B17607, Informs of Determination That Util Will Be Ready for Commencement of 40500 Insp, Effectiveness of Licensee Controls in Identifying,Resolving & Preventing Problems, on 990118

From kanterella
Jump to navigation Jump to search
Informs of Determination That Util Will Be Ready for Commencement of 40500 Insp, Effectiveness of Licensee Controls in Identifying,Resolving & Preventing Problems, on 990118
ML20206P525
Person / Time
Site: Millstone Dominion icon.png
Issue date: 01/04/1999
From: Bowling M
NORTHEAST NUCLEAR ENERGY CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
B17607, NUDOCS 9901120133
Download: ML20206P525 (2)


Text

. . . . . .-

N:rthe:st Rope Ferry Rd. (Route 156), Wtterford, CT 06385 Nucles Energy Minstone Nudear her Station Northeas Nudear Energy Company P.O. Box 128 Taterford, CT 06385-0128 (860) 447-1791 Fax (860) 444-4277 The Northeast Utilities S tem JAN - 4 1999 Docket No. 50-336 B17607 U.S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, D.C. 20555 Millstone Nuclear Power Station, Unit No. 2.

Readiness for the NRC 40500 Inspection Effectiveness of Licensee Controls in Identifyino. Resolvino. and Preventino Probiems Northeast Nuclear Energy Company (NNECO), committed, in a letter dated November 5,1997, to notify the NRC when ready for the performance of the 40500 Inspection, " Effectiveness of Licensee Controls in Identifying, Resolving, and Preventing Problems," at Millstone Unit No. 2. In preparation for the performance of this inspection, NNECO has completed assessments of the elements associated with the inspection scope. Based upon these assessments, we have determined that we will be ready for the commencement of this inspection on January 18,1999. Nuclear Oversight has performed their own independent assessments and concur with this conclusion. An Inspection Response Team has been established to work with your staff under the direction of Mr. Harry Miller.

There are no regulatory committments contained within this letter. 3 if there are any further questions on the information provided in this letter, please contact Mr. Jay M. Gionet at 860-444-5505. J  ;

q()0/

l Very truly yours, NORTHEAST NUCLEAR ENERGY COMPANY s

_ *)

Martin L. Bowling, Jr. d Recovery Officer - Technical Services l

cc: See Page 2 9901120133 990104 ~

PDR ADOCK 05000336 P PDR_

- -.. U.S. Nucl::r R:gul: tory Commission B17607\Page 2 cc- H.'J. Miller, Region I Administrator W. D. Lanning, Director, Millstone inspections, S. Dembek, NRC Project Manager, Millstone Unit No. 2 D. P. Beaulieu, Senior Resident inspector, Millstone Unit No. 2 J. P. Durr, Chief, inspections Branch, Millstone inspections W. M. Dean, Director, Millstone Project Directorate s

. ________,