3, for failing to revise procedures to implement Non-Power Operation requirements for National Fire Protection Association (NFPA) 805. Specifically, Davis-Besse failed to incorporate strategies committed by the licensee in response to Frequently Asked Question (FAQ) 070040 to reduce fire risk during Non-Power Operation (NPO) high risk evolutions (HREs) into their procedures.

Description:

During the Fire Protection Team Inspection in 2022, the inspectors identified that the licensee failed to implement part of their NFPA 805 NPO commitments made in response to FAQ 07-0040 during the NFPA 805 license amendment process. Additional information and discussions with the licensee were required to bring the issue of concern to closure, Therefore, an Unresolved Item (URI) 05000346/202201101 was documented in the triennial fire protection inspection report (ADAMS Accession Number ML23004A217). In order to resolve the URI, a review of the licensees NFPA 805 license amendment request (ADAMS Accession Number ML1530A314) and associated supplement (ADAMS Accession Number ML16351A330), dated January 17, 2017, the inspectors found that the licensee stated they would revise plant procedures to incorporate the insights, strategies, and analysis recommended or documented in their NPO Modes Transition Report and add the necessary procedure steps to ensure that key safety functions (KSFs) are achieved and maintained. The inspectors found that the licensee implemented software controls instead of procedure changes and did not incorporate the insights, strategies, and analysis from their NPO Modes Transition Report into their plant procedures. Additionally, the inspectors identified that the licensee did not add the necessary procedure steps to ensure that KSFs were achieved and maintained.

The licensees fire risk software was intended to prohibit hot work permits in fire compartments that contained pinch points during outage HREs. A pinch point is a fire area or compartment where a single fire could cause a loss of all success paths for a specific shutdown KSF. During the inspection, the inspectors identified the software was missing at least 10 fire compartments that should have been flagged as containing pinch points. Some of the missing fire compartments contained multiple KSF pinch points including one compartment that contained 3 KSFs (decay heat removal, inventory control, and support/electrical). These missing fire compartments were unprotected during the 2022 refueling outage HRE (deep drain of the reactor coolant system). In addition, an outage review found that three work orders (200767710, Inspect Main Feedwater Pump Turbine (MFPT) 2 per PM 1557 (overhaul); 200767729, Inspect MFPT 1 per PM 1556 (disassembly/overhaul; and 200851468, Restore Valve Heater Drain HD146 from Temporary Leak Seal) conducted hot work activities in fire area II01 (rooms 252 and 431) during the HRE time frame. In reviewing the work orders, the inspectors noted that, even though hot work activities were not permitted during the HRE, all necessary precautions and compensatory measures were implemented in accordance with the licensees procedure DBFP00018, Control of Ignition Sources, Revision 13.

The inspectors also identified that the licensee did not have procedures for implementing all the necessary NFPA 805 NPO features within their fire risk software but relied on informal notes. The licensees informal notes did not specify that all pinch points needed to be protected during HREs. During the 2022 refueling outage HRE, the licensee only selected inventory control for hot work permit prevention; however, the decay heat removal, reactivity and support/electrical KSFs should have also been selected. The licensees Fire Hazards Analysis Report, which is also their fire protection program design-basis document, contained an NPO Modes Compliance Summary for each fire area/compartment. The NPO Modes Compliance Summary template stated, in part, that each compartment summary will contain any associated pinch points in the fire compartment and any features and/or controls that provide reasonable assurance that the fuel will be maintained in a safe and stable configuration The inspectors found that the NPO Modes Compliance Summary was inaccurate for all fire compartments that contained a pinch point at Davis-Besse. Specifically, all 46 pinch point fire compartments contained the following summary, The potential effects of a fire occurring during NPO modes in this fire compartment were reviewed. This review was conducted using the methodology as described in Calculation ARS-DB11003. This area does not have any associated pinch points. The lack of failures resulting in a pinch point provides reasonable assurance the fuel will be maintained in a safe and stable configuration.

Therefore, the NFPA 805 performance goal for NPO is satisfied.

Corrective Actions: Davis-Besse documented the performance deficiency in their corrective action program. Davis-Besses actions included completing the procedure revisions and instituting necessary changes to the software to comply with the requirements.

Corrective Action References: CR202207442, CR202207489, CR202207930.

