Letter Sequence Request |
---|
|
|
MONTHYEARHL-3014, Forwards Response for Table 3 Items from App a of IST Program Safety Evaluation.Response to Section 3.2.3.1 of SE Also Encl1992-11-17017 November 1992 Forwards Response for Table 3 Items from App a of IST Program Safety Evaluation.Response to Section 3.2.3.1 of SE Also Encl Project stage: Other ML20116M8991992-11-23023 November 1992 Forwards NRC Response to Section 3.2.3.1 of SE for Second Ten Year Insp Interval for IST Program Project stage: Other HL-4433, Forwards Revs to Relief Requests RR-V-17,RR-V-19,RR-V-20, RR-V-32,RR-V-40 & RR-V-41,providing Addl Info as Discussed in 930901 Telcon Re Second 10-yr Insp Interval IST Program1993-12-21021 December 1993 Forwards Revs to Relief Requests RR-V-17,RR-V-19,RR-V-20, RR-V-32,RR-V-40 & RR-V-41,providing Addl Info as Discussed in 930901 Telcon Re Second 10-yr Insp Interval IST Program Project stage: Request HL-4550, Informs That in Response to Listed Items from SE for 18 Responses Provided in Util ,Util Has Revised Relief Requests RR-P-6 & RR-P-7 of Second 10-yr Insp Interval IST Program.Revised Relief Requests Encl1994-04-0404 April 1994 Informs That in Response to Listed Items from SE for 18 Responses Provided in Util ,Util Has Revised Relief Requests RR-P-6 & RR-P-7 of Second 10-yr Insp Interval IST Program.Revised Relief Requests Encl Project stage: Request 1992-11-23
[Table View] |
Forwards Revs to Relief Requests RR-V-17,RR-V-19,RR-V-20, RR-V-32,RR-V-40 & RR-V-41,providing Addl Info as Discussed in 930901 Telcon Re Second 10-yr Insp Interval IST ProgramML20059B407 |
Person / Time |
---|
Site: |
Hatch |
---|
Issue date: |
12/21/1993 |
---|
From: |
Beckham J GEORGIA POWER CO. |
---|
To: |
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM) |
---|
References |
---|
HL-4433, TAC-M59202, TAC-M59203, TAC-M83192, TAC-M83193, NUDOCS 9401040118 |
Download: ML20059B407 (16) |
|
Similar Documents at Hatch |
---|
Category:CORRESPONDENCE-LETTERS
MONTHYEARML20217D2901999-10-13013 October 1999 Forwards SER Accepting Licensee 990305 Proposed Changes to Edwin I Hatch Nuclear Plant Emergency Classification Scheme to Add Emergency Action Levels Related to Operation of Independent Spent Fuel Storage Installation ML20217G0401999-10-0707 October 1999 Forwards Insp Repts 50-321/99-09 & 50-366/99-09 on 990607-11 & 0823-27.One Violation Occurred Being Treated as NCV ML20217G2631999-10-0707 October 1999 Informs That on 990930,NRC Staff Completed mid-cycle PPR of Hatch Plant & Did Not Identify Any Areas Where Performance Warranted More than Core Insp Program.Regional Initiative Insps to Observe Const Activities Will Be Conducted ML20216G0251999-09-24024 September 1999 Concludes That All Requested Info of GL 98-01 & Supplement 1 Provided & Licensing Action for GL 98-01 & Supplement 1 Complete for Plant ML20216H3641999-09-20020 September 1999 Forwards NRC Form 536 in Response to AL 99-03, Preparation & Scheduling of Operator Licensing Exams HL-5839, Forwards Three New & One Revised Relief Requests for Third 10-year Interval ISI Program for Plant,Developed to Clarify Documentation Requirements,To Propose Alternate Exam Requirements IAW ASME Code Cases N-598 & N-5731999-09-16016 September 1999 Forwards Three New & One Revised Relief Requests for Third 10-year Interval ISI Program for Plant,Developed to Clarify Documentation Requirements,To Propose Alternate Exam Requirements IAW ASME Code Cases N-598 & N-573 ML20217B5271999-09-16016 September 1999 Forwards Insp Repts 50-321/99-05 & 50-366/99-05 on 990711-0821.No Violations Noted ML20212A6411999-09-13013 September 1999 Forwards Safety Evaluation of Relief Request RR-V-16 for Third Ten Year Interval Inservice Testing Program HL-5837, Informs That Recent Evaluation of Inservice Testing Program Activities Has Resulted in Requirement for Snoc to Revise Two Existing Requests for Relief,Withdraw One Request for Relief & Revise One Existing Cold SD Justification1999-09-13013 September 1999 Informs That Recent Evaluation of Inservice Testing Program Activities Has Resulted in Requirement for Snoc to Revise Two Existing Requests for Relief,Withdraw One Request for Relief & Revise One Existing Cold SD Justification HL-5832, Submits Comments Concerning Reactor Vessel Integrity Database (Rvid),Version 2 for Plant Hatch,Per NRC1999-09-0101 September 1999 Submits Comments Concerning Reactor Vessel Integrity Database (Rvid),Version 2 for Plant Hatch,Per NRC ML20211Q4801999-09-0101 September 1999 Informs That on 990812-13,Region II Hosted Training Managers Conference on Recent Changes to Operator Licensing Program. List of Attendees,Copy of Slide Presentations & List of Questions Received from Participants Encl HL-5825, Forwards Response to Informal NRC RAI Re Proposed Emergency Actions Levels Associated with Independent Spent Fuel Storage Operations1999-08-20020 August 1999 Forwards Response to Informal NRC RAI Re Proposed Emergency Actions Levels Associated with Independent Spent Fuel Storage Operations HL-5827, Forwards Fitness for Duty Performance Data for six-month Reporting period,Jan-June 1999,as Required by 10CFR26.71(d)1999-08-19019 August 1999 Forwards Fitness for Duty Performance Data for six-month Reporting period,Jan-June 1999,as Required by 10CFR26.71(d) HL-5788, Forwards Owner Activity Repts,Form OAR-1 for Ei Hatch Nuclear Plant for First Period of Third 10-yr Interval ISI Program.Repts Are for Unit 2 Refueling Outages 13 & 141999-08-19019 August 1999 Forwards Owner Activity Repts,Form OAR-1 for Ei Hatch Nuclear Plant for First Period of Third 10-yr Interval ISI Program.Repts Are for Unit 2 Refueling Outages 13 & 14 HL-5824, Requests Exemption from Expedited Implementation Requirements of Paragraph 10CFR50.55a(g)(6)(ii)(B) as Applicable to Containment General Visual Exams of Subsection Iwe,Table IWE-2500-1,Category E-A,Item E1.111999-08-18018 August 1999 Requests Exemption from Expedited Implementation Requirements of Paragraph 10CFR50.55a(g)(6)(ii)(B) as Applicable to Containment General Visual Exams of Subsection Iwe,Table IWE-2500-1,Category E-A,Item E1.11 ML20210T6421999-08-17017 August 1999 Discusses Licensee 950814 Initial Response to GL 92-01, Rev 1,Supp 1, Rv Structural Integrity (Rvid), Issued on 950519 to Plant.Staff Revised Info in Rvid & Being Released as Rvid Version 2 ML20210V3311999-08-13013 August 1999 Provides Synposis of NRC OI Report Re Alleged Untruthful Statements Made to NRC Re Release of Contaminated Matl to Onsite Landfill.Oi Unable to Conclude That Untruthful state- Ments Were Provided to NRC ML20210Q4821999-08-0505 August 1999 Informs That NRC Plans to Administer Gfes of Written Operator Licensing Exam on 991006.Authorized Representative of Facility Must Submit Ltr,As Listed,Identifying