IR 05000341/2024004

From kanterella
Jump to navigation Jump to search
Integrated Inspection Report 05000341/2024004
ML25029A079
Person / Time
Site: Fermi 
Issue date: 01/29/2025
From: Sanchez-Santiago E
NRC/RGN-III/DORS/RPB2
To: Peter Dietrich
DTE Electric Company
References
IR 2024004
Download: ML25029A079 (1)


Text

SUBJECT:

FERMI POWER PLANT, UNIT 2 - INTEGRATED INSPECTION REPORT 05000341/2024004

Dear Peter Dietrich:

On December 31, 2024, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Fermi Power Plant, Unit 2. On January 13, 2025, the NRC inspectors discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.

One finding of very low safety significance (Green) is documented in this report. This finding involved a violation of NRC requirements. We are treating this violation as a non-cited violation (NCV) consistent with Section 2.3.2 of the Enforcement Policy.

If you contest the violation or the significance or severity of the violation documented in this inspection report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region III; the Director, Office of Enforcement; and the NRC Resident Inspector at Fermi Power Plant, Unit 2.

If you disagree with a cross-cutting aspect assignment in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region III; and the NRC Resident Inspector at Fermi Power Plant, Unit 2.

January 29, 2025 This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Elba M. Sanchez Santiago, Chief Reactor Projects Branch 2 Division of Operating Reactor Safety Docket No. 05000341 License No. NPF-43

Enclosure:

As stated

Inspection Report

Docket Number:

05000341

License Number:

NPF-43

Report Number:

05000341/2024004

Enterprise Identifier:

I2024004-0059

Licensee:

DTE Electric Company

Facility:

Fermi Power Plant, Unit 2

Location:

Newport, MI

Inspection Dates:

October 01, 2024 to December 31, 2024

Inspectors:

J. Cassidy, Senior Health Physicist

J. Gewargis, Resident Inspector

J. Kutlesa, Senior Emergency Preparedness Inspector

T. Taylor, Senior Resident Inspector

Approved By:

Elba M. Sanchez Santiago, Chief

Reactor Projects Branch 2

Division of Operating Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Fermi Power Plant, Unit 2, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

Failure to Establish Required Firewatch with Reactor Building Southwest Quadrant Fire Detectors Nonfunctional Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000341/202400401 Open/Closed

[H.5] - Work Management 71111.05 A self-revealed Green Finding and associated Non-Cited Violation (NCV) of Fermi License Condition 2.C.(9) was identified during performance of surveillance 28.505.03, Fire Detection Zone 3 Operability Test RB BMT and SBMT SW Quad, for nonfunctional fire detectors in a reactor building fire zone. Specifically, two of four early warning, notification only, fire detectors in the reactor building southwest quadrant, fire zone 3, were deenergized and nonfunctional without the appropriate hourly fire watch established in accordance with the sites fire protection program.

Additional Tracking Items

Type Issue Number Title Report Section Status LER 05000341/2023003-00 LER 2023003-00 for Fermi 2 Power Plant, Reactor Pressure Boundary Leakage at Socket Weld on Reactor Recirculation Sample Line Caused by Fatigue Failure 71153 Closed LER 05000341/2024001-00 LER 2024001-00 for Fermi 2 Power Plant, Automatic RPS SCRAM on High RPV Pressure While Attempting to Lower Generator Output During RF22 71153 Closed LER 05000341/2023001-00 LER 2023001-00 for Fermi,

Unit 2, Loss of Mechanical Draft Cooling Tower Fan Brakes during High Speeds Leads to Loss of Safety Function and Inoperability,

Revision 0 71153 Closed

LER 05000341/2023001-01 LER 2023001-01 for Fermi 2 Power Plant, Loss of Mechanical Draft Cooling Tower Fan Brakes during High Speeds Leads to Loss of Safety Function and Inoperability, Revision 1 71153 Closed LER 05000341/2023002-00 LER 2023002-00 for Fermi 2 Power Plant, Technical Specification Completion Time Exceeded Due to Repairs on the Mechanical Draft Cooling Tower (MDCT)

Fan D 71153 Closed

PLANT STATUS

Unit 2 began the inspection period at or near rated thermal power. On October 4, 2024, power was reduced to approximately 75 percent for routine rod pattern adjustments and surveillances.

