Category:Letter
MONTHYEARML24268A3382024-10-16016 October 2024 Issuance of Amendment No. 253 Regarding the Modification of TS Surveillance Requirement 4.3.6.a Related to Adoption of TSTF-425, Revision 3 RS-24-093, Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-10-10010 October 2024 Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests ML24275A2442024-10-0303 October 2024 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief, Division of Operating Reactor Licensing IR 05000220/20243022024-10-0303 October 2024 Initial Operator Licensing Examination Report 05000220/2024302 NMP1L3608, Supplemental Information Letter No. 3 - Revision to the Technical Specifications Design Features Sections to Remove the Nine Mile 3 Nuclear Project, LLC, Designation2024-09-20020 September 2024 Supplemental Information Letter No. 3 - Revision to the Technical Specifications Design Features Sections to Remove the Nine Mile 3 Nuclear Project, LLC, Designation RS-24-090, Response to Request for Additional Information - Relief Request Concerning Extension of Permanent Relief from Ultrasonic Examination of Reactor Pressure Vessel Circumferential Shell Welds2024-09-12012 September 2024 Response to Request for Additional Information - Relief Request Concerning Extension of Permanent Relief from Ultrasonic Examination of Reactor Pressure Vessel Circumferential Shell Welds ML24249A1362024-09-0404 September 2024 EN 57304 - Westinghouse Electric Company, LLC, Final Report - No Embedded Files. Notification of the Potential Existence of Defects Pursuant to 10 CFR Part 21 IR 05000220/20240052024-08-29029 August 2024 Updated Inspection Plan for Nine Mile Point Nuclear Station, Units 1 and 2 (Report 05000220/2024005 and 05000410/2024005) IR 05000220/20240102024-08-22022 August 2024 Age-Related Degradation Inspection Report 05000220/2024010 and 05000410/2024010 NMP1L3603, Submittal of Preliminary Decommissioning Cost Estimate and Irradiated Fuel Management Plan2024-08-20020 August 2024 Submittal of Preliminary Decommissioning Cost Estimate and Irradiated Fuel Management Plan ML24222A6772024-08-0909 August 2024 Response to Request for Additional Information for Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition IR 05000220/20240022024-08-0505 August 2024 Integrated Inspection Report 05000220/2024002 and 05000410/2024002 ML24215A3002024-08-0202 August 2024 Operator Licensing Examination Approval ML24213A1412024-07-31031 July 2024 Requalification Program Inspection NMP1L3601, Supplemental Information Letter No. 2 - Revision to the Technical Specifications Design Features Sections to Remove the Nine Mile 3 Nuclear Project, LLC, Designation2024-07-31031 July 2024 Supplemental Information Letter No. 2 - Revision to the Technical Specifications Design Features Sections to Remove the Nine Mile 3 Nuclear Project, LLC, Designation NMP2L2883, Fourth Inservice Inspection Interval, Second Inservice Inspection Period 2024 Owner’S Activity Report for RFO-19 Inservice Examinations2024-07-24024 July 2024 Fourth Inservice Inspection Interval, Second Inservice Inspection Period 2024 Owner’S Activity Report for RFO-19 Inservice Examinations ML24198A0852024-07-16016 July 2024 Senior Reactor and Reactor Operator Initial License Examinations RS-24-070, Independent Spent Fuel Storage Installation, Nine Mile Point, Units 1 and 2, Quad Cities, Units 1 and 2, R. E. Ginna - Nuclear Radiological Emergency Plan Document Revisions2024-07-12012 July 2024 Independent Spent Fuel Storage Installation, Nine Mile Point, Units 1 and 2, Quad Cities, Units 1 and 2, R. E. Ginna - Nuclear Radiological Emergency Plan Document Revisions RS-24-061, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-06-14014 June 2024 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations NMP1L3584, License Amendment Request to Revise Technical Specifications to Adopt TSTF-230, Revision 1, Add New Condition B to LCO 3.6.2.3, RHR Suppression Pool Cooling2024-06-13013 June 2024 License Amendment Request to Revise Technical Specifications to Adopt TSTF-230, Revision 1, Add New Condition B to LCO 3.6.2.3, RHR Suppression