Letter Sequence Approval |
---|
EPID:L-2022-LLA-0094, License Amendment Request - Revision to Alternative Source Term Calculation for Main Steam Isolation Valve (MSIV) Leakage and Non-MSIV Leakage (Approved, Closed) |
|
|
|
---|
Category:Letter
MONTHYEARML24268A3382024-10-16016 October 2024 Issuance of Amendment No. 253 Regarding the Modification of TS Surveillance Requirement 4.3.6.a Related to Adoption of TSTF-425, Revision 3 RS-24-093, Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-10-10010 October 2024 Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests NMP2L2890, Submittal of Revision 26 to the USAR and Reference Figures, 10 CFR 50.59 Evaluation Summary Report, TS Bases, TRM Requirements Manual Changes, and 10 CFR 54.37(b) Aging Management Review (Excludes Attachment 6)2024-10-0404 October 2024 Submittal of Revision 26 to the USAR and Reference Figures, 10 CFR 50.59 Evaluation Summary Report, TS Bases, TRM Requirements Manual Changes, and 10 CFR 54.37(b) Aging Management Review (Excludes Attachment 6) IR 05000220/20243022024-10-0303 October 2024 Initial Operator Licensing Examination Report 05000220/2024302 ML24275A2442024-10-0303 October 2024 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief, Division of Operating Reactor Licensing ML24190A0012024-09-26026 September 2024 Issuance of Amendment Nos. 252 and 197 Regarding the Revision to Technical Specification Design Features Section to Remove Nine Mile Point Unit 3 Project Designation NMP1L3608, Supplemental Information Letter No. 3 - Revision to the Technical Specifications Design Features Sections to Remove the Nine Mile 3 Nuclear Project, LLC, Designation2024-09-20020 September 2024 Supplemental Information Letter No. 3 - Revision to the Technical Specifications Design Features Sections to Remove the Nine Mile 3 Nuclear Project, LLC, Designation RS-24-090, Response to Request for Additional Information - Relief Request Concerning Extension of Permanent Relief from Ultrasonic Examination of Reactor Pressure Vessel Circumferential Shell Welds2024-09-12012 September 2024 Response to Request for Additional Information - Relief Request Concerning Extension of Permanent Relief from Ultrasonic Examination of Reactor Pressure Vessel Circumferential Shell Welds ML24249A1362024-09-0404 September 2024 EN 57304 - Westinghouse Electric Company, LLC, Final Report - No Embedded Files. Notification of the Potential Existence of Defects Pursuant to 10 CFR Part 21 IR 05000220/20240052024-08-29029 August 2024 Updated Inspection Plan for Nine Mile Point Nuclear Station, Units 1 and 2 (Report 05000220/2024005 and 05000410/2024005) IR 05000220/20240102024-08-22022 August 2024 Age-Related Degradation Inspection Report 05000220/2024010 and 05000410/2024010 NMP1L3603, Submittal of Preliminary Decommissioning Cost Estimate and Irradiated Fuel Management Plan2024-08-20020 August 2024 Submittal of Preliminary Decommissioning Cost Estimate and Irradiated Fuel Management Plan ML24222A6772024-08-0909 August 2024 Response to Request for Additional Information for Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition IR 05000220/20240022024-08-0505 August 2024 Integrated Inspection Report 05000220/2024002 and 05000410/2024002 ML24215A3002024-08-0202 August 2024 Operator Licensing Examination Approval ML24213A1412024-07-31031 July 2024 Requalification Program Inspection NMP1L3601, Supplemental Information Letter No. 2 - Revision to the Technical Specifications Design Features Sections to Remove the Nine Mile 3 Nuclear Project, LLC, Designation2024-07-31031 July 2024 Supplemental Information Letter No. 2 - Revision to the Technical Specifications Design Features Sections to Remove the Nine Mile 3 Nuclear Project, LLC, Designation NMP2L2883, Fourth Inservice Inspection Interval, Second Inservice Inspection Period 2024 Owner’S Activity Report for RFO-19 Inservice Examinations2024-07-24024 July 2024 Fourth Inservice Inspection Interval, Second Inservice Inspection Period 2024 Owner’S Activity Report for RFO-19 Inservice Examinations ML24198A0852024-07-16016 July 2024 Senior Reactor and Reactor Operator Initial License Examinations RS-24-070, Independent Spent Fuel Storage Installation, Nine Mile Point, Units 1 and 2, Quad Cities, Units 1 and 2, R. E. Ginna - Nuclear Radiological Emergency Plan Document Revisions2024-07-12012 July 2024 Independent Spent Fuel Storage Installation, Nine Mile Point, Units 1 and 2, Quad Cities, Units 1 and 2, R. E. Ginna - Nuclear Radiological Emergency Plan Document Revisions RS-24-061, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-06-14014 June 2024 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations NMP1L3584, License Amendment Request to Revise Technical Specifications to Adopt TSTF-230, Revision 1, Add New Condition B to LCO 3.6.2.3, RHR Suppression Pool Cooling2024-06-13013 June 2024 License Amendment Request to Revise Technical Specifications to Adopt TSTF-230, Revision 1, Add New Condition B to LCO 3.6.2.3, RHR Suppression Pool Cooling IR 05000220/20244012024-05-30030 May 2024 Security Baseline Inspection Report 05000220/2024401 and 05000410/2024401(Cover Letter Only) ML24079A0762024-05-23023 May 2024 Issuance of Amendments to Adopt TSTF 264 NMP1L3591, Response to Ny State Pollutant Discharge Elimination System (SPDES) Permit Request for Information & Modification Request2024-05-18018 May 2024 Response to Ny State Pollutant Discharge Elimination System (SPDES) Permit Request for Information & Modification Request NMP1L3589, Special Report: Containment High Range Radiation Monitor Instrumentation Channel 12 Inoperable2024-05-16016 May 2024 Special Report: Containment High Range Radiation Monitor Instrumentation Channel 12 Inoperable NMP1L3582, 2023 Annual Radioactive Environmental Operating Report for Nine Mile Point Units 1 and 22024-05-15015 May 2024 2023 Annual Radioactive Environmental Operating Report for Nine Mile Point Units 1 and 2 ML24158A2052024-05-15015 May 2024 Annual Radioactive Environmental Operating Report IR 05000220/20240012024-05-10010 May 2024 Integrated Inspection Report 05000220/2024001 and 05000410/2024001 RS-24-049, Updated Notice of Intent to Pursue Subsequent License Renewal Applications2024-05-0909 May 2024 Updated Notice of Intent to Pursue Subsequent License Renewal Applications RS-24-038, Relief Request Concerning Extension of Permanent Relief from Ultrasonic Examination of Reactor Pressure Vessel Circumferential Shell Welds2024-05-0202 May 2024 Relief Request Concerning Extension of Permanent Relief from Ultrasonic Examination of Reactor Pressure Vessel Circumferential Shell Welds 05000410/LER-2024-001, Automatic Reactor Scram on Turbine Trip Due to Low Condenser Vacuum2024-05-0101 May 2024 Automatic Reactor Scram on Turbine Trip Due to Low Condenser Vacuum NMP1L3581, Independent Spent Fuel Storage Installation (ISFSI) - 2023 Radioactive Effluent Release Report2024-04-30030 April 2024 Independent Spent Fuel Storage Installation (ISFSI) - 2023 Radioactive Effluent Release Report RS-24-041, Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-04-30030 April 2024 Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests NMP2L2877, 2023 Annual Environmental Operating Report2024-04-19019 April 2024 2023 Annual Environmental Operating Report NMP2L2878, Core Operating Limits Report2024-04-16016 April 2024 Core Operating Limits Report ML24103A2042024-04-12012 April 2024 Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition ML24092A3352024-04-0101 April 2024 NRC Office of Investigations Case No. 1-2023-002 RS-24-002, Constellation Energy Generation, LLC - Annual Property Insurance Status Report2024-04-0101 April 2024 Constellation Energy Generation, LLC - Annual Property Insurance Status Report ML24074A2812024-03-14014 March 2024 Request for Information and Notification of Conduct of IP 71111.21.N.04, Age-Related Degradation, Reference Inspection Report 05000220/2024010 and 05000410/2024010 NMP1L3577, Special Report: Containment High Range Radiation Monitor Instrumentation Channel 12 Inoperable2024-03-13013 March 2024 Special Report: Containment High Range Radiation Monitor Instrumentation Channel 12 Inoperable IR 05000220/20230062024-02-28028 February 2024 Annual Assessment Letter for Nine Mile Point Nuclear Station, Units 1 and 2, (Reports 05000220/2023006 and 05000410/2023006) NMP1L3570, Supplemental Information Letter - Revision to the Technical Specifications Design Features Sections to Remove the Nine Mile 3 Nuclear Project, LLC, Designation2024-02-0101 February 2024 Supplemental Information Letter - Revision to the Technical Specifications Design Features Sections to Remove the Nine Mile 3 Nuclear Project, LLC, Designation IR 05000220/20230042024-02-0101 February 2024 Integrated Inspection Report 05000220/2023004 and 05000410/2023004 05000410/LER-2023-001, Supplement to LER 2023-001-00, Automatic Reactor Scram on Low Level Due to Partial Loss of Feedwater2024-01-30030 January 2024 Supplement to LER 2023-001-00, Automatic Reactor Scram on Low Level Due to Partial Loss of Feedwater NMP1L3569, CFR 50.46 Annual Report2024-01-26026 January 2024 CFR 50.46 Annual Report ML24004A2122024-01-0808 January 2024 Senior Reactor and Reactor Operator Initial License Examinations ML23354A0012024-01-0404 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0059 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) 05000220/LER-2023-002, Average Power Range Monitors Declared Inoperable Due to Trip of Reactor Recirculation Pump 122023-12-15015 December 2023 Average Power Range Monitors Declared Inoperable Due to Trip of Reactor Recirculation Pump 12 IR 05000410/20243012023-12-14014 December 2023 Initial Operator Licensing Examination Report 05000410/2024301 2024-09-04
[Table view] Category:License-Operating (New/Renewal/Amendments) DKT 50
MONTHYEARML24268A3382024-10-16016 October 2024 Issuance of Amendment No. 253 Regarding the Modification of TS Surveillance Requirement 4.3.6.a Related to Adoption of TSTF-425, Revision 3 ML24079A0762024-05-23023 May 2024 Issuance of Amendments to Adopt TSTF 264 ML23305A1402023-12-13013 December 2023 Units 1 & 2; Nine Mile Point, Unit 2; Peach Bottom, Units 2 & 3; and Quad Cities, Units 1 and 2 - Issuance of Amendments to Adopt Traveler TSTF-580 ML23291A4642023-12-0707 December 2023 Issuance of Amendment No. 251 Regarding the Adoption of Title 10 the Code of Federal Regulations Section 50.69, Risk-Informed Categorization and Treatment of SSC for Nuclear Power Plants ML23289A0122023-12-0606 December 2023 Issuance of Amendment No. 250 Regarding the Revision to Technical Specifications to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b ML23131A4242023-06-23023 June 2023 Issuance of Amendment No. 249 Regarding the Revision to Technical Specification 3.3.1 to Adopt Technical Specifications Task Force Traveler TSTF-568 ML23118A3472023-05-0101 May 2023 County, 1 & 2; Nine Mile Point, 2; and Quad Cities, 1 & 2 - Correction