02-22-2017 | At 1302 hours0.0151 days <br />0.362 hours <br />0.00215 weeks <br />4.95411e-4 months <br /> Eastern Daylight Time (EDT) on 10 08 2016 with the plant in Mode 1 at 100 percent power, H. B. Robinson Steam Electric Plant, Unit No. 2 (HBRSEP2), experienced a grid perturbation. As a result, HBRSEP2 experienced a reactor trip due to low voltage on the 4kV buses. Plant safety systems responded with the emergency buses separating from offsite power due to emergency bus undervoltage. The emergency diesel generators ( EDG) started and powered the 480V emergency buses. 'A' service water pump did not start on the blackout sequencer; however, sufficient service water flow was available from the three operating service water pumps.
This failure did not aggravate this event. The site declared an Unusual Event (UE) at 1317 EDT for loss of power to emergency buses.
At 0011 EDT on 10 09'16, the UE was terminated.
Once the power grid was stable, plant personnel commenced restoration of offsite power to allow shutdown of the the EDGs. During this evolution, at approximately 2323 EDT on 10 . 08 2016, an automatic actuation of the 'B' auxiliary feedwater (AFW) pump occurred due to improper breaker coordination that satisfied the autostart logic for the AFW system.
The apparent cause of the voltage transient in the HBRSEP2 switchyard is a failed fault detection relay, which prevented the grid fault from being immediately isolated. The failed relay has been replaced. |
---|
|
---|
Category:Letter
MONTHYEARIR 05000261/20230042024-01-31031 January 2024 Integrated Inspection Report 05000261/2023004 ML24009A2432024-01-25025 January 2024 Unit, No. 2 - Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0047 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML24009A2712024-01-24024 January 2024 Revision to Reactor Vessel Material Surveillance Capsule Withdrawal Schedule ML23354A0052024-01-0808 January 2024 Request for Withholding Information from Public Disclosure, H. B. Robinson Steam Electric Plant, Unit No. 2 ML23342A0902023-12-0808 December 2023 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection IR 05000261/20234202023-11-30030 November 2023 Security Baseline Inspection Report 05000261/2023420 (Cover Letter with Report) IR 05000261/20230102023-11-28028 November 2023 Fire Protection Team Inspection Report 05000261/2023010 ML23317A3462023-11-14014 November 2023 Duke Fleet - Correction Letter to License Amendment Nos. 312 & 340 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1 IR 05000261/20230032023-11-0707 November 2023 Integrated Inspection Report 05000261 2023003 and 07200060 2023001 ML23226A0862023-10-12012 October 2023 Issuance of Amendment No. 277 Regarding Revision of TSs to Add High-High Steam Generator Level Function to Table 3.3.2-1 and Remove Obsolete Content from TSs 2.1.1.1 and 5.6.5.b ML23346A1322023-10-0606 October 2023 Communication from C-10 Research & Education Foundation Regarding NextEra Common Emergency Fleet Plan License Amendment Request and Related Documents Subsequently Published ML23256A0882023-09-25025 September 2023 Issuance of Alternative to Steam Generator Welds ML23195A0782023-08-29029 August 2023 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1 ML23235A0552023-08-23023 August 2023 Notification of an Fire Protection Team Inspection (FPTI) (NRC Inspection Report 05000261/2023010) and Request for Information (RFI) IR 05000261/20230052023-08-21021 August 2023 Updated Inspection Plan for H.B. Robinson Steam Electric Plant (Report 05000261/2023005) IR 05000261/20230022023-08-0707 August 2023 Integrated Inspection Report 05000261/2023002 IR 05000261/20234022023-05-30030 May 2023 Cyber Security Inspection Report 05000261/2023402 ML23145A1602023-05-25025 May 2023 Submittal of Updated Final Safety Analysis Report (Revision No. 30), Independent Spent Fuel Storage Installation Safety Analysis Report (Revision No. 28), Technical Specifications Bases Revisions, Quality IR 05000261/20230012023-05-0202 May 2023 Integrated Inspection Report 05000261/2023001 ML23118A0762023-05-0101 May 2023 Approval for Use of Specific Provision of a Later Edition of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section XI ML22332A4932023-03-10010 March 2023 William States Lee III 1 and 2 - Issuance of Amendments Regarding the Relocation of the Emergency Operations Facility IR 05000261/20220062023-03-0101 March 2023 Annual Assessment Letter for H.B. Robinson Steam Electric Plant, Unit 2 (Report 05000261/2022006) ML23047A4512023-02-21021 February 2023 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000261/2023402 