Power was restored to 100 percent on October 6, 2024. The plant remained at or near rated thermal power for the remainder of the inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed activities described in IMC 2515, Appendix D, Plant Status, observed risk significant activities, and completed onsite portions of IPs. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.01 - Adverse Weather Protection

Seasonal Extreme Weather Sample (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated readiness for seasonal extreme weather conditions prior to the onset of seasonal cold temperatures for the following systems:

General service water, emergency diesel generators (EDGs), and condensate system, completed the week ending December 14, 2024

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (1 Sample)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1) EDG 12 during maintenance on EDG 14 completed the week of October 19, 2024

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (1 Sample)

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1) Zone 3, reactor building basement and subbasement southwest quad on December 11, 2024

71111.06 - Flood Protection Measures

Flooding Sample (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated internal flooding mitigation protections in the torus room, reactor building quadrant subbasements, and the high pressure coolant injection (HPCI) room on December 11, 2024

71111.11A - Licensed Operator Requalification Program and Licensed Operator Performance

Requalification Examination Results (IP Section 03.03) (1 Sample)

(1) The inspectors reviewed and evaluated the licensed operator examination failure rates for the requalification annual operating exam administered from October 21, 2024, to November 22, 2024

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (2 Samples)

(1) The inspectors observed and evaluated licensed operator performance in the control room during down power on October 4, 2024
(2) The inspectors observed and evaluated licensed operator performance in the control room during reactor core isolation cooling (RCIC) system testing on November 8, 2024

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) The inspectors observed and evaluated a portion of the annual licensed operator requalification exam simulator scenarios

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (2 Samples)

The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components remain capable of performing their intended function:

(1) Standby feedwater system, completed the week ending November 2, 2024
(2) Residual heat removal service water (RHRSW) system, completed the week ending November 16, 2024

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (4 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:

(1) Failure, troubleshooting, and repair of battery charger 2A2, completed the week ending October 26, 2024
(2) Repair of an oil leak from the 'B' reactor recirculation motor-generator set oil system, completed the week ending November 1, 2024
(3) Coordination of work involving a reactor building steam tunnel entry, a HPCI maintenance outage, and emergent work on an electrical connection associated with division 2 of reactor pressure system (RPS), completed the week ending November 23, 2024
(4) Failure of low pressure coolant injection loop select circuitry due to degraded relay contacts, completed the week ending December 14, 2024

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (6 Samples)

The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:

(1) Control complex heating ventilation and air conditioning (CCHVAC) leakage past operability/inoperability, completed the week ending October 12, 2024
(2) Calculation error regarding density of emergency equipment service water (EESW)piping supports P454630-G01 and P453352-G22, completed the week ending November 16, 2024
(3) Review of missed oil and coolant samples for station blackout generator CTG111, completed the week ending December 14, 2024
(4) Past operability of battery charger 2A2 following discovery of phase imbalance during maintenance, completed the week ending December 14, 2024
(5) RHRSW pump 'B' approaching required action high range on December 9, 2024
(6) Review of circumstances regarding environmental qualification of 'A' and 'C' RHR pump motors described in CR202444589, completed the week ending December 28, 2024

71111.24 - Testing and Maintenance of Equipment Important to Risk

The inspectors evaluated the following testing and maintenance activities to verify system operability and/or functionality:

Post-Maintenance Testing (PMT) (IP Section 03.01) (6 Samples)

(1) Division I CCHVAC high vibrations and dampener installation, completed the week ending November 1, 2024
(2) EDG 14 following a planned maintenance outage, completed the week ending November 16, 2024
(3) HPCI system following a maintenance outage completed the week ending November 16, 2024
(4) Alternate electrical protection assembly (EPA) breaker repair and PMT, completed the week ending December 6, 2024
(5) Division I ultimate heat sink inspection and bolt replacement for EESW and RHRSW pumps on December 11, 2024
(6) Division I CCHVAC emergency inlet air radiation (CCEA) monitor RM1000 engineering change, completed the week ending December 31, 2024

Surveillance Testing (IP Section 03.01) (2 Samples)

(1) Testing criteria for E4150F067, high pressure coolant injection pump steam admission valve, completed the week ending November 1, 2024
(2) EDG 11 fast start, completed the week ending November 8, 2024

Diverse and Flexible Coping Strategies (FLEX) Testing (IP Section 03.02) (1 Sample)

(1) Diesel full load test and Neptune/Dominator full load test surveillance review on December 11, 2024

71114.04 - Emergency Action Level and Emergency Plan Changes

Inspection Review (IP Section 02.0102.03) (1 Sample)

(1) The inspectors evaluated the following submitted Emergency Action Level and Emergency Plan changes.
  • RERP Plan Fermi 2 Radiological Emergency Response Preparedness Plan, Rev 49
  • RERP Plan Fermi 2 Radiological Emergency Response Preparedness Plan, Rev 50
  • RERP Plan Fermi 2 Radiological Emergency Response Preparedness Plan, Rev 51 This evaluation does not constitute NRC approval.

