IR 05000219/1988017

From kanterella
Jump to navigation Jump to search
Insp Rept 50-219/88-17 on 880613-17.No Violations Noted. Major Areas Inspected:Previously Identified Findings,Spds & Planned Mods to Institute Corrective Measures to Satisfy ATWS
ML20151Q064
Person / Time
Site: Oyster Creek
Issue date: 07/26/1988
From: Blumberg N, Rebelowski T
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML20151Q061 List:
References
50-219-88-17, NUDOCS 8808100307
Download: ML20151Q064 (11)


Text

.

-

.

.

,

.

,-

U.S. NUCLEAR REGULATORY COMMISSION

REGION I

Report No.

50-219/88-17 Docket No.-50-219 License No. DPR-16 Licensee: CPU Nuclear Corporation Oyster Creek Nuclear Generating Station P.O. Box 388 Forked River, New Jersey Facility Name: Oyster Creek Nuclear Generating Station Inspection At:

Forked River, New Jersey Inspectior. Conducted:

J_une 13-17, 1988 u

Inspector: M M kM'

74 M Theodore A.

RebelowsM, Senior Reactor Engineer date

~

~

Approved by:

%

N Norman J. 81 umber OperationalProgr/j, Chief,

/

date

.

ams Section Operations Branch, DRS

-

Inspection Summary:

Routine inspection on June 13-17, 1988 (Report No. 50-219/88-17)

Areas Inspected: The inspection included Previously Identified luspection Findings; Audit of Safety Parameters Display System and the planned modifica-

)

tions to institute corrective measures to satisfy the Anticipated Transients Without Scram (ATWS), including the Alternate Rod Injection (ARI) System and the Standby Liquid Control System (SLCS).

Results: The licensee's Safety Parameters Display System is operational.

Elements that would improve the. system such as additional training, completion of trending of the displayed parameters, additional inputs to aid in determining reactor vessel water levels and *.ne use of source range monitors are under review by licensee.

The ATWS modifications (ARI and SLCS) scheduled for the next outage were acceptable in the areas of safety evaluations and installation specifications.

l 8808100307 880725 PDR ADOCK 05000219 G

PNV

-

. - - -

-

-

-

.

.

.

.

.-

DETAILS 1.

Persons Contacted GPU Nuclear Corporation-Oyster Creek Nuclear Generating Station

  • R.

Barrett, Plant Operations Ofrector

  • P. Crosby, Supervisor, Plant Engineering B. DeMerchant, Licensing Engineer
  • E. Fitzpatrick, Vice President and Director, Oyster Creek
  • J. Kowalski, Licensing Manager J. Laden Meyer, Licensing Engineer
  • D. MacFarlane, Site Audit Manager G. Olaf, Computer Applications
  • W. Pelenski, Manager, Computer Applications
  • A. Rone, Plant Engineering Director
  • P. Smith, Senior Engineer Safeguards J. Sullivan, Plant Operations Director U.S. Nuclear Regulatory Commission E. Collins, Resident inspector
  • L. Meyers, Resident Inspector, Peach Bottom N.P.S.
  • W. Wechselberger, Senior Resident Inspector The inspector also held discussions with other licensee personnel during the course of the inspection.

2.

Previously Identified Inspection Findings (92703)

2.1 (Closed) Violation (NC4) 50-219/85-35-02:

The licensee failed to specify design requirements for partial penetration structural weld used for the installation of instrument racks RK01 and RK02.

The inspector ver ified that the Field Change Request (FCR) C-039642 issued to General Public Utilities Nuclear (GPUN) drawings SN 15081.02 ES-03 and SN 15081.02-ESO4 were corrected and the identified problem welds were documented in a Material Non Conformance Report (MNCR)85-275.

The partial penetration weld repair war completed and verified acceptable by the licensee's Quality Control personnel. Additional corrective actions included inhouse training to site engineers and contracted engineering personnel on the requirements for an adequate weli designs. The inspector observed the configuration of the instrument racks RK01 and RK02.

This item is close _ _ _ _ _ _

'

'.

.-

,.

