IR 05000206/1986011

From kanterella
Jump to navigation Jump to search
Insp Repts 50-206/86-11,50-361/86-16 & 50-362/86-16 on 860414-25.No Violation Noted.Major Areas Inspected:Inservice Insps,Open Items,Part 21 Item & IE Notices & Bulletins
ML13323B134
Person / Time
Site: San Onofre  Southern California Edison icon.png
Issue date: 05/15/1986
From: Clark C, Jim Melfi, Thomas Young
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
To:
Shared Package
ML13323B133 List:
References
50-206-86-11, 50-361-86-16, 50-362-86-16, GL-85-22, IEB-85-003, IEB-85-3, IEIN-84-37, IEIN-85-047, IEIN-85-049, IEIN-85-066, IEIN-85-071, IEIN-85-47, IEIN-85-49, IEIN-85-66, IEIN-85-71, NUDOCS 8605300638
Download: ML13323B134 (10)


Text

U. S. NUCLEAR REGULATORY COMMISSION

REGION V

Report Nos 50-206/86-11,

-361/86-16, 50-362/86-16 Docket Nos. 50-206,

-361, 50-362 License Nos. DPR-13, NPF-10, NPF-15 Licensee: Southern California Edison Company P. 0..Box 800 2244 Walnut Grove Avenue Rosemead, California 91770 Facility Name:

San Onofre Nuclear Generating Station Units 1, 2 and 3 Inspection at:, San Clemente, California Inspection conducted:

Arpil 14-25, 1986 Inspectors:

C. C

, Reactor Inspector Date Signed Ali pcf o nspe Dfte igned Approved by:

T. Young Jr.,

ief Date Signed Engineering Section Inspection During the Period April 14-25, 1986 (Report Nos. 50-206/86-11, 50-361/86-16 and 50-362/86-16)

Areas Inspected: A routine unannounced inspection of Inservice Inspections (ISI), Open Items, Part 21 Item, IE Notices and Bulletins. The inspection involved Module Nos. 73753, 92701, 92702 and 9270 Results:

In the areas inspected, no. violations of NRC requirements were identifie PDR ADOCK 05000206 G

PDR

_

DETAILS Personnel Contacted

  • H. Morgan, Station Manager
  • M. Wharton, Deputy Station Manager
  • J. Reilly,. Station Tech. Manager
  • J. Curran, Manager, QA
  • W. Zintl, Manager,.Compliance C. Couser, Lead Compliance Engineer V. Gow, Codes QA Engineer
  • W. Savage,'Maintenance Planning Supervisor
  • C. Olvera, ISEG Engineer
  • D. Herbst, ISEG Supervisor
  • M. Sullivan, ISEG Engineer
  • D. Henry, ISI Engineer
  • D. Schone, Site QA Manager J. Schramm, Unit 1 OP P. Croy, IST Coordinator W. Lazear, QA Supervisor M. Ramsey, Codes.QA Engineer R. Phelps, Supervisor, Nuclear Systems Engineering G. Gibson, Supervisor, Compliance T..Graham, Supervisor, Electrical Test J. Grimes, Supervisor, Plant Maintenance, Electrical and Mechanical J. Cronk, Electrical Supervisor
  • Denotes those. individuals attending the exit meeting April 18, 198 The inspectors also held discussions with other licensee and contractor personnel during the inspectio.

Licensee Action on Previously Inspector Identified Items (Closed) Followup Item No. 50-206/85-26-01:

Licensee Review of Inservice Testing (IST) Program Procedures During the previous-IST inspection the licensee stated they would review the inspectors identified procedure discrepancies and/or weaknesses and take remedial action as require During this inspection a licensee representative stated that they had performed a 100 percent review of all IST procedures and issued

.

changes addressing the previously identified procedure discrepancies and/or weaknesses, plus some additional items they identified during their review. The above procedure improvements were-confirmed by a sample review of the.latest IST procedure This item is close (Closed) Notice of Violation No. 50-206/85-26-02:

Incomplete Summary Records of Corrective Actions Performed on Pumps During the previous IST inspection the licensee IST procedures required.a summary record of corrective action or.a licensee check-off sheet 5.2 in the IST program records or station engineering files, for pump repair work. The above identified repair documents were not-always file During this inspection the licensee identified that the missing records had been placed in the IST program records/station engineering files, and this was confirmed. IST procedures have been changed for San Onofre 1 to eliminate the use of the licensee summary record of corrective action (check-off.sheet 5.2) form for future pump repair work. The licensee has taken the position that the San Onofre Maintenance Management System (SOMMS) contains Maintenance Order (MO) records and the Corporate Documentation Management (CDM) records contains completed test records, memoranda, Nonconformance Reports (NCRs), and all this data is readily available to site personnel as a summary record of corrective actions performed on pump This it~m is close (Closed) Followup Item No. 50-206/85-26-03: Review.of Licensee

Memorandum on Acceptance Criteria for RHR Pump Differential. Pressure The acceptance criteria used for differential pressure (DP) during IST of RHR pumps, did not appear to agree with the reference test values specified.in pump test records.. After the previous IST inspection, the licensee identified a.memorandum that explained th basis for use of the subject acceptance criteri During this inspection a memorandum -for file, subject: -Inservice Testing of Residual Heat Removal.(RHR) Pumps at-SONGS-1,'.dated September 18, 1981, from D. W. Bailey, was reviewe This subject memorandum stated that "setting reference pump test conditions from previous tests every time would be a difficult task and in some cases could be harmful to the system. Therefore, as an intermediate method, until a design change can be completed, installing inlet pressure gauges on the pumps, the calculated DP will be compared to the as-built pump performance curve The

"acceptable" range will then become greater than or equal to 0.93 times the differential head taken from the point on the curve, at a reference flow rate. This and the vibration data results will be used as the basis for pump operability."

Based on the above memorandum and other information provided by the licensee, the question on the subject DP discrepancy appears to have been answere This item is close (Closed) Unresolved Item No. 50-206/85-26-04: Records for 14 Relief Valves Were Not Readily Accessible for Audit During the previous IST inspection the licensee-was not able to provide requested associated records on 14 relief valves, for review during the site inspection perio..During this inspection, available records were.reviewed."

This item is close (Closed) Followup Item No. 50-206/85-26-05: ' A Comprehensive Licensee Review of IST Program Activities'Appears Necessary A licensee representative stated a comprehensive review of all IST

.program activities was performed after the initial IST inspection and provided documentation of some of the improvements and training generated from this review. During discussions with the licenseeit was identified to them, that it is to their advantage to clearly record all the changes, positions and results generated,during'

reviews of activities at their sit It'appears that the-licensee has taken positive action on this subject and the program has improved since the initial inspectio This item is close (Closed) Unresolved Item No. 50-206/86-05-01: The Location of All of San Onofre Unit No.1 ISI Records Were Not Readily Identified During this inspection the licensee provided copies of inservice inspection (ISI) reports, which were issued by the organizations that performed inservice inspections on San Onofre Unit' No. These reports contained copies of ISI records, inspection results and evaluations, for inspections performed during the years 1973, 1975, 1976, 1978, 1979, 1980 and 198 During this inspection, licensee representatives stated the following:

"The only complete set of or copies of ISI records on site for San Onofre Unit No. 1, if the original inspection records we-re not maintained on site, were the ISI reports identified above."

f

"Some companies like Westinghouse, who performed ISI's in 1980 and 1984,'.have retained the original ISI record This will not be the case for future inspections.."

o

"During.this and the previous inspections, the licensee copy of the ISI reports identified above, were not index in a system

'maintained in the corporation 'documentation management (CDM)

system."

