MONTHYEARNMP1L3622, Request for Exemption from Certain Requirements of 10 CFR 72.212 and 10 CFR 72.2142025-01-30030 January 2025 Request for Exemption from Certain Requirements of 10 CFR 72.212 and 10 CFR 72.214 NMP1L3618, CFR 50.46 Annual Report2025-01-27027 January 2025 CFR 50.46 Annual Report ML25022A2402025-01-22022 January 2025 Request for Exemption from Certain Requirements of 10 CFR 72.212 and 10 CFR 72.214 for Nine Mile Point Nuclear Station - Holtec HI-STORM FW Ad HI-TRAC Vw IR 05000220/20254032025-01-16016 January 2025 Information Request for the Cyber Security Baseline Inspection, Notification to Perform Inspection 05000220/2025403 and 05000410/2025403 ML24353A1372025-01-15015 January 2025 Proprietary Determination Constellation Energy Generation, LLC 2024 Deferred Premiums 05000410/LER-2024-002-01, Supplement to NMP2 Licensee Event Report 2024-002-00, Automatic Reactor Scram on Turbine Trip Due to Failed Breaker2025-01-10010 January 2025 Supplement to NMP2 Licensee Event Report 2024-002-00, Automatic Reactor Scram on Turbine Trip Due to Failed Breaker ML24358A1832025-01-0707 January 2025 Issuance of Relief Proposed Alternative Request Associated with Ultrasonic Examination of Reactor Pressure Vessel Circumferential Shell Welds ML24344A2742024-12-19019 December 2024 Alternative Request to Use American Society of Mechanical Engineers Boiler and Pressure Vessel Code Case OMN-32 ML24339B7292024-12-18018 December 2024 Amd - Constellation - Adoption of TSTF-591 ML24331A2592024-11-27027 November 2024 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch III ML24331A2792024-11-26026 November 2024 Supplement to Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition - Revise LaSalle, Units 1 and 2 Technical Specificati NMP1L3614, Response to Request for Additional Information for License Amendment Request to Adopt TSTF-230, Revision 1, Add New Condition B to LCO 3.6.2.3, RHR Suppression Pool Cooling2024-11-22022 November 2024 Response to Request for Additional Information for License Amendment Request to Adopt TSTF-230, Revision 1, Add New Condition B to LCO 3.6.2.3, RHR Suppression Pool Cooling 05000410/LER-2024-002, Automatic Reactor Scram on Turbine Trip Due to Failed Breaker2024-11-22022 November 2024 Automatic Reactor Scram on Turbine Trip Due to Failed Breaker IR 05000220/20244022024-11-20020 November 2024 Material Control and Accounting Program Inspection Report 05000220/2024402 and 05000410/2024402 (Cover Letter Only) IR 05000410/20240032024-11-0808 November 2024 Integrated Inspection Report 05000220/1014003 and 05000410/2024003 ML24317A1432024-11-0404 November 2024 Constellation Energy Generation, LLC, 2024 Annual Report - Guarantees of Payment of Deferred Premiums ML24268A3382024-10-16016 October 2024 Issuance of Amendment No. 253 Regarding the Modification of TS Surveillance Requirement 4.3.6.a Related to Adoption of TSTF-425, Revision 3 RS-24-093, Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-10-10010 October 2024 Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests NMP2L2890, Submittal of Revision 26 to the USAR and Reference Figures, 10 CFR 50.59 Evaluation Summary Report, TS Bases, TRM Requirements Manual Changes, and 10 CFR 54.37(b) Aging Management Review (Excludes Attachment 6)2024-10-0404 October 2024 Submittal of Revision 26 to the USAR and Reference Figures, 10 CFR 50.59 Evaluation Summary Report, TS Bases, TRM Requirements Manual Changes, and 10 CFR 54.37(b) Aging Management Review (Excludes Attachment 6) ML24275A2442024-10-0303 October 2024 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief, Division of Operating Reactor Licensing IR 05000220/20243022024-10-0303 October 2024 Initial Operator Licensing Examination Report 05000220/2024302 ML24190A0012024-09-26026 September 2024 Issuance of Amendment Nos. 252 and 197 Regarding the Revision to Technical Specification Design Features Section to Remove Nine Mile Point Unit 3 Project Designation NMP1L3608, Supplemental Information Letter No. 3 - Revision to the Technical Specifications Design Features Sections to Remove the Nine Mile 3 Nuclear Project, LLC, Designation2024-09-20020 September 2024 Supplemental Information Letter No. 3 - Revision to the Technical Specifications Design Features Sections to Remove the Nine