IR 05000261/2025004

From kanterella
Jump to navigation Jump to search
Integrated Inspection Report 05000261/2025004
ML26016A662
Person / Time
Site: Robinson 
Issue date: 01/22/2026
From: Matthew Fannon
NRC/RGN-II/DORS/PB2
To: Basta L
Duke Energy Progress
References
EPID I-2025-004-0021 IR 2025004
Download: ML26016A662 (0)


Text

SUBJECT:

H. B. ROBINSON STEAM ELECTRIC PLANT - INTEGRATED INSPECTION REPORT 05000261/2025004

Dear Laura Basta:

On December 31, 2025, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at H. B. Robinson Steam Electric Plant. On January 12, 2026, the NRC inspectors discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Matthew S. Fannon, Chief Projects Branch 2 Division of Operating Reactor Safety Docket No. 05000261 License No. DPR-23

Enclosure:

As stated

Inspection Report

Docket Number:

05000261

License Number:

DPR-23

Report Number:

05000261/2025004

Enterprise Identifier:

I-2025-004-0021

Licensee:

Duke Energy Progress, LLC

Facility:

H. B. Robinson Steam Electric Plant

Location:

Hartsville, SC

Inspection Dates:

October 1, 2025, to December 31, 2025

Inspectors:

C. Dorman, Resident Inspector

J. Zeiler, Senior Resident Inspector

Approved By:

Matthew S. Fannon, Chief

Projects Branch 2

Division of Operating Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at H. B. Robinson Steam Electric Plant, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

PLANT STATUS

Unit 2 operated at or near rated thermal power for the entire duration of the period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed activities described in IMC 2515, Appendix D, Plant Status, observed risk significant activities, and completed on-site portions of IPs. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (1 Sample)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1)

'A' and 'B' motor driven auxiliary feedwater pumps while the steam driven auxiliary feedwater pump was out-of-service for planned maintenance on November 3, 2025

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (3 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1)component cooling water (CCW) pump room (fire zone 5) on October 6, 2025 (2)charging pump room (fire zone 4) on October 28, 2025 (3)

'A' and 'B' vital battery room (fire zone 16) on November 12, 2025

71111.11A - Licensed Operator Requalification Program and Licensed Operator Performance

Requalification Examination Results (IP Section 03.03) (1 Sample)

The licensee completed the annual requalification operating examinations and biennial written examinations required to be administered to all licensed operators in accordance with Title 10 of the Code of Federal Regulations 55.59(a)(2), "Requalification Requirements," of the NRC's "Operator's Licenses." The inspector performed an in-office review of the overall pass/fail results of the individual operating examinations, the crew simulator operating examinations, and the biennial written examinations in accordance with IP 71111.11, "Licensed Operator Requalification Program and Licensed Operator Performance." These results were compared to the thresholds established in Section 3.03, "Requalification Examination Results," of IP 71111.11.

(1) The inspectors reviewed and evaluated the licensed operator examination failure rates for the requalification annual operating exam administered on March 7, 2025, and the biennial written examinations completed on March 7, 2025.

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)

(1) The inspectors observed and evaluated licensed operator performance in the control room during the following risk significant activities:
  • calibration of power range nuclear instruments per process instrument calibration procedure 112 on November 20, 2025

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) The inspectors observed and evaluated a licensed operator as-found simulator exam which included a containment cooling fan failure, a seismic event, high main turbine bearing vibrations, and a faulted steam generator in containment on November 18, 2025.

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (3 Samples)

The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components (SSCs) remain capable of performing their intended function:

(1)

'B' service water booster pump trip on September 17, 2025, due to shorted diodes in motor breaker starter relay coil (Nuclear Condition Report (NCR) 02569145)

(2)loss of turbine electrohydraulic control fluid inventory results in rapid unit downpower and removal of main turbine from service (NCR 02557259), review completed November 28, 2025 (3)exceeded performance criteria for unavailability for 'A' CCW pump during maintenance to replace the inboard pump seal (NCRs 02568758, 02569119,

02569188, and 02566982), review completed December 3, 2025 Aging Management (IP Section 03.03) (1 Sample)

The inspectors evaluated the effectiveness of the aging management program for the following SSCs that did not meet their inspection or test acceptance criteria:

(1)preventive maintenance replacement schedule exceeded for 'A' and 'B' emergency diesel generator dresser couplings for the lube oil and jacket water support systems (NCRs 02555345 and 02502887), review completed November 19, 2025

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (1 Sample)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:

(1)elevated risk (Green) during planned maintenance to replace degrading 'A' reactor coolant system (RCS) loop flow transmitter FT-416 electronics on November 5, 2025

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (3 Samples)

The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:

(1) NCR 02572591, NRC inspector-identified 'A' train 125-volt DC vital battery cells 19 and 46 with cracks or bulging deformation in plastic surrounding positive posts with noticeable battery corrosion emanating from locations, review completed on October 17, 2025
(2) NCR 02571974, 'B' train 125-volt DC vital battery distribution system spurious ground alarms beginning October 10, 2025, review completed on October 23, 2025
(3) NCR 02573570, RCS loop 'A' flow transmitter FT-416 output slowly drifting downward due to instrument degradation, review completed on November 3, 2025

71111.24 - Testing and Maintenance of Equipment Important to Risk

The inspectors evaluated the following testing and maintenance activities to verify system operability and/or functionality:

Post-Maintenance Testing (PMT) (IP Section 03.01) (4 Samples)

(1) OST-908-2, Component Cooling Water Pump A Test, following completion of an extended maintenance and unavailability period on October 7, 2025
(2) OST-101-3, CVCS Component Test Charging Pump C, following replacement of plungers and the primary seal on October 15, 2025
(3) Work Order (WO) 20755434 PMT instructions for validating proper response output following replacement of 'A' RCS loop flow transmitter FT-416 circuitry board due to degraded output performance on November 5, 2025
(4) WO 20762980 PMT instructions for validating proper response output following emergent replacement of reactor trip protection system overpower delta-temperature degrading circuitry module NM-422B on December 10-11, 2025

Surveillance Testing (IP Section 03.01) (2 Samples)

(1) MST-020, Reactor Protection Logic Train 'A' At Power, on November 18, 2025
(2) OST-202, Steam Driven Auxiliary Feedwater System Component Test, on December 3, 2025

OTHER ACTIVITIES - BASELINE

71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:

MS07: High Pressure Injection Systems (IP Section 02.06) (1 Sample)

(1) Unit 2 (October 1, 2024, through September 30, 2025)

BI01: Reactor Coolant System (RCS) Specific Activity Sample (IP Section 02.10) (1 Sample)

(1) Unit 2 (October 1, 2024, through September 30, 2025)

71152S - Semiannual Trend Problem Identification and Resolution Semiannual Trend Review (Section 03.02) (1 Sample)

(1) The inspectors reviewed the licensees corrective action program to identify potential trends in equipment reliability or human performance that might be indicative of a more significant safety issue. The inspectors did not identify a negative trend that could lead to a more significant safety issue.

INSPECTION RESULTS

No findings were identified.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On January 12, 2026, the inspectors presented the integrated inspection results to Laura Basta and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.04

Procedures

OP-402

Auxiliary Feedwater System

Rev. 125

CSD-RNP-PFP-

AB2-0226-001

Auxiliary Building Elevation 226 Pre-Fire Plan

Rev. 3

Fire Plans

CSD-RNP-PFP-

AB2-0246-001

Auxiliary Building Elev 246 Pre-Fire Plan

Rev. 1

AD-FP-ALL-1520

Transient Combustible Control

Rev. 3

AD-FP-ALL-1522

Duties of a Compensatory Fire Watch

Rev. 4

FPP-012

Fire Protection Systems Minimum Equipment and

Compensatory Actions

Rev. 40

71111.05

Procedures

OMM-002

Fire Protection Manual

Rev. 59

71111.11Q

Procedures

PIC-112

F Delta I Calibration

Rev. 18

AD-EG-ALL-1202

Preventive Maintenance and Surveillance Testing

Administration

Rev. 15

71111.12

Procedures

AD-EG-ALL-1210

Maintenance Rule Program

Rev. 5

AD-OP-ALL-0210

Operational Risk Management

Rev. 4

AD-WC-ALL-

200

On-Line Risk Management Process

Rev. 22

AD-WC-ALL-

240

On-Line Risk Management Process

Rev. 6

71111.13

Procedures

CSD-WC-RNP-

240-00

RNP ERAT Guidance

Rev. 1

71111.15

Procedures

AD-OP-ALL-0105

Operability Determinations

Rev. 9

OP-301C

Chemical and Volume Control System Charging Pump C

Operation

Rev. 8

71111.24

Procedures

PLP-033

Post-Maintenance Testing (PMT) Program

Rev. 70

AD-EG-ALL-1217

Mitigating System Performance Index (MSPI)

Rev. 3

71151

Procedures

AD-PI-ALL-0700

Performance Indicators

Rev. 7