ML23041A2272023-02-13013 February 2023 2022 Q4 Robinson_Workflow Final ML22329A2982023-01-19019 January 2023 Issuance of Amendment No. 274 Regarding Revision of Technical Specification 3.8.1 Surveillance Requirement 3.8.1.16 ML22294A0922022-12-15015 December 2022 Issuance of Amendment No. 273 Regarding Adoption of TSTF-577, Revised Frequencies for Steam Generator Tube Inspections, Revision 1 ML22339A1362022-12-0101 December 2022 2023 Requalification Program Inspection - H.B. Robinson Nuclear Plant ML22096A0032022-11-18018 November 2022 McGuire Nuclear Station and Shearon Harris Nuclear Power Plant Authorization of RA-19-0352 Regarding Use of Alternative for RPV Head Closure Stud Examinations ML22322A1322022-11-18018 November 2022 301, NRC Operator License Examination Report & Cover Letter Merged ML22256A2532022-11-14014 November 2022 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-541, Rev. 2 IR 05000261/20220032022-11-0303 November 2022 Integrated Inspection Report 05000261 2022003 IR 05000261/20224022022-10-19019 October 2022 Security Baseline Inspection Report 05000261/2022402 IR 05000261/20220102022-09-26026 September 2022 Design Basis Assurance Inspection (Teams) Inspection Report 05000261/2022010 IR 05000261/20223012022-09-23023 September 2022 301 Operator License Exam Approval Letter (05000261/2022301) ML22258A0302022-09-15015 September 2022 Evacuation Time Estimate Reports IR 05000261/20220052022-08-26026 August 2022 Updated Inspection Plan for the H.B Robinson Steam Electric Plant - Report 05000261/2022005-Final IR 05000261/20214042022-08-10010 August 2022 Reissue - H.B. Robinson Steam Electric Plant Security Baseline Inspection Report 05000261/2021404 IR 05000261/20220022022-08-0909 August 2022 Integrated Inspection Report 05000261 2022002, 07200060 2022001 and Exercise of Enforcement Discretion ML22213A0682022-08-0505 August 2022 Request for Withholding Information from Public Disclosure for H. B. Robinson Steam Electric Plant, Unit 2 ML22193A2122022-08-0404 August 2022 Request of Alternatives to ASME Code Section XI Subsection IWE Requirements for Containment Inspections ML22159A2952022-08-0303 August 2022 Issuance of Amendment No. 271 Regarding Correction to Non-Conservative Technical Specifications Figure 3.4.3-2, Pressure/Temperature Limit Cooldown Curves IR 05000261/20220112022-07-19019 July 2022 Biennial Problem Identification and Resolution Inspection Report 05000261/2022011 ML22167A1702022-07-14014 July 2022 Closeout of Generic Letter 2004 02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors ML22046A0222022-06-14014 June 2022 Issuance of Amendments to Adopt TSTF-439, Eliminate Second Completion Times Limiting Time from Discovery of Failure to Meet an LCO ML22125A1942022-05-12012 May 2022 Request for Withholding Information from Public Disclosure for H.B. Robinson Steam Electric Plant, Unit 2 IR 05000261/20220012022-05-0202 May 2022 Integrated Inspection Report 05000261/2022001 IR 05000261/20224012022-04-19019 April 2022 Security Baseline Inspection Report 05000261/2022401 ML22098A2262022-04-11011 April 2022 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection ML22083A0032022-03-29029 March 2022 Closeout of Bulletin 2012 01, Design Vulnerability in Electric Power System IR 05000261/20210062022-03-0202 March 2022 Annual Assessment Letter for H.B. Robinson Steam Electric Plant Unit 2 (Report No. 05000261/2021006) 2024-01-08
[Table view] Category:Licensee Event Report (LER)
MONTHYEARRA-19-0384, LER 20190-001-00 for H.B. Robinson Steam Electric Plant, Unit 2, Turbine Trip/Reactor Trip Due to Main Generator Lockout2019-10-0909 October 2019 LER 20190-001-00 for H.B. Robinson Steam Electric Plant, Unit 2, Turbine Trip/Reactor Trip Due to Main Generator Lockout 05000261/LER-2017-0022017-12-14014 December 2017 Plant Vital Area Security Vulnerability Discovered Without Compensatory Security Measures, LER 17-002-00 for H.B. Robinson, Unit 2, Regarding Plant Vital Area Security Vulnerability Discovered Without Compensatory Security Measures 05000261/LER-2017-0012017-06-0101 June 2017 Auxiliary Feedwater System Actuation During Surveillance Testing, LER 17-001-00 for H.B. Robinson, Unit 2, Regarding Auxiliary Feedwater System Actuation During Surveillance Testing 05000261/LER-2016-0052017-02-22022 February 2017 Reactor Trip and Automatic System Actuation Due to Weather-Related Grid Disturbance, LER 16-005-01 for H. B. Robinson Steam Electric Plant, Unit 2 Regarding Reactor Trip and Automatic System Actuation Due to Weather-Related Grid Disturbance 05000261/LER-2016-0022016-06-13013 