of Amendment No. 193 Adoption of TSTF-306, Revision 2, Add Action to LCO 3.3.6.1 to Give Option to Isolate the Penetration EPID L-2022-LLA-0143 ML23081A0382023-04-25025 April 2023 County, 1 & 2; Nine Mile Point, 2; and Quad Cities, 1 & 2 - Issuance of Amendments to Adopt TSTF-306, Rev. 2, Add Action to LCO 3.3.6.1 to Give Option to Isolate the Penetration ML23082A3502023-04-17017 April 2023 Issuance of Amendment No. 192, Revision of Surveillance Requirements Associated with Emergency Diesel Generator Testing ML23025A4122023-02-28028 February 2023 Issuance of Amendment No. 248 to Revise Alternative Source Term Calculation for Main Steam Isolation Valve Leakage and Non-MSIV Leakage ML22090A0862022-04-29029 April 2022 Amendments to Adopt TSTF-541,Rev.2,Add Exceptions to Surveillance Requirements for Valves,Dampers Locked in Actuated Position ML22033A3102022-03-0404 March 2022 Issuance of Amendment No. 190, Changes to Reactor Pressure Vessel Water Inventory Control Technical Specification Requirements ML22021B6602022-02-0101 February 2022 Issuance of Amendments Related to Order Approving Transfer of Licenses (EPID L-2022-LLM-0000)-Enclosure 1 ML22021B6592022-02-0101 February 2022 Issuance of Amendments Related to Order Approving Transfer of Licenses (EPID L-2022-LLM-0000) (Letter) ML22031A2762022-02-0101 February 2022 Issuance of Indemnity Agreement Amendments-Enclosure 2 ML21347A0382022-01-13013 January 2022 Issuance of Amendments to Revise Reactor Coolant Leakage Requirements ML21295A7342021-11-15015 November 2021 Issuance of Amendment No. 187 Adoption of Technical Specification Task Force (TSTF) Traveler TSTF-501, Revision 1, Relocate Stored Fuel Oil and Lube Oil Volume Values to Licensee Control ML21082A2212021-04-29029 April 2021 Issuance of Amendment No. 186, Adoption of TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4B ML21033A5302021-04-0101 April 2021 Issuance of Amendments to Adopt Technical Specifications Task Force TSTF-566, Revise Actions for Inoperable RHR Shutdown Cooling Subsystems ML21083A1752021-03-24024 March 2021 Correction to License Page for Amendment No. 245 Related to Relaxation of Surveillance Frequency for Instrument Line Flow Check Valve ML21049A0062021-03-16016 March 2021 Issuance of Amendment No. 245 for Relaxation of Surveillance Frequency for Instrument-Line Flow Check Valve ML21013A0052021-02-0404 February 2021 Issuance of Amendments to Adopt Technical Specifications Task Traveler TSTF-568, Revise Applicability of BWR/4 TS 3.6.2.5 and TS 3.6.3.2 ML21033A9432021-02-0202 February 2021 Correction to Acceptance of Requested License Amendment to Adopt Technical Specification Task Force Traveler 582 ML20332A1152021-01-29029 January 2021 Issuance of Amendment No. 183 Regarding Risk-Informed Categorization and Treatment of Structures, Systems, and Components ML20241A1902020-10-20020 October 2020 Issuance of Amendment No. 182 to Change Allowable Main Steam Isolation Valve Leak Rates ML20141L6362020-07-10010 July 2020 Issuance of Amendments Based on TSTF-427,Allowance for Nontechnical Specification Barrier Degradation on Supported System Operability,Rev 2 ML20134H9402020-07-0808 July 2020 Issuance of Amendments Revising the High Radiation Area Administrative Controls ML20021A0702020-04-0606 April 2020 Issuance of Amendments to Delete License Conditions for Decommissioning Trusts ML20034G5462020-03-12012 March 2020 Issuance of Amendments Revising Instrument Testing and Calibration Definitions ML19301B0052019-11-25025 November 2019 Issuance of Amendment No. 239 Administrative Edits to the Technical Specifications ML19204A0632019-09-13013 September 2019 Independent Spent Fuel Storage Installation, James A. FitzPatrick, and Nine Mile Point - Issuance of Amendments to Revise the Emergency Response Organization Staff ML19176A0332019-08-28028 August 2019 Issuance of Amendments to Adopt TSTF-564, Safety Limit MCPR ML19176A0862019-07-30030 July 2019 Issuance of Amendment No. 237 Changes to Containment Oxygen Concentration Requirements RS-19-017, Application to Remove the Table of Contents from Technical Specifications and Place It Under Licensee Control2019-06-14014 June 2019 Application to Remove the Table of Contents from Technical Specifications and Place It Under Licensee Control ML19008A4542019-01-22022 January 2019 Issuance of Amendment No. 236 Revising Technical Specifications to Adopt TSTF-542, Revision 2, Reactor Pressure Vessel Water Inventory Control ML18304A3652019-01-16016 January 2019 2. Issuance of Amendments to Revise the Average Power Range Monitor Requirements ML18344A4522019-01-11011 January 2019 Issuance of Amendment No. 234 Change to Remove Boraflex Credit from Spent Fuel Racks ML18324A7232018-12-13013 December 2018 Issuance of Amendment No. 233 Relocation of Surveillance Requirement Frequencies to Inservice Testing Program ML18342A0152018-12-0909 December 2018 Issuance of Amendment No. 174 to Revise TS 3.5.1, ECCS-Operating, for One-Time Extension of High Pressure Core Spray Completion Time & Associated Surveillance Requirement (Emergency Circumstances) ML18309A3012018-11-15015 November 2018 R. E. Ginna - Issuance of Amendment Nos. 327, 305, 232, 173, and 133, Respectively, Eliminating the Nuclear Advisory Committee Requirements ML18206A2822018-08-0202 August 2018 Issuance of Amendments to Relocate the Staff Qualification Requirements ML18137A6142018-06-26026 June 2018 Calvert Cliffs Independent Spent Fuel Storage Installation; Nine Mile