'

2.2 (Closed) VI lation (NC4) 50-219/85-35-04: The Modification Change Form (MCF) and completion of the Quality Control (QC) inspection of the modifications to the instrument racks RK01 and RK02 was reviewed by the NRC inspectors and a number of discrepancies between procedures / drawing requirements and as-built conditions were identified that were not previously documented by Material Nonconformance Reports (MNCR), Field Change Request (CCR), or any other licensee documentation. The problems and resolution follow:

a)

FCRC-0396(2 to drawings ES-04 and ES-05 specifies partial penetration butt weld, MCF made a seal weld and not the required partial penetration butt weld.

The licensee has determined that the seal weld was substituted for a partial penetration weld due to inadequate guidance

provided on the Field Change Report FCRC-039642.

Corrective actions included the placement of welded stiffener plate over the identified weld.

In addition a technical evaluation dated April 15, 1986, which described the Welding Qualification requirements between American Society of Mechanical Engineers (ASME) and American Welding Society (AWS) codes clarified licensee's welding practices.

b)

The licensee substituted a round hole for a slotted hole in joining two structural members with bolts.

The Material Non-Conformance Report 85-275 corrects drawings ES-04 and ES-05 to use the round hole. The original slotted holes were for ease of construction to give bolts additional clearance, c)

Bolting decalls on ES-04 and ES-05 show the use of washer under both the bolt head and nut. Washers were not installed as required. Additionally, due to the approved use of shorter bolts than specified on the material list, examples of partial thread engagement of nuts on bolts were observed.

The licensee's corrective action included review of specifications for structural joints determining that the bolt ends did not require washers.

The short bolts identified were due to a material receipt problem. Material Nonconformance Reports88-273, 85-274,85-265 documented the problem.

The bolts werc replaced, oroperly torqued and proper thread engagement verified.

The inspector observed repaired areas and verified the material condition.

d)

The licensee placed a smaller sized fillet weld, 1/8" versus 3/16" during steel fabricucion as found on the drawing ES-04 Section 1-1.

l i

.

'.

-

.

..

The placement of this smaller fillet weld was due to the limited accessibility to the structure, as it was previously fabricated off-location versus the modifications in place.

The Licensee evaluation of the weld indicated that the bolting was the prime connector and that welds were placed to hold plates together for ease during drilling.

e)

During construction, three valve manifold was inverted on the instrument rack.

The licensee corrected the reversed manifold.

Additional training was given to contractor personnel to aid identification of component locations.

A training program was conducted for supervision that addressed the need to maintain job surveillance to prevent this type of misassemble.

These items, a to e, are closed.

2.3 (Closed) Violation (NC4) 50-219/85-35-06:

The inspectors review of the prerequisites as aciated with GPUN procedure A158-G1136.010, Rev.

0, PK01 Rack Modif:

lon - Electrical, and a review of plant conditions to det-ae if the prerequisites were met, identified a discrepancy in that paragraph 4.7.3 required the closure of the isolation condenser vent valves and main steam isolation valves when secondary containment is required for work at or near the fuel pool.

This prerequisite was not met.

The licensee recognized the need to place "special precaution and limitation" warnings in the body of a procedure prior to the

'

precedural step where the conditions should be applied.

The Work Management System Manual No. A00-WMS-1220.14 addresses this concern.

This item is closed.

2.4 (Closed) Violation (NC4) 50-219/86-12o02:

The licensee did not perform a determination of the load carrying capacity of existing non-seismic floor penetrations as required in Procedure ES-014 Piping Design Standard for OCHS.

The inspector reviewed licensee's calculation (C1302-251-5320-021/V-1302 251-02) that determined that

,

i the penetration sleeve will carry the load impactad by the restraints.

Carrying load was 2403 psi versus a criteria of 14401 psi. This item is closed.

2.5 (Closed) Violation (NC4) 50-219/86-12-03:

The licensee failed to identify the material of a penetration sleeve prior to a welding attachment. A cheinical analysis was performed and annotated on i

structural weld record.

In addition, engineering personnel were advised that material composition must be determined prior to the performance of a weiding attachmert.

This item is closed.

- -

.

.-

-

'

,

.

.

.

4 2.6 (Closed) Unresolved Item (219/85-13-04):

Pipe hanger support on the Containment Spray System, NQ-2-H39 was not performing its function, i.e., there was-approximately a 3/8" gap between the support and botton of the pipe.

The inspector examined the containment spray piping hanger support NQ-2-H-39 observed that the and the gap had been eliminated by placement of a shim support plate that allows pipe to contact support.