Pool Cooling IR 05000220/20244012024-05-30030 May 2024 Security Baseline Inspection Report 05000220/2024401 and 05000410/2024401(Cover Letter Only) ML24079A0762024-05-23023 May 2024 Issuance of Amendments to Adopt TSTF 264 NMP1L3591, Response to Ny State Pollutant Discharge Elimination System (SPDES) Permit Request for Information & Modification Request2024-05-18018 May 2024 Response to Ny State Pollutant Discharge Elimination System (SPDES) Permit Request for Information & Modification Request NMP1L3589, Special Report: Containment High Range Radiation Monitor Instrumentation Channel 12 Inoperable2024-05-16016 May 2024 Special Report: Containment High Range Radiation Monitor Instrumentation Channel 12 Inoperable NMP1L3582, 2023 Annual Radioactive Environmental Operating Report for Nine Mile Point Units 1 and 22024-05-15015 May 2024 2023 Annual Radioactive Environmental Operating Report for Nine Mile Point Units 1 and 2 ML24158A2052024-05-15015 May 2024 Annual Radioactive Environmental Operating Report IR 05000220/20240012024-05-10010 May 2024 Integrated Inspection Report 05000220/2024001 and 05000410/2024001 RS-24-049, Updated Notice of Intent to Pursue Subsequent License Renewal Applications2024-05-0909 May 2024 Updated Notice of Intent to Pursue Subsequent License Renewal Applications RS-24-038, Relief Request Concerning Extension of Permanent Relief from Ultrasonic Examination of Reactor Pressure Vessel Circumferential Shell Welds2024-05-0202 May 2024 Relief Request Concerning Extension of Permanent Relief from Ultrasonic Examination of Reactor Pressure Vessel Circumferential Shell Welds NMP2L2880, Automatic Reactor Scram on Turbine Trip Due to Low Condenser Vacuum2024-05-0101 May 2024 Automatic Reactor Scram on Turbine Trip Due to Low Condenser Vacuum NMP1L3581, Independent Spent Fuel Storage Installation (ISFSI) - 2023 Radioactive Effluent Release Report2024-04-30030 April 2024 Independent Spent Fuel Storage Installation (ISFSI) - 2023 Radioactive Effluent Release Report RS-24-041, Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-04-30030 April 2024 Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests NMP2L2877, 2023 Annual Environmental Operating Report2024-04-19019 April 2024 2023 Annual Environmental Operating Report NMP2L2878, Core Operating Limits Report2024-04-16016 April 2024 Core Operating Limits Report ML24103A2042024-04-12012 April 2024 Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition ML24092A3352024-04-0101 April 2024 NRC Office of Investigations Case No. 1-2023-002 RS-24-002, Constellation Energy Generation, LLC - Annual Property Insurance Status Report2024-04-0101 April 2024 Constellation Energy Generation, LLC - Annual Property Insurance Status Report ML24074A2812024-03-14014 March 2024 Request for Information and Notification of Conduct of IP 71111.21.N.04, Age-Related Degradation, Reference Inspection Report 05000220/2024010 and 05000410/2024010 NMP1L3577, Special Report: Containment High Range Radiation Monitor Instrumentation Channel 12 Inoperable2024-03-13013 March 2024 Special Report: Containment High Range Radiation Monitor Instrumentation Channel 12 Inoperable IR 05000220/20230062024-02-28028 February 2024 Annual Assessment Letter for Nine Mile Point Nuclear Station, Units 1 and 2, (Reports 05000220/2023006 and 05000410/2023006) NMP1L3570, Supplemental Information Letter - Revision to the Technical Specifications Design Features Sections to Remove the Nine Mile 3 Nuclear Project, LLC, Designation2024-02-0101 February 2024 Supplemental Information Letter - Revision to the Technical Specifications Design Features Sections to Remove the Nine Mile 3 Nuclear Project, LLC, Designation IR 05000220/20230042024-02-0101 February 2024 Integrated Inspection Report 05000220/2023004 and 05000410/2023004 05000410/LER-2023-001, Supplement to LER 2023-001-00, Automatic Reactor Scram on Low Level Due to Partial Loss of Feedwater2024-01-30030 January 2024 Supplement to LER 2023-001-00, Automatic Reactor Scram on Low Level Due to Partial Loss of Feedwater NMP1L3569, CFR 50.46 Annual Report2024-01-26026 January 2024 