71114.06 - Drill Evaluation

Additional Drill and/or Training Evolution (1 Sample)

The inspectors evaluated:

(1) Tabletop drill conducted in the emergency operations facility on October 8,

OTHER ACTIVITIES

BASELINE

===71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:

BI01: Reactor Coolant System (RCS) Specific Activity Sample (IP Section 02.10)===

(1) September 1, 2023 through September 30, 2024

OR01: Occupational Exposure Control Effectiveness Sample (IP Section 02.15) (1 Sample)

(1) September 1, 2023 through September 30, 2024 PR01: Radiological Effluent Technical Specifications/Offsite Dose Calculation Manual Radiological Effluent Occurrences (RETS/ODCM) Radiological Effluent Occurrences Sample (IP Section 02.16) (1 Sample)
(1) September 1, 2023 through September 30, 2024

71152S - Semiannual Trend Problem Identification and Resolution Semiannual Trend Review (Section 03.02)

(1) The inspectors reviewed the licensees corrective action program to identify potential trends that might be indicative of a more significant safety issue.

71153 - Follow Up of Events and Notices of Enforcement Discretion Event Report (IP Section 03.02)

The inspectors evaluated the following licensees event reporting determinations to ensure it complied with reporting requirements.

(1) LER 2023001-00, and LER 2023001-01, Loss of Mechanical Draft Cooling Tower Fan Brakes during High Speeds Leads to Loss of Safety Function and Inoperability (ADAMS Accession Nos. ML23142A189; ML23177A043). The inspection conclusions associated with this LER are documented in Inspection Report 05000341/2023003 under Inspection Results Section 71152A, NCV 05000341/202300302. This LER is Closed.
(2) LER 2023002-00, Technical Specification Completion Time Exceeded Due to Repairs on the MDCT Fan D (ADAMS Accession No. ML23258A067)

The inspection conclusions associated with this LER are documented in Inspection Report 05000341/2023004 under Inspection Results Section 71152A, NCV 05000341/202300403. This LER is Closed.

(3) LER 2023003-00, Reactor Pressure Boundary Leakage at Socket Weld on Reactor Recirculation Sample Line Caused by Fatigue Failure (ADAMS Accession No. ML24031A549).

The inspection conclusions associated with this LER are documented in Inspection Report 05000341/2023004 under Inspection Results Section 71152A, NCV 05000341/202300404. This LER is Closed.

(4) LER 2024001-00, Automatic RPS SCRAM on High RPV Pressure While Attempting to Lower Generator Output During RF22 (ADAMS Accession No. ML24136A211).

The inspection conclusions associated with this LER are documented in Inspection Report 05000341/2024003 under Inspection Results Section 71152A, FIN 05000341/202400304. This LER is Closed.

INSPECTION RESULTS

Failure to Establish Required Firewatch with Reactor Building Southwest Quadrant Fire Detectors Nonfunctional Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000341/202400401 Open/Closed

[H.5] - Work Management 71111.05 A self-revealed Green Finding and associated Non-Cited Violation (NCV) of Fermi License Condition 2.C.(9) was identified during performance of surveillance 28.505.03, Fire Detection Zone 3 Operability Test RB BMT and SBMT SW Quad, for nonfunctional fire detectors in a reactor building fire zone. Specifically, two of four early warning, notification only, fire detectors in the reactor building southwest quadrant, fire zone 3, were deenergized and nonfunctional without the appropriate hourly fire watch established in accordance with the sites fire protection program.

Description:

The southwest reactor building quadrant basement and subbasement contains important to safety equipment that is relied upon to achieve safe shutdown during potential fire scenarios in the reactor building. This includes the Division II RHR pumps. The reactor building southwest quadrant, fire detection zone 3, is equipped with four early warning, notification only, ionization fire detectors, to warn the main control room of potential fire in that quadrant so that field operators can quickly be deployed, and the fire can be suppressed via manual firefighting means before significant damage can occur in the reactor building. There are two detectors in the basement, detectors C and D, and two detectors in the subbasement, detectors A and B. Detectors A and C are powered from one independent circuit and detectors B and D are powered from a different independent circuit.

During the Division II RHR pump motor replacement activities in RF22, the most recent refueling outage, interference removal work governed by three separate work orders (WO)was performed on equipment in the southwest quadrant that needed to be removed from service and relocated so that there would be enough physical clearance to facilitate the installation of the new pump motors. This interference removal work included removing from service all the ionization detectors in the southwest quadrant. During completion of these three WOs, the work groups deferred restoration of all four ionization detectors to the work order that was completed last. However, the WO that was completed last did not have the necessary steps to restore all four detectors. The last work order only had steps to restore the B and D ionization detectors. Upon completion of the last WO, detectors A and C were left deenergized and nonfunctional. This degraded condition was discovered on September 19, 2024, when the Instrumentation and Controls (I&C) department was performing surveillance 28.505.03, Fire Detection Zone 3 Operability Test RB BMT and SBMT SW Quad.

Technical Requirements Manual Limiting Condition for Operation (TRLCO) 3.12.1 Condition B requires that an hourly fire watch be established to inspect the affected zone(s) if one or more zones with less than or equal to one-half of the total number of instruments shown in Table 3.12.11 for Function A are functional. Technical Requirements Manual (TRM)

Table 3.12.11 shows 4 ionization instruments in that zone for Function A. The requirement to comply with the TRM action statements and implement a fire watch in response to the degraded condition was required to be in effect from when the site was relying on Division II RHR for shutdown cooling, beginning on May 3, 2024, until the degraded condition was discovered and corrected on September 19, 2024.

