IR 05000341/2025003

From kanterella
Jump to navigation Jump to search
Integrated Inspection Report 05000341/2025003
ML25352A054
Person / Time
Site: Fermi 
Issue date: 12/22/2025
From: Sanchez Santiago E
NRC/RGN-III/DORS/RPB2
To: Peter Dietrich
DTE Electric Company
References
IR 2025003
Download: ML25352A054 (0)


Text

SUBJECT:

FERMI POWER PLANT, UNIT 2 - INTEGRATED INSPECTION REPORT 05000341/2025003

Dear Peter Dietrich:

On September 30, 2025, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Fermi Power Plant, Unit 2. On November 20, 2025, the NRC inspectors discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.

Due to the temporary cessation of government operations, which commenced on October 01, 2025, the NRC began operating under its Office of Management and Budget-approved plan for operations during a lapse in appropriations. Consistent with that plan, the NRC operated at reduced staffing levels throughout the duration of the shutdown. However, the NRC continued to perform critical health and safety functions and make progress on other high-priority activities associated with the ADVANCE Act and Executive Order 14300. On November 13, 2025, following the passage of a continuing resolution, the NRC resumed normal operations. However, due to the 43-day lapse in normal operations, the Office of Nuclear Reactor Regulation granted the regional offices an extension on the issuance of the calendar year 2025, third quarter integrated inspection reports normally issued by November 15, 2025, to December 31, 2025. The NRC will resume the routine cycle of issuing inspection reports on a quarterly basis beginning with the calendar year 2025, fourth quarter integrated inspection reports, which will be issued 45 days after the fourth quarter ends on December 31, 2025.

Two findings of very low safety significance (Green) are documented in this report. Two of these findings involved violations of NRC requirements. We are treating these violations as non-cited violations (NCVs) consistent with Section 2.3.2 of the Enforcement Policy.

If you contest the violations or the significance or severity of the violations documented in this inspection report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN:

Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region III; the Director, Office of Enforcement; and the NRC Resident Inspector at Fermi Power Plant, Unit 2.

December 22, 2025 If you disagree with a cross-cutting aspect assignment in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region III; and the NRC Resident Inspector at Fermi Power Plant, Unit 2.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Elba M. Sanchez Santiago, Chief Reactor Projects Branch 2 Division of Operating Reactor Safety Docket No. 05000341 License No. NPF-43 Enclosure:

As stated cc: Distribution via LISTSERV Signed by Sanchez Santiago, Elba on 12/22/25

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Fermi Power Plant, Unit 2, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

Failure to Ensure Acceptance Criteria for Maintenance on Air Compressor Inlet Valves Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000341/202500301 Open/Closed

[P.3] -

Resolution 71111.12 A self-revealed Green finding and associated non-cited violation (NCV) of 10 CFR 50 Appendix B, Criterion V, Instructions, Procedures, and Drawings, occurred when the licensee did not have procedures with appropriate quantitative or qualitative acceptance criteria for determining that important activities have been satisfactorily accomplished.

Specifically, the maintenance procedure for the safety-related air compressors lacked sufficient detail to ensure proper clearances existed in the compressor inlet valves.

Inoperable Division of Control Room Ventilation System due to Incorrect Post-Maintenance Testing Cornerstone Significance Cross-Cutting Aspect Report Section Barrier Integrity Green NCV 05000341/202500302 Open/Closed

[H.4] -

Teamwork 71111.24 A self-revealed Green finding and associated non-cited violation (NCV) of 10 CFR 50 Appendix B, Criterion V, Instruction, Procedures, and Drawings, was identified for the failure to include instructions appropriate to the circumstance for performing post-maintenance testing on the division II control center heating, ventilation, and air conditioning (CCHVAC)system following replacement of a static pressure controller. This resulted in the system being inoperable due to its inability to perform its function in the recirculation mode.

Additional Tracking Items

None.

PLANT STATUS

Unit 2 began the assessment period at or near 100 percent power. On August 10, 2025, a planned downpower to approximately 90 percent was performed to investigate elevated turbine building steam tunnel temperatures. Power was restored to 100 percent on August 13, 2025. On September 26, 2025, a planned downpower to approximately 90 percent was performed for maintenance on the hydraulic controls for a high pressure stop valve. Power was restored to 100 percent the same day.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed activities described in IMC 2515, Appendix D, Plant Status, observed risk significant activities, and completed onsite portions of IPs. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (2 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1) Division II standby gas treatment system (SGTS) while division I in maintenance on August 5, 2025
(2) Electric driven fire pump while diesel driven fire pump in maintenance on September 23, 2025

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (5 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1) Fire zone 7, reactor building first floor control rod drive and railroad bay area, completed during the week ending September 6, 2025
(2) Fire zone 52, emergency diesel generator (EDG) 11 switchgear room, completed during the week ending September 6, 2025
(3) Fire zone 53, EDG 12 switchgear room, completed during the week ending September 6, 2025
(4) Fire zone 50, residual heat removal (RHR) complex division I pump room, completed during the week ending September 27, 2025
(5) Fire zone 54, RHR complex EDG 13 switchgear and switchgear ventilation room, completed during the week ending September 27, 2025

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)

(1) The inspectors observed and evaluated licensed operator performance in the control room and in the field during a planned surveillance of the high pressure coolant injection system, a heightened-risk activity, on August 21, 2025

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) The inspectors observed and evaluated a portion of the annual operating exam in the control room simulator on September 10, 2025

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (2 Samples)

The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components (SSCs) remain capable of performing their intended function:

(1) Core spray system, completed during the week ending August 16, 2025
(2) Non-interruptible air supply system, completed during the week ending September 27, 2025

Quality Control (IP Section 03.02) (1 Sample)

The inspectors evaluated the effectiveness of maintenance and quality control activities to ensure the following SSC remains capable of performing its intended function:

(1) Warehouse A and B walkdowns and qualification test report review of safety-related control relays, completed during the week ending July 19, 2025

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (2 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:

(1) Elevated turbine building steam tunnel temperatures approaching main steam isolation valve isolation setpoint, completed during the week ending August 23, 2025
(2) Troubleshooting associated with a low voltage from reactor protection system motor-generator set 'B' and water leakage into hydraulic oil for high pressure turbine control valve 3, completed during the week ending September 13, 2025

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (3 Samples 1 Partial)

The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:

(1) Smoke from EDG 12 exhaust piping area during a surveillance on July 10, 2025
(2) Reactor building stationary particulate iodine and noble gas (SPING) flow issues, completed during the week ending August 2, 2025
(3) Division II primary containment monitoring system pump repairs, completed during the week ending August 9, 2025 (4)

(Partial)

Review of degraded load tap changer for technical specification transformer 64

71111.18 - Plant Modifications

Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02) (1 Sample)

The inspectors evaluated the following temporary or permanent modifications:

(1) Containment high range radiation monitors modifications, completed during the week ending July 19, 2025

71111.24 - Testing and Maintenance of Equipment Important to Risk

The inspectors evaluated the following testing and maintenance activities to verify system operability and/or functionality:

Post-Maintenance Testing (PMT) (IP Section 03.01) (4 Samples)

(1) Testing and replacement of safety-related air regulators associated with division I of the standby gas treatment system, completed during the week ending August 9, 2025
(2) Replacement of division II control center heating, ventilation, and air conditioning static pressure controller T41K414, completed during the week ending August 30, 2025
(3) Testing the diesel driven fire pump following the drain, clean, inspect of the diesel fire pump fuel oil tank, completed during the week ending September 27, 2025
(4) Division II emergency equipment service water (EESW) motor testing and piping replacement, completed during the last week of September, 2025

Surveillance Testing (IP Section 03.01) (2 Samples)

(1) Review of fire suppression water system flow test, completed during the week ending September 6, 2025
(2) Observation and review of Surveillance Testing for "SLC Pump and Check Valve Operability Test" 24.139.02, completed during the week ending September 27, 2025

71114.02 - Alert and Notification System Testing

Inspection Review (IP Section 02.0102.04) (1 Sample)

(1) The inspectors evaluated the following maintenance and testing of the alert and notification system:
  • Annual siren inspection and maintenance records for the period of August 1, 2024 through July 31, 2025

71114.03 - Emergency Response Organization Staffing and Augmentation System

Inspection Review (IP Section 02.0102.02) (1 Sample)

(1) The inspectors evaluated the readiness of the emergency preparedness organization

71114.05 - Maintenance of Emergency Preparedness

Inspection Review (IP Section 02.01 - 02.11) (1 Sample)

(1) The inspectors evaluated the maintenance of the emergency preparedness program

71114.06 - Drill Evaluation

Required Emergency Preparedness Drill (1 Sample)

(1) Multi-facility drill (emergency operations facility/simulator observed) on July 1,

RADIATION SAFETY

71124.05 - Radiation Monitoring Instrumentation

Walkdowns and Observations (IP Section 03.01) (5 Samples)

The inspectors evaluated the following radiation detection instrumentation during plant walkdowns:

(1) Portable friskers stored ready for use
(2) Portable ion chambers stored ready for use
(3) High range extendable GM dose rate instruments stored available ready for use
(4) Personnel contamination monitors in the drywell entrance and exit building
(5) Tool contamination monitors in the drywell entrance and exit building

Calibration and Testing Program (IP Section 03.02) (10 Samples)

The inspectors evaluated the calibration and testing of the following radiation detection instruments:

(1) Mirion FASTSCAN
(2) Containment area high range radiation monitor division II
(3) Ludlum 12 Frisker serial number 341398 with 4392 alpha probe
(4) MGPI telepole serial number 6618066
(5) Canberra Tennelec alpha/beta counting system detector 3
(6) Gamma spectroscopy system 2 serial number 09079301
(7) Thermo Eberline AMS4 serial number 1058
(8) Ludlum model 93 serial number 343169
(9) MGP DMC2000 serial number 912915
(10) Cronos serial number 1611283 Effluent Monitoring Calibration and Testing Program Sample (IP Section 03.03) (2 Samples)

The inspectors evaluated the calibration and maintenance of the following radioactive effluent monitoring and measurement instrumentation:

(1) Turbine building vent exhaust PRM
(2) Circulating water system decant line rad monitor

71124.08 - Radioactive Solid Waste Processing & Radioactive Material Handling, Storage,

& Transportation

Radioactive Material Storage (IP Section 03.01)

The inspectors evaluated the licensees performance in controlling, labeling and securing the following radioactive materials:

(1) Warehouse G satellite radiologically controlled area

Radioactive Waste System Walkdown (IP Section 03.02) (1 Sample)

The inspectors walked down the following accessible portions of the solid radioactive waste systems and evaluated system configuration and functionality:

(1) Solid radwaste system with RDS1000 portable system connected

Waste Characterization and Classification (IP Section 03.03) (2 Samples)

The inspectors evaluated the following characterization and classification of radioactive waste:

(1) Spent resin liner L24012
(2) Condensate resin

Shipment Preparation (IP Section 03.04) (1 Sample)

(1) The inspectors observed the preparation of radioactive shipment EF225-038 of an 8120B cask containing a spent resin liner on September 10, 2025.

