ML20202A983

From kanterella
Jump to navigation Jump to search
Informs That Modesto Irrigation District No Longer Seeking Addl Interconnection with Pacific Gas & Electric Co at Pittsburg,Ca & Matters First Addressed in 980429 Comments in Opposition to Restructuring of Util Have Now Become Moot
ML20202A983
Person / Time
Site: Diablo Canyon, Humboldt Bay
Issue date: 01/18/1999
From: Duncan W
DUNCAN, WEINBERG, MILLER & PEMBROKE, P.C. (FORMERLY
To: Steven Bloom
NRC (Affiliation Not Assigned)
References
NUDOCS 9901280332
Download: ML20202A983 (2)


Text

.__

1- .

. r

.$aw &

Banoan, TL/my, fe- V9%/4,908

-EDYWovE Is"CYG i. . * ,

SUITE 800 .44( eIR,pil /(f.,

1615 M STREET. N.W. $U'TE a*'s JAMESo.rCMeROne

'* **#'""^**""'

('C""0"D F ^"^" WASHINGTON, D.C. 20036 PORTLAND, OREGON .750s i ROBERT WEINSERG JANICC L. LOWER esO3sg437gaa j JErrREY C. GENZER 4202)4674370 MEuNDA J. HORGAN S. DRADLEY VAN CLEVE M C AE R. T TELECOPY 4202) 4474379 TANJA M. SHONMWILER dwgpSN$wgp.00m USA c. oAST *

"""C # """"# *

  1. u _g seO MGC' A NDLESS TOWERS l 3.. rREEoOM CIRCLE  ;

Or COUNSEL rREDER Cx L. wuER.JR. sANT4 CLARA. CAurORNiA ..o.. q RsCHARD pl PEL21 44oesess.4404 TERRY E. SINGER gARRyr,NcCARTHY JAMES r. rLUG Or COUNSEL .

PAULA 01. DINERSTEIN t ADMITTED IN WA ONLY 2700 SELLEVUE AVENUE

  • ADMITTED IN MO ONLY

. ADM,TTEo N NJ ONLY January 18,1999 SvRACUSE,NEWyOR ,u ,.

UMITED TO MATTERS AND (3153 4 76-4318 PROCECDINGS DErORE THOMAS J. LYNCH FEDERAL COURTS AND AGENCIES Or COUNSEL Mr. Steven D. Bloom i Project Manager Project Directorate IV-2  ;

Division of Reactor Projects Ill/IV ,

Office ofNuclear Regulation United States Nuclear Regulatory Commission  !

Washington, DC 20555-0001 -

1 Re: Pacific Gas and Electric Company; Humboldt Bay Power Plant, Unit 3; Diablo Canyon Nuclear Power Plant, Units 1 and 2; NRC Docket Nos. 50-133, 50-275, and 50-323

Dear Mr. Bloom:

As I have previously advised by telephone, Modesto Irrigation District ("MID") is 1 no longer seeking an additional interconnection with Pacific Gas and Electric Company ("PG&E")  !

I at Pittsburg, California and the matters first addressed in MID's April 29,1996 Comments in opposition to the restructuring of PG&E have now become moot.

Based upon MID's initial comments and subsequent correspondence, your office initiated an investigation as to whether PG&E, in refusing to interconnect with MID and provide i transmission service to MID's Pittsburg Substation under PG&E's Control Area Transmission l l Service Agreement with Destec,was in violation of PG&E's nuclear license conditions in its  ;

licenses for the Humboldt Bay Power Plant, Unit 3 and Diablo Canyon Nuclear Power Plant, '

Units 1 and 2.

9901200332 9901187 \g l PDR ADOCK 05000133 l

! P PE l I

~

.; t We appreciate your effons and those of the NRC Staff that have devoted time and ,

attention to this matter. Unfortunately, superseding developments have led MID to abandon its plans,to provide electric service to Praxair, Inc. and other potential customers in Pittsburg, ,

l California at this time. MID is pursuing its remedy against both PG&E and Destec in an antitrust  ;

l suit in the Federal District Court for the Northern District of California.

.i

Under these circumstances, we see no useful purpose in continuing to pursue this  ;

l matter before the Nuclear Regulatory Commission. MID, therefore, respectfully withdraws its l complaint and request for reliefin these proceedings and asks that the NRC close its files on the l l

investigation. i l Again, we appreciate your interest and attention to this matter. Please advise ,

whether you will need anything further from MID to terminate your inquiry or close your files.

Sincerely,  !

4e+ = A -

Wallace L. Duncan" ~ ~ ' ~ l

, cc: William Manheim, Esquire (PG&E)  ;

l Scott Steffen, Esquire (MID) i WLD:yob l

?

l l

l J

l L