IR 05000281/1979077

From kanterella
Jump to navigation Jump to search
IE Insp Rept 50-281/79-77 on 791002-05.No Noncompliance Noted.Major Areas Inspected:Auxiliary Bldg,Steam Generator Replacement & Observation of Welding
ML18136A254
Person / Time
Site: Surry Dominion icon.png
Issue date: 10/24/1979
From: Herdt A, Kleinsorge W
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML18136A253 List:
References
50-281-79-77, NUDOCS 7912050555
Download: ML18136A254 (7)


Text

--*------ ---

'

UNITED STATES NUCLEAR REGULATORY COMMISSION

REGION II

Report No. 50-281/79-77 101 MARIETTA ST., N.W., SUITE 3100 ATLANTA, GEORGIA 30303 OCT 2 5 1979 Licensee:

Virginia Electric and Power Company Richmond, Virginia 23261 Facility Name:

Surry Power Station 2 Docket No. 50-281 License No. DPR-37 Inspection at S~_n 1 rte '/near Williamsburg, Virginia Inspect<)'t"""':

L//C)/11;(1

,ft-, W. P. Kleinsorge Approved by: ti/8!'1cll'

A. R. Herdt, Section Chief, RCES Branch SUMMARY Inspection on October 2-5, 1979 Areas Inspected This routine, unannounced inspection involved 29 inspector-hours onsite in the areas of observation of welding, non-destructive examination and associated activities of the Steam Generator Replacement Progra Results Of the two areas inspected, no items of noncompliance or deviations were identifie ss-s-

--,

DETAILS Persons Contacted Licensee Employees

  • W. L. Stewart, Station Manager
  • J. L. Wilson, Superintendent-Operations
  • F. L. Rentz, Resident QC Engineer
  • W.R. Skelley, Jr., SGRP Staff Assistant
  • E. P. Dewandel, Station Staff Assistant
  • C. Rhodes, SGRP Resident Engineer
  • C. Embler, SGRP Welding Engineer
  • J. Goodson, SGRP Resident QC Engineer
  • R. L. Baldwin, Station Supe'rvisor Admin. Services Other licensee employees contacted included 3 construction craftsmen, 5 technicians, 2 security force member Other Organizations Daniel Construction Company (DCC)

C. W. Smith - QC Leader-Technical Service Laboratory D. L. Council - Project Manager NRC Resident Inspector

  • D. J. Burke
  • Attended exit interview Exit Interview The inspection scope and findings were summarized on October 5, 1979 with those persons indicated in Paragraph 1 abov.

Licensee Action on Previous Inspection Findings Not inspecte.

Unresolved Items Unresolved items were not identified during this inspectio.

Independent Inspection Effo_rt The inspector conducted a general inspection of the auxiliary building, the containment and radiographic laboratory to observe construction

-2-progress and construction activities such as welding, post weld heat-treatment, NDE inspection, radiation control, material handling and control, housekeeping and storag The inspector examined the below listed welds while post-weld heat treatment was in progress to determine compliance with applicable regulatory requirements and licensee approved program and procedures.,

Weld N Drawing N RYS 40007-RZ-U2B ETA 40007-EZ-UZB System Main Steam Main Steam In the areas inspected no items of noncompliance or deviations were identifie.

Steam Generator Replacement Observation of Welding and Associated Activities The inspector observed field repair welding of reactor coolant pressure boundry piping at various stages of weld completio The applicable code as required by VEPCO's licensee submittal (Steam Generator Project Surry Power Station Unit Nos. 1 and 2, Revision 9), is ASME Section XI, 1974 Edition with Addenda through the Winter of 197 Based on paragraph IWA-7000 of Section XI, VEPCO is using the original construction code (USAS B31. ) for pipe weldin Welding qualifications and procedure qualifications are being performed in accordance with the latest edition and addenda of ASME Section IX in effect at the time of the qualification. All welding materials were purchased and certified in accordance with Class I require-ments of the ASME cod Nondestructive testing is being performed in accordance with ASME code,Section III and V, 1974 Edition with Addenda through the Winter of 197 The inspector made the following examinations of the repairs to weld N ¥2A of ETA 40004D-1 The inspector examined repair excavations, prior to welding, to deter-mine-whether weld identification/location, and preparation, evidence of QC verification meet applicable procedure The inspector examined weld repairs where the root pass (only) has been completed to determine; weld/welder identification, qualified welder/weld procedure, physical appearance of weld and evidence of QC verificatio The inspector examined weld repairs where welding was beyond the root pass to determine; weld/welder identification, qualified welder/weld procedure, periodic checks of welding variables, use of specified weld material, proper interpass temperature and where applicable pre-heat and post-weld heat treatment and physical appearance of weld ( starts, stops, undercut and surface imperfections).