Individual to Take Exam,Thirty Days Before Exam Date ML20210L7581999-08-0404 August 1999 Forwards Insp Repts 50-321/99-04 & 50-366/99-04 on 990530-0710.One Violation of NRC Requirements Occurred & Being Treated as Ncv,Consistent with App C of Enforcement Policy ML20210J9501999-08-0202 August 1999 Forwards SER Finding Licensee Established Acceptable Program to Verify Periodically design-basis Capability of safety-related MOVs at Edwin I Hatch Nuclear Plant,Units 1 & 2 ML20210J9021999-08-0202 August 1999 Forwards SER Finding Licensee Adequately Addressed Actions Requested in GL 95-07, Pressure Locking & Thermal Binding of Safety-Related Power-Operated Gate Valves, for Edwin I Hatch Nuclear Plant,Units 1 & 2 HL-5814, Forwards New Relief Requests for Third 10-year Interval Inservice Insp Program for Ei Hatch Nuclear Plant.New Relief Requests Were Developed to Propose Alternate Insps & to Allow Use of ASME Code Cases N-605,N-508-1,N-323-1 & N-5281999-07-30030 July 1999 Forwards New Relief Requests for Third 10-year Interval Inservice Insp Program for Ei Hatch Nuclear Plant.New Relief Requests Were Developed to Propose Alternate Insps & to Allow Use of ASME Code Cases N-605,N-508-1,N-323-1 & N-528 05000366/LER-1999-007, Forwards LER 99-007-00 Re Personnel Error & Inadequate Corrective Action Causing Automatic Reactor Shutdown1999-07-27027 July 1999 Forwards LER 99-007-00 Re Personnel Error & Inadequate Corrective Action Causing Automatic Reactor Shutdown ML20210E1601999-07-20020 July 1999 Forwards Insp Repts 50-321/99-10 & 50-366/99-10 on 990616-25.One Violation Noted Being Treated as Ncv.Team Identified Lack of Procedural Guidance for Identification & Trending of Repetitive Instrument Drift & Calibr Problems HL-5810, Forwards Rev 17B to Ei Hatch FSAR & Rev 14B to Fire Hazards Analysis & Fire Protection Program, for Plant.Encls Reflect Changes Made Since Previous Submittal.With Instructions1999-07-15015 July 1999 Forwards Rev 17B to Ei Hatch FSAR & Rev 14B to Fire Hazards Analysis & Fire Protection Program, for Plant.Encls Reflect Changes Made Since Previous Submittal.With Instructions HL-5808, Forwards Ei Hatch Nuclear Plant,Unit 1 Extended Power Uprate Startup Test Rept for Cycle 19. Rept Summarizes Startup Testing Performed on Unit 1 Following Implementation of Extended Uprate During Eighteenth Refueling Outage1999-07-15015 July 1999 Forwards Ei Hatch Nuclear Plant,Unit 1 Extended Power Uprate Startup Test Rept for Cycle 19. Rept Summarizes Startup Testing Performed on Unit 1 Following Implementation of Extended Uprate During Eighteenth Refueling Outage HL-5807, Estimates That Seventeen (17) Submittals Will Be Made During Fy 2000 & Two (2) Submittals Will Be Made During Fy 2001,in Response to Administative Ltr 99-02, Operating Reactor Licensing Action Estimates1999-07-14014 July 1999 Estimates That Seventeen (17) Submittals Will Be Made During Fy 2000 & Two (2) Submittals Will Be Made During Fy 2001,in Response to Administative Ltr 99-02, Operating Reactor Licensing Action Estimates ML20210J1091999-07-10010 July 1999 Submits Suggestions & Concerns Re Y2K & Nuclear Power Plants HL-5804, Informs NRC That on or After 991018,SNOC Plans to Begin Storing Spent Fuel in Ei Hatch ISFSI IAW General License Issued,Per 10CFR72.2101999-07-0909 July 1999 Informs NRC That on or After 991018,SNOC Plans to Begin Storing Spent Fuel in Ei Hatch ISFSI IAW General License Issued,Per 10CFR72.210 HL-5796, Forwards Response to NRC 990331 Request for Supplemental Info Re SNC Earlier GL 95-07 Responses.Gl 95-07 Evaluation Sheets for Units 1 & 2 RHR Torus Spray Isolation Valves Are Encl1999-07-0909 July 1999 Forwards Response to NRC 990331 Request for Supplemental Info Re SNC Earlier GL 95-07 Responses.Gl 95-07 Evaluation Sheets for Units 1 & 2 RHR Torus Spray Isolation Valves Are Encl HL-5801, Forwards New Relief Requests for Third 10-Yr Interval ISI Program for Ei Hatch Nuclear Plant.New Relief Requests RR-25 & RR-26 Were Developed to Propose Alternate Repair Techniques IAW ASME Code N-562 & N-561,respectively1999-07-0909 July 1999 Forwards New Relief Requests for Third 10-Yr Interval ISI Program for Ei Hatch Nuclear Plant.New Relief Requests RR-25 & RR-26 Were Developed to Propose Alternate Repair Techniques IAW ASME Code N-562 & N-561,respectively ML20209E4801999-06-30030 June 1999 Confirms 990630 Telcon Between M Crosby & DC Payne Re Arrangements Made for Administration of Licensing Exam at Plant During Weeks of 991018-1101 ML20196H8811999-06-25025 June 1999 Forwards Insp Repts 50-321/99-03 & 50-366/99-03 on 990418- 0529.No Violations Occurred.Conduct of Activities at Plant Generally Characterized by safety-conscious Operations & Sound Engineering & Maint Practices HL-5790, Responds to NRC RAI Re GL 98-01, Y2K Readiness of Computer Sys at Nuclear Power Plants1999-06-21021 June 1999 Responds to NRC RAI Re GL 98-01, Y2K Readiness of Computer Sys at Nuclear Power Plants ML20212J0541999-06-17017 June 1999 Responds to Requesting That NRC Staff ...Allow BWR Plants Identified to Defer Weld Overlay Exams Until March 2001 or Until Completion of NRC Staff Review & Approval of Proposed Generic Rept,Whichever Comes First ML20207E7561999-06-0303 June 1999 Informs of Completion of Review & Evaluation of Info Provided by Southern Nuclear Operating Co by Ltr Dtd 980608, Proposing Changes to Third 10-Yr Interval ISI Program Plan Requests for Relief RR-4 & R-6.Requests Acceptable HL-5763, Informs That Util Is Changing Responsibility for Periodic Concerns Program Review,Per Insp Repts 50-321/95-12 & 50-366/95-12.Reviews Will Now Be Performed Under Direction of Vice President & Corporate Counsel1999-05-20020 May 1999 Informs That Util Is Changing Responsibility for Periodic Concerns Program Review,Per Insp Repts 50-321/95-12 & 50-366/95-12.Reviews Will Now Be Performed Under Direction of Vice President & Corporate Counsel HL-5785, Forwards New Relief Requests RR-V-16 for Third 10-yr Interval Inservice Testing Program for Ei Hatch Nuclear Plant.Relief Request Was Developed to Propose Alternate Schedule for Replacement of HPCI Rupture Disks1999-05-18018 May 1999 Forwards New Relief Requests RR-V-16 for Third 10-yr Interval Inservice Testing Program for Ei Hatch Nuclear Plant.Relief Request Was Developed to Propose Alternate Schedule for Replacement of HPCI Rupture Disks ML20206Q0751999-05-0606 May 1999 Forwards Insp Repts 50-321/99-02 & 50-366/99-02 on 990307-0417.No Violations Noted ML20206G1611999-05-0404 May 1999 Forwards SER Approving Util 990316 Revised Relief Request RR-P-14,for Inservice Testing Program for Pumps & Valves Pursuant to 10CFR50.55a(a)(3)(ii) ML20206P6921999-04-27027 April 1999 Discusses 990422 Public Meeting at Hatch Facility Re Results of Periodic Plant