Shipping Records (IP Section 03.05) (3 Samples)

The inspectors evaluated the following non-excepted radioactive material shipments through a record review:

(1) EF224-005, 8120B cask with dewatered powered/bead resin, Type B
(2) EF224-044, AVANTech Skids in SeaLand, LSA-II
(3) EF224-074, 8120B cask with dewatered powered/bead resin, Type B

OTHER ACTIVITIES-BASELINE

===71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:

MS08: Heat Removal Systems (IP Section 02.07)===

(1) July 1, 2024 through June 30, 2025

MS09: Residual Heat Removal Systems (IP Section 02.08) (1 Sample)

(1) July 1, 2024 through June 30, 2025

MS10: Cooling Water Support Systems (IP Section 02.09) (1 Sample)

(1) July 1, 2024 through June 30, 2025

EP01: Drill/Exercise Performance (DEP) Sample (IP Section 02.12) (1 Sample)

(1) October 1, 2024 through June 30, 2025 EP02: Emergency Response Organization (ERO) Drill Participation (IP Section 02.13) (1 Sample)
(1) October 1, 2024 through June 30, 2025 EP04: Emergency Response Facility and Equipment Readiness (ERFER) (IP Section 02.14) (1 Sample)
(1) January 1, 2025 through June 30,

INSPECTION RESULTS

Failure to Ensure Acceptance Criteria for Maintenance on Air Compressor Inlet Valves Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000341/202500301 Open/Closed

[P.3] -

Resolution 71111.12 A self-revealed Green finding and associated non-cited violation (NCV) of 10 CFR 50 Appendix B, Criterion V, Instructions, Procedures, and Drawings, occurred when the licensee did not have procedures with appropriate quantitative or qualitative acceptance criteria for determining that important activities have been satisfactorily accomplished.

Specifically, the maintenance procedure for the safety-related air compressors lacked sufficient detail to ensure proper clearances existed in the compressor inlet valves.

Description:

On May 23, 2025, during a surveillance test of the division II non-interruptible air system (NIAS), a safety-related system, the licensee noted the division II control air compressor was slow to load compared to the division I compressor and prior experience. As a result, the licensee performed the capacity test and found the acceptance criteria were not met. The licensee considered the air compressor nonfunctional and cross-tied division I NIAS to serve division II loads. As a result, several technical specification limiting conditions for operation (LCO) actions were entered for division II NIAS loads, such as the reactor building to torus vacuum breakers (72-hour shutdown action), and the standby gas treatment system and control room heating, ventilation, and air conditioning systems (7day shut down actions).

Troubleshooting revealed binding in the inlet valve was the cause of the reduced capacity.

The inlet valve consists of slots, through which fingers, driven by a yoke, slide thru to open and close the inlet during operation. The license discovered a lack of clearance between the fingers and the slots due to manufacturing imperfections of these cast-components. This caused the fingers to hang up and allowed the valve to remain partially open during compression, allowing air to escape. While some imperfections would not appear to pose a problem on initial fit up, they could cause binding with the fingers over time.

The same type of failure occurred on the division II compressor on February 9, 2023. At the time, the cause was determined to be imperfections that could impede the smooth operation of the fingers. Following the 2023 failure, the replacement valve slots were machined prior to installation to ensure proper operation throughout the slot. Additional corrective actions were to enhance the procurement process and add details to maintenance procedure 35.622.003, Control Air Compressor Maintenance, for inspection and installation of the valves. The valves remained installed until the next planned inspection/replacement period in September of 2024. However, the valves installed during the preventative maintenance activity did not have all of the casting imperfections removed. No direction existed to check for, or ensure, the surface was machined on the entirety of slots. While the procedure had added steps to inspect for and remove (as necessary) slag and other material or imperfections, there was no direction to machine the surfaces to remove all the imperfections. Additionally, a 1/32" clearance requirement from the vendor manual (recognized following the 2023 failure) was not incorporated into the procedure. As a result, binding occurred again, resulting in the failure on May 23, 2025. The NRC became aware of the issue on May 23, 2025, and performed a review of the licensee's corrective actions as part of a maintenance effectiveness sample in the third quarter of 2025. Part of the review included the past operability evaluation for the failed compressor. While degraded, the compressor maintained adequate capacity to fulfill its safety functions given the as-measured leakage in the system was less than assumed in design (amongst other conservative factors assumed in the design used to determine capacity).

Corrective Actions: The licensee replaced the suction valve that was binding and entered the issue into the corrective action program.

Corrective Action References: CR 202547768

Performance Assessment:

Performance Deficiency: The licensee's failure to ensure procedure 35.622.003, Control Air Compressor Maintenance, included appropriate quantitative or qualitative acceptance criteria for determining that important activities have been satisfactorily accomplished, as required by 10 CFR 50 Appendix B, Criterion V, Instructions, Procedures, and Drawings, was a performance deficiency. Specifically, Section 5.5.7 of maintenance procedure 35.622.003 provided direction for inspecting the inlet valves. While steps existed to check for and remove foreign material, slag, and casting imperfections that could result in binding, and to remove such material as necessary, specific tolerances and the need to remove imperfections via machining from the entire surface area of the slots was not provided.

Screening: The inspectors determined the performance deficiency was more-than-minor because it was associated with the Procedure Quality attribute of the Mitigating Systems cornerstone and adversely affected the cornerstone objective to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences. Specifically, multiple TS LCO actions were entered for division II systems such as CCHVAC, SGTS, and the reactor building to torus vacuum breakers. While a review of the technical evaluation supporting past operability determined the control air compressor would have maintained operability of the supported components in its degraded state, reasonable doubt existed for the as-found condition. Multiple examples in IMC 0612 Appendix E support a more-than-minor determination, such as 3.h and 3.i.

Significance: The inspectors assessed the significance of the finding using IMC 0609 Appendix A, The Significance Determination Process (SDP) for Findings At-Power. The finding screened to Green, or very low safety significance, based on the questions in Exhibit 2 of IMC 0609 Appendix A. Specifically, the past operability evaluation demonstrated the air compressor could still fulfill its required safety functions.

Cross-Cutting Aspect: P.3 - Resolution: The organization takes effective corrective actions to address issues in a timely manner commensurate with their safety significance. Specifically, corrective actions from the May 2023 failure were not effective, in that the same failure occurred after preventative maintenance was performed.

Enforcement:

Violation: 10 CFR Part 50, Appendix B, Criterion V, Instructions, Procedures, and Drawings, requires, in part, that procedures shall include appropriate quantitative or qualitative acceptance criteria for determining that important activities have been satisfactorily accomplished. The licensee established procedure 35.622.003, Control Air Compressor Maintenance, Revision 30, as the implementing procedure for maintenance on the safety-related control air compressors.

