IR 05000333/2020003

From kanterella
Jump to navigation Jump to search
Integrated Inspection Report 05000333/2020003
ML20315A323
Person / Time
Site: FitzPatrick Constellation icon.png
Issue date: 11/10/2020
From: Erin Carfang
Reactor Projects Branch 1
To: Bryan Hanson
Exelon Generation Co, Exelon Nuclear
Carfang E
References
IR 2020003
Download: ML20315A323 (19)


Text

November 10, 2020

SUBJECT:

JAMES A. FITZPATRICK NUCLEAR POWER PLANT - INTEGRATED INSPECTION REPORT 05000333/2020003

Dear Mr. Hanson:

On September 30, 2020, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at James A. FitzPatrick Nuclear Power Plant. On October 22, 2020, the NRC inspectors discussed the results of this inspection with Mr. Pat Navin, Site Vice President, and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, X /RA/

Signed by: Erin E. Carfang Erin E. Carfang, Chief Reactor Projects Branch 1 Division of Reactor Projects Docket No. 05000333 License No. DPR-59

Enclosure:

As stated

Inspection Report

Docket Number: 05000333 License Number: DPR-59 Report Number: 05000333/2020003 Enterprise Identifier: I-2020-003-0019 Licensee: Exelon Generation Company, LLC Facility: James A. FitzPatrick Nuclear Power Plant Location: Oswego, NY Inspection Dates: July 1, 2020 to September 30, 2020 Inspectors: E. Miller, Senior Resident Inspector J. England, Resident Inspector H. Anagnostopoulos, Senior Health Physicist E. Andrews, Health Physicist M. Henrion, Health Physicist C. Lally, Senior Project Engineer M. Patel, Senior Reactor Inspector R. Rolph, Resident Inspector J. Rady, Emergency Preparedness Inspector B. Sienel, Resident Inspector A. Turilin, Reactor Inspector Approved By: Erin E. Carfang, Chief Reactor Projects Branch 1 Division of Reactor Projects Enclosure

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at James A. FitzPatrick Nuclear Power Plant, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

PLANT STATUS

FitzPatrick began the inspection period at rated thermal power. On July 25, 2020, FitzPatrick began end of cycle coastdown. On August 12, 2020, operators reduced reactor power to 85 percent to perform control rod hydraulic control unit maintenance. Following repairs to the control rod hydraulic control unit, operators restored reactor power to maximum achievable thermal power the same day. On September 5, 2020, operators reduced reactor power to 80 percent due to degraded feedwater heater performance. Following removal of a condensate booster pump from service to stabilize feedwater heating, operators maintained power at 80 percent until September 13, 2020. On September 13, 2020, operators removed FitzPatrick from service to commence refueling outage 24 (J1R24). FitzPatrick remained offline for the remainder of the inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

Starting on March 20, 2020, in response to the National Emergency declared by the President of the United States on the public health risks of the coronavirus (COVID-19), resident and regional inspectors were directed to begin telework and to remotely access licensee information using available technology. During this time the resident inspectors performed periodic site visits each week, increasing the amount of time on site as local COVID-19 conditions permitted. As part of their onsite activities, resident inspectors conducted plant status activities as described in IMC 2515, Appendix D, observed risk significant activities, and completed on site portions of IPs. In addition, resident and regional baseline inspections were evaluated to determine if all or portion of the objectives and requirements stated in the IP could be performed remotely. If the inspections could be performed remotely, they were conducted per the applicable IP. In some cases, portions of an IP were completed remotely and on site. The inspections documented below met the objectives and requirements for completion of the IP.

REACTOR SAFETY

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (5 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1) A emergency diesel generator on July 8, 2020
(2) A residual heat removal service water loop 'A' on July 23, 2020
(3) A residual heat removal system in shutdown cooling mode on September 15, 2020
(4) Decay heat removal standby diesel generator on September 19, 2020
(5) Decay heat removal system on September 20, 2020

Complete Walkdown Sample (IP Section 03.02) (2 Samples)

(1) The inspectors evaluated system configurations during a complete walkdown of the reactor building closed loop cooling system on August 5, 2020.
(2) The inspectors evaluated system configurations during a complete walkdown of the standby gas treatment system on August 21, 2020.