Performance Review for Hatch Nuclear Facility for Period of Feb 1997 to Jan 1999.List of Attendees & Copy of Handouts Used by Hatch,Encl HL-5777, Notifies NRC That Exam Coverage for One Weld Exceeded Criteria for Plant.Reasons for Exam Coverage Being Less than Initially Estimated as Listed1999-04-26026 April 1999 Notifies NRC That Exam Coverage for One Weld Exceeded Criteria for Plant.Reasons for Exam Coverage Being Less than Initially Estimated as Listed HL-5758, Forwards Response to NRC 990129 RAI Re GL 96-05 Program at Ei Hatch Nuclear Plant1999-04-0909 April 1999 Forwards Response to NRC 990129 RAI Re GL 96-05 Program at Ei Hatch Nuclear Plant ML20205T1831999-04-0909 April 1999 Informs That on 990316,S Grantham & Ho Christensen Confirmed Initial Operator Licensing Exam Schedule for Ei Hatch NPP for FY00.Initial Exam Dates Are 991001 & 2201 for Approx 12 Candidates.Chief Examiner Will Be C Payne ML20205M3181999-04-0707 April 1999 Confirms Telcon Between D Crowe & Ph Skinner Re Mgt Meeting Scheduled for 990422 in Conference Room of Maint Training Bldg.Purpose of Meeting to Discuss Results of Periodic PPR for Plant for Period of Feb 1997 - Jan 1999 ML20205M3011999-04-0202 April 1999 Forwards Insp Repts 50-321/99-01 & 50-366/99-01 on 990124-0306.Non-cited Violation Identified HL-5761, Forwards Revised Ei Hatch Nuclear Plant Psp,Effective 990331,per 10CFR50.54(p)(2).Justification & Detailed Instructions Encl.Plan Withheld,Per 10CFR73.211999-03-31031 March 1999 Forwards Revised Ei Hatch Nuclear Plant Psp,Effective 990331,per 10CFR50.54(p)(2).Justification & Detailed Instructions Encl.Plan Withheld,Per 10CFR73.21 HL-5750, Forwards Status of Decommissining Funding,Per Requirements 10CFR50.75(f)(1),on Behalf of Licensed Owners of Ei Hatch Nuclear Plant1999-03-30030 March 1999 Forwards Status of Decommissining Funding,Per Requirements 10CFR50.75(f)(1),on Behalf of Licensed Owners of Ei Hatch Nuclear Plant ML20205H1491999-03-25025 March 1999 Forwards Info for OLs DPR-7 & NPF-5 Re Financial Assurance Requirements for Decommissioning Nuclear Power Reactors,Per 10CFR50.75(f)(1).Municipal Electric Authority of Georgia Is One of Licensed Owners of Ei Hatch,Owning 17.7% of Facility ML20205D3211999-03-24024 March 1999 Informs That Safety Sys Engineering Insp Previously Scheduled for 990405-09 & 19-23,rescheduled for 990607-11 & 21-25 1999-09-24
[Table view] Category:INCOMING CORRESPONDENCE
MONTHYEARML20216H3641999-09-20020 September 1999 Forwards NRC Form 536 in Response to AL 99-03, Preparation & Scheduling of Operator Licensing Exams HL-5839, Forwards Three New & One Revised Relief Requests for Third 10-year Interval ISI Program for Plant,Developed to Clarify Documentation Requirements,To Propose Alternate Exam Requirements IAW ASME Code Cases N-598 & N-5731999-09-16016 September 1999 Forwards Three New & One Revised Relief Requests for Third 10-year Interval ISI Program for Plant,Developed to Clarify Documentation Requirements,To Propose Alternate Exam Requirements IAW ASME Code Cases N-598 & N-573 HL-5837, Informs That Recent Evaluation of Inservice Testing Program Activities Has Resulted in Requirement for Snoc to Revise Two Existing Requests for Relief,Withdraw One Request for Relief & Revise One Existing Cold SD Justification1999-09-13013 September 1999 Informs That Recent Evaluation of Inservice Testing Program Activities Has Resulted in Requirement for Snoc to Revise Two Existing Requests for Relief,Withdraw One Request for Relief & Revise One Existing Cold SD Justification HL-5832, Submits Comments Concerning Reactor Vessel Integrity Database (Rvid),Version 2 for Plant Hatch,Per NRC1999-09-0101 September 1999 Submits Comments Concerning Reactor Vessel Integrity Database (Rvid),Version 2 for Plant Hatch,Per NRC HL-5825, Forwards Response to Informal NRC RAI Re Proposed Emergency Actions Levels Associated with Independent Spent Fuel Storage Operations1999-08-20020 August 1999 Forwards Response to Informal NRC RAI Re Proposed Emergency Actions Levels Associated with Independent Spent Fuel Storage Operations HL-5827, Forwards Fitness for Duty Performance Data for six-month Reporting period,Jan-June 1999,as Required by 10CFR26.71(d)1999-08-19019 August 1999 Forwards Fitness for Duty Performance Data for six-month Reporting period,Jan-June 1999,as Required by 10CFR26.71(d) HL-5788, Forwards Owner Activity Repts,Form OAR-1 for Ei Hatch Nuclear Plant for First Period of Third 10-yr Interval ISI Program.Repts Are for Unit 2 Refueling Outages 13 & 141999-08-19019 August 1999 Forwards Owner Activity Repts,Form OAR-1 for Ei Hatch Nuclear Plant for First Period of Third 10-yr Interval ISI Program.Repts Are for Unit 2 Refueling Outages 13 & 14 HL-5824, Requests Exemption from Expedited Implementation Requirements of Paragraph 10CFR50.55a(g)(6)(ii)(B) as Applicable to Containment General Visual Exams of Subsection Iwe,Table IWE-2500-1,Category E-A,Item E1.111999-08-18018 August 1999 Requests Exemption from Expedited Implementation Requirements of Paragraph 10CFR50.55a(g)(6)(ii)(B) as Applicable to Containment General Visual Exams of Subsection Iwe,Table IWE-2500-1,Category E-A,Item E1.11 HL-5814, Forwards New Relief Requests for Third 10-year Interval Inservice Insp Program for Ei Hatch Nuclear Plant.New Relief Requests Were Developed to Propose Alternate Insps & to Allow Use of ASME Code Cases N-605,N-508-1,N-323-1 & N-5281999-07-30030 July 1999 Forwards New Relief Requests for Third 10-year Interval Inservice Insp Program for Ei Hatch Nuclear Plant.New Relief Requests Were Developed to Propose Alternate Insps & to Allow Use of ASME Code Cases N-605,N-508-1,N-323-1 & N-528 05000366/LER-1999-007, Forwards LER 99-007-00 Re Personnel Error & Inadequate Corrective Action Causing Automatic Reactor Shutdown1999-07-27027 July 1999 Forwards LER 99-007-00 Re Personnel Error & Inadequate Corrective Action Causing Automatic Reactor Shutdown HL-5810, Forwards Rev 17B to Ei Hatch FSAR & Rev 14B to Fire Hazards Analysis & Fire Protection Program, for Plant.Encls Reflect Changes Made Since Previous Submittal.With Instructions1999-07-15015 July 1999 Forwards Rev 17B to Ei Hatch FSAR & Rev 14B to Fire Hazards Analysis & Fire Protection Program, for Plant.Encls Reflect Changes Made Since Previous Submittal.With Instructions HL-5808, Forwards Ei Hatch Nuclear Plant,Unit 1 Extended Power Uprate Startup Test Rept for Cycle 19. Rept Summarizes Startup Testing Performed on Unit 1 Following Implementation of Extended Uprate During Eighteenth Refueling Outage1999-07-15015 July 1999 Forwards Ei Hatch Nuclear Plant,Unit 1 Extended Power Uprate Startup Test Rept for Cycle 19. Rept Summarizes Startup Testing Performed on Unit 1 Following Implementation of Extended Uprate During Eighteenth