CFR 50.46 Annual Report ML24004A2122024-01-0808 January 2024 Senior Reactor and Reactor Operator Initial License Examinations ML23354A0012024-01-0404 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0059 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML23278A1292023-12-14014 December 2023 Units 1 & 2; Limerick, Units 1 & 2; Nine Mile Point, Units 1 & 2; and Peach Bottom, Units 2 & 3 -Revision to Approved Alternatives to Use Boiling Water Reactor Vessel and Internals Project Guidelines NMP1L3566, Radiological Emergency Plan Document Revision. Includes EP-AA-1013, Revision 10, Radiological Emergency Plan Annex for Nine Mile Point Station2023-12-14014 December 2023 Radiological Emergency Plan Document Revision. Includes EP-AA-1013, Revision 10, Radiological Emergency Plan Annex for Nine Mile Point Station IR 05000410/20243012023-12-14014 December 2023 Initial Operator Licensing Examination Report 05000410/2024301 ML23305A1402023-12-13013 December 2023 Units 1 & 2; Nine Mile Point, Unit 2; Peach Bottom, Units 2 & 3; and Quad Cities, Units 1 and 2 - Issuance of Amendments to Adopt Traveler TSTF-580 2024-09-04
[Table view] Category:License-Operator Examination Report
MONTHYEARIR 05000220/20243022024-10-0303 October 2024 Initial Operator Licensing Examination Report 05000220/2024302 IR 05000410/20243012023-12-14014 December 2023 Initial Operator Licensing Examination Report 05000410/2024301 IR 05000220/20233032023-09-20020 September 2023 Retake Operator Licensing Examination Report 05000220/2023303 IR 05000220/20203012021-01-25025 January 2021 Initial Operator Licensing Examination Report 05000220/2020301 IR 05000410/20193012020-02-11011 February 2020 Initial Operator Licensing Examination Report 05000410/2019301 IR 05000220/20183012019-02-21021 February 2019 Initial Operator Licensing Examination Report 05000220/2018301 IR 05000410/20173022018-02-12012 February 2018 Initial Operator Licensing Examination Report 05000410/2017302 IR 05000220/20173012017-04-13013 April 2017 NRC Initial Operator Licensing Examination Report 05000220/2017301 IR 05000410/20153022016-01-27027 January 2016 Er 05000410/2015302; 11-30-12/22/2015; Nine Mile Point Unit 2 Initial Operator Licensing Examination Report IR 05000220/20153012015-05-0606 May 2015 Er 05000220/2015301; March 2- to 10, 2015, and March 12, 2015; Nine Mile Point Nuclear Station, Unit 1; Initial Operator Licensing Examination Report ML15057A0142015-02-25025 February 2015 Initial Operator Licensing Operating Test and Written Examination Approval, Nine Mile Point, Unit 1 RS-14-164, (EGC) Response to NRC Regulatory Issue Summary 2014-05, Preparation and Scheduling of Operator Licensing Examinations2014-05-29029 May 2014 (EGC) Response to NRC Regulatory Issue Summary 2014-05, Preparation and Scheduling of Operator Licensing Examinations IR 05000410/20143012014-05-0505 May 2014 Er 05000410/2014301; March 3 10, 2014; Nine Mile Point Nuclear Station, Unit 2; Initial Operator Licensing Examination Report ML13200A0062013-07-15015 July 2013 Response to NRC Regulatory Issue Summary 2013-06 IR 05000410/20123012012-04-23023 April 2012 Er 05000410-12-301, on March 19-26, 2012, Nine Mile Point Unit 2, Initial Operator Licensing Examination Report IR 05000410/20103022011-01-18018 January 2011 Er 05000410-10-302, on 11/15/10 - 11/22/10, Nine Mile Point, Unit 2, Initial Operator Licensing Examination Report ML0931404432009-10-24024 October 2009 Er 05000220-09-303; 08/31/2009 - 09/08/2009; Nine Mile Point Nuclear Station Unit 1; Initial Operator Licensing Examination Report (Corrected Report) IR 05000220/20093012009-10-24024 October 2009 Er 05000220-09-301 on 09/08/09 for Nine Mile Point Unit 1 ML0909801382009-04-0808 April 2009 Er 05000220-09-301; March 3, 2009; Nine Mile Point Nuclear Generating Station Unit 1, Operator Licensing Retake Examination Report IR 05000220/20083022008-11-26026 November 2008 Er 05000220-08-302, on October 6-23, 2008, Nine Mile Point Nuclear Station, Unit 1; Initial Operator Licensing Examination Report IR 05000410/20083032008-11-10010 November 2008 Er 05000410-08-303; on October 6-10, 