Corrective Actions: After discovering the degraded condition on September 19, 2024, the site implemented an hourly fire watch in accordance with the TRM, entered an associated fire impairment, and documented the condition in their corrective action program under CR202442326.

Corrective Action References: CR202442326

Performance Assessment:

Performance Deficiency: The licensee failed to follow TRM Section 3.12.1, from May 3, 2024, to September 19, 2024, which requires the site to establish an hourly fire watch when less than or equal to one-half of early warning, notification only, ionization detectors, in fire detection zone 3, the reactor building southwest quadrant basement and subbasement, are functional.

Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the Protection Against External Factors attribute of the Mitigating Systems cornerstone and adversely affected the cornerstone objective to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences. Specifically, with two of the four ionization detectors being left nonfunctional, and no required hourly fire watch being established, the capability of the southwest quadrant important to safety equipment to perform their fire safe shutdown function was adversely impacted.

Significance: The inspectors assessed the significance of the finding using IMC 0609 Appendix F, Fire Protection and Post - Fire Safe Shutdown SDP. Specifically, the fire finding category for this performance deficiency was Fixed Fire Protection Systems, which led the inspectors to answer step 1.3 as "high" because more than 10 percent of detectors in the affected fire zone were nonfunctional. Next, the inspectors conservatively answered step 1.4 as no and moved on to step 1.5. In step 1.5, the inspectors determined the finding screened to Green based on the NRC regional Senior Risk Analysts review of the licensees fire PRA and their analysis for the nonfunctional fire detectors. Specifically, the associated change in core damage frequency was below the Green threshold of 1E6 per year.

Cross-Cutting Aspect: H.5 - Work Management: The organization implements a process of planning, controlling, and executing work activities such that nuclear safety is the overriding priority. The work process includes the identification and management of risk commensurate to the work and the need for coordination with different groups or job activities. Specifically, the work group implementing the three job activities deferred the fire detector restoration to a work order without the appropriate restoration steps and thus failed to adequately coordinate.

Enforcement:

Violation: Fermi Operating License Condition 2.C.(9) states, in part, the licensee, shall implement and maintain in effect all provisions of the approved fire protection program as described in its Final Safety Analysis Report.

Updated Final Safety Analysis Report (UFSAR) Section 9A describes, in part, the sites fire protection program. UFSAR Section 9A.6, Fire Protection Conditions for Operation states, The Fire Protection Conditions for Operation portion of Appendix 9A is in the TRM.

TRM Section 3.12 "Fire Protection" Subsection 3.12.1 Fire Detection Instrumentation limiting condition of operation (TRLCO) 3.12.1 states, in part, The fire detection instrumentation for each fire detection zone shown in Table TR3.12.11 shall be operable.

Table TR3.12.11 line item 1.c, SW corner rooms RHR pump, identifies the four early warning, notification only, fire detection ionization detectors of fire detection zone 3, the southwest quadrant basement and subbasement of the reactor building, to be governed under Section 3.12.1.

TRLCO 3.12.1 Condition B states, in part, that if the following condition exists, one or more zones with less than or equal to one-half of the total number of instruments shown in Table 3.12.11 for Function A, then perform the required action B.1, establish an hourly fire watch patrol to inspect the zone(s).

Contrary to the above, from May 3, 2024, to September 19, 2024, the licensee failed to implement and maintain in effect all provisions of the approved fire protection program as described in the UFSAR. Specifically, the licensee failed to implement an hourly fire watch for fire detection zone 3, the reactor building southwest quadrant, basement and subbasement, when two of the four early warning, notification only, ionization detectors were left deenergized and nonfunctional after the failure to restore the detectors following maintenance activities during RF22.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On January 13, 2025, the inspectors presented the integrated inspection results to Peter Dietrich and other members of the licensee staff.
  • On December 20, 2024, the inspectors presented the emergency action level and emergency plan changes inspection results to A. Mann, Emergency Preparedness Manager and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

CR202443880

[NRC Identified] 2023 MWC16100 Enclosure F,

Documentation Unavailable

11/21/2024

Corrective Action

Documents

Resulting from

Inspection

CR202444240

NRC Identified - Flooded Pit and Submerged Insulated

Piping at GSW Pump House

2/10/2024

Drawings

6M7212010

Diagram General Service Water System

DF

23.131

General Service Water System

116

71111.01

Procedures

MWC16100

Seasonal Readiness

Operator Outside Rounds Logs

10/13/2024 -

10/18/2024

Miscellaneous

DBD X4103

Residual Heat Removal Complex Heating and Ventilating

System

B

71111.04

Procedures

MMA08

Scaffolding

2.1

Corrective Action

Documents

CR202442326

When Attempting to Perform 28.505.03 Fire Detection Zone

Operability Test RB BMT and SBMT SW Quad Found End

of Line Resistor (91K ohm) on ZIU31A + and - Terminals.