Refueling Outage HL-5807, Estimates That Seventeen (17) Submittals Will Be Made During Fy 2000 & Two (2) Submittals Will Be Made During Fy 2001,in Response to Administative Ltr 99-02, Operating Reactor Licensing Action Estimates1999-07-14014 July 1999 Estimates That Seventeen (17) Submittals Will Be Made During Fy 2000 & Two (2) Submittals Will Be Made During Fy 2001,in Response to Administative Ltr 99-02, Operating Reactor Licensing Action Estimates ML20210J1091999-07-10010 July 1999 Submits Suggestions & Concerns Re Y2K & Nuclear Power Plants HL-5801, Forwards New Relief Requests for Third 10-Yr Interval ISI Program for Ei Hatch Nuclear Plant.New Relief Requests RR-25 & RR-26 Were Developed to Propose Alternate Repair Techniques IAW ASME Code N-562 & N-561,respectively1999-07-0909 July 1999 Forwards New Relief Requests for Third 10-Yr Interval ISI Program for Ei Hatch Nuclear Plant.New Relief Requests RR-25 & RR-26 Were Developed to Propose Alternate Repair Techniques IAW ASME Code N-562 & N-561,respectively HL-5796, Forwards Response to NRC 990331 Request for Supplemental Info Re SNC Earlier GL 95-07 Responses.Gl 95-07 Evaluation Sheets for Units 1 & 2 RHR Torus Spray Isolation Valves Are Encl1999-07-0909 July 1999 Forwards Response to NRC 990331 Request for Supplemental Info Re SNC Earlier GL 95-07 Responses.Gl 95-07 Evaluation Sheets for Units 1 & 2 RHR Torus Spray Isolation Valves Are Encl HL-5804, Informs NRC That on or After 991018,SNOC Plans to Begin Storing Spent Fuel in Ei Hatch ISFSI IAW General License Issued,Per 10CFR72.2101999-07-0909 July 1999 Informs NRC That on or After 991018,SNOC Plans to Begin Storing Spent Fuel in Ei Hatch ISFSI IAW General License Issued,Per 10CFR72.210 HL-5790, Responds to NRC RAI Re GL 98-01, Y2K Readiness of Computer Sys at Nuclear Power Plants1999-06-21021 June 1999 Responds to NRC RAI Re GL 98-01, Y2K Readiness of Computer Sys at Nuclear Power Plants HL-5763, Informs That Util Is Changing Responsibility for Periodic Concerns Program Review,Per Insp Repts 50-321/95-12 & 50-366/95-12.Reviews Will Now Be Performed Under Direction of Vice President & Corporate Counsel1999-05-20020 May 1999 Informs That Util Is Changing Responsibility for Periodic Concerns Program Review,Per Insp Repts 50-321/95-12 & 50-366/95-12.Reviews Will Now Be Performed Under Direction of Vice President & Corporate Counsel HL-5785, Forwards New Relief Requests RR-V-16 for Third 10-yr Interval Inservice Testing Program for Ei Hatch Nuclear Plant.Relief Request Was Developed to Propose Alternate Schedule for Replacement of HPCI Rupture Disks1999-05-18018 May 1999 Forwards New Relief Requests RR-V-16 for Third 10-yr Interval Inservice Testing Program for Ei Hatch Nuclear Plant.Relief Request Was Developed to Propose Alternate Schedule for Replacement of HPCI Rupture Disks HL-5777, Notifies NRC That Exam Coverage for One Weld Exceeded Criteria for Plant.Reasons for Exam Coverage Being Less than Initially Estimated as Listed1999-04-26026 April 1999 Notifies NRC That Exam Coverage for One Weld Exceeded Criteria for Plant.Reasons for Exam Coverage Being Less than Initially Estimated as Listed HL-5758, Forwards Response to NRC 990129 RAI Re GL 96-05 Program at Ei Hatch Nuclear Plant1999-04-0909 April 1999 Forwards Response to NRC 990129 RAI Re GL 96-05 Program at Ei Hatch Nuclear Plant HL-5761, Forwards Revised Ei Hatch Nuclear Plant Psp,Effective 990331,per 10CFR50.54(p)(2).Justification & Detailed Instructions Encl.Plan Withheld,Per 10CFR73.211999-03-31031 March 1999 Forwards Revised Ei Hatch Nuclear Plant Psp,Effective 990331,per 10CFR50.54(p)(2).Justification & Detailed Instructions Encl.Plan Withheld,Per 10CFR73.21 HL-5750, Forwards Status of Decommissining Funding,Per Requirements 10CFR50.75(f)(1),on Behalf of Licensed Owners of Ei Hatch Nuclear Plant1999-03-30030 March 1999 Forwards Status of Decommissining Funding,Per Requirements 10CFR50.75(f)(1),on Behalf of Licensed Owners of Ei Hatch Nuclear Plant ML20205H1491999-03-25025 March 1999 Forwards Info for OLs DPR-7 & NPF-5 Re Financial Assurance Requirements for Decommissioning Nuclear Power Reactors,Per 10CFR50.75(f)(1).Municipal Electric Authority of Georgia Is One of Licensed Owners of Ei Hatch,Owning 17.7% of Facility ML20205H1411999-03-24024 March 1999 Forwards Info for OLs DPR-7 & NPF-5 Re Financial Assurance Requirement for Decommissioning Nuclear Power Reactors,Per 10CFR50.75(f)(1).Oglethorpe Power Corp Is One of Licensed Owners of Ei Hatch,Units 1 & 2,owning 30% of Facility HL-5754, Forwards Ei Hatch Nuclear Plant Unit 2 Extended Power Uprate Startup Test Rept for Cycle 15, IAW Regulatory Commitments.Testing Identified No Major Problems.Startup Testing for Unit 1 Is Scheduled for Spring 1999 RFO1999-03-22022 March 1999 Forwards Ei Hatch Nuclear Plant Unit 2 Extended Power Uprate Startup Test Rept for Cycle 15, IAW Regulatory Commitments.Testing Identified No Major Problems.Startup Testing for Unit 1 Is Scheduled for Spring 1999 RFO ML20205H1381999-03-22022 March 1999 Forwards Info for OLs DPR-7 & NPF-5 Re Financial Assurance Requirements for Decommissioning Nuclear Power Reactors,Per 10CFR50.75(f)(1).Georgia Power Is One of Licensed Owners of Ei Hatch,Units 1 & 2,owning 50.1% of Facility ML20205H1581999-03-16016 March 1999 Forwards Info for OLs DPR-5 & NPF-7 Re Financial Assurance Requirements for Decommissioning Nuclear Power Reactors,Per 10CFR50.75(f)(1).Dalton Utilities Is One of Licensed Owners of Ei Hatch,Units 1 & 2,owning 2.2% of Facility HL-5753, Submits Response to Five Criteria Described in NUREG/CR-6396 Section 3.3.2.Attachment Contains Relief Request RR-P-14, Which Has Been Revised & Enhanced to Include Addl Info to Justify Proposed Alternative1999-03-16016 March 1999 Submits Response to Five Criteria Described in NUREG/CR-6396 Section 3.3.2.Attachment Contains Relief Request RR-P-14, Which Has Been Revised & Enhanced to Include Addl Info to Justify Proposed Alternative HL-5757, Informs That SNC Withdraws SNC Proposed Rev to Plant Hatch QA Program Submitted 9901271999-03-15015 March 1999 Informs That SNC Withdraws SNC Proposed Rev to Plant Hatch QA Program Submitted 990127 HL-5756, Submits Summary Rept of Present Level & Source of Onsite Property Damage Insurance Coverage for Ei Hatch Nuclear Plant,Units 1 & 21999-03-12012 March 1999 Submits Summary Rept of Present Level & Source of Onsite Property Damage Insurance Coverage for Ei Hatch Nuclear Plant,Units 1 & 2 HL-5751, Forwards Change to Hatch EP for Review & Approval,Per Requirements of 10CFR50,App E,Section Iv.B.Bases for Proposed EALs & Statements of Agreement from State & Local Governmental Authorities1999-03-0505 March 1999 Forwards Change to Hatch EP for Review & Approval,Per Requirements of 