ML20212B16813 September 1999Forwards Insp Repts 50-275/99-12 & 50-323/99-12 on 990711- 08-21.Four Violations Being Treated as Noncited Violations
ML20211A95012 August 1999Discusses 990720-21 Workshop Conducted in Region IV Ofc,Re Exchange of Info in Area of Use of Risk Insights in Regulatory Activities.List of Attendees,Summary of Topic & Issues,Agenda & Copies of Handouts Encl
ML20210L1463 August 1999Informs That NRC Plans to Administer Gfes of Written Operator Licensing Exam on 991006.Requests Submittal of Ltr Identifying Individuals Taking Exam,Personnel Allowed Access to Exams & Mailing Address for ExamsGeneric Fundamentals Examination
ML20210H61827 July 1999Forwards Insp Repts 50-275/99-07 & 50-323/99-07 on 990503- 0714.Apparent Violations Being Considered for Escalated Enforcement Action
ML18107A70125 June 1999Requests Rev of NRC Records to Reflect Change of PG&E Address
ML20205J3388 April 1999Informs That Time Provided by NRC Regulation within Which Commission May Act to Review Director'S Decision Expired. Commission Declined Any Review & Became Final Agency Action on 990406.With Certificate of Svc.Served on 990409
DCL-99-038, Forwards Decommissioning Funding Repts for Diablo Canyon Power Plant,Units 1 & 2 & Humboldt Bay Power Plant,Unit 3, Per Requirements of 10CFR50.75(f)31 March 1999Forwards Decommissioning Funding Repts for Diablo Canyon Power Plant,Units 1 & 2 & Humboldt Bay Power Plant,Unit 3, Per Requirements of 10CFR50.75(f)
DCL-99-033, Forwards Change 16 to Rev 18 of Diablo Canyon Power Plant Physical Security Plan,Per 10CFR50.54(p).Changes Do Not Decrease Safeguards Effectiveness of Plan.Without Encl12 March 1999Forwards Change 16 to Rev 18 of Diablo Canyon Power Plant Physical Security Plan,Per 10CFR50.54(p).Changes Do Not Decrease Safeguards Effectiveness of Plan.Without Encl
DCL-99-010, Forwards Change 15 to Rev 18 of Dcnpp Physical Security Plan,Per 10CFR50.54(p).Changes Do Not Decrease Effectiveness of Plan.Encl Withheld26 January 1999Forwards Change 15 to Rev 18 of Dcnpp Physical Security Plan,Per 10CFR50.54(p).Changes Do Not Decrease Effectiveness of Plan.Encl Withheld
ML20202A98318 January 1999Informs That Modesto Irrigation District No Longer Seeking Addl Interconnection with Pacific Gas & Electric Co at Pittsburg,Ca & Matters First Addressed in 980429 Comments in Opposition to Restructuring of Util Have Now Become Moot
IR 05000275/199801213 January 1999Informs That Insp Repts 50-275/98-12 & 50-323/98-12 Have Been Canceled
DCL-98-163, Forwards Change 14 to Rev 18 of Physical Security Plan. Changes Do Not Decrease Safeguards Effectiveness of Plan & Submitted Pursuant to 10CFR50.54(p).Encl Withheld24 November 1998Forwards Change 14 to Rev 18 of Physical Security Plan. Changes Do Not Decrease Safeguards Effectiveness of Plan & Submitted Pursuant to 10CFR50.54(p).Encl Withheld
ML20195G51616 November 1998Forwards Insp Repts 50-275/98-16 & 50-323/98-16 on 980913- 1024.No Violations NotedEnforcement Discretion
ML20155F7953 November 1998Second Partial Response to FOIA Request for Documents. Records Subj to Request Encl & Identified in App C
DCL-98-123, Submits Listed Address Changes for NRC Service Lists for Listed Individuals9 September 1998Submits Listed Address Changes for NRC Service Lists for Listed Individuals
DCL-98-108, Submits 90-day Response to NRC GL 98-01, Yr 2000 Readiness of Computer Sys at Nuclear Power Plants. Util Has Pursued & Continuing to Pursue Year 2000 Readiness Program Similar to That Outlined in Nei/Nusmg 97-07, Nuclear Util Year..7 August 1998Submits 90-day Response to NRC GL 98-01, Yr 2000 Readiness of Computer Sys at Nuclear Power Plants. Util Has Pursued & Continuing to Pursue Year 2000 Readiness Program Similar to That Outlined in Nei/Nusmg 97-07, Nuclear Util Year..