Contrary to the above, since September 16, 2024, a procedure did not include appropriate quantitative or qualitative acceptance criteria for determining that important activities have been satisfactorily accomplished. Specifically, procedure 35.622.003 did not contain criteria to ensure adequate clearance existed between the valve guides and unloader fingers, which caused binding and degraded capacity on the division 2 control air compressor.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

Inoperable Division of Control Room Ventilation System due to Incorrect Post-Maintenance Testing Cornerstone Significance Cross-Cutting Aspect Report Section Barrier Integrity Green NCV 05000341/202500302 Open/Closed

[H.4] -

Teamwork 71111.24 A self-revealed Green finding and associated non-cited violation (NCV) of 10 CFR 50 Appendix B, Criterion V, Instruction, Procedures, and Drawings, was identified for the failure to include instructions appropriate to the circumstance for performing post-maintenance testing on the division II control center heating, ventilation, and air conditioning (CCHVAC)system following replacement of a static pressure controller. This resulted in the system being inoperable due to its inability to perform its function in the recirculation mode.

Description:

On July 22, 2025, the licensee performed maintenance on the division II CCHVAC system.

One of the planned activities was to replace static pressure controller T41K414, which acts to maintain a positive pressure in the control room (relative to the surroundings outside) while in the recirculation mode of operation. The recirculation mode performs a safety-related function of minimizing radiation doses to control room personnel during design basis events. During the recirculation mode, the normal air intakes are shut, and air is brought in through an emergency filtration train. The controller senses pressure in the control room and sends a signal to modulate the emergency intake modulating dampers and recirculation pressure control dampers to ensure the proper positive pressure is maintained in the control room. The maintenance was completed on July 23, 2025, and the system was returned to service. Later that night, a routine surveillance was performed which placed the system in the recirculation mode of operation. When the system was placed in recirculation mode, control room pressure dropped low out of specification. Instead of modulating to control pressure, the emergency air intake dampers were found closed. Division II of CCHVAC was declared inoperable.

Licensee investigation revealed that the T41K414 controller had been installed in the 'manual' mode of operation. The new controller had been bench-checked in the manual mode prior to installation, and no work order steps existed to place it in the 'auto' mode during the maintenance activity. Had the controller been installed in the 'auto' mode, appropriate pressure control would have occurred. In the weeks leading up to the maintenance, comments had been logged as part of the work order review process stating the post-maintenance testing (PMT) was inappropriate. Specifically, it was noted that the controller should be tested in the recirculation mode. However, the comments were never addressed, as WO 69381742, Replace electrolytic Capacitors in Div II CCHVAC Instruments, only stipulated that the normal mode should be utilized for PMT. In the normal mode, another controller is utilized to control pressure. Assumptions were made during finalization of the work order that the prior controller replacement in 2010 contained the proper PMT (instead of reviewing all of the work order processing comments). The 2010 replacement work order only stipulated using the normal mode for PMT. An issue was not detected then as the controller happened to have been installed in the correct configuration (auto). Therefore, any subsequent testing or operation in the recirculation mode with the prior controller resulted in satisfactory pressure control. The NRC became aware of the issue on July 24, 2025.

Corrective Actions: The licensee changed the controller setting to 'auto' and tested the controller in the recirculation mode satisfactorily.

Corrective Action References: CR202549030

Performance Assessment:

Performance Deficiency: The failure to include instructions appropriate to the circumstance for performing a PMT on the CCHVAC in accordance with 10 CFR 50 Appendix B Criterion V, Instructions, Procedures and Drawings, was a performance deficiency. Additionally, the licensee failed to follow procedure MMA11, Post Maintenance Testing Guidelines, step 3.2.1, which stated a satisfactory PMT is one that ensures the system or component can perform its intended function. Specifically, the licensee failed to include instructions in WO 69381742 to perform a PMT in the recirculation mode (required to demonstrate operability) following replacement of controller T41K414, which resulted in the CCHVAC system being inoperable due to its inability to perform it safety function in the recirculation mode.

Screening: The inspectors determined the performance deficiency was more-than-minor because it was associated with the Procedure Quality attribute of the Barrier Integrity cornerstone and adversely affected the cornerstone objective to provide reasonable assurance that physical design barriers protect the public from radionuclide releases caused by accidents or events. Specifically, the division II CCHVAC system was found to be inoperable in the recirculation mode, whose function is to protect control room operators from the radiological effects of design basis events. The inspectors informed their decision by referencing IMC 0612 Appendix E, Examples of Minor Issues, examples 1.a, 1.b, and 12.d.

Examples 1.a and 1.b refer to issues regarding questionable equipment testing being more-than-minor if it is later determined the equipment was inoperable as a result of the test issues. Example 12.d refers specifically to the barrier integrity cornerstone and states a minor issue would involve no impacts to the function of equipment, while a more-than-minor issue would involve a performance deficiency that impaired the function of one or more channels of instrumentation.

Significance: The inspectors assessed the significance of the finding using IMC 0609 Appendix A, The Significance Determination Process (SDP) for Findings At-Power.

Specifically, utilizing Exhibit 3 for the barrier integrity screening questions, Section 'D' was used as the performance deficiency affected the control room barrier. The finding screened to Green, or very low safety significance, because it only affected the radiological barrier function for the control room, therefore question 1 was answered 'yes.' A review of the circuitry revealed the toxic and smoke barrier functions would not have been impacted.

Cross-Cutting Aspect: H.4 - Teamwork: Individuals and work groups communicate and coordinate their activities within and across organizational boundaries to ensure nuclear safety is maintained. Specifically, during the development of the work order, multiple departments had opportunities to check and/or emphasize that the correct PMT was incorporated.