10CFR50,App E,Section Iv.B.Bases for Proposed EALs & Statements of Agreement from State & Local Governmental Authorities HL-5735, Provides NRC with Update Status of Progress Util Is Making Toward Development of Product That Was Originally Identified in to NRC1999-03-0202 March 1999 Provides NRC with Update Status of Progress Util Is Making Toward Development of Product That Was Originally Identified in to NRC HL-5737, Forwards Part of Table (Table 1) Util Provided in 980728 Response to RAI for GL 92-01,Rev 1,Suppl 1,reflecting Lower Shell Axial Welds Identified as C-4-A Through C-4-C & Lower Intermediate Axial Welds Identified as C-3-A Through C-3-C1999-02-0505 February 1999 Forwards Part of Table (Table 1) Util Provided in 980728 Response to RAI for GL 92-01,Rev 1,Suppl 1,reflecting Lower Shell Axial Welds Identified as C-4-A Through C-4-C & Lower Intermediate Axial Welds Identified as C-3-A Through C-3-C HL-5733, Forwards Rev 17A to Ei Hatch FSAR & Rev 14A to Fire Hazards Analysis & Fire Protection Program, for Plant.Encl Reflects Changes Made Since Previous Submittal.With Instructions1999-01-29029 January 1999 Forwards Rev 17A to Ei Hatch FSAR & Rev 14A to Fire Hazards Analysis & Fire Protection Program, for Plant.Encl Reflects Changes Made Since Previous Submittal.With Instructions HL-5729, Submits Proposed Rev to Plant QA Program as Described in Chapter 17 of Unit 2 Fsar,Per 10CFR50.54(a)(3).Rev Would Relocate to Controlled Document Other than Fsar,Units 1 & 2 Lists of SR SSC Comprising Items Covered Under QA Program1999-01-27027 January 1999 Submits Proposed Rev to Plant QA Program as Described in Chapter 17 of Unit 2 Fsar,Per 10CFR50.54(a)(3).Rev Would Relocate to Controlled Document Other than Fsar,Units 1 & 2 Lists of SR SSC Comprising Items Covered Under QA Program HL-5728, Requests That RPV Shell Weld Ultrasonic Exams Be Performed Using Techniques & Procedures,Iaw ASME Section Xi,App Viii, 1992 Edition,1993 Addendum,In Lieu of ASME Section XI,1989 Edition Exam Techniques & Procedures1999-01-19019 January 1999 Requests That RPV Shell Weld Ultrasonic Exams Be Performed Using Techniques & Procedures,Iaw ASME Section Xi,App Viii, 1992 Edition,1993 Addendum,In Lieu of ASME Section XI,1989 Edition Exam Techniques & Procedures HL-5712, Forwards Ehnp Intake Structure License Rept, to Provide Example of Technical Content & Level of Detail Planned for Application for License Renewal,For NRC Review1999-01-0707 January 1999 Forwards Ehnp Intake Structure License Rept, to Provide Example of Technical Content & Level of Detail Planned for Application for License Renewal,For NRC Review HL-5725, Informs That SNC Intends to Examine Approx Dozen Weld Overlays During Unit 1 Spring 1999 Outage That to Date Have Not Been Examined Three Times Since Weld Overlay Was Supplied1999-01-0707 January 1999 Informs That SNC Intends to Examine Approx Dozen Weld Overlays During Unit 1 Spring 1999 Outage That to Date Have Not Been Examined Three Times Since Weld Overlay Was Supplied 05000366/LER-1998-004, Forwards LER 98-004-01 Re Personnel Error Which Resulted in Condition Prohibited by Ts.Rev Is Necessary Because Original LER Reported Inadvertent Criticality Could Have Occurred1999-01-0404 January 1999 Forwards LER 98-004-01 Re Personnel Error Which Resulted in Condition Prohibited by Ts.Rev Is Necessary Because Original LER Reported Inadvertent Criticality Could Have Occurred HL-5710, Requests Approval of Alternative Reactor Vessel Weld Exam for Ehnp,Unit 1,per 10CFR50.55a(g)(6)(ii)(A)(5) for Permanently Excluding Exam of RPV Circumferential Shell Welds1998-12-0202 December 1998 Requests Approval of Alternative Reactor Vessel Weld Exam for Ehnp,Unit 1,per 10CFR50.55a(g)(6)(ii)(A)(5) for Permanently Excluding Exam of RPV Circumferential Shell Welds HL-5708, Provides Updated Response to RAI for GL 96-06, Waterhammer in Containment Coolers1998-11-20020 November 1998 Provides Updated Response to RAI for GL 96-06, Waterhammer in Containment Coolers HL-5573, Withdraws Requesting Exemption from Requirements of GDC 56 with Respect to Ei Hatch,Unit 2 Reactor bldg-to- Suppression Chamber Vacuum Relief Sys Design Due to Listed Reasons1998-10-19019 October 1998 Withdraws Requesting Exemption from Requirements of GDC 56 with Respect to Ei Hatch,Unit 2 Reactor bldg-to- Suppression Chamber Vacuum Relief Sys Design Due to Listed Reasons HL-5687, Forwards Required 120-day Response to GL 98-04, Potential for Degradation of ECCS & Containment Spray Sys After LOCA Because of Const & Protective Coating Deficiencies & Foreign Matl in Containment1998-10-19019 October 1998 Forwards Required 120-day Response to GL 98-04, Potential for Degradation of ECCS & Containment Spray Sys After LOCA Because of Const & Protective Coating Deficiencies & Foreign Matl in Containment HL-5686, Informs That Corrective Actions Relative to Thermo-Lag 330-1 Issues Are Complete1998-10-16016 October 1998 Informs That Corrective Actions Relative to Thermo-Lag 330-1 Issues Are Complete HL-5697, Requests Delay of Insp of RPV Circumferential Shell Welds for Two Operating Cycles as Outlined in NRC Info Notice 97-63,Suppl 1 & That Proposed Alternative Be Authorized Per 10CFR50.55a(a)(3)(i),per1998-10-16016 October 1998 Requests Delay of Insp of RPV Circumferential Shell Welds for Two Operating Cycles as Outlined in NRC Info Notice 97-63,Suppl 1 & That Proposed Alternative Be Authorized Per 10CFR50.55a(a)(3)(i),per HL-5689, Forwards Request for NRC Finding of Exigent Circumstance Re License Amend for Extended Power Update Operation.Changes Would Be Made While Plant Is Operating,Which as Stated,Has Potential to Create Unnecessary Plant Transients1998-09-30030 September 1998 Forwards Request for NRC Finding of Exigent Circumstance Re License Amend for Extended Power Update Operation.Changes Would Be Made While Plant Is Operating,Which as Stated,Has Potential to Create Unnecessary Plant Transients HL-5673, Informs NRC That Util Intends to Load Four Lead Use Assemblies Into Unit 2 Core as Part of Reload 14/Cycle 15 During Fall 1998 Refueling Outage.Proprietary Info Encl. Proprietary Info Withheld,Per 10CFR2.7901998-09-18018 September 1998 Informs NRC That Util Intends to Load Four Lead Use Assemblies Into Unit 2 Core as Part of Reload 14/Cycle 15 During Fall 1998 Refueling Outage.Proprietary Info Encl. Proprietary Info Withheld,Per 10CFR2.790 HL-5680, Informs NRC of Util Plans & Schedule for Exam of Unit 1 RPV Shell Welds.Util Anticipates Having Final Relief Request Submitted to NRC for Review by 9907011998-09-18018 September 1998 Informs NRC of Util Plans & Schedule for Exam of Unit 1 RPV Shell Welds.Util Anticipates Having Final Relief Request Submitted to NRC for Review by 990701 1999-09-20
[Table view] |
Text
.
