DCL-98-163, Forwards Change 14 to Rev 18 of Physical Security Plan. Changes Do Not Decrease Safeguards Effectiveness of Plan & Submitted Pursuant to 10CFR50.54(p).Encl Withheld

From kanterella
Jump to navigation Jump to search
Forwards Change 14 to Rev 18 of Physical Security Plan. Changes Do Not Decrease Safeguards Effectiveness of Plan & Submitted Pursuant to 10CFR50.54(p).Encl Withheld
ML20196B901
Person / Time
Site: Diablo Canyon  Pacific Gas & Electric icon.png
Issue date: 11/24/1998
From: Oatley D
PACIFIC GAS & ELECTRIC CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
DCL-98-163, NUDOCS 9812010207
Download: ML20196B901 (1)


Text

.. . . _ . - . . . -.

Pacific Gas and

,m -Electric Company David H. Catley Diablo Canyon Power Plant Vce President-Diablo Canyon PO Box 56 Operations and Plant Manager Acla Beach, CA 93424 805 545 6000 1

November 24,1998 PG&E Letter No. DCL-98-163 U.S. Nuclear Regulatory Commission

! ATTN: Document Control Desk

! Washington, DC 20555 i Docket No. 50-275, OL-DPR-80 Docket No. 50-323, OL-DPR-82 Diablo Canyon Units 1 and 2 Chance 14 to Revision 18 of the Physical Security Plan l

Dear Commissioners and Staff:

l Enclosures 1 and 2 contain safeguards information regarding changes to Revision 18 of the Diablo Canyon Power Plant Physical Security Plan (PSP). These l changes do not decrease the safeguards effectiveness of the plan and are submitted pursuant to 10 CFR 50.54(p).

Enclosure 1 describes the proposed revisions to the PSP. Enclosure 2 includes the pages of the PSP incorporating the changes identified in Enclosure 1. Changes are indicated by side bars in the left margin.

Should you require further information or clarification, please contact Ron Todaro, Security Director, at (805) 545-4309.

Since ,

David H. Oatley l cc: Ronald G. Todaro CCC/RMS

[e gI r

l I I Enclosurey g(J.C i

SECURITY SAFEGUARDS INFORMATION

[When Separated From Enclosures Handle This Document As Decontrolled) 9812010207 981124 I PDR ADOCK 05000275 F P4

!