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (6 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1) East diesel fire pump room, elevation 255, fire area/zone IB/FP-3, on July 7, 2020
(2) Reactor building, elevation 344 and 369, fire area/zone IX/RB-1A, on July 15, 2020
(3) Turbine building south, elevation 252, fire area/zone IE/TB-1 on September 17, 2020
(4) Reactor building, elevation 242' & 227', fire area/zone XVII/RB-1E, on September 19, 2020
(5) Drywell, elevation 268, fire area/zone XIV/PC-1 on September 21, 2020
(6) Turbine building, elevation 252 and 272, fire area/zone IE/TB-1, OR-1 on

September 24, 2020 Fire Brigade Drill Performance Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated the onsite fire brigade performance during an unannounced fire drill in the auxiliary boiler room on August 3, 2020.

71111.07A - Heat Sink Performance

Annual Review (IP Section 03.01) (1 Sample)

The inspectors evaluated readiness and performance of:

(1) Reactor building closed loop cooling heat exchanger 'C'

71111.08G - Inservice Inspection Activities (BWR)

BWR Inservice Inspection Activities Sample - Nondestructive Examination and Welding

Activities (IP Section 03.01)

(1) The inspectors verified that the reactor coolant system boundary, reactor vessel internals, risk-significant piping system boundaries, and containment boundary are appropriately monitored for degradation and that repairs and replacements were appropriately fabricated, examined and accepted by reviewing the following activities from September 21, 2020 to October 8, 2020:
  • Ultrasonic examination of recirculation system valve to elbow weld overlay on weld 28-02-2-92 (ISI-UT-20-015)
  • Ultrasonic examination of recirculation system nozzle N-1B-IR inner radius (J1R24-VEN-005)
  • Visual examination (VT-G) of ASME Section XI IWE accessible containment surfaces including general exam of torus interior, reactor building, drywell dome interior, drywell head bolting and drywell dome flange surface (CISI-VT-20-001 to CISI-VT-20-008, CISI-VT-20-013, CISI-VT-20-015)

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01)

(1 Sample)

(1) The inspectors observed and evaluated licensed operator performance in the control room during a power reduction to begin refueling and maintenance outage J1R24 on September 13, 2020

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) The inspectors observed a simulator evaluation that involved implementation of digital feedwater level control during reactor startup and during transients on September 3, 2020

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (2 Samples)

The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components (SSCs) remain capable of performing their intended function:

(1) Torus internal structural monitoring on September 18, 2020
(2) Drywell internal structural monitoring on September 22, 2020

Quality Control (IP Section 03.02) (1 Sample)

The inspectors evaluated the effectiveness of maintenance and quality control activities to ensure the following SSC remains capable of performing its intended function:

(1) Commercial dedication of emergency diesel fuel oil and breaker component on September 9, 2020

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (7 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed;

(1) Elevated risk during residual heat removal service water heat exchanger outlet isolation valve,10MOV-89B, repair on July 29, 2020
(2) B reactor feedwater pump motor gear unit failure on July 29, 2020
(3) Emergent repair of hydraulic control unit associated with control rod 14-27 on August 12, 2020
(4) Elevated risk while placing shutdown cooling in service on September 14, 2020
(5) Elevated risk during reactor cavity flood-up on September 15, 2020
(6) Elevated risk during planned B 125 volts direct current battery maintenance on September 18, 2020
(7) Elevated risk during reactor cavity draindown on September 28, 2020

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (5 Samples)

The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:

(1) 'A emergency service water supply piping line 46-10-WES-151-37 through-wall leak on July 21, 2020
(2) A emergency service water supply piping line 46-10-WES-151-37 through-wall leak flaw extent of condition evaluation on July 30, 2020
(3) A residual heat removal system snubber support failure on August 11, 2020
(4) P4 test port leak on hydraulic control unit 14-27 on August 11, 2020
(5) Reactor core isolation cooling condensate storage tank 'B' logic level switch on September 2, 2020