Goorgia Power Company
~*
- 40 trwerrtsss Contor Parkway Post Office Box 1295 ' ,
Strmingham, Alabama 3s201 Telephone 205 877 7279 L
J. T. Beckham, Jr. Georgia Power Vice Presdent - Nuclear Hatch Project the soutoem electic sptem December 21, 1993 Docket Nos. 50-321 HL-4433 50-366 TAC Nos. M59202, M83192 M59203, M83193 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555 Edwin I. Hatch Nuclear Plant Second Ten Year Inspection Interval IST Program Safety Evaluation Response Gentlemen:
By letter dated November 17,1992, Georgia Power Company (GPC) provided responses to the 11 remaining anomalies identified in the Nuclear Regulatory Commission (NRC) stafl"s safety evaluation transmitted to GPC by letter dated December 10,1991. These anomalies are currently being evaluated by the NRC staff.
On September 1,1993, a conference call was held between GPC representatives and the appropriate Nuclear Reactor Regulation (NRR) staff to discuss relief requests RR-V-17, RR-V-19, RR-V-20, RR-V-32, RR-V-40, and RR-V-41. The enclosure to this letter provides revisions to these relief requests which provide additional information as discussed in the conference call.
Should you have any questions in this regard, please call this oflice.
Sincerely,
/ y/
1 T. Beckham, Jr. /
- JKB/cr Enclosure 940104o13s 931221 e dj I hDR. ADOCK 050003g3 f
""" I f, 1
4 V
Geo@ia Po ver 1
)
U.S. ' Nuclear Regulatory Commission Page Two December 21, 1993 cc: Georgia Power Company Mr. H. L. Sumner, Nuclear Plant General Manager .
NORMS US. Nuclear Regulatory Commission. Washington. D.C, Mr. K. Jabbour, Licensing Project Manager - Hatch U.S. Nuclear]Legulatory Commission. Region 11 Mr. S. D. Ebneter, Regional Administrator Mr. L. D. Wert, Senior Resident Inspector - Hatch i
-004433 j
. - . . - . _ . ~. -. =. .
6 d
Enclosure Edwin I. Hatch Nuclear Plant Second Ten Year Inspection Interval .
IST ProgLam Safety Evaluation Respong - ,
d The enclosure provides revisions to six relief requests previously submitted by letter dated.
November 17,1992.
- 1. Relief Request RR-V-17 Relief Request RR-V-17 requested relief from exercising the Unit 2 residual heat -
removal injection check valves on a quarterly basis to verify forward flow operability.
Relief Request RR-V-17 was revised and submitted on November 17,1992 to provide justification for not partial-stroke exercising both valves during each cold shutdown.
The revision also provided for a full-stroke exercise of both valves each refueling.. L outage. During the conference call, the NRR staff questioned _ how GPC is determining that the valves are fully exercised during shutdown cooling operations - '
every refueling outage.
Relief Request RR-V-17 has been revised to provide additional information. :
Verification will be accomplished by an external visual determination of the disk position. The valve design incorporates a two piece hinge pin 'which allows for a visual determination of hinge pin rotation. A copy of the revised relief request is attached to the enclosure. ,
e
- 2. Relief Request RR-V-19 Relief Request RR-V-19 has been revised to clarify that the requested relief is applicable only to the Unit 2 high pressure coolant injection system pump room cooler .
outlet check valves. ~ The relief request submitted on- November .17, .1992 was :
incorrect in that the core spray and residual heat removal pump room coolers were ,
included.' A copy of the revised relief request is attached to the enclosure.
' 3. Relief Request RR-V-20 ;
Relief Request RR-V-20 originally requested relief from_ exercising and switch-to-light ;
stroke timing several plant sewice water power operated valves and proposed to verify ' -.
proper operation by assigning a maximum stroke time and measuring stroke times by ? ?
direct observation. Relief Request . RR-V-20 was revised - and submitted on November 17,1992 such that the valves will be stroke timed by observing actual stem movement. During the conference call, the NRR staff questioned the applicability of -
data trending.
i HL-4433 E-1 .l
.l,
Enclosure Second Ten Year Inspection Interval IST Program Safety Evaluation Response Relief Request RR-V-20 has been revised to include comparative trending of stroke time data to monitor for valve degradation. The relief request has also been revised to clarify the actual code requirement for which reliefis being requested and to provide additional information relative to the accuracy of stroke time measurements by.
observation of valve stem movement. A copy of the revised relief request is attached -
to the enclosure.
- 4. Relief Requ_ests RR-V-32 and RR-V-40 Relief Requests RR-V-32 and RR-V-40 requested relief from measuring the stroke-time of the traversing incore probe (TIP) purge supply valves. The relief requests were revised and submitted on November 17,1992 to propose trending oflocal leak rate testing data to monitor for valve degradation. During the conference call, the NRR staff questioned the adequacy of the proposed method to identify valve degradation.
Relief Requests RR-V-32 and RR-V-40 have been revised to provide additionai' justification supporting the proposed alternative testing. Plant design did not require or incorporate remote' indicating lights for the TIP purge supply valves. The subject valves perform a safety function for containment isolation only, and the FSAR analysis indicates that the associated I;ne is of such a size that even if the valve did not close and the line ruptured, the plant would still comply'with offsite release limits.
Testing to monitor.for degradation does not add any _ additional confidence level or margin of safety. The subject valves are leakrate tested each refueling ~o utage which verifies their ability to close and provide containmen' t isolation. Testing to monitor degradation will require a system modification or the use of specialized testing equipment, .either of which imposes additional burden and hardship on the utility .
without a commensurate confirmation or increase in the level of safety afforded the i public. The proposed alternative testing identified in Relief Requests RR-V-32 and RR-V-40 is appropriate to confirm the subject valves' operability, Copics of the revised relief reguests are attached to the enclosure.
l HL-4433 E-2 i .
Enclosure Second Ten Year Inspection Interval i IST Program Safety Evaluation Response ;
t
.i
- 5. . ReliefReauest RR-V-41 Relief Request RR-V-41 requested relief from full flow exercising the diesel generator. ,
service water outlet check valves quarterly and proposed to perform exercising in . ,
conjunction with diesel generator tests. The relief request was revised and submitted on November '17,1992 to provide the approximate power levels at which the diesels -
are tested and to include a proposal to disassemble, manually exercise, and visually ,
inspect one valve every third refueling outage on a rotating basis. During Lthe ' j conference call, the NRR staff questioned the stated interval and inquired into the !
service conditions and maintenance history applicable to these valves. l Relief Request RR-V-41 has been revised to provide additional justification for the ,
disassembly and inspection frequency and to clarify the justification for the proposed ;
alternative testing. A copy of the revised relief request is attached to the enclosure. ,
.i l
-i t
[
l
.i l
i HL-4433 E-3
.l
. ~ - - . ..
.- -. .. 2 -
RELIEF REQUEST RR-V-17 SYSTEM: RHR VALVE (S): 2 Ell-F050A,B CATEGORY: AC CLASS: 1 FUNCTION: LPCI and Pressure Isolation TEST REQUIREMENT: Verify forward flow operability quarterly or at cold shutdown per IWV-3520.