Point Nuclear Station; and R. E. Ginna Nuclear Power Plant - Issuance of Amendments Revising Emergency Action Level Schemes ML18131A2912018-06-0808 June 2018 Issuance of Amendment No. 170 Removal of Note Associated with Surveillance Requirement 3.5.1.2 (CAC No. MGO148; EPID L-2017-LLA-0294) ML18113A0452018-05-29029 May 2018 Issuance of Amendments to Revise Technical Specification Requirements for Secondary Containment ML18073A3642018-03-28028 March 2018 Issuance of Amendment No. 168 to Revise Technical Specifications to Adopt TS Traveler Force 542, Revision 2, Reactor Pressure Vessel Water Inventory Control (CAC No. MF9357; EPID L-2017-LLA-0178) ML18060A0162018-03-16016 March 2018 Issuance of Amendment No. 167 to Revise Technical Specifications 2.1.1.2 Safety Limit Minimum Critical Power Ratio ML18032A1772018-03-0606 March 2018 Issuance of Amendment No. 166 to Adopt Technical Specifications Task Force (TSTF) Traveler TSTF-522 (CAC No. MF9804; EPID L-2017-LLA-0232) ML17324B1782017-12-21021 December 2017 Issuance of Amendment to Allow Greater Flexibility in Performing Surveillance Testing in Modes 1, 2, or 3 of Emergency Diesel Generators(Cac No. MF9579; EPID L-2017-LLA-0203) ML17268A2632017-10-31031 October 2017 Issuance of Amendment to Reduce Steam Dome Pressure in Reactor Core Safety Limits (CAC No. MF8942; EPID L-2016-LLA-0038) ML17163A3552017-08-31031 August 2017 Calvert Cliff, Clinton, Dresden, LaSalle, Limerick, Nine Mile Point, Peach Bottom, Quad Cities, R. E. Ginna, and Three Miles Island - Issuance of Amendments to Adopt TSTF-529, Clarify Use and Application Rules(Cac Nos. MF9470-MF9490) 2024-05-23
[Table view] Category:Safety Evaluation
MONTHYEARML24268A3382024-10-16016 October 2024 Issuance of Amendment No. 253 Regarding the Modification of TS Surveillance Requirement 4.3.6.a Related to Adoption of TSTF-425, Revision 3 ML24190A0012024-09-26026 September 2024 Issuance of Amendment Nos. 252 and 197 Regarding the Revision to Technical Specification Design Features Section to Remove Nine Mile Point Unit 3 Project Designation ML24145A1862024-05-30030 May 2024 Authorization and Safety Evaluation of Alternative Relief Request I5R-12 Concerning the Installation of a Full Structural Weld Overlay on RPV Recirculation Inlet Nozzle N2E ML23305A1402023-12-13013 December 2023 Units 1 & 2; Nine Mile Point, Unit 2; Peach Bottom, Units 2 & 3; and Quad Cities, Units 1 and 2 - Issuance of Amendments to Adopt Traveler TSTF-580 ML23291A4642023-12-0707 December 2023 Issuance of Amendment No. 251 Regarding the Adoption of Title 10 the Code of Federal Regulations Section 50.69, Risk-Informed Categorization and Treatment of SSC for Nuclear Power Plants ML23289A0122023-12-0606 December 2023 Issuance of Amendment No. 250 Regarding the Revision to Technical Specifications to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b ML23151A3472023-08-21021 August 2023 Issuance of Amendments to Adopt TSTF-295-A, Modify Note 2 to Actions of PAM Table to Allow Separate Condition Entry for Each Penetration ML23131A4242023-06-23023 June 2023 Issuance of Amendment No. 249 Regarding the Revision to Technical Specification 3.3.1 to Adopt Technical Specifications Task Force Traveler TSTF-568 ML23156A6832023-06-22022 June 2023 Authorization and Safety Evaluation of Alternative Relief Request I5R-14 ML23156A6822023-06-22022 June 2023 Authorization and Safety Evaluation of Alternative Relief Request I5R-11 ML23114A2522023-04-28028 April 2023 Request to Use a Provision of a Later Edition of the ASME Boiler & Pressure Vessel Code, Section XI ML23081A0382023-04-25025 April 2023 County, 1 & 2; Nine Mile Point, 2; and Quad Cities, 1 & 2 - Issuance of Amendments to Adopt TSTF-306, Rev. 2, Add Action to LCO 3.3.6.1 to Give Option to Isolate the Penetration ML23103A1912023-04-20020 April 2023 Request for Threshold Determination Under 10 CFR 50.80 ML23082A3502023-04-17017 April 2023 Issuance of Amendment No. 192, Revision of Surveillance Requirements Associated with Emergency Diesel Generator Testing ML23094A1422023-04-0505 April 2023 Approval of Alternative Request I5R-13 to Utilize Specific Provisions of Code Case N-716-3 ML23025A4122023-02-28028 February 2023 Issuance of Amendment No. 248 to Revise Alternative Source Term Calculation for Main Steam Isolation Valve Leakage and Non-MSIV Leakage ML22339A0582022-12-21021 December 2022 Relief Request Associated with Pump Periodic Verification Tests of Core Spray System Pumps ML22293B8052022-11-30030 November 2022 Constellation Energy Generation, Llc_Fleet - Request to Authorize Use Honeywell Mururoa V4F1 R Supplied Air Suits ML22090A0862022-04-29029 April 2022 Amendments to Adopt TSTF-541,Rev.2,Add Exceptions to Surveillance Requirements for Valves,Dampers Locked in Actuated Position ML22094A0012022-04-15015 April 2022 Constellation Energy Generation, LLC - Proposed Alternative for Repair of Water Level Instrumentation Partial Penetration Nozzles (Epids L-2021-LLR-0057 and L-2021-LLR-0058) ML22061A0402022-03-11011 March 2022 Relief Request Associated with Excess Flow Check Valves ML22033A3102022-03-0404 March 2022 Issuance of Amendment No. 190, Changes to Reactor Pressure Vessel Water Inventory Control Technical Specification Requirements ML21347A0382022-01-13013 January 2022 Issuance of Amendments to Revise Reactor Coolant Leakage Requirements ML21277A2482021-11-16016 November 2021 Letter with Enclosure 4, Safety Evaluation for Transfer of Licenses and Draft Conforming License