Not Expected

09/19/2024

6I7212868-37

Wiring Diagram Fire Detection System Reactor Building

Basement and Sub-Basement

D

6I7212868-40

Wiring Diagram Fire Detection System Panel H11P916A1

and H11P916A2

L

6I7212868-41

Wiring Diagram Fire Detection System Panel H11916B1

and Panel H11P916B2

L

Drawings

6I7212868-8

Installation Fire Detection System Reactor Building

Basement and Subbasement

C

FPRB-B3b

Reactor Building Basement Southwest Corner Room, Zone

3, EL. 562'0"

71111.05

Fire Plans

FPRB-SB3a

Reactor Building Sub-Basement Southwest Corner Room,

Zone 3, EL. 540'0"

Miscellaneous

VMB112.0

Fire and Smoke Detection Systems Vendor Manual

D

28.505.03

Fire Detection Zone 3 Operability Test RB BMT and SBMT

SW

MES 35

Engineering Support Conduct Manual MES 35: Fire

Protection

MMA20

Maintenance Conduct Manual MMA20: Work Execution and

Closure

Procedures

MWC10

Work Control Conduct Manual MWC10: Work Package

Preparation

70025156

EDP80186C02 RHR Motors - Remove (Online) / Install

(Outage) RB1 SW Hatch

4/22/2024

70935801

RF22 EDP 80186C02 Relocate RHR E1102C002B Pump

Seal Heat Exchanger

04/30/2024

71111.05

Work Orders

709360079

RF22 EDP 80186C02 RHR Motor C002B - Relocate

E113177-G18 Pipe Support

04/22/2024

DC4689 VOL I

Flood Depth in the Torus Room Assuming a Torus Rupture

A

DC5426

High and Moderate Energy Line Break Evaluation

Calculations

DECO04519

Pipe Break Outside Containment High and Moderate Energy

Line Break Evaluation

Drawings

6M7215706-2

Residual Heat Removal Division I Functional Operating

Sketch

EF2PRA012

Internal Flood Analysis Notebook

Engineering

Evaluations

XXX02

Design Basis Document: Design Basis Event Combinations

A

23.702.01

Plant System Leakage Check Procedure

29.100.01 SH 2

Emergency Operating Procedure: Primary Containment

Control Sheet 2

ARP 2D82

Reactor Building Torus Sump Level HiHi/LoLo

ARP 2D83

Reactor Building Leakage to Torus Sump High

71111.06

Procedures

ARP 2D84

Reactor Building Northwest Leakage to Equipment Drain

Sump High

71111.11A

Procedures

ODE3

Operations Department Expectation ODE3:

Communications

2.000.03

Power Operation 25% to 100% to 25%

108

24.206.01

RCIC System Pump and Valve Operability Test

57.000.22

Load Profile Plan: 10/04/2024 Downpower

MOP01

Operations Conduct Manual MOP01: Conduct of Operations

SSOP9042485

LOR Scenario One: 10/23/2024

10/23/2024

71111.11Q

Procedures

SSOP9042490

LOR Scenario Two: 10/23/2024

10/23/2024

CARD 1327286

Broken Fuse Clip Protector for MCC 2PC15A

10/10/2013

CARD 1327290

AFCC 4 "Open" Contactor for N2103F001 has Degraded

Pickup Voltage Above Acceptance Criteria

10/10/2013

CARD 1624781

2016 CDBI QHSA No. 2 Deficiency: Apparent Lack of

Demonstrated Alternate Boron Injection Pump Operation

07/20/2016

CARD 1627995

Low Meggar Readings on MOV Control Circuit

10/07/2016

CARD 2123001

CARD on PMs Not Meeting Critical Dates for RF23

04/05/2021

CARD 2125962

AIM for 24 Month Fuel Cycle PM Project PMO 07/02/2021

07/07/2021

Corrective Action

Documents

CARD 2130613

PMO 7 AIM Action Items

2/02/2024

CR202443340

NRC Identified - Component Criticality on N2000F800

(CNDS CPD Alternate RPV Boron Injection Pump Suction

Valve) is Incorrect

10/30/2024

Corrective Action

Documents

Resulting from

Inspection

CR202443532

NRC Identified-Evaluate Current SBFW Component

Classifications

11/07/2024

6M7215715-3

Standby Feedwater System Functional Operating Sketch

O

Drawings

6M7215715-4

Standby Feedwater Lube Oil System Turbine Building

Functional Operating Sketch

F

23.107.01

Standby Feedwater System

24.107.03

SBFW Pump and Valve Operability and Lineup Verification

Test

Procedures

24.321.05

Dedicate Shutdown Panel H21P623 Operability Test EF2

System Transfer

255091

Perform 24.107.03 Sec 5.3 SBFW Pump "B" Flow Test

2/09/2024

67179602

Perform 24.107.03 Sec 5.3 SBFW Pump "B" Flow Test

05/14/2024

71111.12

Work Orders

67334311

Perform 24.107.03 Sec 5.3 SBFW Pump "B" Flow Test

08/09/2024

Calculations

DC2565

R111 Blast Door 1st Floor Reactor Building

B

71111.13

Corrective Action

Documents

2444120

44.030.279 Fail Due to E11A-K32A Contacts Indicating

Open Instead of Closed (High Risk Surveillance)