BASIS FOR RELIEF: The plant and RHR system configuration does not provide for.
full or partial flow exercising during normal operation. ;
LPCI injection during normal operation is impossible because reactor pressure is significantly greater than LPCI injection pressure. Therefore, full or partial exercising with flow quarterly is impossible.
During the shutdown cooling mode of RHR operation, the normal flow rate is between 7700 and 8200 gpm. At 7700 gpm the flow velocity is approximately 14 fps. Valve vendor information ;
indicates that a flow velocity of a 10 fps is sufficient to fully open the valve disk if.the valve is in good operating condition. Therefore, normal shutdown cooling flow rates are <
sufficient to fully open the disk of a valve .in good -
operating condition.
Valve design incorporates a two piece (outside hollow cylinder and inside solid cylinder) hinge pin because the valve was initially provided with an operator which was used. t to minimally exercise the valve disk. The operator.is no..
longer utilized for disk exercising, but the'two piece hinge "
pin allows for external visual determination of the disk :
position by observing the inside hinge pin position.
It is normal plant practice to utilize only one loop of RHR in shutdown cooling for any unscheduled shutdown due to the extra efforts involved in system alignment, flushing, pipe warm-up and swapping of loops. To require both loops of RHR shutdown cooling to be. placed in operation during an -
unplanned shutdown for the sole purpose of exercising each -
check valve seems unwarranted. Therefore, exercising both~
valves at each shutdown'is impractical.
Page 1 of 2
i A
RR-V-17 (cont.)
ALTERNATE TESTING: At least one of these check valves receives shutdown cooling flow (7700 - 8200 gpm), therefore is at least partially exercised, each cold shutdown. The loop of RHR shutdown cooling placed into service will be alternated for each unplanned shutdown. Therefore, a different valve will be at '
least partially exercised each time shutdown cooling is utilized.
During each refueling outage, both loops of RHR shutdown cooling are utilized in support of normal shutdown and fuel Therefore both valves are exercised handling activities.
during each refueling outage.
In conjunction with RHR shutdown cooling operation each refueling outage, external visual observation of rotation of the' inside hinge pin will be utilized to confirm that the valve disk is fully open. Scribe marks, angular measurements '
or some other positive means will be.used to ensure that the flow actually moves the valve disk to the full open position.
If visual observation does not confirm that the flow has '
fully exercised the valve disk, then appropriate additional actions will be taken (e.g. mechanically exercising the valve perIWV-3522(b) disassemble, exercise and visually inspect, etc.).
1 Page 2 of 2
RELIEF REQUEST' RR-V-19 SYSTEM: P' ant Service Water-VALVE (T) co24A&B CATEGUM: t, CLASS: 3 FUNCTION: Provide cooling water flow to HPCI pump' room coolers l!
TEST REQUIREMENT: Verify forward flow operability quarterly or at cold shutdown ,
per IWV-3520.
~
~
BASIS FOR RELIEF: Dur_ing quarterly testing of the HPCI pumps, the associated. l room coolers are placed . in operation,J thereby exercising these valves. However, system _designLdoes not provide for positive verification (flow instrumentation) of.the flow rate -
through each valve. Therefore, . confirmation of full flow exercising quarterly or at cold shutdown:is impossible. .
ALTERNATE TESTING: GPC has implemented a Plant Service Water System Performance Monitoring Program which performs' periodic flow measurements at various' locations throughout the systemi'tol detect potential flow'or component degradation. These measurements are performed prior to each scheduled- refueling ontage in-order that any required -corrective measures. 'can be implemented during the -subsequent' outage. LTemporary ultrasonic flow measuring _ instrument's are utilized to obtain -
the required system flow rates and the architect engineer has provided .the design basis acceptance criteria for each -
location included in the program.
The- ECCS room coolers .-are considered . important pieces L of equipment, and thus Lservice water flow to-- and from each cooler is included in the services water performance-monitoring nrogram.. '
The GPC Service Water Performance Monitoring Program will, be.
utilized prior to each refueling outage to' confirm that these check valves are capable of opening.sufficiently to perform !
their safety related function. -Trending of the associated ;
flow measurements will provide data' which is potential.ly; indicative of' check valve degradation.
1 4-21a Rev. 2 i
.-i
t 4
j l
RR-V-19 (cont.) l Partial exercising of each check valve is confirmed during quarterly testing of the associated ECCS room coolers. .l Temperature indicators are provided in the system piping H which will provide some. assurance that the check valves are 1 not stuck in the closed position. - ;
6 1
I
+
i 4
i l
4-21b Rev. 2 :
1
i 1
RELIEF REQUEST RR-V-20 SYSTEM: - Plant Service Water VALVE (S): IP41-F035A&B, IP41-F036A&B, IP41-F037A-D,-IP41-F039A&B, IP41-F340' 2P41-F035A&B, 2P41-F036A&B, 2P41-F037A-D, 2P41-F039A&B, 2P41-F339A&B :
CATEGORY: B :
CLASS: 3 FUNCTION: Equipment Cooling Water Supply Valves TEST REQUIREMENT: IWV-3413(a) requires stroke timing of power operated valves from initiation of- actuating signal to the end of. the i actuating cycle. This is commonly referred to as " switch-to- l-light" timing.
BASIS FOR RELIEF: These valves are normally closed, fail open air operated i
. valves which have a safety function _to .open and provide.
cooling water flow to .the associated safety related- -i equipment. System design did not provide indicating lights .
or direct valve control switches. Therefore, " switch-to- !
light" timing is not possible.
The valves receive an open signal upon initiation of the ,
associated equipment and a close signal upon termination of operation of the associated equipment. .Therefore,: !
measurement of valve stroke . time can only be performed by i observation of the actual valve stem movement when the-associated equipment is placed into service. -:
These valves have allowable stroke times ranging from 5; :i seconds for the smallest valves to 30 seconds for the largest-valves. IWV-3413(b) requires stroke times to be measured to the nearest second for stroke times of 10 seconds or less and - !
within 10% of the specified limiting. stroke time for times >
greater than 10 seconds. . Review of past stroke time data and interviews with operations personnel directly involved'with the testing,-indicate-that.the requirements of.IWV-3413(b) are achievable utilizing a digital stop watch and observing-actual valve stem movement from the closed to open. position. ;
ALTERNATE TESTING: Each valve _ wil.1 be. stroke timed by observing actual valve .
stem movement. Stroke time will be considered to be the time :
from start to stop of valve stem movement. The requirements of.IWV-3417(a) _will be applied to monitor valve degradation.
l Page 1 of 1 ;
I l
I
'i
RELIEF REQUEST RR-V-32 SYSTEM: Traversing Incore Probe (TIP)
VALVE: 2C51-F3012 CATEGORY: A CLASS: 2 FUNCTION: Containment Isolation TEST REQUIREMENT: IWV-3413 requires power operated valves be stroke timed quarterly and IVV-3417(b) requires comparison testing.
BASIS FOR RELIEF: The safety . "' of this valve is CLOSED to provide containment isolation which is initiated by a LOCA signal and results in isolation of TIP purge and the TIP probes.
Neither the Technical Specifications or the FSAR have any specific requirements for isolation stroke time for this valve.
This is a normally open, nonmally energized solenoid operated valve which strokes in milliseconds. The valve was not provided with remote indicating lights and its design does not provide for observation of actual stem movement (stem is fully enclosed).
A simple check valve is located upstream of this solenoid-valve which provides. outboard-containment isolation of the penetration. Nitrogen purge is at a steady flow anc. p essure which does not impose any harsh operating conditions on this check valve. Therefore, this upstream check valve provides additional assurance for isolation of the associated penetration.
The purge line is small (3/8") and the FSAR evaluation indicates that even in the event of a TIP dry tube failure and non-isolation of the purge line, the radioactive release .
would remain within-the allowable limits.
