IR 05000333/2020003

From kanterella
Jump to navigation Jump to search
Integrated Inspection Report 05000333/2020003
ML20315A323
Person / Time
Site: FitzPatrick Constellation icon.png
Issue date: 11/10/2020
From: Erin Carfang
Reactor Projects Branch 1
To: Bryan Hanson
Exelon Generation Co, Exelon Nuclear
Carfang E
References
IR 2020003
Download: ML20315A323 (19)


Text

November 10, 2020

SUBJECT:

JAMES A. FITZPATRICK NUCLEAR POWER PLANT - INTEGRATED INSPECTION REPORT 05000333/2020003

Dear Mr. Hanson:

On September 30, 2020, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at James A. FitzPatrick Nuclear Power Plant. On October 22, 2020, the NRC inspectors discussed the results of this inspection with Mr. Pat Navin, Site Vice President, and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, X /RA/

Signed by: Erin E. Carfang

Erin E. Carfang, Chief Reactor Projects Branch 1 Division of Reactor Projects

Docket No. 05000333 License No. DPR-59

Enclosure:

As stated

Inspection Report

Docket Number:

05000333

License Number:

DPR-59

Report Number:

05000333/2020003

Enterprise Identifier: I-2020-003-0019

Licensee:

Exelon Generation Company, LLC

Facility:

James A. FitzPatrick Nuclear Power Plant

Location:

Oswego, NY

Inspection Dates:

July 1, 2020 to September 30, 2020

Inspectors:

E. Miller, Senior Resident Inspector

J. England, Resident Inspector

H. Anagnostopoulos, Senior Health Physicist

E. Andrews, Health Physicist

M. Henrion, Health Physicist

C. Lally, Senior Project Engineer

M. Patel, Senior Reactor Inspector

R. Rolph, Resident Inspector

J. Rady, Emergency Preparedness Inspector

B. Sienel, Resident Inspector

A. Turilin, Reactor Inspector

Approved By:

Erin E. Carfang, Chief

Reactor Projects Branch 1

Division of Reactor Projects

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at James A. FitzPatrick Nuclear Power Plant, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

PLANT STATUS

FitzPatrick began the inspection period at rated thermal power. On July 25, 2020, FitzPatrick began end of cycle coastdown. On August 12, 2020, operators reduced reactor power to 85 percent to perform control rod hydraulic control unit maintenance. Following repairs to the control rod hydraulic control unit, operators restored reactor power to maximum achievable thermal power the same day. On September 5, 2020, operators reduced reactor power to 80 percent due to degraded feedwater heater performance. Following removal of a condensate booster pump from service to stabilize feedwater heating, operators maintained power at 80 percent until September 13, 2020. On September 13, 2020, operators removed FitzPatrick from service to commence refueling outage 24 (J1R24). FitzPatrick remained offline for the remainder of the inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

Starting on March 20, 2020, in response to the National Emergency declared by the President of the United States on the public health risks of the coronavirus (COVID-19), resident and regional inspectors were directed to begin telework and to remotely access licensee information using available technology. During this time the resident inspectors performed periodic site visits each week, increasing the amount of time on site as local COVID-19 conditions permitted. As part of their onsite activities, resident inspectors conducted plant status activities as described in IMC 2515, Appendix D, observed risk significant activities, and completed on site portions of IPs. In addition, resident and regional baseline inspections were evaluated to determine if all or portion of the objectives and requirements stated in the IP could be performed remotely. If the inspections could be performed remotely, they were conducted per the applicable IP. In some cases, portions of an IP were completed remotely and on site. The inspections documented below met the objectives and requirements for completion of the IP.

REACTOR SAFETY

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (5 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1) A emergency diesel generator on July 8, 2020
(2) A residual heat removal service water loop 'A' on July 23, 2020
(3) A residual heat removal system in shutdown cooling mode on September 15, 2020
(4) Decay heat removal standby diesel generator on September 19, 2020
(5) Decay heat removal system on September 20, 2020

Complete Walkdown Sample (IP Section 03.02) (2 Samples)

(1) The inspectors evaluated system configurations during a complete walkdown of the reactor building closed loop cooling system on August 5, 2020.
(2) The inspectors evaluated system configurations during a complete walkdown of the standby gas treatment system on August 21, 2020.