June 2016 Unanalyzed Condition Related to Main Steam Line Break Inside Containment, LER 16-002-00 for H.B. Robinson Steam Electric Plant, unit No. 2, Regarding Unanalyzed Condition Related to Main Steam Line Break Inside Containment 05000261/LER-2016-0012016-03-21021 March 2016 Inoperability of Motor-Driven Auxiliary Feedwater Pumps Due to Insufficient Lube Oil Cooling, LER 16-001-00 for H.B. Robinson, Unit 2, Regarding Inoperability of Motor-Driven Auxiliary Feedwater Pumps Due to Insufficient Lube Oil Cooling RNP-RA/11-0057, LER 011-001-00 for H. B. Robinson, Unit 2, Regarding Condition Prohibited by Technical Specifications When Non-Seismic System Was Aligned to Refueling Water Storage Tank Due to Regulatory Requirements Not Adequately Incorporated in Pl2011-06-30030 June 2011 LER 011-001-00 for H. B. Robinson, Unit 2, Regarding Condition Prohibited by Technical Specifications When Non-Seismic System Was Aligned to Refueling Water Storage Tank Due to Regulatory Requirements Not Adequately Incorporated in Plant Do 2019-10-09
[Table view] |
comments regarding burden estimate to the FOIA, Privacy and Information Collections Branch (T-5 F53), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by e-mail to Infocollects.Resource@nrc gov, and to the Desk Officer, Office of Information and Regulatory Affairs used to Impose an information collection does not display a currently valid OMB control number, the NRC may not conduct or sponsor, and a person is not required to respond to, the information collection 05000- 261 H. B. Robinson Steam Electric Plant, Unit No. 2 2016 - 005 - 01
BACKGROUND
At the time this condition was identified, H. B. Robinson Steam Electric Plant, Unit No. 2 (HBRSEP2) was operating in Mode 1 at approximately 100 percent power. No structures, systems or components were out of service at the time of the event that contributed to this event.
HBRSEP2 is connected to the transmission grid via six 230kV lines leaving the 230kV switchyard[FK]. The transmission line initiating this event is the Rockingham 230kV line.
This event is reportable under 10 CFR 50.73(a)(2)(iv)(A), any event or condition that resulted in valid manual or automatic actuation of any of the following systems: reactor protection system[JC], general containment isolation signals[BD], emergency core cooling systems[BQ], auxiliary or emergency feedwater system[BA], containment heat removal and depressurization systems[BE], emergency AC electrical systems[EK], emergency service water systems[BI].
On 10/08/2016, notification to the NRC Operations Center was made (EN# 52290) under 10 CFR 50.72(b)(2)(iv)(B) due to automatic actuation of several safety systems, and under 10 CFR 50.72(b)(3)(iv)(A) due to the valid subsequent actuation of the auxiliary feedwater system.
EVENT DESCRIPTION
At 1302 hrs on 10/08/16, a severe voltage depression in the HBRSEP2 switchyard was caused by a fault on the Robinson-Rockingham 230kV transmission line that was not immediately isolated due to a failed fault detector (50L) relay[RLY] in the HBRSEP2 switchyard. Failure of the 50L relay prevented the transmission of a trip signal to the Rockingham 230kV line circuit breakers[BKR] in the HBRSEP2 switchyard. The reduced voltage was then transferred to all of the HBRSEP2 auxiliary electrical buses[BU], including the 4kV buses. The reactor[RCT] tripped when a two out of three coincidence was satisfied for the 4kV bus undervoltage relays. The undervoltage caused the actuation of several safety systems, including the reactor protection system (RPS), emergency diesel generators (EDGs), emergency service water system, and the auxiliary feedwater system (AFW). These systems functioned as designed, with the exception of the 'A' service water pump[P], which did not start on the blackout sequencer due to high contact resistance within the sequencer relay[44]. However, sufficient service water flow was available from the three operating service water pumps.
The 'A' service water pump failure did not aggravate this event, and the failed sequencer relay was replaced.
After grid stability was achieved, plant operations personnel commenced restoration of offsite power to the emergency buses to allow the shutdown of the EDGs. At approximately 2323 on 10/8/2016, an inadvertent valid actuation of the 'B' motor-driven AFW pump occurred when the 'B' EDG output breaker was opened as part of restoring offsite power to the emergency bus. This actuation initiated due to the presence of an actuation signal that was no longer being defeated with the 'B' EDG output breaker closed.