Mile 3 Nuclear Project, LLC, Designation RS-24-090, Response to Request for Additional Information - Relief Request Concerning Extension of Permanent Relief from Ultrasonic Examination of Reactor Pressure Vessel Circumferential Shell Welds2024-09-12012 September 2024 Response to Request for Additional Information - Relief Request Concerning Extension of Permanent Relief from Ultrasonic Examination of Reactor Pressure Vessel Circumferential Shell Welds ML24249A1362024-09-0404 September 2024 EN 57304 - Westinghouse Electric Company, LLC, Final Report - No Embedded Files. Notification of the Potential Existence of Defects Pursuant to 10 CFR Part 21 IR 05000220/20240052024-08-29029 August 2024 Updated Inspection Plan for Nine Mile Point Nuclear Station, Units 1 and 2 (Report 05000220/2024005 and 05000410/2024005) IR 05000220/20240102024-08-22022 August 2024 Age-Related Degradation Inspection Report 05000220/2024010 and 05000410/2024010 NMP1L3603, Submittal of Preliminary Decommissioning Cost Estimate and Irradiated Fuel Management Plan2024-08-20020 August 2024 Submittal of Preliminary Decommissioning Cost Estimate and Irradiated Fuel Management Plan ML24222A6772024-08-0909 August 2024 Response to Request for Additional Information for Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition IR 05000220/20240022024-08-0505 August 2024 Integrated Inspection Report 05000220/2024002 and 05000410/2024002 ML24215A3002024-08-0202 August 2024 Operator Licensing Examination Approval ML24213A1412024-07-31031 July 2024 Requalification Program Inspection NMP1L3601, Supplemental Information Letter No. 2 - Revision to the Technical Specifications Design Features Sections to Remove the Nine Mile 3 Nuclear Project, LLC, Designation2024-07-31031 July 2024 Supplemental Information Letter No. 2 - Revision to the Technical Specifications Design Features Sections to Remove the Nine Mile 3 Nuclear Project, LLC, Designation NMP2L2883, Fourth Inservice Inspection Interval, Second Inservice Inspection Period 2024 Owner’S Activity Report for RFO-19 Inservice Examinations2024-07-24024 July 2024 Fourth Inservice Inspection Interval, Second Inservice Inspection Period 2024 Owner’S Activity Report for RFO-19 Inservice Examinations ML24198A0852024-07-16016 July 2024 Senior Reactor and Reactor Operator Initial License Examinations RS-24-070, Independent Spent Fuel Storage Installation, Nine Mile Point, Units 1 and 2, Quad Cities, Units 1 and 2, R. E. Ginna - Nuclear Radiological Emergency Plan Document Revisions2024-07-12012 July 2024 Independent Spent Fuel Storage Installation, Nine Mile Point, Units 1 and 2, Quad Cities, Units 1 and 2, R. E. Ginna - Nuclear Radiological Emergency Plan Document Revisions RS-24-061, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-06-14014 June 2024 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations NMP1L3584, License Amendment Request to Revise Technical Specifications to Adopt TSTF-230, Revision 1, Add New Condition B to LCO 3.6.2.3, RHR Suppression Pool Cooling2024-06-13013 June 2024 License Amendment Request to Revise Technical Specifications to Adopt TSTF-230, Revision 1, Add New Condition B to LCO 3.6.2.3, RHR Suppression Pool Cooling IR 05000220/20244012024-05-30030 May 2024 Security Baseline Inspection Report 05000220/2024401 and 05000410/2024401(Cover Letter Only) ML24079A0762024-05-23023 May 2024 Issuance of Amendments to Adopt TSTF 264 NMP1L3591, Response to Ny State Pollutant Discharge Elimination System (SPDES) Permit Request for Information & Modification Request2024-05-18018 May 2024 Response to Ny State Pollutant Discharge Elimination System (SPDES) Permit Request for Information & Modification Request NMP1L3589, Special Report: Containment High Range Radiation Monitor Instrumentation Channel 12 Inoperable2024-05-16016 May 2024 Special Report: Containment High Range Radiation Monitor Instrumentation Channel 12 Inoperable ML24158A2052024-05-15015 May 2024 Annual Radioactive Environmental Operating Report NMP1L3582, 2023 Annual Radioactive Environmental Operating Report for Nine Mile Point Units 1 and 22024-05-15015 May 2024 2023 Annual Radioactive Environmental Operating Report for Nine Mile Point Units 1 and 2 IR 05000220/20240012024-05-10010 May 2024 Integrated Inspection Report 