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (6 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1) East diesel fire pump room, elevation 255, fire area/zone IB/FP-3, on July 7, 2020
(2) Reactor building, elevation 344 and 369, fire area/zone IX/RB-1A, on July 15, 2020
(3) Turbine building south, elevation 252, fire area/zone IE/TB-1 on September 17, 2020
(4) Reactor building, elevation 242' & 227', fire area/zone XVII/RB-1E, on September 19, 2020
(5) Drywell, elevation 268, fire area/zone XIV/PC-1 on September 21, 2020
(6) Turbine building, elevation 252 and 272, fire area/zone IE/TB-1, OR-1 on September 24, 2020

Fire Brigade Drill Performance Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated the onsite fire brigade performance during an unannounced fire drill in the auxiliary boiler room on August 3, 2020.

71111.07A - Heat Sink Performance

Annual Review (IP Section 03.01) (1 Sample)

The inspectors evaluated readiness and performance of:

(1) Reactor building closed loop cooling heat exchanger 'C'

71111.08G - Inservice Inspection Activities (BWR)

BWR Inservice Inspection Activities Sample - Nondestructive Examination and Welding

Activities (IP Section 03.01)

(1) The inspectors verified that the reactor coolant system boundary, reactor vessel internals, risk-significant piping system boundaries, and containment boundary are appropriately monitored for degradation and that repairs and replacements were appropriately fabricated, examined and accepted by reviewing the following activities from September 21, 2020 to October 8, 2020:
  • Ultrasonic examination of recirculation system valve to elbow weld overlay on weld 28-02-2-92 (ISI-UT-20-015)
  • Ultrasonic examination of recirculation system nozzle N-1B-IR inner radius (J1R24-VEN-005)
  • Visual examination (VT-G) of ASME Section XI IWE accessible containment surfaces including general exam of torus interior, reactor building, drywell dome interior, drywell head bolting and drywell dome flange surface (CISI-VT-20-001 to CISI-VT-20-008, CISI-VT-20-013, CISI-VT-20-015)

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)

(1) The inspectors observed and evaluated licensed operator performance in the control room during a power reduction to begin refueling and maintenance outage J1R24 on September 13, 2020

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) The inspectors observed a simulator evaluation that involved implementation of digital feedwater level control during reactor startup and during transients on September 3, 2020

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (2 Samples)

The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components (SSCs) remain capable of performing their intended function:

(1) Torus internal structural monitoring on September 18, 2020
(2) Drywell internal structural monitoring on September 22, 2020

Quality Control (IP Section 03.02) (1 Sample)

The inspectors evaluated the effectiveness of maintenance and quality control activities to ensure the following SSC remains capable of performing its intended function:

(1) Commercial dedication of emergency diesel fuel oil and breaker component on September 9, 2020

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (7 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed;

(1) Elevated risk during residual heat removal service water heat exchanger outlet isolation valve,10MOV-89B, repair on July 29, 2020
(2) B reactor feedwater pump motor gear unit failure on July 29, 2020
(3) Emergent repair of hydraulic control unit associated with control rod 14-27 on August 12, 2020
(4) Elevated risk while placing shutdown cooling in service on September 14, 2020
(5) Elevated risk during reactor cavity flood-up on September 15, 2020
(6) Elevated risk during planned B 125 volts direct current battery maintenance on September 18, 2020
(7) Elevated risk during reactor cavity draindown on September 28, 2020

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (5 Samples)

The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:

(1)

'A emergency service water supply piping line 46-10-WES-151-37 through-wall leak on July 21, 2020