Without an index of available.quality ISI inspection reports, there i no-controls or' identificatio n as to what and where this information is on site... Some ISI reports were found in an uncontrolled area, in another building, on the floor and

in boxes under an TSI engineer desk and work table Some SI reports were setting on various desks in the CDM, not in a controlled file.are It is the-licensee position that the official records (not on site) are maintained off site under the control of the ISI contractor who performed the IST inspection and issued the original repor The subject copies of the reports had been removed from a control area prior to January 1986, when that area was reassigned. This movement was not controlled by written documents, and that is the reason all the copies of the reports did not end up in a controlled are This lack of control of copies of ISI reports/inspection information at all times on site, does not appear to follow the licensee position/statement that all quality records/information required o site are stored in CDM for accurate retrieval of information without undue delay. When the above situation was brought to the licensee attention, they took immediate actions to transfer the applicable copies of the ISI.reports into the CDM system and stated they will ensure all future movement of -similar information on site is controlled by written documentatio This item~is close (Open) Followup Item No. 50-361/85-22-03:

Safety Analysis and ASME Section XI Operability Limits for Inservice Testing of Pumps During a previous inspection, inspectors questioned whether the operability limits-of IST requirements for pumps were bounded by the safety analysi During this inspection the licensee provided a copy of a memorandum from K. D. Flynn to P. A. Croy, dated February.17, 1986, on the subject.of "Safety:Analysis and ASME Section XI Operability Limits for In Service Testing of Pumps". This memorandum provided the results of a licensee evaluation of the inservice testing of pumps program at SONGS 1, 2 & 3, in order to determine whether ASME Section XI acceptable test parameter.ranges are bounded by FSAR analyses. The last paragraph of the subject memorandum stated in part, "from the above discussion it appears that the inservice testing of-pumps program conducted in accordance with section XI of the ASME B&PV code provides adequate assurance that pump performance will not be allowed to degrade to the point where FSAR analyses become invalid."

The inspector noted that attachment I to this memorandum, titled "Unit 1 Pump IST Reference Values", did not list the RHR pumps. A licensee representative stated this deletion of the RHR pumps from attachment I, appeared to be an oversight and they will look into it. The.memorandum identified below, includes the RHR pump A memorandum from P. A. Croy to.J. Rainsberry, dated April 7, 1986, on the subject of "In-Service Inspection Acceptance.,Criteria San Onofre Nuclear Generating Station, Unit 1", requested a new review

to determine if any pumps are currently being tested and accepted which do.not meet the minimum.required performance criteria of the safety analysis.. As of this inspection a-,reply to the above memorandum, with the results of this latest review, were not available for inspector review. This is followup item no.:

50-206/86-11-01 for Unit This item will'remain open until the identified review in the April 7, 1986 memorandum is completed and reviewed by an inspecto (Open) Unresolved Item No. 50-206/85-12-01 Failure to Correctly Calculate the As-Found Leakage Rate from Containment During an Integrated Leak Rate Tes The licensee is still working on this Item and has not completed its revie This item will-remain open until the li'censee's review is completed and reviewed by an inspecto.

Licensee Action on IE Bulletins (Open for Units 1, 2 and 3) IE Bulletin 85-03:

Motor-Operated Valve Common Mode Failures During Plant Transients Due to Improper Switch Setting This TE Bulletin deals with Motor Operated Valve (MOV) common mode failure This bulletin specifically addresses MOVs located in the High Pressure Safety Injection (HPSI), Core Spray and Emergency Feedwater system There have been instances where valves did not lift because the Differential Pressure (DP) across the valve was such that the torque generated by the motor could not lift the valve. The licensees were requested to develop.and implement a program to ensure that the torque and torque bypass 'switches-were correctly set to operate the valve against the maximum DP. The basis for this maximum DP has to be an analysis for both normal and abnormal event During the inspection, it was noted that the licensee was proceeding with work per this bulletin, in Unit 2. In addition, the licensee personnel stated that they were looking at other MOVs in other safety related systems (e.g. Low Pressure Safety Injection) and will attempt to complete the bulletin specific MOVs before restart. The valves in Unit 3 will be checked per this bulletin, during the next refueling (Cycle 4).