Since this valve strokes in milliseconds, it is classified as a rapid acting valve per GL 89-04, Position 6. Therefore,. )
if indicating lights or valve stem movement were observable, i comparison time testing of valves with stroke times of less than or equal to 2 seconds is not required.
Industry history' indicates that solenoid valves either j operate properly or not at all. It has not been established that stroke time testing of solenoid valves provides data ,
l Page 1 of 2 ;
i
i s
, u RR-V-32.(cont'.) !
applicable for evaluation of; degradation. The application: y of some type of electronic monitoring would.be on a trial and 1 error basis - since. .no such ' equipment has : been proven to - .j provide useful: test data to date. Considering' the safety .;
function of the- valve (containment oisolation only) and:the'
~
redundancy of this function'provided by a simple check valve,- :!
testing to monitor degradation will not provide a significant increase in assurance _that the. valve is capable of performing. .
its intended function. -i ALTERNATE TESTING: This valve will be exercised closed quarterly. and - e observation that nitrogen flow in the associated tubing'has stopped will be utilized as confirmation 'that ~ the' valve is in the safety related closed position. -i This valve is local leak rate tested (LLRT).at' each refueling - l outage in accordance with 10 CFR-. 50, Appendix J. . LLRT i
- provides assurance that the valve is in the closed position ;
and thus is capable ~of'.providing its safety function of-containment isolation.- ,
1
'i
-i i
b s
i i
.I 1
Page 2 of 2 '
)
RELIEF REQUEST RR-V-40 SYSTEM: Traversing Incore Probe (TIP) ,
VALVE: IC51-F3012 CATEGORY: A CLASS: 2 FUNCTION: Containment Isolation TEST REQUIREMENT: IWV-3413 requires power operated valves be stroke timed
. quarterly and IWV-3417(b) requires comparison testing.
BASIS FOR RELIEF: The safety position of this valve is CLOSED to provide , .;
containment isolation which is initiated by a LOCA signal and -
results in isolation of TIP purge and the TIP probes. !
Neither the Technical Specifications or the FSAR have any specific requirements for isolation stroke time for this -
valve.
This is a normally open, normally energized solenoid operated valve which strokes in milliseconds. The valve was not.- i provided with remote indicating lights and its design does i not provide for observation of actual stem movement.
l A simple check valve is located upstream of this solenoid !
valve which provides outboard containment isolation of the )
penetration. Nitrogen purge is at a steady flow and pressure l which does not impose any harsh operating conditions on this' i check valve. Therefore, additional assurance is provided for l isolation of the associated penetration. 1 The purge line is small (3/8") and the FSAR evaluation -l indicates that even in the event of a TIP dry tube failure - i and non-isolation of the purge line, the radioactive release ;
would remain within the allowable limits. i Since this valve strokes in milliseconds, it is classified as a rapid acting valve per GL 89-04, Position 6. Therefore, if indicating lights or valve stem movement were observable, comparison time testing of valves with stroke times of less than or equal to 2 seconds is'not required.
Industry history indicates that'. solenoid valves either.
operate properly or not at all. It has not been established that stroke time testing of solenoid valves provides data applicable for evaluation of degradation. The application of some type of electronic monitoring would be on a trial and Page 1 of 2
a i i
~
RR-V-40 (cont.)
i error.. basis since no suchl equipment has t,een proven ~ to provide useful test data to:date.' Considering the. safetyf ,-
o function of the .. valve (containment - isolation) Jand. the 'j redundancy of thh function provided by a simple check valve,: ,
, testing to monitor degradation will_ not provide a significant increase in assurance thatithe' valve is capable ~of performing its. intended-function.
j ALTERNATE TESTING: The valve will'be exercised closed quarterly, and observation of a decrease in nitrogen pressure in-the. associated tubing: .
will be utilized as confirmation that the valve 'is .in ~ the. >
safety related' closed position.
This valve is local leak rate' tested (LLRT) at each refueling. j outage in accordance' with .10 CFR 50, .. Appendix -J. Ly3T . i provides assurance that the' valve is.in the closed posit 3pn and thus is capable of providing. its safety., function of. i containment' isolation, j l
I b
d 1
l l
l t I y Page 2 of 2
V
~
RELIEF REQUEST RR-V-41 SYSTEM: Plant Service Water VALVE (S): IP41-F552A&C CATEGORY: C CLASS: 3 FUNCTION: Diesel Generator Cooling Water Discharge Line Check Valves TEST REQUIREMENT: Verify forward flow operability quarterly per IWV-3522(b).
BASIS FOR RELIEF: These normally open check valves are located in the cooling water discharge lines from diesel generators lA and IC.
There are no system design provisions to measure cooling water flow and thus verify forward flow operability.
Each diesel generator is operated for a. minimum of one hour at 1710 - 2000 kW (approx. 60 percent of continuous rated load) during testing once each month. Partial forward flow operability is verified during this test by monitoring diesel generator oil and jacket cooling water temperatures. If sufficient cooling water flow was not provided to the diesel generator, elevated oil and jacket cooling water temperatures would be evident.
Each diesel generator is also operated for a minimum of one hour at 2250 - 2400 kW (approx. 80 percent of continuous rated load) semi-annually. Partial flow operability is again verified during this test by monitoring diesel generator oil and jacket cooling water temperatures.
During each refueling outage (at least once per 18 months).
each diesel generator is operated for a minimum of 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.
During the first two hours of this test, the diesel is loaded to 2: 3000 kW (approx. 105. percent of continuous rated load) and during the remaining 22 hours2.546296e-4 days <br />0.00611 hours <br />3.637566e-5 weeks <br />8.371e-6 months <br /> of this test, the diesel is loaded to 2775 - 2825 kW (approx. 90 percent of continuous ratedload). Diesel generator' oil and jacket cooling water temperatures-are monitored during this test to ensure that sufficient cooling water is provided.
Acceptable operation of the diesel generators during the monthly and semi-annual tests verifies .that the valves are not stuck in the closed position. Acceptable operation of the diesel generators during each refueling outage test Page 1 of 2
RR-V-41 (cont.)
verifies that the check valves have opened sufficiently to perform their design function. The diesel . generator oil and-Jacket cooling water temperatures for each test are trended to ensure no significant changes occur from test to test. .
The Architect Engineer-(AE) performed an evaluation of these .,
valves associated with INPO SOER 86-03 in 1987. This evaluation considered valve type, operating conditions and environment, and past valve maintenance history. The AE recommended periodic disassembly and inspection of the valve internals with at least one of the two valves being inspected every third refueling outage. The AE also recommended that the frequency of inspection .be adjusted depending on inspection results.
ALTERNATE TESTING: Existing monthly and semi-annual diesel surveillance testing will be utilized to prove at least partial check valve exercising. The existing refueling outage frequency diesel testing will be utilized to confirm that the valves will open sufficiently to perform their design safety function.
Additionally, at least one of the two valves will be disassembled, manually exercised and visually inspected every refueling outage on a rotating frequency. ' This disassembly frequency should be adequate to detect any valve degradation in sufficient time to take corrective action and prevent the.
valve from being unable to performing ~its safety function.
Inspection results will be reviewed, and the disassembly frequency will be adjusted if warranted. l-The valves are flanged into the system piping and are completely removed when inspected. The valve is visually inspected and manually full stroke exercised prior to being reinstalled in the pipe line. The valve disassembly is performed prior to the 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> diesel surveillance test, thus the safety function of the valve is confirmed after reassembly by monitoring diesel generator cooling during testing. This diesel testing confirms at least partial valve exercising after reinstallation in the system.
Existing diesel generator surveillance testing in conjunction with the periodic disassembly and inspection should confirm the capability of the valves to perform their intended safety function and should identify any degradation concerns prior to the valves becoming inoperable.
'l Page 2 of 2 l l