In addition, a safety analysis was performed by the licensee of conditions that existed prior to addition of the support i

plate and the determination was made that the gap did not impair piping function ability and that the adjacent supports were not overstressed. This item is closed.

2.7 (Closed) Unresolved (50-219/86-12-04): A number'of concerns were ident.ified by the inspector in his review of the Structural Weld Record Sheets (SWRS).

The concerns included Quality Control (QC)

signoffs of final acceptance of welds, better job package formats, additional instructions on preparation SWRS, address material requirements and QC annotation of Plant Inspection Reports.

The following changes have been made to classify various items to the Welding Manual Procedure, Control of Welding and Brazing No.

6150-QAP-7220.01 Rev. 3.

a)

The SWRS has been modified in that additional items appear on each SWRS.

Base material, purchase order and heat numbers are recorded with the final acceptance for the total welds requiring signatures by Guality Control; b)

SWRS format is neater and additional sheets can be added to the job package when required.

Space on SWRS is adequate; c)

The use of SWRS, has designated instructions for the Preparation and Field Use of Structures Weld Record Sheets (Exhibit 6)

E6-1 to E6-6 of Welding Manual No. 6150-QAP-7220.1; d)

The revision of GPUN Welding Manual addresses the requirements to list material traceability when welds are not listed individually on the SWRS and, e)

The SWRS requires QC sign-offs including QC-PIR (Plant Inspection Reports).

This unresolved item is closed.

3.0 Safety Parameter Display System (25005]

3.1 Background On October 31, 1980, the NRC published NUREG-0737 which identified Item I.O.2, Plant-Safety Parameters Display Console and' requested

.

-_

__

_

.

.

,

.-

,

.

each licensee to describe, install and fully implement this item using the guidance provided by NUREG-0696 Rev. 2 titled, "Functional Criteria for Emergency Response Facilities."

The purpose of the safety parameter display system'(SPDS) is to assist control room personnel in evaluating the safety status of the plant.

NUREG-0696 final report published in February 1981, described the SPDS. The criteria used in design of systems including function, location size, staffing and display considerations are stated in the report.

NRR/ Licensing SPDS Considerations The licensee has made several submittals over a four year period that addressed schedules for the completion and implementation of SPDS.

(See Attachment A).

In correspondence from NRR to Oyster Creek N.G.S., dated March 5, 1986, NRR concluded that the documentation of SPDS was acceptable with comments.

The Safety Evaluation was issued by NRR and would be confirmed by a post implementation audit. The licensee placed the SPDS on line in December 1987.

3.2 Scope The inspector's guidance for acceptable systems criteria is addressed in NUREG-0696 Final Report, Section 5.0, Safety Parameter Display Systems (SPDS).

3.3 Findings Observations and system reviews for the various subsections of NUREG-0696 Secticn 5 were performed. The subsections titles ard i

number, with the inspector's findings follow.

Subsection 5.1 Functions:

The SPOS op rator aid has been programmed into one of three mnnitors in the control room.

The grouping of information displayed allows operators to readily determine the plant conditions. The displayed parameters were reviewed by the licensee for Human Factor inputs, in that instruments on control boards can be used to serify SPDS displays.

The Emergency Operating Procedures (EOP's' are reflected in thc displays systems.

A validation and verf F; cation program was performed during startup of the SPDS.

The PDS reliability is assured by the use of two (2) redundant computers units.

The computer allows the check of sensors on the SPDS which will display the questionable outputs.

The various interfaces with non-safety related systems is protected by isolation units.

One area not presently included in SPDS is the ibility to automatically compute the displayed parameter trends.

The licensee stated that this item would be modified at the next outage.

..

.-

-

-.

_-

.. -.

'

'.

-

.

.

Subsection 5.2-Location:

The SPOS is located on one of three monitors on center console.

It is readily accessible to senior operators, shift advisors and shift supervisor.

Subsection 5.3-Size:

The SPDS is of a s;ze compatible with the existing space in the control room.

It doas not interfere with normal movement or full visual access to control board.

Subsection 5.4-Staffing:

The design of SPDS is such that no additional personnel are required to monitor the screens during an emergency.

Subsection 5.5-Display Consideration:

The SPDS display addresses the five areas of interest.

These are related to functions that include the monitoring of Reactivity Centrol, Reactor Coolant System Intagrity, Radioactivity Control, Reactor Care Cooling and Heat Removal and Containment integrity.