2/05/2024

CR202442816

Divisional Battery Charger 2A2 Panel Mounted Ammeter

Failed to Calibrate

10/09/2024

CR202442844

Phasing Balance Acceptance Criteria Unsat for 2A2 Battery

Charger

10/10/2024

CR202442852

Nuclear Oversight - Potential Missed Opportunity to Align

the Station on Risk During Application of MOP05

10/11/2024

CR202442938

DPM Oil Leak on RR MG Set B Lube Oil Pumps

Discharge Header

10/14/2024

Corrective Action

Documents

CR202443083

B3103C001D is Approaching the Vibration Investigative

Limit

10/21/2024

240009.002

RVH 7206 DPN A2 (File B616)

24.0009.001

RVH 7206 DPN A2 (File B616)

6I7212045-20

Internal External Wiring Diagram RPS Trip System 'B' CAB

H11P611 PT. 2

T

6I7212151-02

Schematic Diagram RX Protection System Motor-Generator

Set 'B'

Z

6I7212154-01

Internal and External Wiring Diagram RPS PWR Dist Cable

'A' and 'B' C71P001A and C71P011B

Q

Drawings

6SD7212531-13

Internal Wiring Diagram 130V ESF Battery Chargers

O

240019

Commercial Change Package: Online Leak Repair Near

B3100F056

10/17/2024

Engineering

Changes

DC240009

Replace Reactor Building Steam Tunnel R11 Door Latch

Mechanism with Manual Sliding Pins

Fire Plans

FPRB417b

Reactor Building Recirculation System Motor-Generator

Area, Zone 17, EL 659'0"

ODE20

Protected Equipment

Miscellaneous

Risk Management

Plant

950008820 - Critical Hot Spots on RPS 'B' Trip Cabinet

H11P611

11/15/2024

20.138.01

Recirculation Pump Trip

35.000.242,

UFSAR Analyzed Event Barrier Form

44.030.279

ECCS-Reactor Steam Dome Pressure-RHR Loop Select

Permissive Division 1, Channel Functional Test

71111.13

Procedures

6I7212095-30

Schematic Diagram Nuclear Boiler PRCS Instrumentation A

and B Circuits Testability Modification

L

ARP 3D154

Recirculation System B Circulating Lube Oil Pump Auto

ARP 3D155

Recirculation System B Emergency Lube Oil Pump Auto

Start

EF2PRA011

Internal Flood Walkdown Summary Notebook

MMR Appendix H

Online Core Damage Risk Management Guidelines

MMR12

Equipment out of Service Risk Management

20A

MOP05100

Protected Equipment

2C

ODE2

PRS B Hotspot Repair

950008210

Install Temp Mod 240019

10/17/2024

Work Orders

950008820

H11P611 Hot Spot Repair Bypass Terminal CC9

11/18/2024

CARD 1625611

EQ Central Files EQ1EF2020 and -058 Lack Formal

Documentation for the Use of "Sound Reasons to the

Contrary" IAW 10CFR50.49 Par. (I)