71111.18 - Plant Modifications

Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02)

(1 Sample)

The inspectors evaluated the following temporary or permanent modifications:

(1) Permanent Modification: Engineering Change 629806, 10700 Bus Trip on Loss of Coolant Accident Project to Support Replacement of Normal Station Service Transformer 71T-4, on September 15, 2020

71111.19 - Post-Maintenance Testing

Post-Maintenance Test Sample (IP Section 03.01) (7 Samples)

The inspectors evaluated the following post maintenance test activities to verify system operability and functionality:

(1) 88CR-2, post maintenance test review for the reactor building crane following removal of the trolley festoon cable tray on July 15, 2020
(2) 10MOV-89B, residual heat removal service water heat exchanger outlet isolation valve following packing replacement on August 11, 2020
(3) 23MOV-15, high pressure coolant injection inboard steam isolation valve following diagnostic testing on September 23, 2020
(4) ST-22J, safety relief valve electric lift logic system functional and simulated actuation test following main valve replacement on September 25, 2020
(5) 12MOV-69, reactor water cleanup outboard isolation valve following stem nut cleaning and repacking on September 25, 2020
(6) High pressure coolant injection system turbine overspeed trip test following preventative maintenance overhaul on September 27, 2020 and September 29, 2020
(7) ST-39H, reactor pressure vessel leakage test following refueling on September 30, 2020

71111.20 - Refueling and Other Outage Activities

Refueling/Other Outage Sample (IP Section 03.01) (1 Partial)

(1) The inspectors evaluated refueling outage J1R24 activities from September 13, 2020 through September 30, 2020

71111.22 - Surveillance Testing

The inspectors evaluated the following surveillance tests:

Surveillance Tests (other) (IP Section 03.01)

(1) ST-24J, RCIC Flow Rate and Inservice Test (IST) on September 2, 2020
(2) ST-39B-X7A, B, C, D Type C Leak Test Main Steam Line MSIV on September 15, 2020
(3) ST-22A, ADS Simulated Automatic Actuation Test on September 25, 2020
(4) ST-9CB, Emergency Diesel Generator (EDG) B and D Load Sequencing Test and 4KV Emergency Power System Voltage Relays Instrument Functional Test on September 27, 2020
(5) ST-6M, Standby Liquid Control Recirculation, Injection Test (IST, ISI) on

September 29, 2020 Containment Isolation Valve Testing (IP Section 03.01) (1 Sample)

(1) ST-1B, Main Steam Isolation Valve Fast Closure Test on September 14, 2020

71114.02 - Alert and Notification System Testing

Inspection Review (IP Section 02.01-02.04) (1 Sample)

(1) The inspectors evaluated Exelon's maintenance and testing of the FitzPatrick alert and notification system on July 13-16, 2020, for the period of July 2018 through June 2020

71114.03 - Emergency Response Organization Staffing and Augmentation System

Inspection Review (IP Section 02.01-02.02) (1 Sample)

(1) The inspectors evaluated the readiness of FitzPatrick's emergency preparedness organization on July 13-16, 2020

71114.04 - Emergency Action Level and Emergency Plan Changes

Inspection Review (IP Section 02.01-02.03) (1 Sample)

(1) The inspectors evaluated the following submitted Emergency Action Level and Emergency Plan changes onsite on July 13-16, 2020:
  • Evaluation No. 19-54, EP-AA-121-F-11, James A. FitzPatrick Equipment Matrix, Revision 3
  • Evaluation No. 19-62, EAP-44, Core Damage Estimation, Revision 9
  • Evaluation No. 20-03, EP-AA-111-F-15, FitzPatrick PAR Flowchart, Revision B This evaluation does not constitute NRC approval

71114.05 - Maintenance of Emergency Preparedness

Inspection Review (IP Section 02.01 - 02.11) (1 Sample)

(1) The inspectors evaluated the maintenance of the emergency preparedness program on July 13-16, 2020, for the period of July 2018 through June 2020

71114.06 - Drill Evaluation

Select Emergency Preparedness Drills and/or Training for Observation (IP Section 03.01)

(1 Sample)

(1) The inspectors evaluated the conduct of a routine emergency planning drill on August 13,

RADIATION SAFETY

71124.01 - Radiological Hazard Assessment and Exposure Controls

Radiological Hazard Assessment (IP Section 03.01) (1 Partial)

(1) The inspectors reviewed logs and discussed the conduct of radiologically significant work via telephone. Comprehensive documents for two jobs were requested. This was done remotely due to the COVID-19 public health emergency.