Amendments (Public Version) ML21295A7342021-11-15015 November 2021 Issuance of Amendment No. 187 Adoption of Technical Specification Task Force (TSTF) Traveler TSTF-501, Revision 1, Relocate Stored Fuel Oil and Lube Oil Volume Values to Licensee Control ML21256A1792021-11-0202 November 2021 Issuance of Amendment No. 246 Changes to Reactor Pressure Vessel Water Inventory Control Technical Specification Requirements ML21280A0782021-10-27027 October 2021 Proposed Alternative to Use of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code Case N-893 (Epids L-2020-LLR-0147 and L-2020-LLR-0148) ML21230A2062021-09-0303 September 2021 Proposed Alternative to Use ASME OM Code Case OMN-28 ML21216A2202021-08-0505 August 2021 Proposed Alternative to Eliminate Certain Documentation Requirements for Pressure Retaining Bolting ML21166A1682021-06-25025 June 2021 ML21140A1532021-06-0303 June 2021 Correction to April 22, 2021 Safety Evaluation for Requests for Alternative to the Inservice Testing Requirements of the ASME OM Code for the Fifth 10-Year Program Interval ML21082A2212021-04-29029 April 2021 Issuance of Amendment No. 186, Adoption of TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4B ML21109A2162021-04-22022 April 2021 Proposed Alternative to Inservice Testing Requirements of the ASME OM Code for the Fifth 10-Year Interval ML21105A3382021-04-22022 April 2021 Relief from the Requirements of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code Concerning Examination Coverage of Certain Class 1 and 2 Component Welds ML21033A5302021-04-0101 April 2021 Issuance of Amendments to Adopt Technical Specifications Task Force TSTF-566, Revise Actions for Inoperable RHR Shutdown Cooling Subsystems ML21049A0062021-03-16016 March 2021 Issuance of Amendment No. 245 for Relaxation of Surveillance Frequency for Instrument-Line Flow Check Valve ML21049A0242021-02-23023 February 2021 Alternative Request to the Requirements of the ASME OM Code for the Testing Intervals for the Instrument-Line Flow Check Valves ML21013A0052021-02-0404 February 2021 Issuance of Amendments to Adopt Technical Specifications Task Traveler TSTF-568, Revise Applicability of BWR/4 TS 3.6.2.5 and TS 3.6.3.2 ML21028A6732021-02-0303 February 2021 Request to Use a Provision of Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI (EPID L-2020-LLR-011 ML20332A1152021-01-29029 January 2021 Issuance of Amendment No. 183 Regarding Risk-Informed Categorization and Treatment of Structures, Systems, and Components ML21005A0612021-01-14014 January 2021 Proposed Alternatives to Extend the Safety Relief Valve Testing Interval (EPID L-2020-LLR-0014 Through L-2020-LLR-0018) ML20287A1302020-11-0505 November 2020 Review of Quality Assurance Program Changes ML20241A1902020-10-20020 October 2020 Issuance of Amendment No. 182 to Change Allowable Main Steam Isolation Valve Leak Rates ML20269A2002020-09-30030 September 2020 Request to Use a Provision of Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI (EPID L2020-LLR-0117 ML20232A1712020-09-0101 September 2020 Request to Use Alternative Code Case OMN-26 ML20141L6362020-07-10010 July 2020 Issuance of Amendments Based on TSTF-427,Allowance for Nontechnical Specification Barrier Degradation on Supported System Operability,Rev 2 ML20134H9402020-07-0808 July 2020 Issuance of Amendments Revising the High Radiation Area Administrative Controls ML20141L0532020-06-0202 June 2020 Relief from the Requirements of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code ML20113F0412020-04-30030 April 2020 Proposed Alternative to the Submittal Schedule for Certain Reports (COVID-19) ML20021A0702020-04-0606 April 2020 Issuance of Amendments to Delete License Conditions for Decommissioning Trusts 2024-09-26
[Table view] |
Text
February 28, 2023 Mr. David P. Rhoades Senior Vice President Constellation Energy Generation, LLC President and Chief Nuclear Officer Constellation Nuclear 4300 Winfield Road Warrenville, IL 60555
SUBJECT:
NINE MILE POINT NUCLEAR STATION, UNIT 1 - ISSUANCE OF AMENDMENT NO. 248, REVISION TO ALTERNATIVE SOURCE TERM CALCULATION FOR MAIN STEAM ISOLATION VALVE LEAKAGE AND NON-MAIN STEAM ISOLATION VALVE LEAKAGE (EPID L-2022-LLA-0094)
Dear Mr. Rhoades:
The U.S. Nuclear Regulatory Commission (NRC or the Commission) has issued the enclosed Amendment No. 248 to Renewed Facility Operating License No. DPR-63 for the Nine Mile Point Nuclear Station, Unit 1 (Nine Mile Point 1). The amendment consists of changes to the licensing basis for post-loss-of-coolant accident alternative source term analysis for containment leakage at Nine Mile Point 1 in response to your application dated June 29, 2022.
The amendment includes corrections to the chemical group assignment for various radionuclides modeled in the RADionuclide, Transport, Removal and Dose Estimation computer code, Version 3.03, and updates to the modeling of both Main Steam Isolation Valve (MSIV) leakage and non-MSIV leakage. The amendment request was submitted in response to an Inspection Finding from the NRC which identified that changes were made to the original 2007 AST analysis that when taken consecutively, would not have been allowed under the guidance for meeting the requirements specified in Title 10 of the Code of Federal Regulations, Section 50.59, Changes, Tests, and experiments.
A copy of the related safety evaluation is enclosed. A Notice of Issuance will be included in the next Commissions monthly Federal Register notice.