Also, the bulletin specific MOVs for Unit 1 will be checked per this bulletin, before restar The inspectors understanding of additional information required for closing this bulletin includes the following items: Review and document the design basis for the calculated maximum DP across the valve Review the switch settings for valves, that are derived from the design basis, to ensure the valve will lif '6 Review documentation on switch settings and/or-changes to switch setting Review the appropriateprocedures on switch setting Determine how the correct switch settings will be-maintained over plant lif Observe work on several MOVs and ensure that procedures are bein properly implemente INSPECTION RESULTS:.

Item A -

above, will be.discussed in the licensee report on IEB 85-03, which is due May 15, 1986. The licensee.stated that the basis for the maximum calculated DP across the valve would include line breaks.' This sub item will remain open pending review of the report at a-later tim Item B --is the amount of movement that the bypass switches are set fo The licensee stated that the bypass switches are set to 15-20%.of movement for gate valve's, 20-25% for globe valves. This setting appears adequate to ensure proper lifting of the valves. This sub-item is close Item C.- is the documentation on the switch settings. The licensee had started work on this bulletin for Unit 2. In the procedure data sheets, the licensee recorded as-found and as left switch settings for the torque and bypass switches. A review of 3 completed data forms, revealed that they appeared to be complete with signoffs and the documentation seems adequate. This sub-item is close Item D - is the review of the procedures used in adjusting the torque and bypass switche The procedures used are S0123-I-6.7 and S0123-1-6.8 for the motor operated valves and 30123-1-8.313 is the procedure for th Motor Operated Valve Analysis and Testing System (MOVATS).. The MOVATS system may be used as a diagnostic aid for the. motor operators. Switch settings are kept in the as found condition or, when changed, generally require supervisor approval. When setting of the limit and/or torque bypass switches, the-licensee normally appears to rely on the number of hand cranks. The torque-switches, when set, are verified to be in the mid position. The MOVATS system may be used to help verify the switch settings. This sub-item is-open, pending work on sub item Item E -

The correct switch settings will be maintained 'over core life with the -official copies in the CDM, and MOV data also maintained in the maintenance department (for information). This sub-item is close Item F -

The observation of actual work was not performed by the inspector. Actual -work should be observed on the valve This sub-item remains open, pending further inspectio.

Licensee Action on-I.E. Information Notices (Closed for Units 1, 2.and 3) I.E. Information Notice No. 84-37:

Use of Lifted Leads and Jumpers During Maintenance or Surveillance Testing This notice deals with the independent review of the use of lifted leads and jumpers. Mentioned in tihis notice is San Onofre Unit 3, where 4 of 8 reactor trip breakers did not have their shunt tri devices operable because some leads were not connected to the Reactor Protection System (RPS). The cause for this was personnel failing to reconnect leads that had been lifted during an 18 month surveillance. The surveillance procedure lacked independent verification of proper system restoratio There are 2 solutions to this problem. Either hardware changes or procedural changes to prevent further problems. Due to the infrequency of the root cause event (once in 18 months), the licensee decided not to install switche The procedural changes initiated by the licensee requires a second operator verification-of proper system configuration. The licensee has also modified 235 procedures and implemented training on the revised procedure This item is close (Closed for Units 1, 2 and 3) I.E. Information N6tice No. 85-47:

Potential Effect of Line-Induced Vibration in Target Rock Solenoid Operated Valve This notice alerts the licensee that certain models of Target Rock (TR) solenoid operated valves failed during Environmental Qualification (EQ) testing. San Onofre Nuclear Genbrating Station (SONGS) has.several of the TR valves mentioned in this notic This item was addressed in previous inspction report no /85-18, 50-361/85-17 and 50-362/85-16 issued July 2, 1985, under a Part 21 Item. This item was considered closed for Units 2&3 based on the licensee's issued Design ChangePackages (DCPs)-.