(2) A emergency service water supply piping line 46-10-WES-151-37 through-wall leak flaw extent of condition evaluation on July 30, 2020
(3) A residual heat removal system snubber support failure on August 11, 2020
(4) P4 test port leak on hydraulic control unit 14-27 on August 11, 2020
(5) Reactor core isolation cooling condensate storage tank 'B' logic level switch on September 2, 2020

71111.18 - Plant Modifications

Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02) (1 Sample)

The inspectors evaluated the following temporary or permanent modifications:

(1) Permanent Modification: Engineering Change 629806, 10700 Bus Trip on Loss of Coolant Accident Project to Support Replacement of Normal Station Service Transformer 71T-4, on September 15, 2020

71111.19 - Post-Maintenance Testing

Post-Maintenance Test Sample (IP Section 03.01) (7 Samples)

The inspectors evaluated the following post maintenance test activities to verify system operability and functionality:

(1)88CR-2, post maintenance test review for the reactor building crane following removal of the trolley festoon cable tray on July 15, 2020 (2)10MOV-89B, residual heat removal service water heat exchanger outlet isolation valve following packing replacement on August 11, 2020 (3)23MOV-15, high pressure coolant injection inboard steam isolation valve following diagnostic testing on September 23, 2020

(4) ST-22J, safety relief valve electric lift logic system functional and simulated actuation test following main valve replacement on September 25, 2020 (5)12MOV-69, reactor water cleanup outboard isolation valve following stem nut cleaning and repacking on September 25, 2020
(6) High pressure coolant injection system turbine overspeed trip test following preventative maintenance overhaul on September 27, 2020 and September 29, 2020
(7) ST-39H, reactor pressure vessel leakage test following refueling on September 30, 2020

71111.20 - Refueling and Other Outage Activities

Refueling/Other Outage Sample (IP Section 03.01) (1 Partial)

(1) The inspectors evaluated refueling outage J1R24 activities from September 13, 2020 through September 30, 2020

71111.22 - Surveillance Testing

The inspectors evaluated the following surveillance tests:

Surveillance Tests (other) (IP Section 03.01)

(1) ST-24J, RCIC Flow Rate and Inservice Test (IST) on September 2, 2020
(2) ST-39B-X7A, B, C, D Type C Leak Test Main Steam Line MSIV on September 15, 2020
(3) ST-22A, ADS Simulated Automatic Actuation Test on September 25, 2020
(4) ST-9CB, Emergency Diesel Generator (EDG) B and D Load Sequencing Test and 4KV Emergency Power System Voltage Relays Instrument Functional Test on September 27, 2020
(5) ST-6M, Standby Liquid Control Recirculation, Injection Test (IST, ISI) on September 29, 2020

Containment Isolation Valve Testing (IP Section 03.01) (1 Sample)

(1) ST-1B, Main Steam Isolation Valve Fast Closure Test on September 14, 2020

71114.02 - Alert and Notification System Testing

Inspection Review (IP Section 02.01-02.04) (1 Sample)

(1) The inspectors evaluated Exelon's maintenance and testing of the FitzPatrick alert and notification system on July 13-16, 2020, for the period of July 2018 through June 2020

71114.03 - Emergency Response Organization Staffing and Augmentation System

Inspection Review (IP Section 02.01-02.02) (1 Sample)

(1) The inspectors evaluated the readiness of FitzPatrick's emergency preparedness organization on July 13-16, 2020

71114.04 - Emergency Action Level and Emergency Plan Changes

Inspection Review (IP Section 02.01-02.03) (1 Sample)

(1) The inspectors evaluated the following submitted Emergency Action Level and Emergency Plan changes onsite on July 13-16, 2020:
  • Evaluation No. 19-54, EP-AA-121-F-11, James A. FitzPatrick Equipment Matrix, Revision 3
  • Evaluation No. 19-62, EAP-44, Core Damage Estimation, Revision 9
  • Evaluation No. 20-03, EP-AA-111-F-15, FitzPatrick PAR Flowchart, Revision B

This evaluation does not constitute NRC approval

71114.05 - Maintenance of Emergency Preparedness

Inspection Review (IP Section 02.01 - 02.11) (1 Sample)