Sincerely,
/RA/
Richard V. Guzman, Senior Project Manager Plant Licensing Branch I Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-220
Enclosures:
- 1. Amendment No. 248 to DPR-63
- 2. Safety Evaluation cc: Listserv
NINE MILE POINT NUCLEAR STATION, LLC CONSTELLATION ENERGY GENERATION, LLC DOCKET NO. 50-220 NINE MILE POINT NUCLEAR STATION, UNIT 1 AMENDMENT TO RENEWED FACILITY OPERATING LICENSE Amendment No. 248 Renewed License No. NPF-63
- 1. The U.S. Nuclear Regulatory Commission (the Commission) has found that:
A. The application for amendment by Constellation Energy Generation, LLC dated June 29, 2022, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act), and the Commission's rules and regulations set forth in 10 CFR Chapter I; B. The facility will operate in conformity with the application, the provisions of the Act, and the regulations of the Commission; C. There is reasonable assurance: (i) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commissions regulations; D. The issuance of this amendment will not be inimical to the common defense and security or to the health and safety of the public; and E. The issuance of this amendment is in accordance with 10 CFR Part 51 of the Commissions regulations and all applicable requirements have been satisfied.
Enclosure 1
- 2. Accordingly, by Amendment No. 248, Renewed Facility License No. DPR-63 is hereby amended to authorize revision to the Nine Mile Point Nuclear Station, Unit No. 1 licensing basis associated with the post-loss-of-coolant accident alternative source term analysis, as set forth in the application dated June 29, 2022.
- 3. This amendment is effective as of its date of issuance and shall be implemented within 60 days from the date of issuance.
FOR THE NUCLEAR REGULATORY COMMISSION Digitally signed by Hipolito Hipolito J. J. Gonzalez Date: 2023.02.28 Gonzalez 15:46:13 -05'00' Hipólito J. González, Chief Plant Licensing Branch I Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Date of Issuance: February 28, 2023
SAFETY EVALUATION BY THE OFFICE OF NUCLEAR REACTOR REGULATION RELATED TO THE REVISION OF THE ALTERNATIVE SOURCE TERM CALCULATION FOR MAIN STEAM ISOLATION VALVE AND NON-MAIN STEAM ISOLATION VALVE LEAKAGE AMENDMENT NO. 248 TO RENEWED FACILITY OPERATING LICENSE NO. DPR-63 CONSTELLATION ENERGY GENERATION, LLC NINE MILE POINT NUCLEAR STATION, UNIT 1 DOCKET NO. 50-220
1.0 INTRODUCTION
In a letter dated June 29, 2022 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML22180A020), Constellation Energy Generation, LLC requested approval of proposed changes to the post-loss-of-coolant accident (LOCA) Alternative Source Term (AST) analysis for containment leakage at Nine Mile Point Nuclear Station, Unit 1 (NMP1).
The proposed changes include corrections to the chemical group assignment for various radionuclides modeled in the RADionuclide, Transport, Removal and Dose Estimation (RadTrad) computer code, Version 3.03, and updates to the modeling of both Main Steam Isolation Valve (MSIV) leakage and non-MSIV leakage. This request was submitted in response to an Inspection Finding from the U.S. Nuclear Regulatory Commission (NRC) which identified that changes were made to the original 2007 AST analysis that when taken consecutively, would not have been allowed under the guidance for meeting the requirements specified in Title 10 of the Code of Federal Regulations (10 CFR), Section 50.59 Changes, Tests, and experiments.
2.0 REGULATORY EVALUATION
The NRC staff evaluated the radiological consequences of affected design basis accidents (DBAs) for NMP1 as proposed by the licensee against the dose criteria specified in 10 CFR 50.67(b)(2). These criteria are: 25 roentgen equivalent man (rem) total effective dose equivalent (TEDE) at the exclusion area boundary (EAB) for any 2-hour period following the onset of the postulated fission product release; 25 rem TEDE at the outer boundary of the low population zone (LPZ) for the duration of the postulated fission product release; and 5 rem TEDE for access and occupancy of the control room (CR) for the duration of the postulated fission product release.
This safety evaluation (SE) addresses the impact of the proposed changes on previously analyzed DBA radiological consequences and the acceptability of the revised analysis results.
The regulatory requirements from which the NRC staff based its acceptance are the accident Enclosure 2
dose criteria in § 50.67, as supplemented in Regulatory Position 4.4 of Regulatory Guide (RG) 1.183 and NUREG-0800 Standard Review Plan Section 15.0.1. The NRC staff's evaluation is based upon the following regulatory codes, guides, and standards:
10 CFR Part 50.67, Accident Source Term.
10 CFR Part 50, Appendix A, "General Design Criterion [GDC] for Nuclear Power Plants: GDC 19, Control room.
RG 1.183, Alternative Radiological Source Terms for Evaluating Design Basis Accidents at Nuclear Power Reactors, Rev. 0, July 2000.
The licensee has not proposed any significant deviation or departure from the guidance provided in RG 1.183.
3.0 TECHNICAL EVALUATION
3.1 Background In a letter dated December 19, 2007 (ML073230597), the NRC issued License Amendment No. 194 implementing AST methodology for NMP1. The dose consequence values in the LOCA evaluation approved in license Amendment No. 194 were based on Revision 0 of Calculation H21C092, NMP1 LOCA w/[loss of off-site power] LOOP, AST Methodology, dated December 14, 2006. On January 24, 2008, the licensees Nuclear Analysis Group issued Incident Report (IR) 02036454 identifying a conservative error in Calculation H21C092 Revision 0. The error related to the source term used by the RadTrad 3.03 code to calculate the dose consequences to the CR personnel and offsite locations. Specifically, 20 radionuclides out of the 63 modeled were assigned incorrect chemical groups. The error resulted in the dose consequences as documented in Calculation H21C092, Revision 0, being overestimated by approximately 10 percent.
On April 8, 2008, the Nuclear Analysis Group issued Revision 1 of Calculation H21C092. The revised calculation corrected the identified errors and modified the dose consequence results accordingly. The objective of Revision 1 was to determine the increase in bypass leakage that would yield dose consequences that would be bounded by the original AST licensing basis.
Revision 1 to Calculation H21C092 provided two sets of LOCA dose consequences. Revision 1 indicated a reduction in doses as a result of assigning the affected radionuclides to their correct chemical groups while keeping all other assumptions consistent with Revision 0. For example, if the leakage values were maintained at the Revision 0 values of 50 standard cubic feet per hour (scfh) per line (100 scfh total) for MSIV leakage and 41.5 scfh for other bypass leakage, the revised CR dose would be reduced from 4.81 rem TEDE to 4.37 rem TEDE.