Enforcement:

Violation: Title 10 CFR Part 50, Appendix B, Criterion V, Instructions, Procedures, and Drawings, requires, in part, that activities affecting quality be prescribed by documented procedures of a type appropriate to the circumstances and be accomplished in accordance with these procedures. The licensee established WO 69381742 as the implementing procedure for performing a post-maintenance test after maintenance on the CCHVAC system, an activity affecting quality.

Contrary to the above, on July 23, 2025, the licensee failed to have a procedure of a type appropriate to the circumstances for the performance of the post-maintenance test following maintenance on the CCHVAC system. Specifically, following replacement of controller T41K414, WO 69381742 did not include instruction for performing a PMT in the recirculation mode of CCHVAC, resulting in an inoperable division II CCHVAC system.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On November 20, 2025, the inspectors presented the integrated inspection results to P. Dietrich, Senior VP and CNO, and other members of the licensee staff.
  • On August 29, 2025, the inspectors presented the emergency preparedness inspection results to P. Dietrich, Senior VP and CNO, and other members of the licensee staff.
  • On September 11, 2025, the inspectors presented the radiation protection inspection results to C. Domingos, Site Vice President, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

M21351

Diagram Fire Protection System

71111.04

Drawings

M5737

Standby Gas Treatment System Functional Operating

Sketch

Corrective Action

Documents

Resulting from

Inspection

CR202550220

DCR request FPRHR150

09/25/2025

FPRB17b

Reactor Building South Control Rod Drive (CRD) and

Railroad Bay Area Zone 7

FPRHR150

RHR Complex, Division I Pump Room, Zone 50, El. 590' 0"

FPRHR252

RHR Complex, EDG11, Switchgear and Switchgear

Ventilation Room Zone 52, EL 617'0"

FPRHR253

RHR Complex, EDG12 Switchgear and Switchgear

Ventilation Room Zone 53, EL 617'0"

71111.05

Procedures

FPRHR254

RHR Complex, EDG13 Switchgear and Switchgear

Ventilation Room, Zone 54, EL 617' 0"

CR202548817

MDCT Fan 'A' Found Inoperable

07/12/2025

CR202548820

Shift 3 CLO for Division I UHS Inoperability

07/13/2025

Corrective Action

Documents

CR202549600

E4100F029 Stroked Open Faster Than IST Limit

08/21/2025

6M7212035

Diagram High Pressure Coolant Injection System (HPCI)

Reactor Building

6M7212043

Diagram High Pressure Coolant Injection System Barometric

CNDR (HPCI) Reactor Building

AJ

Drawings

6M7212045

Diagram Cooling Power Fan Overspeed Protection RHR

Complex

G

EF2PRA005.20

Residual Heat Removal Service Water (RHRSW) System

Information Notebook

Miscellaneous

SSOP9042588

Evaluation Scenario

23.205

Residual Heat Removal System

151

23.601

Instrument Trip Sheets

Procedures

29.100.01

Primary Containment Control

71111.11Q

Work Orders

69500666

24.202.01 HPCI Pump/Flow Test & Vlv Stoke at 1025 PSIG

08/21/2025

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Calculations

DC4931 Vol I

Non-Interruptible Control Air System (NIAS) Calculations

28665

Leaking Valve

09/04/2023

29589

Excess Flow Check Valve Open Indication Lightbulb Socket

Broken

09/04/2023

230060

Procedure Enhancement 24.321.03

09/04/2023

231557

DP Extension for CFD E for Maintenance Activities

09/04/2023

20619

Div II NIAS Pressure Switch Found Outside APT, Calibrated

within ALT

08/14/2023

21395

Div II Dryer Solenoid Buzzing

08/15/2023

CR202330937

Buzzing Solenoid on NIAS Div. II Dryer

06/14/2023

CR202331963

Serveron WIFI Node Issues

07/28/2023

CR202332411

Incomplete Part Number in CECO for E21R001C

08/19/2023

CR202335258

Condensate Filter Demin Pushbutton Collars Need

Replaced

2/24/2023

CR202435455

Received 7D52 Div2 Control Air System Trouble Multiple

Times During Shift

01/09/2024

CR202436996

Incorrect Critical Complete Dates for PM Events 3304,

3304A, 3304B

03/19/2024

CR202438768

SRV Tailpipe Press Switch AsFound UNSAT

04/24/2024

CR202438785

SRV Tailpipe Pressure Switch Failure History

04/24/2024

CR202439089

Revise Documents to Show Abandoned Instruments

05/01/2024

CR202441189

There are no Instrument Spec Sheets (ICSS's) in

Documentum for E21R001A thru D

07/26/2024

CR202441243

E21N006B-S Revision Required

07/30/2024

CR202441493

2D5 Testability Div 2 ECCS Power Failure

08/10/2024

CR202441501

Evaluation of E21K601A/B (Div 1/2 CS DC & AC INVERTER

PWR SPLY) Component Criticality is Needed

08/12/2024

CR202441639

Request Review of PM Frequency for Replacement of 2KVA

Inverters

08/17/2024

71111.12

Corrective Action

Documents

CR202441641

Delay in Replacing E21K601B (Nova Inverter)

08/17/2024

CR202441644

Delay in Executing E21K601B Inverter Replacement PM

May have Contributed to Inverter Failure

08/17/2024

CR202442168

WO Not Scheduled Goes Critical on 9/15/24

09/12/2024

CR202442192

Blown Fuse E41F2B in H21P081 Panel

09/12/2024

CR202442239

Stray Wire Strands at Terminals Found in P50P401B

Terminal Box - NIAS

09/16/2024

CR202442278

Leak Identified During Leak Check on P50F514B

09/17/2024

CR202442300

Poor Fitting Choice Causing Unnecessary Extended LCO

Durations during NIAS System Outage and Challenges to

Plant

09/18/2024

CR202443746

P50F411 H21P420 NIAS Regulator Low in Band but

Acceptable

11/14/2024

CR202444514

Implement Solutions Such as a Different Packing Material or

Work Practice Changes to Prevent Recurring Core Spray

System Packing Leaks on AOVs E2100F006A/B and

E21F026A

2/16/2024

CR202545011

E21N007B (CS PUMPS DISCHARGE PRESS HI ALARM

DIV2 PRESS SW) Found Outside APT during Performance

of WO 64128338

01/14/2025

CR202545473

Div I Core Spray Pump Discharge Flow Loop Spec Sheets

Are Incorrect (E21N003A-SS)