07/14/2016

CARD 2126201

Pump E1151C001C (Div. I RHRSW Pump C) Exceeded IST

Alert Criteria

07/14/2021

CARD 2228972

Safety Issue - Program/Process Breakdown Leading to

Procedure Violations

08/23/2022

CARD 2231593

Oil Samples Not Being Shipped after Being Turned in

2/06/2022

CARD 2322542

Chemistry Samples to Ship Out

04/03/2023

CR202334791

CTG Lube Oil Samples at Warehouse B

11/30/2023

CR202436427

RHRSW Pump D in the Alert Range Low for Calculated D/P

2/20/2024

CR202440585

RHRSW Pump A D/P Near the Alert Range

06/28/2024

CR202441183

Leak from T4100F0375

07/26/2024

CR202442816

Divisional Battery Charger 2A2 Panel Mounted Ammeter

Failed to Calibrate

10/09/2024

CR202442844

Phasing Balance Acceptance Criteria Unsat for 2A2 Battery

Charger

10/10/2024

CR202443237

Samples Should Be No Longer Taken from the CTGs

10/28/2024

CR202443341

PT Event WO 73592852 Does Not Identify Chemistry Tasks

or Resources Required

10/30/2024

CR202443428

DC6048 Vol 1: Legacy Errors Discovered for Pipe Supports

P454630-G01 and P453352-G22

11/01/2024

CR202443891

RHRSW Pump B D/P Approaching IST Alert Limit

11/21/2024

71111.15

Corrective Action

Documents

CR202444589

TMTE240026 ERVR117: Replace RHR Pump Motors A

and C Per EDP80186 in RF23

2/17/2024

6SD7212531-13

Internal Wiring Diagram 130V ESF Battery Chargers

O

Drawings

M46301

Hanger Drawing for P454630-G01

2019

ISI/IST Program Evaluation Sheet

Engineering

Evaluations

DC5803 Vol I

RHRSW Design Basis Requirements

A

245100

Perform 24.205.06 Division 2 RHRSW Pump and Valve

Operability

05/04/2024

71880678

Perform 24.205.06 Division 2 RHRSW Pump and Valve

Operability

05/28/2024

71907133

Perform 24.205.06 Division 2 RHRSW Pump and Valve

Operability

06/23/2024

71907147

Perform 24.205.06 Division 2 RHRSW Pump and Valve

Operability

08/18/2024

Work Orders

950008047

Phasing Balance Acceptance Criteria Unsat for 2A2 Battery

Charger

10/11/2024

2443700

E4150F001 Packing Gland Follower Live Loaded Washers

Crushed and Stem Found Dry

11/13/2024

CARD 2124430

Trip of RPS B, B EPA Tripped Causing Loss of RPS B

05/19/2021

CARD 2124511

Failed PMT During EPA B Channel Functional - 61260479

06/17/2021

CARD2320285

No Response From Division I North CCEA Radiation

Monitor

01/11/2023

CR202332515

EPA Breaker C7100S003B

08/22/2023

CR202436205

Received 3D18 IPCS Inputs Abnormal For Division II

CHRRMS Downscale

2/11/2024

CR202439322

Division 2 CHRRMS Failed Downscale during Performance

of 24.000.05

05/07/2024

CR202440138

Technical Specification 3.3.3.1 Required Action A.1 Will Not

be Completed in Required Time for Division II CHRRMS

06/07/2024

CR202440250

TS LCO Expired without Priority WO to Repair Condition

06/12/2024

CR202442633

UNSAT PMT on T4100B007

10/01/2024

CR202442684

Review Spare Motor Inventory for T4100B007 Supply Fan

Motor

10/03/2024

71111.24

Corrective Action

Documents

CR202442699

Missing Bolts Discovered on Div. I CCHVAC Supply Fan

Plenum

10/03/2024

CR202442784

NQA - T4100B007 Motor Vibration Dampener Does Not

Align With Design Equivalent Change Package 700050

10/09/2024

CR202442927

Timing Chain As Found Out of Spec

10/14/2024

CR202442937

Emergency Overspeed Switch Oil Intrusion and Oil-Soaked

Wires

10/14/2024

CR202443092

RM1000 Battery Replacement PMs Missed Significant

Detail

10/21/2024

CR202443272

1518 DPM Lube Oil Leak Coming from Discharge Piping of

EDG11 Engine Driven Lube Oil Pump While EDG11

Running

10/28/2024

CR202443272

Governor Oil Level Low out of Green Band during EDG11

Fast Start

10/28/2024

Corrective Action

Documents

CR202443963

C7100S003G Failed to Trip When S1 Switch Was Placed in

CAL/TEST

11/25/2024

6I721N271117

Schematic Diagram Emerg. Diesel Generator 11, 12, 13,

and 14 Exciter - Voltage Regulator

X

6I721N271134

Schematic Diagram Exciter and Voltage Regulator and

Governor Control Diesel Generator 13

AF

I218103

Process Radiation Monitor Subsystems System Diagram

I218104

System Diagram-Process Radiation Monitoring System

I218302

Schematic Wiring Diagram PRMS D11N436 A, B and

D11N437 A, B CAHRM D11N443A, B

T

I3010007

Instrument Loop Diagram Accident Monitor Containment

Area High Range Division I RY-D11K816A

G

Drawings

M57363

Control Center A/C Air System Functional Operating Sketch

K

Engineering

Changes

EDP 70050

CCHVAC Div, I T4100B007 Motor Vibration Dampener

10/05/2024

DC4535

Calculation for CAHRM System Instrumentation

C

EFA-E4124-002

Evaluation of E4100F067 Hydraulic Piston Seal

Engineering

Evaluations

ISI/NDE-IST

13029

IST Classification Change for E4100F067

24149

Dive Report: Fermi RHR Online Inspection Division I

ACMP 22011

Division I CCHVAC Supply Motor Vibrations

10/05/2021

71111.24

Miscellaneous

E4100

High Pressure Coolant Injection Design Basis Document

G

HX Inspection

Report

EDG 14 Lube Oil HX

10/14/2024

HX Inspection

Report

EDG 14 Jacket Coolant HX

10/14/2024

HX Inspection

Report

EDG 14 Air Coolant HX

10/14/2024

Operations

Evolution Order

HPCI November 2024 SSO

VMES22

Instruction Manual for Generator Excitation System

[CONFIDENTIAL]