-3-The inspector observed activities at weld material issue station to determine adequacy of; weld material storage/segregation, oven tem-peratures, issue records and return of unused weld materia Also observed work areas for uncontrolled weld materia Within the areas examined, there were no items of noncompliance or deviations identifie r Steam Generator Replacement - Non-Destructive Examination The applicable codes are specified in Paragraph 6 abov Review of Procedure The inspector reviewed the below listed procedures to determine whether the procedures were consistent with regulatory requirements and licensee commitment (1)

DCC QCP-600 Rev. 1 dtd 1-9-79 "Non-Destructive Examination" (2)

DCC PT-A-0-77 VS Rev O dtd 11-30-78 "Liquid Penetrant Examination of Weldments" (3)

DCC m-A-A-77 VS Rev O dtd 11-30-78 "Magnetic Particle Examination of Weldments" (4)

DCC UT-A-0-77 VS Rev O dtd 1-30-78 "Ultra sonic Examination of Weldments and Thickness Measurements of Pipe and Plate-ASME Code" (5)

DCC RT-A-G-77 VS Rev O dtd 11-30-78 "Radiographic Requirements for X'.'"Ray and Gamma Ray Examination of Weldments". Observation of Work Activities The inspector observed the nondestructive examination activities described below to determine whether these activities were being performed in accordance with regulatory requirements and licensee approved procedure (1)

In-Process Liquid Penetrant Examination was observed for the following welds:

Weld N F lF Drawing N E34 40011-E69 Material Stainless Steel Carbon Steel

-4-The above examinations were compared with the applicable procedure in the following areas:

Use of specified method Penetrant materials identified Penetrant materials analyzed for sulfur Penetrant materials analyzed for ten total halogens Acceptable pre-examination surface Drying time Method of penetrant application Surface temperature Solvert removal Dry surface prior to developing Type of Developing Examination technique Evaluation technique Reporting Results

,

Requalification conducted when required (2)

In-process Magnetic Particle Examination was deserved observed for the following weld:

Weld N R3 Drawing N EOI-U2A Material Carbon Steel The above examination was compared with the applicable procedure in the following areas:

Examination by continuous method Color contrast Overlap technique Yoke Pole Spacing Results consistant with acceptance criteri (3)

In process visual examination was observed for the following welds:

Weld N F IF 3R3 Drawing N E-34 40011-E-69 40007-EOI-U2A Material Stainless Steel Carbon Steel Carbon Steel The above examinations were compared with the applicable procedure in the following areas:

Type of Visual Examination Extent of Examination Qualification and training of personne *

-5-(4)

Completed accepted radiographs for the following welds were reviewed:

Weld N FRI

Drawing N E05 U2C 40007-E03 U2C System Feed Water Main Steam Size Material 16"Sch80 Carbon Steel*

32"xl.312 Carbon Steel

40004-D-1-5 Reactor 31"x 3" Stainless Coolant Steel The above review was compared with the applicable procedure in the following areas:

Film processing requirements Quality of radiographs Film density Use of densitameters Identification Use of Location Markers Method of reducing and testing for back-scutter Selection of Penetrameters Evaluation and disposition of radiographs Data Review and Evaluation

,,

The inspector reviewed one hundred thirty-nine liquid penetrant exami-nation reports, forty-five ultrasonic examination reports, twenty-eight magnetic particul inspection reports, twelve radiographic examination

.reports and the applicable procedures to determine whether the selected records contained or provided reference to the following documents:

(1)

Examination results and data sheets (2)

Examination equipment data (3)

Calibration data sheets (4)

Records on program deviations, if any (5)

Identification of N.D.E. Material such as penetrant, cleaner, couplant, films, tape, et (6)

(7)

The recording, evaluation and disposition of findings are in compliance with the applicable N.D.E. procedures and code requirement Evaluation of data complies with the criteria of the N. procedure.

-6-(8) Evaluation of data performed by a level II or level III examine In the areas inspected, no items of noncompliance or deviation were identical.