The licensee stated that there are no Target Rock Valves in Unit This item is close (Closed for Units 1, 2 and 3) I.E. Information Notice No..85-49:

Relay Calibration Problem This notice provides information on calibration of an Agastat Time-Delay Relay. An Agastat is a solenoid switch with a air passage that slows down the action of the solenoi If this switch was calibrated horizontally, then operated vertically, gravity has an effect in the time to operate the switc The licensee addresses this with procedures S0123-II-li.152 and S0123-II-11.160. These procedures address the functioning of newly

installed circuitry and calibration of time delay relays in place for the proper time dela This item is close (Closed for Units 1, 2 and 3) I.E. Information Notice No. 85-66:

Discrepancies Between As-Built Construction Drawings and Equipment Installations This notice deals with the as-built construction drawing not

completely reflecting equipment installations. Also, modifications of equipment might be susceptible to the same proble To verify that construction drawings reflected as-built installation, the licensee has performed a plant walkdown of Unit During construction of units 2 and 3, design changes were incorporated into the drawings in a formal review process. When Units 2 and 3 completed their start-up phase,'the drawings were verified to reflect as-built installation To ensure that drawings will reflect any modifications to Units 1, 2 and 3, the licensee issued procedures S0123-XIV-3.1 and S0123-V-4.1 These procedures require a review process at.several levels, system walkdowns (before any changes are made), contkol documents, quality assurance.(QA) procedures,,and configuration control personne The procedures appear to adequately addressthis notic This item.is close (Open for Units 1, 2 and 3) I.E. Information Notice No. 85-71:

Containment Integrated Leak.Rate Tests This notice addresses a potentially significant problem pertaining to Containment Integrated Leak Rate Tests (CILRTs). The problem is a misinterpretation between Local Leak Rate Testing and CILRT The licensee currently is reviewing this problem. This item will remain open until the licensee's review is completed and reviewed by an inspecto.

LicenseeAction on Generic Letters (Open for Units 1, 2 and 3) Generic Letter No. 85-22:

Potential for Loss of Post-Loca Recirculation Capability Due to Insulation Debris Blockage:

This letter addresses the potential loss of recirculation capacity due to a LOCA. This letter informs the licensee of the concern of LOCA generated debris blocking the emergency sum The analysis of this item was based on Regulatory Guide 1.82, Rev. The letter informs the licensee of a new revision of this Regulatory

.9 Guide, which has new insights into the amount of debris that might be generator during a LOC At the time of this inspection, a licensee representative stated they had notreceived this generic letter and could not provide any documentation that.the subject of the letter had been reviewed or evaluated by the license This item will remain open until the licensee has completed a review of-the new-information and the results.of this review are reviewed by an inspecto.

Licensee Action on Part 21 Items (Closed for Units 1, 2 and 3) Part 21 No. 85-13-PO: Anchor/Darling-- Missing Lock-Welds on Swing Check Valves o

The licensee received the two letters from Anchor/Darling identified below: Anchor/Darling to Greg Agosti, Procurement Agent, dated July 31, 1985, on the subject of missing lock welds on hinge pin set screws 'at Palo Verde Nuclear Generating Statio Anchor/Darling to Greg Agosti, Procurement Agent, dated December 11, 1985, on the subject of lock welds also missing at the hinges support/hinge support-capscrews interface and at the hinge support/bonnet interfac After reviewing the two letters identified above, the licensee WII)issued.TCN's to.maintenance procedures S023-I-6.19 and 8023-1-6.71, to include a requirement to verify that setscrews had been lockwelded or peened in place and that missing hinge support welds were installe This item is close.

Observation of NDE Activities The inspectors observed ultrasonic examination being performed on selected reactor vessel head weld The following attributes were evaluated and found to be consistent with the.approved procedure and ASME Section XI requirements:

the type of.apparatus used, scanning technique, extent of coverage, calibration of the instrumentation and system prior to examination, beam angles, size and frequency of the search unit, limits of evaluation and recording of indications, and determination of acceptance limit.

Exit.Meeting On April 18, 1986, an exit meeting was conducted with the licensee representatives identified in paragraph 1. The inspectors summarized the scope of the inspection and findings as described in this report.