2008; Nine Mile Point Nuclear Generating Station Unit 2, Operator Licensing Retake Examination Report IR 05000410/20083012008-04-23023 April 2008 Er 05000410-08-301, Exam Dates 3/10 - 3/17/2008, Nine Mile Point Nuclear Station, Unit 2, Initial Operator Licensing Examination IR 05000220/20073012007-04-19019 April 2007 IR 05000220-07-301, on 03/12-16/2007; Nine Mile Point Unit 1; Initial Operator Licensing Examination IR 05000220/20053012005-02-0303 February 2005 IR 05000220-05-301 on November 1-18, 2004 for Nine Mile Point Unit 1; Initial Operator Licensing Examination. Seven of Nine Applicants Passed the Examination (Three Reactor Operators, Four SRO Instants) 2024-10-03
[Table view] |
Text
October 3, 2024
David Senior Vice President Constellation Energy Generation, LLC President and Chief Nuclear Officer (CNO)
Constellation Nuclear 4300 Winfield Road Warrenville, IL 60555
SUBJECT: NINE MILE POINT NUCLEAR STATION, UNIT 1 - INITIAL OPERATOR LICENSING EXAMINATION REPORT 05000220/ 2024 302
Dear David Rhoades:
On August 16, 2024, the U.S. Nuclear Regulatory Commission (NRC) completed an examination at Nine Mile Point Nuclear Station, Unit 1. The enclosed examination report documents the examination results, which were discussed on September 5, 2024, with Thomas Tanguay and other members of your staff.
The examination included the evaluation of three applicants for reactor operator licenses, one applicant for instant senior reactor operator license, and three applicants for upgrade senior reactor operator licenses. The written and operating examinations were developed using NUREG-1021, "Operator Licensing Examination Standards for Power Reactors," Revision 12.
The license examiners determined that all applicants satisfied the requirements of Title 10 of the Code of Federal Regulations (10 CFR) Part 55, and the appropriate licenses were issued on September 5, 2024.
No findings were identified during this examination. In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs Agencywide Documents Access Management System (ADAMS). ADAMS is accessible from the NRC website http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely, Donald E. Jackson, Chief Operations Branch Division of Operating Reactor Safety
Docket No. 05000220 License No. DPR-63
Enclosure:
Examination Report 05000220/2024302 w/Attachment: Supplementary Information
REGION I==
Docket No. 05000220
License No. DPR-63
Report No. 05000220/2024302
Licensee: Constellation Energy Generation, LLC
Enterprise Identifier: L-2024-OLL-0019
Facility: Nine Mile Point Nuclear Station, Unit 1
Location: Lycoming, NY
Dates: August 12 - 15, 2024 (Operating Test Administration)
August 16, 2024 (Written Examination Administration)
August 22, 2024 (Licensee Submitted Post Exam Package)
August 23 - September 4, 2024 (NRC Examination Grading)
September 5, 2024 (Licenses Issued)
Examiners: M. Patel, Chief Examiner, Operations Branch T. Fish, Senior Operations Engineer C. Crisden, Examiner K. Murphy, Operations Engineer
Approved By: Donald E. Jackson, Chief Operations Branch Division of Operating Reactor Safety
Enclosure
SUMMARY
ER 05000220/2024302; August 12 - August 16, 2024; Nine Mile Point Nuclear Station, Unit 1 ;
Initial Operator Licensing Examination Report.
Four NRC examiners evaluated the competency of three applicants for reactor operator licenses, one applicant for instant senior reactor operator license, and three applicants for upgrade senior reactor operator licenses at Nine Mile Point Nuclear Station, Unit 1. The facility licensee developed the examinations using NUREG -1021, "Operator Licensing Examination Standards for Power Reactors," Revision 12. The written examination was administered by the facility on August 16, 2024. NRC examiners administered the operating tests on August 12 through August 15, 2024. The NRC examiners determined that all applicants satisfied the requirements of Title 10 of the Code of Federal Regulations (10 CFR) Part 55, and the appropriate licenses have been issued.
NRC-Identified and Self-Revealing Findings
No findings were identified.
Licensee-Identified Violations
None.