Each display includes a number of significant parameters for the particular area of interest; in some cases two or more screens are used to aid in following an E0P.

The displays are manually selected by the operator.

Two areas not represented on the monitors are (1) the NRC requested source range monitors for reactivity control and (2) no audible notification to alert personnel of a failure of a signal input to SPDS during an uperating conditions.

Licensee comments indicate that placement of SRM's on screens is ur. der review.

The audible alarm has not been addressed.

Section 5.6-Design Criteria:

The licensee has addressed the

~~

interface of signal conditioners such as isolation devices.

The reliability of SPDS is addressed with redundant camputers. No technical specificatio's are necessary based on tqe licensee's safety analysis and no compensetory measures the loss of both computers s'

are necessary.

3.4 General Observation and Conclusions The training provided operators war an informational 'j?e of package with training time on console to being up various screens for E0P training. The validation and verification of SPDS utilized. video licensee's tape that simulated an anomaly.

The training department

will review the video tape with the intent of presenting the l

operators with a dynamic training session.

The licensee sti.ed that l

a review of this area of training would be made during the..oerator requalification program.

The personnel interviewed Cirinc inspection demonstrated sufficient depth of knowledge of the SPDS to determine plant condition and i

implement corrective action; in an efficient manner.

l

-

.

,..

,

,

,

No audible alarm exists to alert personnel c' off normal

-

parameters on SPDS.

NRR requested the inclusion of Source Range Monitors (SRM's) to

-

be displayed. This item has not been resolved.

The NUREGS-0696 states that the SPDS shall be capable of

-

presenting magnitude and the trends of displayed parameters.

The trending presently does not appear on screen.

The areas of uncompensated water levels of vessel presently

-

requires calculations to determine true levels and wave motion in suppression chambers need corrective factors. These level

,

calculations should be incorporated in the SPDS program.

This

item has been identified by the licensee and presently is under review.

The licensee is present SPDS has the ability to aid operators in following the E0P transients. Additional updates nf above items will allow a greater flexibility to monitor plant conditions.

3.5 Update of Emergency Operating Flow Charts While reviewing SPDS parameters to be used by E0Ps, the inspector observed that the licensee has developed flow charts for E0Ps for use in the Control Room.

The flow charts are a duplication of the E0Ps and as such must be under administrative control. At the time of the inspection, no procedure exists that would update flow charts if a revision to a E0P is made.

This item was brought to the attention of the licensee and remains an unresolved item pending revision of the administrative controls to verify control rcom flow chart updates.

(86-18-01)

4.

Anticipated Transients Without Scram Rule (ATWS) 10 CFR 50.62 (25020)

.

The licensee has scheduled for the next refueling outage, two modifica-tions that will provide additional protection to achieve reactor shutdown.

The modifications consist of (1) Alternate Rod Injection System and (2)

the Enrichment of Sodium Pentaborate Solution for the Standby Liquid Control System.

The following reviews were performed.

t 4.1 Alternate Rod Injection System (ARIS)

,

?

The ARIS modificatinn, MDD-QC643A Rev 2 has been generated to mitigate ATWS, which is an operational event caused by a failure of

.

the Reactor Protective System (RPS) to shutdown reactor.

In the

.

l event that RPS fatis to scram, there was no alternate automatic system to cause control rod injection.

_ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ - _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ - _ - _ - _ - - _ - _ _ _ _ _ _ _ - - - _ - _ - _ _ _ _ _ _ _ - _ _ _ - _ _ _ - _ _ - - - _ - - _ - _ _ - _ _ _ _ - - - _ - _ _ - _ _ _ _ _ - _ _ _ _ _ _ _ - - _ - - - _ _ _ _, ~ _ - - _.

-

.

-.

,

.

.

This modification installs a ARI system to cause control rod injection by depressurizing the scram air header.

The inspector reviewed the Modification: Design Description which-specifies the addition of a new ARI system logic relays, test switches and indicating lights in_the rear of Control Panel 8R.

Additional changes that include manual initiation, manual reset, loop isolation devices and-five new ARI solenoid valves are also added to the scram header. Annunciators are to be added to Control Panel 5F/6F.

The modification package description addresses numerous elements that are to be addressed prior to and during outige changeout. The modification is detailed with clearly defined mechanical'and

electrical drawings. Tha work package engineering details were

'

satisfactory. No deficiencies were identified.