A

Miscellaneous

WO 66248962

Risk Management

Plan

WO 66248962 Risk Management Plan: License Renewal

Inspection Perform Division I RHR Reservoir Zebra Mussel

Inspection

11/04/2024

24.202.01

HPCI Pump and Valve Operability Test at 1025 PSI

27

24.202.08

HPCI Time Response and Pump Operability Test at 1025

PSI

24.307.45

EDG 11 Fast Start Followed by Load Reject

6WI-D117171-1

Instrumentation Installation Tubing ISO

D

ARP 3D38

Control Center Emergency Air Division I Radiation Monitor

Trouble

ARP 3D43

Division I/II Containment Area Radiation Monitor Trouble

Procedures

ARP3D39

Control Center Emergency Air Division II Radiation Monitor

Trouble

46682634

Perform 3Year Performance Test of N+1 Train Dominator

and Neptune Equipment

11/15/2018

50966856

Perform 3Year Performance Test of N Train Dominator and

Neptune Equipment

11/13/2018

289097

Perform 3Year Performance Test of N+1 Train Dominator

and Neptune Equipment

08/16/2021

256368

Perform 3Year Performance Test of N Train Dominator and

Neptune Equipment

08/19/2021

2051058

EDG 14 Inspect L1 Connections on EDG 14 AVR Card

10/28/2024

65617405

Perform 42.610.01 Div. I Alternate Feed EPAs E and G

Functional

08/24/2023

71111.24

Work Orders

248962

License Renewal - Perform Division I RHR Reservoir Zebra

Mussel Inspection Dive

11/04/2024

66764024

Plant Health T4100B007 Failed PMT

10/01/2024

67684841

EDG 14 Heat Exchanger Eddy Current Test

10/16/2024

69041446

Perform 24.307.45 EDG 11 Fast Start Followed by Load

Reject

10/28/2024

950007928

T4100B007 Trial Vibration Dampener / Troubleshooting

10/05/2024

EP101

Classification of Emergencies

RERP Plan

Fermi 2 Radiological Emergency Response Preparedness

Plan

RERP Plan

Fermi 2 Radiological Emergency Response Preparedness

Plan

RERP Plan

Fermi 2 Radiological Emergency Response Preparedness

Plan

71114.04

Procedures

RERP Plan

Fermi 2 Radiological Emergency Response Preparedness

Plan

Miscellaneous

Tabletop / Dynamic Learning Activity Drill Scenario

10/08/2024

71114.06

Procedures

EP101

Classification of Emergencies

CARD 0700189

SBO DCS Cabinet S14P004 4B Cooling Unit Malfunction

05/26/2007

CR202441095

Diesel Fire Pump Fuel Oil Level Low - 7D2 is Locked in

07/22/2024

CR202441183

Leak from T4100F375 Instrument Line

07/26/2024

CR202441568

E4150F042 not Closing Remotely when Pushbutton

Depressed

08/14/2025

CR202441598

24 NRC License Renewal Inspection - R300F983B Leak

08/15/2024

CR202442282

Leak Identified During Leak Check on P50F512B and

P50F514B

09/18/2024

CR202443100

2F5A Pos 2A "M" Contactor Both Stationary and

Moveable Contacts Have Excessive Pitting

10/22/2024

CR202443161

1RX62 As Found Did Not Meet Acceptance Criteria

10/24/2024

CR202443747

dpm Leak from NW Corner of HPCI Main Pump

11/14/2024

CR202443891

RHRSW pump B D/P Approaching IST Alert Limit

11/21/2024

CR202444270

RHR Keep Fill Valve Leak By

2/12/2024

71152S

Corrective Action

Documents

CR202445573

11D65 CTG 11 DCS Trouble in Alarm

2/17/2024

LER 2023001-00

Loss of Mechanical Draft Cooling Tower Fan Brakes during

High Speeds Le Ads to Loss of Safety Function and

Inoperability

LER 2023001-01

Loss of Mechanical Draft Cooling Tower Fan Brakes during

High Speeds Leads to Loss of Safety Function and

Inoperability

LER 2023002-00

Technical Specification Completion Time Exceeded due to

Repairs on the MDCT Fan D

09/15/2023

LER 2023003-00

Reactor Pressure Boundary Leakage at Socket Weld on

Reactor Recirculation Sample Line Caused by Fatigue

Failure

10/19/2023

71153

Miscellaneous

LER 2024001-00

Automatic RPS SCRAM on High RPV Pressure While

Attempting to Lower Generator Output during RF22

05/15/2024