(1) The inspectors evaluated the maintenance of the emergency preparedness program on July 13-16, 2020, for the period of July 2018 through June 2020

71114.06 - Drill Evaluation

Select Emergency Preparedness Drills and/or Training for Observation (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated the conduct of a routine emergency planning drill on August 13,

RADIATION SAFETY

71124.01 - Radiological Hazard Assessment and Exposure Controls

Radiological Hazard Assessment (IP Section 03.01) (1 Partial)

(1) The inspectors reviewed logs and discussed the conduct of radiologically significant work via telephone. Comprehensive documents for two jobs were requested. This was done remotely due to the COVID-19 public health emergency.

Instructions to Workers (IP Section 03.02) (1 Partial)

(1) Comprehensive documents for two radiologically significant jobs were requested. This was done remotely due to the COVID-19 public health emergency.

Contamination and Radioactive Material Control (IP Section 03.03) (1 Partial)

The inspectors evaluated licensee processes for monitoring and controlling contamination and radioactive material.

(1) The inspectors reviewed logs and discussed controls via telephone. This was done remotely due to the COVID-19 public health emergency.

Radiological Hazards Control and Work Coverage (IP Section 03.04) (1 Partial)

The inspectors evaluated in-plant radiological conditions during facility walkdowns and observation of radiological work activities.

(1) The inspectors reviewed initial radiological surveys of the drywell and the turbine stop valves. The inspector requested comprehensive documents for two radiologically significant jobs. This was done remotely due to the COVID-19 public health emergency.

High Radiation Area and Very High Radiation Area Controls (IP Section 03.05) (1 Partial)

The inspectors evaluated licensee controls of the following High Radiation Areas and Very High Radiation Areas:

(1) The inspectors reviewed licensee procedures for high and very high radiation area controls and reviewed the results of any events that were documented in Exelon's issue reporting system Radiation Worker Performance and Radiation Protection Technician Proficiency (IP Section 03.06) (1 Partial)
(1) The inspectors reviewed logs and discussed the conduct of radiologically significant work via telephone

71124.05 - Radiation Monitoring Instrumentation

Walkdowns and Observations (IP Section 03.01) (8 Samples)

The inspectors evaluated the following radiation detection instrumentation during plant walkdowns:

(1) Area radiation monitors in the reactor building, turbine building, and radioactive waste building
(2) Ion chambers in use in the reactor building, turbine building, and radioactive waste building
(3) Portable ion chambers and telepoles stored ready for use
(4) Portable friskers used at the exit to the radiologically controlled area
(5) Post-accident liquid sampling station
(6) Process radiation monitors in the control room
(7) Remote gaseous and particulate air monitoring for the drywell
(8) Whole body counter

Calibration and Testing Program (IP Section 03.02) (13 Samples)

The inspectors evaluated the calibration and testing of the following radiation detection instruments:

(1) Eberline RO20AA, SN 12532
(2) Eberline MS-2, SN 1623
(3) Eberline MS-3, SN 1036
(4) Ludlum-3, SN 313206
(5) Ludlum-177, SN 323559
(6) Ludlum L-2000, SN 302439
(7) Mirion BAK-4280, SN 427017-131
(8) Mirion RDS-31ITX, SN 712470
(9) Mirion RDS-31ITXSD, SN 720241
(10) Thermo Fisher AMS-4, SN 13067
(11) Thermo Fisher AMS-4, SN 13070
(12) Radeco AVS, SN 14613
(13) Radeco AVS Gooseneck, SN 1011330082

Effluent Monitoring Calibration and Testing Program Sample (IP Sample 03.03) (2 Samples)

The inspectors evaluated the calibration and maintenance of the following radioactive effluent monitoring and measurement instrumentation:

(1) Radwaste building exhaust radiation monitors 17RM-458A and 17RM-458B
(2) Reactor building closed loop cooling process radiation monitor 17RM-352

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification

The inspectors verified licensee performance indicators submittals listed below:

EP01: Drill/Exercise Performance (IP Section 02.12)===

(1) April 1, 2019 - March 31, 2020

EP02: ERO Drill Participation (IP Section 02.13) (1 Sample)

(1) April 1, 2019 - March 31, 2020

EP03: Alert & Notification System Reliability (IP Section 02.14) (1 Sample)

(1) April 1, 2019 - March 31, 2020

OR01: Occupational Exposure Control Effectiveness Sample (IP Section 02.15) (1 Sample)

(1) April 1, 2019 - March 31, 2020

PR01: Radiological Effluent Technical Specifications/Offsite Dose Calculation Manual Radiological Effluent Occurrences (RETS/ODCM) Radiological Effluent Occurrences Sample (IP Section 02.16) (1 Sample)

(1) April 1, 2019 - March 31,

INSPECTION RESULTS

No findings were identified.

EXIT MEETINGS AND DEBRIEFS

The inspectors confirmed that proprietary information was controlled to protect from public disclosure.

  • On October 22, 2020, the inspectors presented the integrated inspection results to Mr. Pat Navin, Site Vice President, and other members of the licensee staff.
  • On July 16, 2020, the inspectors presented the emergency preparedness program inspection results to Mr. Pat Navin, Site Vice President, and other members of the licensee staff.
  • On July 23, 2020, the inspectors presented the radiation monitoring instrumentation inspection results to Mr. Timothy Peter, Plant Manager, and other members of the licensee staff.
  • On October 8, 2020, the inspectors presented the inservice inspection activities inspection results to Mr. Pat Navin, Site Vice President, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.04