2/25/2025

CR202547227

Close Contactor Failed AsFound Pick up Voltage Testing

04/30/2025

CR202547765

Div-2 Control Air Compressor (CAC) Loading Very Slowly

05/23/2025

CR202548978

WW2532 WO 64696460 (CHECK CALIBRATION OF DIV I

NIAS TO INSTRUMENT RACK H21P440A MAROTTA

REGULATOR) Needs to be Rescheduled due to M&TE

Constraints

07/22/2025

CR202549154

Div I Core Spray Pump Discharge Flow Loop Spec Sheets

Are Still Incorrect After Revision (E21N003A-SS)

07/30/2025

CR202549246

Failed AsFound Pressure for P50F491 CA DIV1 NIAS to

SGT SOLENOID VLVS PRESSURE CONTROL VLV.

Suspect Test Method is the Cause

08/05/2025

CR202549298

AFCC4 on P50F491 (CA DIV1 NIAS TO SGT SOLENOID

VLVS PRESSURE CONTROL VLV) during the Performance

of WO 70297792

08/06/2025

71111.12

Corrective Action

Documents

CR202549303

AFCC 4 P50F431 (CA DIV I NIAS INSTRUMENT RACK

08/06/2025

H21P440A PRESSURE CONTROL VLV) Found out of Spec

Low during the Performance of WO 64696460

CR202549582

Leak Detection Walkdown

08/20/2025

CR202549762

Center Station Air Compressor Failed to Start

08/29/2025

CR202549766

TBCCW from E SAC Outlet Temp Low OOS

08/30/2025

CR202549778

East Station Air Compressor Unleaded, Causing Auto Start

of West Station Air Compressor

09/01/2025

Corrective Action

Documents

Resulting from

Inspection

29590

NRC Identified: Excess Flow Check Valve Open Indication

Light Out

09/04/2023

Engineering

Changes

20009

Remove Testable Function from Check Valve E2100F006A

04/17/2022

Engineering

Evaluations

TEP5025-014

Division II Control Air Compressor Past Operability

Evaluation

1082108

Tyco Electronics Agastat Relay: Performance

Characteristics

B

4890656

EGP Agastat Relays: Performance Characteristics

A

501 529

Model EGP, EML, and ETR Control Relays Test Report

E

501 536

E7000 Series Timing Relay Qualification Test Report

D

IEEE 3231974

IEEE Standard for Qualifying Class 1E Equipment for

Nuclear Power Generating Stations

A

MMM08

Material Shipping Handling and Storage

Miscellaneous

VMB114.1

Vendor Manual, Joy Manufacturing 5" Stroke Oil Free Air

Compressor

B

68328933

Replace RPS Channel 'A2' Reactor Vessel Level 1 & 2

Agastat Relays

07/08/2025

Work Orders

68328942

Replace RPS Channel 'A1' Reactor Vessel Level 1 and 2

07/03/2025

2549808

RPS MG set B Voltage Low Out of Spec

09/02/2025

CR202549373

Rising Steam Tunnel Temperatures Identified

08/09/2025

CR202549379

EQ Impact Assessment for CR202549373: Rising Steam

Tunnel Temperatures Identified

08/10/2025

71111.13

Corrective Action

Documents

CR202549380

Investigation Long Term MTG First Stage Pressure

Modification

08/10/2025

Engineering

Evaluations

TEB2125-024

Justification for Adding Fans in TB2 Steam Tunnel for

Replacement Air Flow

Operations Evolution Order for Adjusting Voltage on RPS B

MG Set

09/05/2025

Miscellaneous

Risk Management Plan for WO 950044299 Bleed and Feed

Oil Swap #3 HPCV

09/04/2025

20.300.RPSB

Loss of RPS B

Procedures

23.601

Instrument Trip Sheets

71111.13

Work Orders

950044240

RPS MG set B Online Voltage Adjustment

09/03/2025

Calculations

DC6447 Volume

I

Auxiliary Power System Analysis

G

CR2024-39536

Transformer 64 Load Tap Changer Not Maintaining Voltage

in Automatic

05/13/2024

CR202548079

EDG 14 Small Oil Leak Causing Exhaust Gas Plumes by

Turbocharger

06/09/2025

CR202548317

Div. I Bus Voltage Low after Starting CWP 4

06/17/2025

CR202548432

Received 3D44 for RB SPING Flow Low

06/22/2025

CR202548621

43.408.001 (Division I Primary Containment Monitoring

System Leakage Test) Exceeded Acceptance Criteria

07/01/2025

CR202548621

43.408.001 (DIV I Primary Containment Monitoring System

Leakage Test) Exceeded Acceptance Criteria

07/01/2025

Corrective Action

Documents

CR202548704

RP SPING Low Flow Failure

07/05/2025

Corrective Action

Documents

Resulting from

Inspection

CR202548791

NRC Identified Leak on EDG 12

07/10/2025

Engineering

Evaluations

EFA-R1421-002

Engineering Functional Analysis: Degraded Voltage

Performance During LOCA Transient in DC6447, Vol I

TRM Volume II

Offsite Dose Calculation Manual

VMC1147.1

Eberline, Model SPING3/SPING4

Miscellaneous

VME81.1

Emergency Diesel Generators [Proprietary-Confidential]