Performance Assessment:

Performance Deficiency: The inspection team determined the licensee failed to revise procedures to implement NPO requirements for NFPA 805. Specifically, Davis-Besse failed to incorporate strategies from FAQ 070040 to reduce fire risk during Non-Power Operation HREs.

Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the Protection Against External Factors attribute of the Initiating Events cornerstone and adversely affected the cornerstone objective to limit the likelihood of events that upset plant stability and challenge critical safety functions during shutdown as well as power operations. Specifically, Davis-Besse not incorporating the strategies from FAQ 070040 into site approved procedures, resulted in hot work being performed during Non-Power Operation HREs.

Significance: The inspectors assessed the significance of the finding using IMC 0609 Appendix G, Shutdown Operations Significance Determination Process. The inspectors assessed the significance of the finding using Inspection Manual Chapter (IMC) 0609, Appendix G, Attachment 1, Shutdown Operations Significance Determination Process, Phase 1, Initial Screening and Characterization of Findings, Exhibit 2-Initiating Events Screening Questions. The inspectors reviewed Section D External Event Initiators, Question 10, Does the finding increase the likelihood of a fire or internal/external flood that could cause a shutdown initiating event? The inspectors answered No to this question because, all necessary precautions and compensatory measures were implemented to prevent a fire from causing a shutdown initiating event. Therefore, the finding screened as Green.

Cross-Cutting Aspect: Not Present Performance. No cross-cutting aspect was assigned to this finding because the inspectors determined the finding did not reflect present licensee performance.

Enforcement:

Violation: Davis-Besse Operating License Condition 2.C(4), Transition License Condition step (3), required Davis-Besse, in part, to implement the items listed in Attachment S, Table S2, Implementation Items committed by the licensee in response to FAQ 07-0040, to the First Energy Nuclear Operating Company (FENOC) letter dated November 20, 2018, within 2 years following issuance of the license amendment. Table S2 requires, under item DB1908, the licensee to revise procedures and conduct training to implement NPO Requirements for NFPA 805 in accordance with license amendment request (LAR) Attachment D.

Contrary to the above, as of November 22, 2022, at the time of the exit meeting, Davis-Besse failed to revise procedures to implement NPO requirements for NFPA 805. Specifically, Davis-Besse failed to revise procedures reduce fire risk during Non-Power Operation HREs as required by their LAR and did not prohibit or limit hot work in fire areas during periods of increased vulnerability.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

The disposition of this finding and associated violation closes URI: 05000346/2022011-01.

Enforcement Discretion Enforcement Action EAF-RIII20250160: Failure to Comply with 10 CFR Part 37 71124.08

Description:

On November 29, 2016, the licensee was issued NRC Inspection Report No.

05000346/2016403, which documented a licensee identified violation of 10 CFR Part 37, Physical Protection of Category 1 and Category 2, Quantities of Radioactive Material at Facilities with a 10 CFR Part 73, Physical Protection Program. The violation met the criteria for enforcement discretion as described in Enforcement Guidance Memorandum (EGM)14001, Interim Guidance for Dispositioning 10 CFR Part 37 Violations with Respect to Large Components or Robust Structures Containing Category 1 or Category 2 Quantities of Material at Power Reactor Facilities Licensed Under 10 CFR Parts 50 and 52.

Subsequently, the inspectors reevaluated this activity and found that while a violation of regulatory requirements continues to exist, the conditions remain within the criteria for enforcement discretion established within the interim Enforcement Policy discussed within NRC's Enforcement Policy, Section 9.3.

Corrective Actions: As specified in the NRCs Enforcement Policy, Section 9.3, the application of discretion is authorized until the underlying technical issue is dispositioned through rulemaking or other regulatory action.

Enforcement:

Violation: On November 29, 2016, a violation of 10 CFR Part 37 was documented in Davis-Besse Inspection Report Number 05000346/2016403. The inspectors determined that the previously identified violation remains.

Basis for Discretion: This violation met all of the criteria for enforcement discretion as described in NRC's Enforcement Policy, Section 9.3, Enforcement Discretion for Physical Protection of Category 1 and Category 2 Quantities of Radioactive Material (10 CFR Part 37).