Instructions to Workers (IP Section 03.02) (1 Partial)

(1) Comprehensive documents for two radiologically significant jobs were requested. This was done remotely due to the COVID-19 public health emergency.

Contamination and Radioactive Material Control (IP Section 03.03) (1 Partial)

The inspectors evaluated licensee processes for monitoring and controlling contamination and radioactive material.

(1) The inspectors reviewed logs and discussed controls via telephone. This was done remotely due to the COVID-19 public health emergency.

Radiological Hazards Control and Work Coverage (IP Section 03.04) (1 Partial)

The inspectors evaluated in-plant radiological conditions during facility walkdowns and observation of radiological work activities.

(1) The inspectors reviewed initial radiological surveys of the drywell and the turbine stop valves. The inspector requested comprehensive documents for two radiologically significant jobs. This was done remotely due to the COVID-19 public health emergency.

High Radiation Area and Very High Radiation Area Controls (IP Section 03.05) (1 Partial)

The inspectors evaluated licensee controls of the following High Radiation Areas and Very High Radiation Areas:

(1) The inspectors reviewed licensee procedures for high and very high radiation area controls and reviewed the results of any events that were documented in Exelon's issue reporting system Radiation Worker Performance and Radiation Protection Technician Proficiency (IP Section 03.06) (1 Partial)
(1) The inspectors reviewed logs and discussed the conduct of radiologically significant work via telephone

71124.05 - Radiation Monitoring Instrumentation

Walkdowns and Observations (IP Section 03.01) (8 Samples)

The inspectors evaluated the following radiation detection instrumentation during plant walkdowns:

(1) Area radiation monitors in the reactor building, turbine building, and radioactive waste building
(2) Ion chambers in use in the reactor building, turbine building, and radioactive waste building
(3) Portable ion chambers and telepoles stored ready for use
(4) Portable friskers used at the exit to the radiologically controlled area
(5) Post-accident liquid sampling station
(6) Process radiation monitors in the control room
(7) Remote gaseous and particulate air monitoring for the drywell
(8) Whole body counter

Calibration and Testing Program (IP Section 03.02) (13 Samples)

The inspectors evaluated the calibration and testing of the following radiation detection instruments:

(1) Eberline RO20AA, SN 12532
(2) Eberline MS-2, SN 1623
(3) Eberline MS-3, SN 1036
(4) Ludlum-3, SN 313206
(5) Ludlum-177, SN 323559
(6) Ludlum L-2000, SN 302439
(7) Mirion BAK-4280, SN 427017-131
(8) Mirion RDS-31ITX, SN 712470
(9) Mirion RDS-31ITXSD, SN 720241
(10) Thermo Fisher AMS-4, SN 13067
(11) Thermo Fisher AMS-4, SN 13070
(12) Radeco AVS, SN 14613
(13) Radeco AVS Gooseneck, SN 1011330082 Effluent Monitoring Calibration and Testing Program Sample (IP Sample 03.03) (2 Samples)

The inspectors evaluated the calibration and maintenance of the following radioactive effluent monitoring and measurement instrumentation:

(1) Radwaste building exhaust radiation monitors 17RM-458A and 17RM-458B
(2) Reactor building closed loop cooling process radiation monitor 17RM-352

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:

EP01: Drill/Exercise Performance (IP Section 02.12) ===

(1) April 1, 2019 - March 31, 2020

EP02: ERO Drill Participation (IP Section 02.13) (1 Sample)

(1) April 1, 2019 - March 31, 2020

EP03: Alert & Notification System Reliability (IP Section 02.14) (1 Sample)

(1) April 1, 2019 - March 31, 2020

OR01: Occupational Exposure Control Effectiveness Sample (IP Section 02.15) (1 Sample)

(1) April 1, 2019 - March 31, 2020 PR01: Radiological Effluent Technical Specifications/Offsite Dose Calculation Manual Radiological Effluent Occurrences (RETS/ODCM) Radiological Effluent Occurrences Sample (IP Section 02.16) (1 Sample)
(1) April 1, 2019 - March 31,

INSPECTION RESULTS

No findings were identified.