4.2 Standby Liquid Control System (SLCS)

The need for additional methods to shut down the reactor in a ATWS event encompassed the need for reduction of risk.

The ATWS Rule as specified in 10 CFR 50.62 states that each boiling water reactor must have a SLCS with a minimum flow capacity and boron content equivalent

in control capacity to 86 gallons per minute (gpm) of 13 weight percent (wt%) sodium pentaborate solution.

Based on review of licensee documentation a modification will be performed during the next outage.

The present solution in SLCS tank is to removed, tank cleaned and a new concentrate solution will be added to conform to the rule.

The inspector review included

licensee's safety evaluation, installation specification and technical specification submittal.

Based on the inspector concerns,

the licensee's has under review the examination of the agitation piping, electrical heater element and possible removal of any i

solidified boron at the tank bottom.

In adoition the review of Technical Specification submittal is identified the need of for accurate SLCS tank level readouts.

The preseat calibration of the ultrasonic level detector requires removal from the SLCS tank. The J

licensee has under review the monitoring of levels during pentaborate i

drainage and refill of SLCS tank.

No deficiencies were identified.

j

t i

.

I

, '

'

.

.

.

-

.

.

.

,.

5.0 Management Meetings Licensee management was informed of the scope and purpose of the inspection at an entrance meeting conducted on June 13, 1988.

The findings of the inspection were periodically discussed with licensee representatives June 17 during the course of the inspection. An exit was conducted on (see paragraph I for attendees) at which time the findings of the inspection were presented.

At no time during this inspection was written material concerning inspection findings provided to the licensee by the inspectors.

The licensee did not indicate if any proprietary information was involved within the scope of this inspection.

--

-

- -

-

-

-

-

-

-

.

.-

.

.

ATTACHMENT A

-

,

A listing of pertinent reference documents is listed by report paragraphs.

Previously Identified Inspection Findings (Paragraph 2)

Field Change Request (FCR) C-039642.

Repairs to Instrument Racks

Material Non Conformance Report-(MNCR)85-275 Titled Partial Penetration

Weld Orawings SN15081.02 ES-04 and ES-05

Material Non Conformance Reports85-265, 273 and 274 addressed bolting

problems General Public Utilities Nuclear (BPUN) procedures A15B-G1136.010 Rev. O,

,

Rack Modification

Management System Manual No. A00WMS-1220.14 titled Preparation, Review

and Approval of Work Procedures Seismic Calculation C 1302-251-530-021 V/-1302-251-02

GPUN Chemical Analysis Report A53 Grade A material

Welding Manual Procedure, Control of Welding and Brazing No. 6150-QAP-

7220.01 Rev. 3 Safety Parameters Display System (Paragraph 3)

NUREG 0737 Classification of TMI Action Plan Review

NUREG 0737 Supplement I Clarification of TMI Action Plan Review

NUREG 0696 Draft Functional Criteria fer Emergency Response

,

NUREG 0696 Final Functional Criteria for Emergency Response t

Generic Letter 82-33, December 1982

'

Licensee subnittals of April 2, June 6 and September 1984

Oyster Creek SPDS-Verification and Validation Report

On Site Computer Configuration Control - SOCS ADM 7340.02

NRR Correspondence to GPUN dated July 19, 1984, and Merch 5, 1986

Installation Specification for Control Room Console - OCIS-402761-002

i Anticipated Transients Without Scram (ATWS) (Paragraph 4)

i Installation Specification for Standby Liquid Control 1.3.328252-001

.

Safety Evaluation for the use of Enriched Sedium Pentaborate Solution in

+

the SLCS Modification Design Description for Alternate Rod Injection Systems

-

,

E Oyster Creek Nuclear Generating Station - Technical Specification (TS)

'

Submittal (TS Change Request No. 162)

,

Liquid Foison System Functional Test - No. 612.4.002

Multi-ranger Programmable Level System (PL-28I)

Temporary Instruction 2500/20 - Inspection to Determine Compilance With

The Anticipated Transit With Scram (ATWS Rule 10 CFR 50.62)

- '

.

v

---

-.

,,.,te,-

-

,-:,-y--n-

,- e e r

e--

-*-r-

--g-~

  • ~---r-'*7

- * * *

-v"*r e

a d-

=,eee

- - - -

- + * - ' - -

--w&+

?-r:

"-