ML20236T29324 July 1998Forwards Order Prohibiting Involvement in NRC Licensed Activities for 5 Yrs.Order Being Issued Due to Falsification of Info on Application to Obtain Unescorted Access to PG&E Plant
ML20236T34322 July 1998Forwards Insp Repts 50-275/98-11 & 50-323/98-11 on 980526-28.Apparent Violations Identified & Being Considered for Escalated Enforcement Action
ML20236J2251 July 1998Ltr Contract,Task Order 232 Entitled, Review of Callaway, Comanche,Diablo Canyon & Wolf Creek Applications for Conversion to Improved TS Based on Standard TS, Under Contract NRC-03-95-026
ML20236G06919 June 1998Forwards Endorsement 123 to Neila Policy NF-228,Endorsement 145 to Neila Policy NF-113,Endorsement 124 to Neila Policy NF-228 & Endorsement 89 to Maelu Policy MF-103
IR 05000275/199800517 April 1998Forwards Insp Repts 50-275/98-05 & 50-323/98-05 on 980202-06 & 23-27 & 0302-18.No Violations Noted.Insp Focused on Resolution of Previous NRC Insp Findings & Included Review of Issues Identified During Architect/Engineering Insp Rept
ML20203G03725 February 1998Forwards Revised Copy of NRC Form 398, Personal Qualification Statement - Licensee, (10/97) Encl 1,which Has Been Revised to Reflect Current Operator Licensing Policy
DCL-98-014, Forwards Change 12 to Rev 18 to Physical Security Plan,Per 10CFR50.54(p).Plan Withheld10 February 1998Forwards Change 12 to Rev 18 to Physical Security Plan,Per 10CFR50.54(p).Plan Withheld
ML20199H6692 February 1998Ack Receipt of ,Transmitting Rev 18,change 11, to Plant Physical Security Plan,Submitted Under Provisions of 10CFR50.54(p).Role of Video Capture Audible Alarm Sys Needs to Be Addressed in Security Plan,Per 980123 Telcon
DCL-97-187, Forwards Change 11,rev 18 to Physical Security Plan.Encl 1 Describes Proposed Revs to Physical Security Plan.Plan Withheld19 November 1997Forwards Change 11,rev 18 to Physical Security Plan.Encl 1 Describes Proposed Revs to Physical Security Plan.Plan Withheld
IR 05000275/199701831 October 1997Forwards Insp Repts 50-275/97-18 & 50-323/97-18 on 971006- 10.Insp Verified That Liquid & Gaseous Radioactive Waste Effluent Mgt Program Was Properly Implemented.No Violations Noted
DCL-97-156, Provides Change 10 to Rev 18 of Physcial Security Plan & Change 2 to Rev 3 of Safeguards Contingency Plan.Plans Withheld16 September 1997Provides Change 10 to Rev 18 of Physcial Security Plan & Change 2 to Rev 3 of Safeguards Contingency Plan.Plans Withheld
ML20210H4672 August 1997Requests That NRC Suspend Investigation & Review of Issues Raised by Modesto Irrigation District & Transmission Agency of Northern CA Re Contention That PG&E Had Violated Nuclear License Conditions Known as Stanislaus Commitments
ML20137N15931 March 1997Informs That Licensee Facility Scheduled to Administer NRC GFE on 970409.Sonalsts,Inc Authorized Under Contract to Support NRC Administration of GFE ActivitiesGeneric Fundamentals Examination
ML16343A48025 February 1997Forwards non-proprietary WCAP-14796 & Proprietary WCAP-14795, Nrc/Util Meeting on Model 51 SG Tube Integrity & ARC Methodology. Proprietary Rept Withheld,Per 10CFR2.90
ML20134H62710 February 1997Fifth Partial Response to FOIA Request for Documents.Records in App I Encl & Available in Pdr.App J Records Withheld in Part (Ref FOIA Exemption 5) & App K Records Completely Withheld (Ref FOIA Exemption 5)
ML20134K3426 February 1997Conveys Results & Conclusions of Operational Safeguards Response Evaluation Conducted by NRR at Plant,Units 1 & 2, on 960909-12.W/o Encl
ML16342D52931 January 1997Transmits WCAPs Supporting NRCs Review of License Amend Request 96-10,rev of TSs to Support Extended Fuel Cycles to 24 months.WCAP-11082,rev 5,WCAP-11594,rev 2 & WCAP-14646,rev 1 Withheld