EXIT MEETINGS AND DEBRIEFS

The inspectors confirmed that proprietary information was controlled to protect from public disclosure.

  • On October 22, 2020, the inspectors presented the integrated inspection results to Mr. Pat Navin, Site Vice President, and other members of the licensee staff.
  • On July 16, 2020, the inspectors presented the emergency preparedness program inspection results to Mr. Pat Navin, Site Vice President, and other members of the licensee staff.
  • On July 23, 2020, the inspectors presented the radiation monitoring instrumentation inspection results to Mr. Timothy Peter, Plant Manager, and other members of the licensee staff.
  • On October 8, 2020, the inspectors presented the inservice inspection activities inspection results to Mr. Pat Navin, Site Vice President, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection Type Designation Description or Title Revision or

Procedure Date

71111.04 Drawings FM-15A Flow Diagram Reactor Building Closed Loop Cooling 67

FM-20A Flow Diagram Residual Heat Removal System 10 72

FM-20B Flow Diagram Residual Heat Removal System 10 73

FM-48A Flow Diagram Standby Gas Treatment System 01-125 32

FM-93A Flow Diagram Fuel Oil Line Emergency Diesel Generators 22

System 93

FM-941 Flow Diagram Air Start-Up Lines Emergency Diesel 13

Generators System 93

FM-94A Flow Diagram Air Start-up Lines Emergency Diesel 13

Generators

Procedures OP-13 Residual Heat Removal System 98

OP-13C Residual Heat Removal System 16

OP-20 Standby Gas Treatment System 41

OP-22 Diesel Generator Emergency Power 69

OP-30B Decay Heat Removal System 20

OP-40 Reactor Building Closed Loop Cooling 53

OSP-30B.001 Operation of the Decay Heat Removal Standby Diesel 7

Generator

71111.05 Corrective Action 04371127

Documents

Fire Plans PFP-PWR 33 Pump Rooms (Screenwell)/Elevation 255 Fire Area/Zone 2

XII/SP-1, XIII/SP-2, IB/FP-1, FP-3

PFP-PWR14 Crescent Area-East/Elev.227', 242' Fire Area/Zone XVII/RB- 3

1E

PFP-PWR18 Drywell Elevation 268 Fire Area/Zone XIV/PC-1 0

PFP-PWR27 Reactor Building / Elevation 344 Fire Area/Zone IX/RB-1A 0

PFP-PWR28 Reactor Building / Elevation 369, Fire Area/Zone IX/RB-1A 0

PFP-PWR42 Turbine Building North/Elev. 252' Fire Area/Zone IE/TB-1 3

PFP-PWR43 Turbine Building-South Elev. 252' Fire Area/Zone IE/TB-1 3

PFP-PWR45 Turbine Building-North/Elev. 272' Fire Area/Zone IE/TB-1 07

PFP-PWR46 Turbine Building-South/Elev. 272' Fire Area/Zone IE/TB-1, 5

Inspection Type Designation Description or Title Revision or

Procedure Date

OR-2

Procedures OP-AA-201-003 Fire Drill Performance 17

71111.07A Drawings 4.95-15 Heat Exchanger Plugging Map 15E-1C RBCLC 3

Procedures SP-01.25 Reactor Building Closed Loop Cooling Sampling and Analysis 21