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On December 2, 2025, the inspectors presented the integrated inspection results to R. Craven, Site Vice President, and other members of the licensee staff.
  • On July 10, 2025, the inspectors presented the radiation protection inspection results to A. Filipiak, Organizational Effectiveness Director, and other members of the licensee staff.
  • On August 28, 2025, the inspectors presented the ISFSI program review and license renewal inspection results to T. Brown, Site Vice President, and other members of the licensee staff.
  • On September 17, 2025, the inspectors presented the URI closure for multiple NFPA 805 Non-Power Operation Transition Issues and URI closure for failure to correctly implement 10 CFR 50.59 administrative procedures inspection results to R. Craven, Site Vice President, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

CR202208332

Missing FME Plugs on DBHSM1 to DBHSM4

11/02/2022

CR202403283

MSC2403-30: Dry Cask Storage Records are Located

Under Wrong Folder Unique Identifier in Records

Management

04/15/2024

CR202407523

24 CETI - ISFSI Pad Survey

09/24/2024

CR202407557

Formation of Ground Depression Beginning Near ZR3004

(HSM Area)

09/25/2024

Corrective Action

Documents

CR202505939

ISFSI Pad Broken Ground Cables

08/20/2025

Miscellaneous

Davis-Besse Nuclear Power Station Emergency Plan

DBNE03400

Horizontal Storage Module (HSM) Monitoring

NOP-LP2001

Corrective Action Program

Procedures

NOP-LP4003

Evaluation of Changes, Tests and Experiments

DBM202306131

23 Dry Fuel Storage Pad Annual Radiological Survey

06/13/2023

DBM202406122

24 Dry Fuel Storage Pad Annual Radiological Survey

06/12/2024

Radiation Surveys

DBM202506048

25 Dry Fuel Storage Pad Annual Radiological Survey

06/10/2025

60855

Self-Assessments

ATA20248686

25 Pre-NRC Inspection Assessment for ISFSI, 72.48 &

2.212 Programs

05/02/2025

CR201312587

HSM Concrete, Conduit, Coating Rework

08/15/2013

CR202007215

DSC 24P-R01 Was Not Rotated 180Degrees Prior to

Loading in 1996

09/16/2020

CR202007216

Foreign Material Identified on the Rail During AMP

Inspections

09/16/2020

CR202008358

Davis-Besse ISFSI Aging Management Program -

Groundwater Sampling Results Exceeded Limits in NOPM-

NF3203

10/28/2020

CR202103959

Results from the 2020 Levelness Survey of the HSM

Basemats

05/15/2021

Corrective Action

CR202308176

ISFSI Pad Levelness Survey

11/01/2023

60859

Miscellaneous

Davis-Besse Tollgate Assessment 3

ATA202112864

Perform ISFSI & HSM Basemat Levelness Surveys

09/27/2022

ATA202216483

Perform ISFSI & HSM Basemat Levelness Surveys

10/30/2023

ATA202318701

Perform ISFSI & HSM Basemat Levelness Surveys

03/28/2025

Miscellaneous

NPE2500015

Review of Contracted NDE Personnel Certifications and

Procedures being used under the Contractors QA Program

08/18/2025

Quality Assurance Program Manual

04/19/2024

DBNE06471

Dry Fuel Storage Unloading

NOP-CC5708

Written Practice for the Qualification and Certification of

Nondestructive Examination Personnel

NOP-CC5709

Review and Approval of Contracted Nondestructive

Examination Activities

NOP-LP2022

Administration of the Quality Assurance Program Manual

(QAPM)

NOP-NF3203

Independent Spent Fuel Storage Installation Aging

Management Program (AMP)