23.320

Balance of Plant Auxiliary Electrical Distribution System

43.408.001

Division I Primary Containment Monitoring System Leakage

Test

71111.15

Procedures

43.408.001

DIV I Primary Containment Monitoring System Leakage Test

MES 28

Leakage Reduction and Primary Containment Leakage Rate

Programs

MES 28

Leakage Reduction and Primary Containment Leakage Rate

Programs

EDP 70198.004 /

I218302

Gas Monitor Assembly

C

Drawings

I216104

System Diagram-Process Radiation Monitoring

50365779

Implement EDP 70198

01/04/2023

256293

Perform 66.000.409 CCHVAC Emergency Air South Inlet

Radiation Monitor Division I Cal-License Renewal

01/07/2022

71111.18

Work Orders

67447555

Division I Control Center Emergency Air (CCEA) South

Radiation Monitor Fails Calibration

08/04/2023

Calculations

DC5713

Hydraulic Evaluation of the Upgraded Fire Distribution Loop

Calibration

Records

T46N013A-SS

Standby Gas Treatment (SGT) Exhaust Fan T4600C001

Division I

F

CR202545358

Revise 28.50404 Underground Flow Test Procedure

01/30/2025

CR202549030

Div II CCHVAC Failed to Modulate MCR Pressure during

24.413.03

07/24/2025

CR202549094

Requesting a WO to Change T41K414 Controller

Programming

07/28/2025

CR202549214

Equipment Cause Evaluation Product for CR202548573

Failed the FBP66 EQRT Review

08/01/2025

CR202549264

Failed AsFound Pressure for P50F491 CA Division I NIAS

to SGT Solenoid Valves Pressure Control Valve Suspect

Test Method is the Cause

08/05/2025

CR202549304

Request Revision to 46.000.119 Marotta Pressure Regulator

Bench Test to Clarify Bench Testing Requirements

08/06/2025

CR202549370

Ops Shift 3 CLO Div 2 CCHVAC Failed to Modulate MCR

Pressure During 24.413.03

06/08/2025

Corrective Action

Documents

CR202550028

EESW Motor Has UNSAT PI Readings P4500C002B

09/15/2025

5I7212612-80

Connection Diagram Auto Temp Control System for Control

Center - Reactor Bldg. Pneumatic Piping PNL H21P296B

L

5I7212612-B1

Auto Temp Control System for Control Center Reactor Bldg.

Pneu Piping Conn. Dia. PNL-H21P296B

G

71111.24

Drawings

5I7212613-62

Auto Temp Control System L/D for Static Pressure Cont.

Control Room Panel H21P296B

P

5I7212615-06

Control Diagram - Ventilation System for Control Center

Reactor Bldg. H21P296A and P296B

P

5I7212615-7

Control Diagram - Ventilation System for Control Center -

Reactor Bldg. H21P296A, P296B, P296E, and P296G-F

CI

6I7212611-13

Schematic Diagram Rx Bldg. Main Control Room A/C Mode

Selection Div II

Y

6I7212611-52

Reactor Building Main Control Room A/C Isolation Dampers

Div II

CI

6I7212868-41

Wiring Diagram Fire Detection System Panel H11P916B1 &

PNL H11F916B2

L

6I7212868-45

Wiring Diagram Fire Detection System Reactor Building 2nd

Floor (Zone 10)

E

6M7212082

Diagram Standby Liquid Control System

6M7215733-1

Fire Protection Functional Operating Sketch

6M7215736-3

Control Center A/C Air System Functional Operating Sketch

K

M57303

Non-interruptible Control Air System Division I and II

Functional Operating Sketch

AL

Engineering

Evaluations

FPEE250003

Evaluation of the Fire Protection Underground Water Supply

Criteria

700051

T41K414 CCHVAC Static Pressure Controller

DBD-T4600

Standby Gas Treatment System

Purchase Order

Change

Purchase Order 4701895450

06/11/2025

Miscellaneous

TER1425-026

EESW Div 2 Motor Did Not Meet Acceptance Criteria during

PDMA Testing

24.139.02

SLC Pump and Check Valve Operability Test

28.504.06

Fire Suppression Water System - Flush

46.000.119

Marotta Pressure Regulator Bench Test

Procedures

ARP 16D27

Fire Alarm

64696460

Check Calibration of Division I NIAS to Instrument Rack

H21P440A Marotta Regulator

08/05/2025

67328194

License Renewal-Drain, Flush, Refill Diesel Fire Pump Fuel

Oil Tank

09/22/2025

Work Orders

205300

PDMA Testing (Motor Tagged) of P4500C002B

08/29/2025

293649

Perform 24.139.02 SLC Pump and Check Valve Operability

Test

04/15/2025

69073584

Perform 24.139.02 SLC Pump and Check Valve Operability

Test

06/29/2025

69381742

Replace Electrolytic Capacitors in Div II CCHVAC

Instruments

07/21/2025

69948343

Perform 24.139.02 SLC Pump and Valve Operability Test

09/25/2025

297792

Check Calibration of Division I NIAS to SGTS Solenoid

Valves Marotta Regulator

08/05/2025

70420752

Replace Thin Section of P4400 Piping Near P4500F205B

09/09/2025

70420752

Replace Thin Section of P4400 Piping Near P4500F205B

09/09/2025

249085

Perform 28.504.04 Fire Suppression Water System

Functional Flow Test - License Renewal

06/30/2025

71111.24

Work Orders

950030525

Reperform the PMT Steps of WO 69381742

07/24/2025

Calculations

N/A

Fermi 2 Alert and Notification System Design Report

71114.02

Miscellaneous

N/A

Current RTU Status Report

August 1,

24 through

July 31,

25

Calculations

N/A

DTE Energy Fermi Unit 2 Power Plant OnShift Staffing

Analysis Report

2/20/2012

Corrective Action

Documents

CR202545441

JIC Team Member Failed to Respond to the ECOS Weekly

Call-Out as Required

2/04/2025

71114.03

Miscellaneous

EP570

ECOS Test Review

10/07/2024

through

08/19/2025

Calculations

KLD TR-251496

Fermi 2 Nuclear Power Plant 2025 Population Update

Analysis

08/12/2025

241002

Nuclear Quality Assurance Audit of the Radiological

Emergency Preparedness Plan Program

09/26/2024

250105

Nuclear Quality Assurance Audit of the Radiological

Emergency Preparedness Plan Program

08/04/2025

71114.05

Miscellaneous

N/A

MOU/LOA with Corewell Health; Frenchtown Fire

Department; Monroe Community Ambulance; Monroe

County Community College; Ontario, Michigan & DTE;

Pro-Medica Monroe Regional Hospital; et al.