SP-04.03 Service and Circulating water Systems Chemical Treatment 19

Work Orders 04682358

71111.08G Corrective Action CR-JAF-2008-3311 09/23/2008

Documents 4138318 Through Wall Leak on ESW Line 3-WES-151-136 05/16/18

NDE Reports APR-R24-02 Safe End to Nozzle 09/21/2020

B20MT046 3" Pipe / Valve 10/01/2020

B20PT026 Valve to Elbow W2 and Elbow to Pipe W4 10/01/2020

CISI-VT-20-001 IWE General Exam Torus interior RB 227 to 272 09/24/2020

CISI-VT-20-002 IWE General Exam RF Cavity 340-369 09/21/2020

CISI-VT-20-003 IWE General Exam Torus supports RB 227 09/21/2020

CISI-VT-20-004 IWE General Exam RB 326 - 344 09/24/2020

CISI-VT-20-005 IWE General Exam RB 227-272 09/21/2020

CISI-VT-20-006 IWE General Exam RB 344 - 369 09/20/2020

CISI-VT-20-007 IWE General Exam RB 300 - 326 09/24/2020

CISI-VT-20-008 IWE General Exam RB 272 -300 09/24/2020

CISI-VT-20-013 IWE General Exam Drywell Dome RF 369 09/24/2020

CISI-VT-20-015 Drywell Head Bolting 09/24/2020

ISI-PT-20-001 Instrumentation Nozzle Weld 09/18/2020

ISI-UT-20-004 Nozzle to Cap Overlay 09/22/2020

ISI-UT-20-015 Valve to Elbow 09/24/2020

J1R24-VEN-001 Valve to Tee Weld Overlay 09/22/2020

J1R24-VEN-005 Nozzle Inner Radius 09/22/2020

Work Orders 04937146 Replace 13MOV-131 in R24 07/21/2020

71111.11Q Miscellaneous N-JF-OPS-LORT- Requalification Guide for DFWLC Mod 20-05 0

DFWLC-2005

71111.12 Miscellaneous Purchase Order EDG A & C Fuel Oil Receipt 34461

0714821

Purchase Order EDG B & D Fuel Oil Receipt 35606

25006

Inspection Type Designation Description or Title Revision or

Procedure Date

Purchase Order EDG A & C Fuel Oil Receipt 35610

26089

Procedures AP-15.12 Receiving Inspection for Dedication of No. 2 Diesel Fuel Oil 9

ER-AA-450 Structures Monitoring 9

NO-AA-30 Independent Inspection Process Description 7

ST-15B Suppression Chamber and Drywell Deterioration Inspection 11

71111.13 Corrective Action 04359266

Documents 04361956

Drawings 2.04-30 RFP Turbine Control Diagram C

FM-27B Flow Diagram Control Rod Drive System 03 35

Miscellaneous G080-0056 Hydraulic Control Unit Part Nos 729E950 G1 thru G6 1

Procedures AOP-27 Control Rod Malfunction 15

MP-004.01 Disassembly of Reactor Vessel for Refueling (ISI) 47

OP-13D RHR - Shutdown Cooling 37

OP-25 Control Rod Drive Hydraulic System 093

OP-30A Refueling Water Level Control 24

OP-43A 125 VDC Power System 32

OP-65 Startup and Shutdown Procedures 127

Work Orders 05068725

71111.15 Corrective Action 04109193

Documents 04164618

04344822

04361956

4351640-09

Drawings 1.61.152 Elem Diag RCIC System 9

FM-46B Flow Diagram Emergency Service Water System 46 & 15 57

Engineering 631938 ESW N-513 Thru-Wall Leak Evaluation 46-10-WES-151-37 0

Changes OP Eval

Miscellaneous 4351640 Operability Evaluation

Procedures OP-AA-108-115 Operability Determination 23

71111.18 Corrective Action 04369111

Documents JAF-LO-2012-

Inspection Type Designation Description or Title Revision or

Procedure Date

00004

Engineering 629806 10700 Bus Trip on Loss of Coolant Accident Project to Support 0

Changes Replacement of Normal Station Service Transformer 71T-4

71111.19 Corrective Action 04371087

Documents CR-JAF-2013-

218

Drawings 6.37-362 Valve Outline Drawing, 23MOV-15 C

FM-24A Flow Diagram Reactor Water Cleanup System 12 73

Miscellaneous A391-0057F(A10) Installation Operation and Maintenance Manual Double Disc 8