REPORT DETAILS
OTHER ACTIVITIES (OA)
4OA5 Other Activities (Initial Operator License Examination)
.1 License Applications
a. Scope
The examiners reviewed all seven license applications submitted by the licensee to ensure the applications reflected that each applicant satisfied relevant license eligibility requirements. The applications were submitted on NRC Form 398, Personal Qualification Statement, and NRC Form 396, Certification of Medical Examination by Facility Licensee. The examiner s also audited all seven of the license applications in detail to confirm that they accurately reflected the subject applicants qualifications. This audit focused on the applicants experience and on-the-job training, including control manipulations that provided significant reactivity changes.
b. Findings
No findings were identified.
.2 Operator Knowledge and Performance
a. Examination Scope
On August 16, 2024, the licensee proctored the administration of the written examinations to all seven applicants. The licensee staff graded the written examinations, analyzed the results, and presented their analysis to the NRC on August 22, 2024.
The NRC examination team administered the various portions of the operating examination to all seven applicants on August 12 through August 15, 2024. The applicants for reactor operator licenses participated in at least two dynamic simulator scenarios, in a control room and facilities walkthrough test consisting of eleven system tasks, and an administrative test consisting of four administrative tasks. The applicants for instant senior reactor operator licenses participated in at least two dynamic simulator scenarios, a control room and facilities walkthrough test consisting of ten system tasks, and an administrative test consisting of five administrative tasks. The applicants for upgrade senior reactor operator licenses participated in at least one dynamic simulator scenario, a control room and facilities walkthrough test consisting of five system tasks, and an administrative test consisting of five administrative tasks.
b. Findings
All seven applicants passed the operating test and the written examination.
For the written examinations, the reactor operator applicants average score was 95.5 percent and ranged from 93.3 to 97.3 percent, the senior operator applicants average score was 94.0 percent and ranged from 93.0 to 97.0 percent.
The NRC examiners completed the final grading of the written examination on August 23, 2024, and conducted a review of each missed question to determine the accuracy and validity of the examination questions. In accordance with current NRC policy, the release of this written examination will be delayed for two years.
The text of the examination questions may be accessed in the ADAMS system under the accession numbers noted in the Attachment.
Chapter ES-403 and Form ES-403-1 of NUREG -1021 require the licensee to analyze the validity of any written examination questions that were missed by half or more of the applicants. The licensee conducted this performance analysis for five questions that met these criteria and submitted the analysis to the chief examiner.
The licensee submitted no post-examination question comments.
.3 Initial Licensing Examination Development
a. Examination Scope
The facility licensee developed the examinations in accordance with NUREG -1021, Revision 12. All licensee facility training and operations staff involved in examination preparation and validation were listed on a security agreement. The facility licensee submitted the operating examination outlines on March 9, 2024. The chief examiner reviewed the outlines against the requirements of NUREG-1021, and provided comments to the licensee. The facility licensee submitted the draft examination package on May 22, 2024. The chief examiner reviewed the draft examination package against the requirements of NUREG -1021 and provided comments to the licensee on the examination on June 6, 2024. The NRC conducted an onsite validation of the operating examinations and provided further comments during the week of July 15, 2024. The licensee satisfactorily completed comment resolution on July 24, 2024.
b. Findings
The NRC approved the initial examination outline and advised the licensee to proceed with the operating examination development.
The examiners determined that the written and operating examinations initially submitted by the licensee were within the range of acceptability expected for a proposed examination.
No findings were identified.
.4 Simulation Facility Performance
a. Examination Scope
The examiners observed simulator performance with regard to plant fidelity during the examination validation and administration.
b. Findings
No findings were identified.
.5 Examination Security
a. Examination Scope
The examiners reviewed examination security for examination development and during both the onsite preparation week and examination administration week for compliance with NUREG-1021, Revision 12 requirements. Plans for simulator security and applicant control were reviewed and discussed with licensee personnel.
b. Findings
No findings were identified.
4OA6 Meetings, Including Exit
The chief examiner presented the examination results to Thomas Tanguay, Senior Manager Site Training, and other members of the licensee's management staff on September 5, 2024.
The licensee did not identify any information or materials used during the examination as proprietary.
4OA7 Licensee-Identified Violations
None
ATTACHMENT:
SUPPLEMENTARY INFORMATION
KEY POINTS OF CONTACT
Licensee Personnel
- M. Dougherty, Senior Nuclear Training Instructor
- P. Ryan, Senior Nuclear Training Instructor
ITEMS OPENED, CLOSED, AND DISCUSSED
Opened
NONE
Opened and Closed
NONE
Closed
NONE
Discussed
NONE
ADAMS DOCUMENTS REFERENCED