CAUSAL FACTORS
The 10/08/2016 grid fault on the Robinson-Rockingham 230kV line was isolated immediately at Rockingham but not at HBRSEP2. The undervoltage transient was allowed to propagate to the HBRSEP2 switchyard due to a failed 50L fault detection relay. This caused a decreased voltage below the HBRSEP switchyard undervoltage relay setpoints.
comments regarding burden estimate to the FOIA, Privacy and Information Collections Branch (T-5 F53), U.S. Nuclear Regulatory Commission, Washington, DC 20555.0001, or by e-mail to Infocollects.Resource©nrc.gov, and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150.0104), Office of Management and Budget, Washington, DC 20503. If a means used to impose an information collection does not display a currently valid OMB control number, the NRC may not conduct or sponsor, and a person is not required to respond to, the information collection 05000- H. B. Robinson Steam Electric Plant, Unit No. 2 261 CAUSAL FACTORS (continued) The AFW system actuation during restoration of offsite power to the emergency buses was due to inadequate procedural guidance to direct an infrequently performed task: offsite power restoration to vital buses post loss of offsite power (LOOP) event, post outage or emergency operating procedure entry. Interviews with the operations crew revealed that the operators were in "knowledge space" due to a lack of procedural guidance regarding the AFW circuitry during restoration of power following a LOOP event. Though the operators understood the interlock[IEL] with the AFW pump autostart, it was not considered during the restoration process. The operators' focus was on ensuring power was restored to the emergency bus to ensure no errors occurred, which could result in an escalation to an ALERT condition.
CORRECTIVE ACTIONS
Complete:
1. Bypass the failed 50L Relay.
2. Replace failed 50L relay (Work Order 20119476) 3. Replaced failed 'A' Service Water pump relay (Work Order 20115561) Planned:
1. Revise procedure OP-603, Electrical Distribution, to address shortcomings related to the AFW autostart during restoration of offsite power to emergency buses.
SAFETY ANALYSIS
The HBRSEP2 reactor trip due to 4kV bus undervoltage and resultant plant safety system actuations due to undervoltage on the 480V buses occurred automatically per system design. The failure of the 50L fault detector relay on the Robinson- Rockingham 230kV line in the Robinson switchyard was self-revealing. The 50L relay is not a safety-related relay, but its failure resulted in the reactor/plant trip. There was no nuclear safety significance beyond a plant trip and related system actuations. There were no industrial or radiological safety impacts.
HBRSEP2 experienced a reduced switchyard voltage to less than 50% nominal voltage. The HBRSEP2 start-up transformer[XFMR] never disconnected from the switchyard and remained energized throughout the event. The HBRSEP2 4kV buses remained energized throughout the event. The HBRSEP2 480V buses tripped on undervoltage, except for 480V bus 5, with the emergency buses and the dedicated shutdown bus being re-energized from diesel generators[DG], per electrical system design.
The automatic actuation of the AFW system during restoration of offsite power was valid, and the system responded to plant conditions as designed. There is no safety consequence to this aspect of the event. The cause was related to inadequate procedural guidance and not attributed to any equipment failures. This event resulted in no significant impact to the health and safety of the public.
ADDITIONAL INFORMATION
An operating experience (OE) search was conducted; there is no prior OE at HBRSEP2 involving failure of a fault detection relay in the HBRSEP2 switchyard within the past three years.
Energy Industry Identification System (EllS) codes for systems and components relevant to this event are identified in the text of this document within brackets [ ].
|
---|
|
|
| | Reporting criterion |
---|
05000261/LER-2016-001 | Inoperability of Motor-Driven Auxiliary Feedwater Pumps Due to Insufficient Lube Oil Cooling LER 16-001-00 for H.B. Robinson, Unit 2, Regarding Inoperability of Motor-Driven Auxiliary Feedwater Pumps Due to Insufficient Lube Oil Cooling | 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications 10 CFR 50.73(a)(2)(i) | 05000261/LER-2016-002 | Unanalyzed Condition Related to Main Steam Line Break Inside Containment LER 16-002-00 for H.B. Robinson Steam Electric Plant, unit No. 2, Regarding Unanalyzed Condition Related to Main Steam Line Break Inside Containment | 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition | 05000261/LER-2016-003 | Failure of Lake Robinson Tainter Gates to Fully Open During Performance of Functionality Testing | 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition 10 CFR 50.73(a)(2)(v)(A), Loss of Safety Function - Shutdown the Reactor 10 CFR 50.73(a)(2)(v)(D), Loss of Safety Function - Mitigate the Consequences of an Accident 10 CFR 50.73(a)(2)(ii) | 05000261/LER-2016-004 | Reactor Trip During The Performance of a Visual Inspection of The Main Turbine Trip Block | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000261/LER-2016-005 | Reactor Trip and Automatic System Actuation Due to Weather-Related Grid Disturbance LER 16-005-01 for H. B. Robinson Steam Electric Plant, Unit 2 Regarding Reactor Trip and Automatic System Actuation Due to Weather-Related Grid Disturbance | 10 CFR 50.73(a)(2)(iv)(A), System Actuation |
|