ML16342D53324 January 1997Requests Proprietary Version of WCAP-14646,rev 1, Instrumentation Calibration & Drift Evaluation for Diablo Canyon Units 1 & 2,24 Month Fuel Cycle Evaluation, Jan 1997 Be Withheld from Public Disclosure Per 10CFR2.790
ML16342D53124 January 1997Requests That WCAP-11594,rev 2, W Improved Thermal Design Procedure Instrument Uncertainty Methodology,Diablo Canyon Units 1 & 2,24 Month Fuel Cycle Evaluation Be Withheld from Public Disclosure,Per 10CFR2.790
ML16342D53224 January 1997Requests WCAP-11082,rev 5, Westinghouse Setpoint Methodology for Protection Sys,Diablo Canyon Units 1 & 2,24 Month Fuel Cycle Evaluation, Jan 1996 Be Withheld from Public Disclosure Per 10CFR2.790
ML20136C35211 January 1997Discusses Japan Oil Spill & Np Intake & Possibilities of Such Event Occurring at SONGS or Dcnpp
ML20133F8969 January 1997Responds to NRC Ltr of 961206 Received on 961210 Which Requested Further Info Re Utils Violations of Conditions of Its Nuclear Licenses Designated to Promote & Protect Competition in Bulk Power Market in Northern & Central CA
ML20133F8729 January 1997Acks & Responds to NRC Ltr of 961206 Received by Undersigned on 961210 Requesting Further Info to Document Tancs Assertion,Per Filing on 960429 That Util Has Violated Terms & Conditions of Nuclear Power Project Licenses
ML16342D55218 December 1996Requests That Proprietary WCAP-14795, Nrc/Util Meeting on Model 51 SG Tube Integrity & ARC Methology, Be Withheld (Ref 10CFR2.790(b)(4))
ML20129J40018 October 1996Forwards Order Approving Corporate Restructuring by Establishment of Holding Company & Safety Evaluation
NSD-NRC-96-4846, Transmits Proprietary & non-proprietary Versions of Preliminary Rept, Incomplete Rcca Insertion. W Authorization ltr,AW-96-1021 & Affidavit Requesting Info Be Withheld from Public Disclosure Encl16 October 1996Transmits Proprietary & non-proprietary Versions of Preliminary Rept, Incomplete Rcca Insertion. W Authorization ltr,AW-96-1021 & Affidavit Requesting Info Be Withheld from Public Disclosure Encl
ML20129G61224 September 1996Second Partial Response to FOIA Request for Documents. Forwards Documents Listed in App C,E,F & G.Documents Available in Pdr.App E,F & G Documents Partially Withheld Ref FOIA Exemptions 4 & 6.App D Record Listed as CopyrightExemption Request
DCL-96-170, Forwards Change 1 to Rev 4 of Training & Qualification Plan, Per 10CFR50.54(p).Plan Withheld14 August 1996Forwards Change 1 to Rev 4 of Training & Qualification Plan, Per 10CFR50.54(p).Plan Withheld
DCL-96-141, Submits Change 9 to Rev 18 of Physical Security Plan.Plan Withheld31 July 1996Submits Change 9 to Rev 18 of Physical Security Plan.Plan Withheld
ML20116B84122 July 1996Forwards Revisions to SR 95-03,SR 95-04 & SR 95-05 Re EDG 1-2 Valid Failures
ML20117E61724 May 1996Forwards Public Version of Rev 11 to EPIP EP R-7, Off-Site Transportation Accidents
DCL-96-102, Submits Change 8 to Rev 18 of Physical Security Plan,Per 10CFR50.54(p).Encl Withheld6 May 1996Submits Change 8 to Rev 18 of Physical Security Plan,Per 10CFR50.54(p).Encl Withheld
DCL-96-096, Forwards Public Version of Rev 3 to Diablo Canyon Power Plant Units 1 & 2 Emergency Plan, Change 1516 April 1996Forwards Public Version of Rev 3 to Diablo Canyon Power Plant Units 1 & 2 Emergency Plan, Change 15Met Tower
Minimum staff
DCL-96-054, Forwards Change 7 to Rev 18 of Physical Security Plan & Change 1 to Rev 3 of Safeguards Contingency Plan.Encl Withheld28 February 1996Forwards Change 7 to Rev 18 of Physical Security Plan & Change 1 to Rev 3 of Safeguards Contingency Plan.Encl Withheld