Gate Valve

TP16-1-112 Recommendations to Resolve Flowserve 10CFR Part 21 5

Notification Affecting Anchor Darling Double Disc Gate Valve (Proprietary)

Wedge Pin Failures

Procedures MA-AA-723-300 Diagnostic Testing of Motor Operated Valves 13

MA-AA-723-302 Installation and Checkout of Quick Stem Sensor (QSS) on 5

Valve Stems

MP-059.60 Anchor Darling Pressure Seal Gate and Globe Valve (ISI) 18

MP-059.78 Disconnecting Leads for MOV Maintenance/Testing 07

MST-023.01 HPCI Turbine Overspeed Trip Test and Calibration 9

ST-22J SRV Electric Lift Logic System Functional and Simulated 9

Automatic Actuation Test

ST-22J SRV Electric Lift Logic System Functional and Simulated 9A

Automatic Actuation Test

ST-22J SRV Electric Lift Logic System Functional and Simulated Automatic 10

Actuation Test

Work Orders 0339333

05061232

71111.20 Procedures OP-65 Startup and Shutdown Procedure 128

Work Orders 04738808

71111.22 Corrective Action 04369251

Documents 04369253

04369255

04369727

Inspection Type Designation Description or Title Revision or

Procedure Date

04369728

Drawings 1.83-37 Auto Depressurization System 22

1.83-38 Elem Diagram - Auto Depressurization System Q

1.83-39 Elem Drawing - Auto Depressurization Sys M

ESK-11AAu Elementary Diagram 09-ECCS1-EP and 09-ECCS2-EP 1

FM-21A Flow Diagram Standby Liquid Control System 11 37

FM-23A Flow Diagram Core Spray System 14 49

FM-29A Flow Diagram Main Steam System 29 63

Procedures ST-1B Main Steam Isolation Valve Fast Closure Test 27

ST-22A ADS Simulated Automatic Actuation Test 26

ST-24J RCIC Flow Rate and Inservice Test (IST) 53

ST-39B-X7A Type C Leak Test Main Steam Line A MSIVs (IST) 17

ST-39B-X7B Type C Leak Test Main Steam Line B MSIVs (IST) 16

ST-39B-X7C Type C Leak Test Main Steam Line C MSIVs (IST) 17

ST-39B-X7D Type C Leak Test Main Steam Line D MSIVs (IST) 17

ST-6M Standby Liquid Control Recirculation, Injection Test (IST, ISI) 11

ST-9CB Emergency Diesel Generator (EDG) B and D Load 6

Sequencing Test and 4KV Emergency Power System Voltage

Relays Instrument Functional Test

Work Orders 04877902

04878371

04878373

04878375

04878383

04878410

05024253

71114.02 Miscellaneous Design Report Nine Mile Point Nuclear Generating Station and James A. 1

FitzPatrick Nuclear Power Plant Public Alert and Notification

System

71114.03 Miscellaneous EP-AA-1014 Radiological Emergency Plan Annex for James A. FitzPatrick 4

Station

EP-AA-1014 James A. FitzPatrick Nuclear Power Plant On-Shift Technical 1

Addendum 1 Basis

Inspection Type Designation Description or Title Revision or

Procedure Date

71114.04 Procedures EP-AA-120-1001 10 CFR 50.54(q) Change Evaluation 10

71114.05 Corrective Action 04170901

Documents 04227133

271107

04302779

04303614

04323222

Miscellaneous Nine Mile Point Nuclear Station and James A. FitzPatrick 0

Nuclear Power Plant 2019 Population Update Analysis

Procedures EP-AA-121-F-11 James A. FitzPatrick Equipment Matrix 3

71114.06 Procedures EP-AA-112-100- Shift Emergency Director Checklist AB

F-01

EP-AA-112-F-01 Command and Control Turnover Briefing Form H

EP-AA-122-300- Drill & Exercise Post-Event Critique & Report Development C

F-04 Guidance

71124.05 Corrective Action 04268293

Documents 04269079

277823

Procedures RP-AA-700 Controls for Radiation Protection Instrumentation 8

17