NOPM-NF3203

Davis-Besse Aging Management Program Basis Document

for the Standardized NUHOMS System

06/12/2025

PTIP 3530210.1

Davis-Besse AMP Inspections

QCP 10

Purchasing Requirements for NDT Vendors

QCP 101

Qualification and Certification of NDT Personnel

Procedures

SPM 10.5

Visual Inspection of Dry Shielded Canisters, Transfer Casks,

and Bolted Storage Casks

200802045

Perform Aging Management Inspections on HSM1 and

DSC1 installed in 1996

2/18/2020

60859

Work Orders

200832101

Perform Aging Management Inspections on HSM1 and

DSC1 Installed in 1996

05/12/2025

M017A

Diesel Generators

Drawings

M017B

Diesel Generators Air Start

71111.04

Procedures

DBSC03071

Emergency Diesel Generator 2 Monthly Test

71111.05

Corrective Action

Documents

Resulting from

Inspection

CR20255046

NRC Question to the Work Support Center

DBFP00005

Fire Brigade

PFP-AB325

High Voltage Switchgear Room A, Room 325, Fire Area S

PFP-AB328

Component Cooling Water Heat Exchanger and Pump

Room, Room 328, Fire Area T

PFP-AB422B

Cable Spreading Room Ladder Space, Fire Area CC

PFP-AB601W

No. 1 Main Steam Line Area and Purge Inlet Equipment

Room, Fire Area DH

PFP-AB602

No. 2 main Steam Line Area, Fire Area DH

Fire Plans

PFP-S60000

Service Building 6, Laydown Area, Station Blackout Diesel

71111.05

Miscellaneous

13-08/08/251

Fire Brigade Drill Record

Miscellaneous

CNSA011.01019

Analysis of Service Water System Online Flow Verification

Data for Train 2

71111.07A

Procedures

DBSP03006

Service Water Train 2 Cold Forebay Design Flow Verification

CR202504921

SW1379 Evaluated Over Thrust During Diagnostic Testing

07/08/2025

CR202506204

Purification Demin Inlet Valve MU1903 OPEN With No

Pressure Drop

09/02/2025

Corrective Action

Documents

CR202506824

Misconfiguration of Battery Test Set Leads

09/29/2025

CME011.01109

Valve Factor Methodology for Determining Required Thrust

Miscellaneous

PMR 601495

Perform PM 11099 More Often (SW1379) 10yr to 6yr

07/09/2025

DBME03003

Station Battery Charger Test

DBME09209

BCT2000 Operating Guide

71111.12

Procedures

NOBP-ER3204A

Check Valve Condition Monitoring Program

Corrective Action

Documents

CR202301493

SAC 1 Auto Trips on Startup

Corrective Action

Documents

Resulting from

Inspection

CR202505430

NRC Identified Items

71111.13

Procedures

NOBP-

OP001502

Davis-Besse Nuclear Power Station Daily Status Report

CR202505442

PAM Temperature Instruments Not Calibrated within Their

Required Frequency

07/30/2025

CR202505483

Recirculation Flow for HPI 2 out of Band

08/01/2025

CR202505675

Received Unexpected Annunciator ICS Input Mismatch

08/09/2025

71111.15

Corrective Action

Documents

CR202505736

Spiking on SP988 and SP989 for SG1 Level Indication

08/12/2025

CR202505747

LCO 3.3.11 Required Action B3 Not Completed in

Completion time

08/13/2025

CR202505854

NI2 SUR and CPS Reading Erratically

08/17/2025

C-ME-050.03-111

MOV Thrust / Torque Calculation for AF599

C-ME-050.03-112

MOV Thrust / Torque Calculation for AF608

C-ME-050.03-117

Limiting Differential Pressure for AF3870 and AF3872

C-ME-050.03-120

MOV Thrust / Torque Calculation for AF3870

C-ME-050.03-121

MOV Thrust / Torque Calculation for AF3872

C-ME-050.03-122

Differential Pressures for AF599 and AF608

Calculations

C-ME-050.03-130

PPM Analysis for AF3869, AF3970, AF3871, and AF3872

15-00776

50.59 Screening - Switchyard 345kV Breaker Replacement

24-01449

50.59 Screening - Calculation C-ME-050.03-112, 111 & 112

71111.21M

Miscellaneous

24-01590

50.50 Screening - Calculation C-ME-050.03-117, 120, 121,

130

CR20255363

Small Oil Puddle Found In Front of SAC 2

07/28/2025

CR20255532

Station Air Compressor 2 Tripped

08/04/2025

CR20255535

SV676 SAC 2 LP Intercooler Moisture Separator Drain

Solenoid Valve Clogged with Sediment

08/04/2025

Corrective Action

Documents

CR20255566

Debris in SAC 2 Intercooler and Aftercooler Condensate