Revision 1 also evaluated the dose consequences for an increase in bypass leakage from the Revision 0 value of 41.5 scfh to a value that would not result in an increase in the Revision 0 CR dose value while keeping the total MSIV leakage to 100 scfh. H21C092 Revision 1, Section 2.0 Conclusions, indicated that with a total MSIV leakage value of 100 scfh, the bypass leakage could be increased to a value of 91 scfh without exceeding the previous licensing basis CR dose value of 4.81 rem.
On March 26, 2021, the Nuclear Analysis Group issued Revision 2 of calculation H21C092 which included sections of Revision 0, Revision 1, as well as a new analysis to evaluate current
leakage rates to achieve greater flexibility on the combination of MSIV leakage rates and bypass leakage rates. This flexibility allows varying combinations of these leakage rates as long as the sum of the leakage from both pathways does not exceed 191 scfh.
3.2 NRC Staff Review of the Revisions to NMP1 AST Licensing Basis The licensees revisions to the current licensing basis (CLB) AST LOCA analysis were limited to the primary containment leakage pathways that bypass the reactor building (RB). The licensee modeled these pathways as leakage through lines which penetrate the primary containment and the reactor building. Postulated leakage through both closed containment isolation valves in these lines will bypass the reactor building and will not be filtered by the RB emergency ventilation system, thereby resulting in unfiltered ground level releases. These release pathways include leakage through MSIVs and leakage via other systems (i.e., feedwater, torus vent, drywell vent and emergency condenser vent and drain) that provide pathways from the primary containment. The CLB MSIV leakage limitation is 100 scfh, with a maximum of 50 scfh per main steam line. The CLB limitation for the combined leakage of the remaining non-MSIV bypass pathways is 41.5 scfh. As a result of the correction of errors in the calculation supporting these leakage values (H21C092 Revision 0) the licensee determined that the primary containment bypass leakage could be increased from a combined total of 141.5 scfh to a combined total of 191 scfh without exceeding the CLB dose values. The NRC staff reviewed the revisions to H21C092 and notes that the licensee maintained all the critical CLB assumptions such as atmospheric dispersion factors and aerosol deposition removal assumptions in the revisions to H21C092. The NRC staff notes that the revised dose consequences for the NMP1 LOCA analysis resulted in a reduction in the off-site estimates while the CR doses remained the same as the previous licensing basis value of 4.81 rem TEDE.
As shown below, Table 1 from RG 1.183 specifies the boiling water reactor (BWR) core inventory fractions that are assumed to be released into the containment for the LOCA dose consequence analysis.
RG 1.183 Table 1 BWR Core Inventory Fraction Released Into Containment Gap Early Group Release In-vessel Total Phase Phase Noble Gases 0.05 0.95 1.0 Halogens 0.05 0.25 0.3 Alkali Metals 0.05 0.20 0.25 Tellurium Metals 0.00 0.05 0.05 Ba, Sr 0.00 0.02 0.02 Noble Metals 0.00 0.0025 0.0025 Cerium Group 0.00 0.0005 0.0005 Lanthanides 0.00 0.0002 0.0002 As described in the Nuclear Analysis Groups Report number IR02036454, several radionuclides were assigned incorrect early in-vessel release fractions in Revision 0 of H21C092. In some cases, barium (Ba) isotopes were assigned to the strontium group but since these groups have the same release fractions (0.02) there was no impact on the dose
consequence analysis. However, there were six noble metal isotopes (release fraction 0.0025) that were assigned to the Ba group (release fraction 0.02). In addition, there were 12 lanthanide radionuclides (release fraction 0.0002) that were assigned to the noble metals group (release fraction 0.0025). These discrepancies resulted in the over prediction of dose consequences in Revision 0 of calculation H21C092. For instance, correction of these errors resulted in a reduction in the calculated CR TEDE dose of 0.44 rem, from 4.81 rem to 4.37 rem as documented in Revision 1 of H21C092. Revision 1 of H21C092 also determined that with a total MSIV leakage rate of 100 scfh, the other permanent bypass leakage could be increased from the previous limitation of 41.5 scfh to a value of 91 scfh without increasing the previous limiting CLB CR dose of 4.81 rem.
The NRC staff notes that as mentioned in the Nuclear Analysis Groups report, the incorrect assignment of chemical groups may have occurred during the process of adding an additional nuclide (determined to have dose significance) to the default radionuclide inventory file developed by the NRC for using the RadTrad code, Version 3.03. The NRC staff recognized the limited number of nuclides in the original RadTrad code some time ago and included a significantly increased nuclide inventory (from 63 nuclides to over 800 nuclides) in the current version of RadTrad which is part of the Symbolic Nuclear Analysis Package.
Revision 2 of H21C092 provided additional flexibility by calculating dose consequences for varying rates of total MSIV leakage in combination with varying rates of other permanent bypass leakage such that the summation of the leakage from these pathways remained at a value of 191 scfh. The licensee determined that the limiting combination of leakage from these pathways in terms of dose consequences would be from an MSIV leakage of 100 scfh and a value for other permanent bypass leakage of 91 scfh. This combination of leakage values was used to compute the NMP1 updated final safety analysis report (UFSAR) revised licensing basis LOCA dose consequences for the control room, the EAB and the outer boundary of the LPZ as shown in Revision 27 of the UFSAR Table XV-32.
(From NMP Unit 1 UFSAR October 2021 Revision 27)
Table XV-32 LOSS-OF-COOLANT ACCIDENT DOSES Total Dose Acceptance Criteria Receptor (rem TEDE) (rem TEDE)
Control Room 4.81 5 EAB* 8.00 25 LPZ 1.58 25
- Worst 2-hour period of the accident duration The changes in the total LOCA dose consequences from the original calculation through the two revisions are shown in the summary table below. The NRC staff notes that H21C092 Revision 1 listed both the reduction in the dose consequences based on correction of the errors in the original calculation as well as the allowable increase in other permanent bypass leakage that
could be accommodated without exceeding the CLB dose consequences as calculated in H21C092 Revision 0 and approved by the NRC in Amendment No. 194.