Various

CR202548374

TSC HVAC Not Operating as Expected

06/19/2025

CR202548794

TSC HVAC System Startup Failures

07/11/2025

Corrective Action

Documents

CR202548805

During the July 1 RERP Drill, the Technical Support Center

(TSC) Did Not Meet the Timeliness Requirement for the First

Follow-up Notification Following the Announcement of a

Radiological Release at 0915, EP290 Section 7.1

07/11/2025

Shift Manager Daily Alignment Meeting Notes

07/24/2025

Blue Team Drill Guide (Green Controllers) for July 1, 2025

Drill

07/01/2025

Miscellaneous

RERP Plan

Radiological Emergency Response Preparedness Plan

EP101

Classification of Emergencies

71114.06

Procedures

EP580

Equipment Important to Emergency Response (EITER)

11.1

AMS4 Serial

Number 1058

AMS4 Calibration Form

07/22/2025

OPS3725

Calibration of the Mirion FASTSCAN' WBC System

2/11/2024

Serial No. 341398

Ludlum 12 Frisker with 4392 Alpha Probe Calibration

08/06/2025

Calibration

Records

Serial No.

6618066

Telepole Calibration Form

05/01/2025

Miscellaneous

NPRP250012

Evaluation of Impact of Current Radionuclide Mix on RP

Instruments

03/25/2025

65.000.156

Radiological Instrumentation Source Checking

66.000.205

Calibration of Portable Ion Chamber Survey Instruments

8A

66.000.220

Calibration of the Radiation Protection/Chemistry Gamma

Spectroscopy System

66.000.248

Calibration of Self Reading Dosimeters

66.000.251

Calibration of the MGPI Telepole Instrument

66.000.253

Calibration of the Canberra Tennelec

Procedures

66.000.255

Calibration of the Canberra Cronos Series Monitor

Self-Assessments 0801.26

NRC 71124.05 Self-Assessment Report-Radiation

Monitoring Instrumentation

2/23/2023

60495674

Perform 64.120.041 Containment Area High Range

Radiation Monitor Div 2 Elec Cal

2/27/2024

71124.05

Work Orders

63858492

Perform 64.080.110 Circ Water System Decant Line Rad

Monitor Calibration

05/03/2023

66524470

Perform 64.120.041 Containment Area High Range

Radiation Monitor Div 2 Rad Cal

04/17/2024

71124.05

Work Orders

67337384

Perform 64.080.214 Turbine Bldg Vent Exhaust PRM SYS

Calibration

06/26/2024

CR202436255

Incoming Radioactive Material Shipment exceeds

Department of Transportation (DOT) Regulations

2/13/2024

CR202440048

Radwaste Decon and Radwaste Operators Running Out of

Room to Store Water

06/04/2024

CR202546785

RP Question on Shipping Requirements during Emergencies

04/09/2025

CR202548591

Sources Incorrectly Input Into Sentinel as, Leak Test

Required

06/30/2025

Corrective Action

Documents

CR202548643

OSSF Liner is Near Full Capacity

07/02/2025

Corrective Action

Documents

Resulting from

Inspection

CR202549943

The Waste Stream Analysis Report for NPRP 250027

Showed Abnormal Comparisons between the Independent

Lab and In-house Sample Results

09/10/2025

Sealed Source Inventory

08/20/2025

NPRP230048

Att. 1

CFR Part 61 Waste Stream Sample Screening and

Evaluation for Condensate Resin

06/13/2023

Miscellaneous

NPRP250020

Att. 4

CFR Part 61 Waste Stream Sample Screening and

Evaluation for liner L24012 Batch 1

05/13/2025

65.000.519

Radioactive Material Receipt/Source Control

67.000.103

Survey of Outgoing Radioactive Material Shipments

67.000.505

Survey and Movement of Waste Liners in the OSSF

Procedures

MRP15

Controlling Radioactive Material Outside the Plant

Radiologically Controlled Area (RCA)

Radiation

Surveys

P-M202408029

Liner L24012

08/02/2024

Audit 240106

Nuclear Quality Assurance Audit of the Radiation Protection,

Radiological Effluents Monitoring, And Radioactive Material,

Transfer & Disposal Programs

08/15/2024

71124.08

Self-Assessments

NPRP240041

Quick Hit Self-Assessment (QHSA): Radioactive Solid

Waste Processing, and Radioactive Material Handling,

Storage and Transportation: 71124.08

07/05/2024

EF224-005

20B Cask with Dewatered Powered/Bead Resin, Type B

03/20/2024

EF224-044

AVANTech Skids in SeaLand, LSA-II

08/08/2024

71124.08

Shipping Records

EF224-074

20B Cask with Dewatered Powered/Bead Resin, Type B

11/07/2024

71151

Corrective Action

Documents

CR202548374

TSC HVAC Not Operating as Expected

06/19/2025

Fermi 2 - RHR Performance Indicators

Various

Fermi 2 - RCIC Performance Indicators

Various

MSPI Derivation Report - Cooling Water System

Unavailability Index

08/07/2025

MSPI Derivation Report - Residual Heat Removal System

Unavailability Index

08/07/2025

MSPI Derivation Report - Heat Removal System

Unavailability Index

08/07/2025

MSPI Derivation Report - Cooling Water System Unreliability

Index

08/07/2025

MSPI Derivation Report - Heat Removal System Unreliability

Index

08/07/2025

MSPI Derivation Report - Residual Heat Removal System

Unreliability Index

08/07/2025

Narrative Logs: July 1, 2024 through June 30, 2025

Various

71151

Miscellaneous

EP540015

Emergency Preparedness Performance Indicator Results

10/01/2024 -

03/31/2025