Drain Bowls

08/05/2025

DbOP06251

Station and Instrument Air System Operating Procedure

DBPF09301

Preventive Maintenance for Type SMB and SB Limitorque

Operators

DBPF09302

Testing Motor Operated Valves

DBPF09302

Testing Motor Operated Valves

DBSC03070

Emergency Diesel Generator 1 Monthly Test

DBSP03151

AFP 1 Quarterly Test

DBSP03218

HPI Train 1 Pump and Valve Test

DBSP03446

Decay Heat Train 1 Pump and Valve Test

DBSS03091

Motor-Driven Feed Pump Quarterly Test

DBSS04202

Emergency Feedwater Pump Monthly Test

Procedures

NOP-WM4004

Foreign Material Exclusion

200811203

PM 10919 MVHP2 Diagnostic Static Test

09/10/2025

200898569

PM2041 Clean/Inspect MDP Coolers

09/17/2025

71111.24

Work Orders

200922321

Test Motor Operated Valve

07/08/2025

200926037

P241 Motor-Driven Feed Pump Quarterly Test

09/17/2025

200947502

PM 2070 MVHP32 Insp HPI 1 Recirc

09/10/2025

200977794

Remove and Clean Intercooler/Aftercooler Drain Bowls

08/05/2025

CR202400592

Type B Fuel Shipping Container Not Shipped due to Not

Being Able to be Properly Closed

01/23/2024

CR202401446

Radioactive Material identified During Baseline Survey

2/23/2024

Corrective Action

Documents

CR202500576

LLRWSF Roll Up Door Would Not Close

01/28/2025

Corrective Action

Documents

Resulting from

Inspection

CR202504934

WO 200883155 Cover Page Requires Updating (NRC

71124.08)

07/09/2025

23 Secondary Resin Analysis

03/03/2023

24 Primary Resin, DAW Smears, PDI, SFP, and Duratek

Resin Analysis

01/25/2024

Radioactive Material Transportation Specialist Training

Records

various

Miscellaneous

Material List Grouped by Location

07/08/2025

Davis-Besse PCP

Process Control Program

DBHP01502

Dewatering of Filter Media

DBHP01510

Solid Radioactive Waste Processing and Handling

DBHP01511

Low-Level Radioactive Waste Storage Facility (LLRWSF)

DBHP01712

CFR 61 Sampling for Waste Classification

DBHP06120

Miscellaneous Liquid Waste Demineralizer Skid Operations

DBHP06121

Portable Demineralizer Sluice and Fill Operations

DBMM09226

Nuclear Filter Replacement Using Transfer Cask

DBMM09228

Nuclear Filter Replacement without Using Transfer Cask

NOP-OP4504

Requirements for Radioactive Materials Stored Outdoors

Procedures

NOP-OP5103

Category 1 and 2 Radioactive Material Accountability

23

Secondary Resin Liners

2/27/2023

231001

Filter

11/18/2023

Shipping Records

251001

Primary Resin Liner

06/27/2025

200867808

H3000001 06.000 Licensed Courses Leak Test

11/30/2023

200883155

HP3000001 06.000 Licensed Sources Leak Test

05/30/2024

71124.08

Work Orders

200915104

HP3000001 06.000 Licensed Sources Leak Test

05/20/2025

CR202107917

Trend - Increased makeup Rate to Fire Water Storage Tank

10/20/2021

Corrective Action

Documents

CR202504947

Trending of Jockey Fire Pump Identified Unexplained Step

Change

07/09/2025

71152S

Corrective Action

Documents

Resulting from

Inspection

CR202503529

LR Phase IV NRC Inspection Self-Assessment: Trending of

Jockey Fire Pump Gap

05/08/2025

CR202100920

EDG 2 Speed Switch Failure from 09/04/2020 Past

Operability

2/1/2021

Corrective Action

Documents

CR202105657

21 EDG Reliability Evaluation: Speed Switch Design

Concern for Application in DC System

07/26/2021

CR202200079

NRC Apparent Violation: Failure to Install EDG Speed

Switch That Was Suitable to the Application

CR202206570

NRC 2022 EDG Inspection: Potential Failure Mechanism for

EDG Speed Switches Not Identified for EDG Speed Switch

Failure

09/01/2022

CR202407266

NRC Identified a New Failure Mechanism for Previously

Installed EDG Speed Switches

09/12/2024

Corrective Action

Documents

Resulting from

Inspection

CR-202407935

EDG Speed Switch Evaluation Concludes an Unanalyzed

Condition Existed

10/10/2024

71153

Miscellaneous

LER

21084/2021001

Emergency Diesel Generator Speed Switch Failure due to

Direct Current System Ground

2