Drawings

FM-15A

Flow Diagram Reactor Building Closed Loop Cooling

FM-20A

Flow Diagram Residual Heat Removal System 10

FM-20B

Flow Diagram Residual Heat Removal System 10

FM-48A

Flow Diagram Standby Gas Treatment System 01-125

FM-93A

Flow Diagram Fuel Oil Line Emergency Diesel Generators

System 93

FM-941

Flow Diagram Air Start-Up Lines Emergency Diesel

Generators System 93

FM-94A

Flow Diagram Air Start-up Lines Emergency Diesel

Generators

Procedures

OP-13

Residual Heat Removal System

OP-13C

Residual Heat Removal System

OP-20

Standby Gas Treatment System

OP-22

Diesel Generator Emergency Power

OP-30B

Decay Heat Removal System

OP-40

Reactor Building Closed Loop Cooling

OSP-30B.001

Operation of the Decay Heat Removal Standby Diesel

Generator

71111.05

Corrective Action

Documents

04371127

Fire Plans

PFP-PWR 33

Pump Rooms (Screenwell)/Elevation 255 Fire Area/Zone

XII/SP-1, XIII/SP-2, IB/FP-1, FP-3

PFP-PWR14

Crescent Area-East/Elev.227', 242' Fire Area/Zone XVII/RB-

1E

PFP-PWR18

Drywell Elevation 268 Fire Area/Zone XIV/PC-1

PFP-PWR27

Reactor Building / Elevation 344 Fire Area/Zone IX/RB-1A

PFP-PWR28

Reactor Building / Elevation 369, Fire Area/Zone IX/RB-1A

PFP-PWR42

Turbine Building North/Elev. 252' Fire Area/Zone IE/TB-1

PFP-PWR43

Turbine Building-South Elev. 252' Fire Area/Zone IE/TB-1

PFP-PWR45

Turbine Building-North/Elev. 272' Fire Area/Zone IE/TB-1

PFP-PWR46

Turbine Building-South/Elev. 272' Fire Area/Zone IE/TB-1,

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

OR-2

Procedures

OP-AA-201-003

Fire Drill Performance

71111.07A

Drawings 4.95-15

Heat Exchanger Plugging Map 15E-1C RBCLC

Procedures

SP-01.25

Reactor Building Closed Loop Cooling Sampling and Analysis

SP-04.03

Service and Circulating water Systems Chemical Treatment

Work Orders

04682358

71111.08G Corrective Action

Documents

CR-JAF-2008-3311

09/23/2008

4138318

Through Wall Leak on ESW Line 3-WES-151-136

05/16/18

NDE Reports

APR-R24-02

Safe End to Nozzle

09/21/2020

B20MT046

3" Pipe / Valve

10/01/2020

B20PT026

Valve to Elbow W2 and Elbow to Pipe W4

10/01/2020

CISI-VT-20-001

IWE General Exam Torus interior RB 227 to 272

09/24/2020

CISI-VT-20-002

IWE General Exam RF Cavity 340-369

09/21/2020

CISI-VT-20-003

IWE General Exam Torus supports RB 227

09/21/2020

CISI-VT-20-004

IWE General Exam RB 326 - 344

09/24/2020

CISI-VT-20-005

IWE General Exam RB 227-272

09/21/2020

CISI-VT-20-006

IWE General Exam RB 344 - 369

09/20/2020

CISI-VT-20-007

IWE General Exam RB 300 - 326

09/24/2020

CISI-VT-20-008

IWE General Exam RB 272 -300

09/24/2020

CISI-VT-20-013

IWE General Exam Drywell Dome RF 369

09/24/2020

CISI-VT-20-015

Drywell Head Bolting

09/24/2020

ISI-PT-20-001

Instrumentation Nozzle Weld

09/18/2020

ISI-UT-20-004

Nozzle to Cap Overlay

09/22/2020

ISI-UT-20-015

Valve to Elbow

09/24/2020

J1R24-VEN-001

Valve to Tee Weld Overlay

09/22/2020

J1R24-VEN-005

Nozzle Inner Radius

09/22/2020

Work Orders

04937146

Replace 13MOV-131 in R24

07/21/2020

71111.11Q Miscellaneous

N-JF-OPS-LORT-

DFWLC-2005

Requalification Guide for DFWLC Mod 20-05

71111.12

Miscellaneous

Purchase Order

0714821

EDG A & C Fuel Oil Receipt 34461

Purchase Order

25006

EDG B & D Fuel Oil Receipt 35606

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Purchase Order

26089

EDG A & C Fuel Oil Receipt 35610

Procedures

AP-15.12

Receiving Inspection for Dedication of No. 2 Diesel Fuel Oil

ER-AA-450

Structures Monitoring

NO-AA-30

Independent Inspection Process Description

ST-15B

Suppression Chamber and Drywell Deterioration Inspection

71111.13

Corrective Action

Documents

04359266

04361956

Drawings 2.04-30

RFP Turbine Control Diagram

C

FM-27B

Flow Diagram Control Rod Drive System 03

Miscellaneous

G080-0056

Hydraulic Control Unit Part Nos 729E950 G1 thru G6

Procedures

AOP-27

Control Rod Malfunction

MP-004.01

Disassembly of Reactor Vessel for Refueling (ISI)

OP-13D

RHR - Shutdown Cooling

OP-25

Control Rod Drive Hydraulic System

093

OP-30A

Refueling Water Level Control

OP-43A

25 VDC Power System

OP-65

Startup and Shutdown Procedures

27

Work Orders

05068725

71111.15

Corrective Action

Documents

04109193

04164618

04344822

04361956

4351640-09

Drawings

1.61.152

Elem Diag RCIC System

FM-46B

Flow Diagram Emergency Service Water System 46 & 15

Engineering

Changes

631938

ESW N-513 Thru-Wall Leak Evaluation 46-10-WES-151-37

OP Eval

Miscellaneous

4351640

Operability Evaluation

Procedures

OP-AA-108-115

Operability Determination

71111.18

Corrective Action

Documents

04369111

JAF-LO-2012-

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

00004

Engineering

Changes

29806

10700 Bus Trip on Loss of Coolant Accident Project to Support

Replacement of Normal Station Service Transformer 71T-4

71111.19

Corrective Action

Documents

04371087

CR-JAF-2013-

218

Drawings 6.37-362

Valve Outline Drawing, 23MOV-15

C

FM-24A

Flow Diagram Reactor Water Cleanup System 12

Miscellaneous

A391-0057F(A10)