Summary Table of NMP1 LOCA Results 30-day Max 2-hour 30-day NMP Unit 1 AST LOCA Dose CR TEDE EAB TEDE LPZ TEDE consequence calculations (rem) (rem) (rem)
NMP Unit 1 LOCA w/LOOP, AST 4.81 9.02 1.60 Methodology H21C092 R0 Results Reduction in doses from H21C092 R0 from the correction of the radionuclide -0.44 -1.59 -0.15 chemical grouping Dose Results from Table 3-1 of H21C092 R1 maintaining leakage limits from H21C092 R0 (other bypass leakage = 4.37 7.43 1.45 41.5 scfh and total MSIV leakage = 100 scfh)
Results from the conclusion of H21C092 R1 Table 2-1 with an increase in other 4.80 8.00 1.58 permanent bypass leakage to 91 scfh and total MSIV leakage = 100 scfh Dose Impact from the values in Table 3-1 of H21C092 R1 to the H21C092 R2
+0.44 +0.57 +0.13 Results for limiting combination of MSIV and other permanent bypass leakage NMP-1 Post-LOCA AST Dose Results 4.81 8.00 1.58 based on calculation H21C092 R2 The NRC staff notes that NMP1 does not have specific technical specification limitations on MSIV leakage. For NMP1, MSIV leakage is treated as a component of containment leakage and is tested in accordance with Appendix J to Part 50, Primary Reactor Containment Leakage Testing for Water-Cooled Power Reactors. The combinations of acceptable MSIV leakage rates and the corresponding other permanent bypass leakage rates are documented in Table P.10 of H21C092 R2 and are shown below. Note that the doses in Table P.10 are only from MSIV and other permanent Bypass leakage as contributions to the total LOCA dose consequence.
H21C092 R2 Table P.10 MSIV and Other Bypass Leakage Cases Analyzed and Dose Consequences Other Total Permanent MSIV Bypass Leakage Leakage CR Dose EAB Dose LPZ Dose (scfh) (scfh) (rem TEDE) (rem TEDE) (rem TEDE) 190 1 1.01E+00 7.74E-01 3.84E-01 180 11 1.02E+00 8.19E-01 3.85E-01 170 21 1.04E+00 8.67E-01 3.86E-01 160 31 1.07E+00 9.21E-01 3.90E-01 150 41 1.09E+00 9.74E-01 3.92E-01 140 51 1.11E+00 1.03E+00 3.94E-01 130 61 1.13E+00 1.09E+00 3.97E-01 120 71 1.16E+00 1.15E+00 4.00E-01 110 81 1.18E+00 1.22E+00 4.04E-01 100 91 1.21E+00 1.28E+00 4.07E-01
- Bold indicates the bounding case.
These combinations of acceptable leakage rates will be controlled by implementation of procedure N1-TSP-201-550, Local Leak Rate Test Summary (Type B and C Tests) for 10 CFR 50, Appendix J, and Secondary Containment Bypass Leakage, in accordance with NMP1 TS 6.5.7, 10 CFR 50, Appendix J, Testing Program Plan.
3.3 Technical Evaluation Conclusion The NRC staff reviewed the assumptions, inputs, and methods used by the licensee to assess the radiological consequences of the LOCA dose consequence analysis for NMP1. The NRC staff finds that the licensee used assumptions, inputs, and methods consistent with the regulatory requirements and guidance identified in Section 2.0 of this SE. The NRC staff compared the doses estimated by the licensee to the applicable criteria identified in Section 2.0 of this SE. The NRC staff concludes, with reasonable assurance, that the licensees estimates of the EAB, LPZ, and CR doses will comply with these criteria. The NRC staff further finds reasonable assurance that NMP1 as modified by this license amendment, will continue to provide sufficient safety margins with adequate defense-in-depth to address unanticipated events and to compensate for uncertainties in accident progression and analysis assumptions and parameters. Therefore, the proposed license amendment is acceptable with respect to the radiological consequences of the LOCA dose consequence analysis for NMP1.
4.0 STATE CONSULTATION
In accordance with the Commissions regulations, the New York State official was notified of the proposed issuance of the amendment on December 19, 2022. The State official had no comments.
5.0 ENVIRONMENTAL CONSIDERATION
The amendment changes a requirement with respect to installation or use of a facility component located within the restricted area as defined in 10 CFR Part 20. The NRC staff has
determined that the amendment involves no significant increase in the amounts, and no significant change in the types, of any effluents that may be released offsite, and that there is no significant increase in individual or cumulative occupational radiation exposure. The Commission has previously issued a proposed finding that the amendment involves no significant hazards consideration, and there has been no public comment on such finding (87 FR 60217). Accordingly, the amendment meets the eligibility criteria for categorical exclusion set forth in 10 CFR 51.22(c)(9). Pursuant to 10 CFR 51.22(b) no environmental impact statement or environmental assessment need be prepared in connection with the issuance of the amendment.
6.0 CONCLUSION
The Commission has concluded, based on the considerations discussed above, that: (1) there is reasonable assurance that the health and safety of the public will not be endangered by operation in the proposed manner, (2) there is reasonable assurance that such activities will be conducted in compliance with the Commissions regulations, and (3) the issuance of the amendment will not be inimical to the common defense and security or to the health and safety of the public.
Principal Contributors: J. Parillo, NRR Date: February 28, 2023
ML23025A412 OFFICE NRR/DORL/LPL1/PM NRR/DORL/LPL1/LA NRR/DRA/ARCB/BC(A)
NAME RGuzman KEntz JDozier DATE 01/26/2023 01/30/2023 12/19/2022 OFFICE OGC NRR/DORL/LPL1/BC NRR/DORL/LPL1/PM NAME MCarpentier HGonzález RGuzman DATE 02/14/2023 02/28/2023 02/28/2023