05000220/2024001 and 05000410/2024001 RS-24-049, Updated Notice of Intent to Pursue Subsequent License Renewal Applications2024-05-0909 May 2024 Updated Notice of Intent to Pursue Subsequent License Renewal Applications RS-24-038, Relief Request Concerning Extension of Permanent Relief from Ultrasonic Examination of Reactor Pressure Vessel Circumferential Shell Welds2024-05-0202 May 2024 Relief Request Concerning Extension of Permanent Relief from Ultrasonic Examination of Reactor Pressure Vessel Circumferential Shell Welds 05000410/LER-2024-001, Automatic Reactor Scram on Turbine Trip Due to Low Condenser Vacuum2024-05-0101 May 2024 Automatic Reactor Scram on Turbine Trip Due to Low Condenser Vacuum NMP1L3581, Independent Spent Fuel Storage Installation (ISFSI) - 2023 Radioactive Effluent Release Report2024-04-30030 April 2024 Independent Spent Fuel Storage Installation (ISFSI) - 2023 Radioactive Effluent Release Report RS-24-041, Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-04-30030 April 2024 Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests 2025-01-07
[Table view] |
Text
August 2, 2024 David P. Rhoades Senior Vice President Constellation Energy Generation, LLC President and Chief Nuclear Officer (CNO)
Constellation Nuclear 4300 Winfield Road Warrenville, IL 60555
SUBJECT:
NINE MILE POINT NUCLEAR STATION, UNIT 1 - OPERATOR LICENSING EXAMINATION APPROVAL
Dear David Rhoades:
The purpose of this letter is to provide U.S. Nuclear Regulatory Commission (NRC) approval of the proposed written examination and operating test under Title 10 of the Code of Federal Regulations 55.40(b)(4) and to confirm the final arrangements for the upcoming operator licensing examination at Nine Mile Point Nuclear Station, Unit 1.
The NRC has approved the subject examinations, and you may administer the written examination the week of August 19, 2024, in accordance with Revision 12 to NUREG-1021, Operator Licensing Examination Standards for Power Reactors, issued September 2021. The NRC staff will administer the operating test during the week of August 12, 2024. The NRC has provided the list of the applicants approved to take the examinations to Thomas Tanguay, Senior Manager, Site Training. The examinations have undergone extensive review by my staff and representatives responsible for licensed operator training at your facility. Based on this review, I have concluded that the examinations meet the guidelines of NUREG-1021 for content, operational, and discrimination validity. By administering the written examination, you also agree that the examinations meet NUREG-1021 guidelines and are appropriate for measuring the qualifications of licensed operator applicants at your facility. If you determine that these examinations are not appropriate for licensing operators at your facility, do not administer the written examination and contact me at (610) 337-5306.
D. Rhoades 2
Please contact your NRC chief examiner, Manan Patel, at (610) 337-5304, if you have questions or identify any errors or changes in the license level (reactor operator or senior reactor operator) or type of examination (partial or complete written examination or operating test, or both) specified for each applicant approved to take the examinations.
Sincerely, Donald E. Jackson, Chief Operations Branch Division of Operating Reactor Safety Docket No. 05000220 License No. DPR-63 cc: Distribution via ListServ DONALD JACKSON Digitally signed by DONALD JACKSON Date: 2024.08.02 10:01:34
-04'00'
D. Rhoades 3
SUBJECT:
NINE MILE POINT NUCLEAR STATION, UNIT 1 - OPERATOR LICENSING EXAMINATION APPROVAL DATED AUGUST 2, 2024 DISTRIBUTION:
MPatel, DORS DJackson, DORS LPinkham, DORS ECarfang, DORS EEve, DORS KSmetana, DORS EAdams, DORS CKline, DORS, SRI BSienel, DORS, RI ATrudell, DORS, AA MSimmons, RI OEDO RidsNrrPMNineMilePoint Resource RidsNrrDorlLpl1 Resource DOCUMENT NAME: G:\\DRS\\Operations Branch\\PATEL\\Exam FY24 - NMP1\\Letters\\FY24 NMP1 Letter 2.3-1 Examination Approval Final.docx ADAMS Accession Number (Package): ML23320A095 ADAMS Accession Number (Letter): ML24215A300 SUNSI Review Non-Sensitive Sensitive Publicly Available Non-Publicly Available OFFICE RI/DORS/OB:CE RI/DORS/OB:BC NAME MPPatel/MPP DEJackson/DEJ DATE 08/02/2024 08/02/2024 OFFICIAL RECORD COPY