Installation Operation and Maintenance Manual Double Disc

Gate Valve

TP16-1-112

Recommendations to Resolve Flowserve 10CFR Part 21

Notification Affecting Anchor Darling Double Disc Gate Valve

Wedge Pin Failures

(Proprietary)

Procedures

MA-AA-723-300

Diagnostic Testing of Motor Operated Valves

MA-AA-723-302

Installation and Checkout of Quick Stem Sensor (QSS) on

Valve Stems

MP-059.60

Anchor Darling Pressure Seal Gate and Globe Valve (ISI)

MP-059.78

Disconnecting Leads for MOV Maintenance/Testing

MST-023.01

HPCI Turbine Overspeed Trip Test and Calibration

ST-22J

SRV Electric Lift Logic System Functional and Simulated

Automatic Actuation Test

ST-22J

SRV Electric Lift Logic System Functional and Simulated

Automatic Actuation Test

9A

ST-22J SRV

Electric Lift Logic System Functional and Simulated Automatic

Actuation Test

Work Orders

0339333

05061232

71111.20

Procedures

OP-65

Startup and Shutdown Procedure

28

Work Orders

04738808

71111.22

Corrective Action

Documents

04369251

04369253

04369255

04369727

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

04369728

Drawings 1.83-37

Auto Depressurization System

1.83-38

Elem Diagram - Auto Depressurization System

Q

1.83-39

Elem Drawing - Auto Depressurization Sys

M

ESK-11AAu

Elementary Diagram 09-ECCS1-EP and 09-ECCS2-EP

FM-21A

Flow Diagram Standby Liquid Control System 11

FM-23A

Flow Diagram Core Spray System 14

FM-29A

Flow Diagram Main Steam System 29

Procedures

ST-1B

Main Steam Isolation Valve Fast Closure Test

ST-22A

ADS Simulated Automatic Actuation Test

ST-24J

RCIC Flow Rate and Inservice Test (IST)

ST-39B-X7A

Type C Leak Test Main Steam Line A MSIVs (IST)

ST-39B-X7B

Type C Leak Test Main Steam Line B MSIVs (IST)

ST-39B-X7C

Type C Leak Test Main Steam Line C MSIVs (IST)

ST-39B-X7D

Type C Leak Test Main Steam Line D MSIVs (IST)

ST-6M

Standby Liquid Control Recirculation, Injection Test (IST, ISI)

ST-9CB

Emergency Diesel Generator (EDG) B and D Load

Sequencing Test and 4KV Emergency Power System Voltage

Relays Instrument Functional Test

Work Orders

04877902

04878371

04878373

04878375

04878383

04878410

05024253

71114.02

Miscellaneous

Design Report

Nine Mile Point Nuclear Generating Station and James A.

FitzPatrick Nuclear Power Plant Public Alert and Notification

System

71114.03

Miscellaneous

EP-AA-1014

Radiological Emergency Plan Annex for James A. FitzPatrick

Station

EP-AA-1014

Addendum 1

James A. FitzPatrick Nuclear Power Plant On-Shift Technical

Basis

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71114.04

Procedures

EP-AA-120-1001

CFR 50.54(q) Change Evaluation

71114.05

Corrective Action

Documents

04170901

227133

271107

04302779

04303614

04323222

Miscellaneous

Nine Mile Point Nuclear Station and James A. FitzPatrick

Nuclear Power Plant 2019 Population Update Analysis

Procedures

EP-AA-121-F-11

James A. FitzPatrick Equipment Matrix

71114.06

Procedures

EP-AA-112-100-

F-01

Shift Emergency Director Checklist

AB

EP-AA-112-F-01

Command and Control Turnover Briefing Form

H

EP-AA-122-300-

F-04

Drill & Exercise Post-Event Critique & Report Development

Guidance

C

71124.05

Corrective Action

Documents

268293

269079

277823

Procedures

RP-AA-700

Controls for Radiation Protection Instrumentation

8