Summary of a Public Meeting with Southern Nuclear Operating Company on August 25, 2022
ML22243A030
Person / Time
Site: Vogtle Southern Nuclear icon.png
Issue date: 09/09/2022
From: Cayetano Santos
NRC/NRR/VPOB
To:
Southern Nuclear Operating Co
Gleaves B
References
Download: ML22243A030 (5)


Text

September 9, 2022 LICENSEE: SOUTHERN NUCLEAR OPERATING COMPANY FACILITY: VOGTLE ELECTRIC GENERATING PLANT, UNIT 4

SUBJECT:

SUMMARY

OF AUGUST 25, 2022, MEETING WITH SOUTHERN NUCLEAR OPERATING COMPANY On August 25, 2022, the U.S. Nuclear Regulatory Commission (NRC) held a virtual public meeting with representatives of Southern Nuclear Operating Company (SNC). The purpose of the meeting was to have a pre-submittal discussion about a potential license amendment to delete and consolidate several electrical inspections, tests, analyses, and acceptance criteria (ITAAC) in the Vogtle Electric Generating Plant (VEGP) Unit 4 combined license (COL)

(Agencywide Documents Access and Management System (ADAMS) Accession No. ML14100A135). The potential license amendment was provided to the NRC in the form of a draft license amendment request (LAR) and was based, in part, on lessons learned from the ITAAC process for VEGP Unit 3. In the draft LAR, SNC proposed two categories of changes to the VEGP Unit 4 COL, which would require an amendment and exemption: first, a deletion of certain redundant ITAAC, and second, a consolidation of certain electrical cable, raceway color coding, and separation ITAAC to improve efficiency of ITAAC completion. The draft LAR and presentation are available at ML22231A349. The meeting notice and agenda are available at ML22231B120. An attendee list is enclosed.

In its draft LAR, SNC proposed the deletion of 14 assigned division ITAAC that were said to be redundant with other Unit 4 ITAAC. The justification for this proposed deletion is that the inspection, test, and analysis (ITA) for these ITAAC are very similar, and the scope of these individual ITAAC fall within the scope of existing ITAAC for Class 1E cables for containment, and radiologically controlled and non-radiologically controlled areas of the auxiliary building, respectively.

The Unit 4 assigned division ITAAC proposed for deletion in the proposed LAR would be as follows:

1. ITAAC 2.1.02.07b (Index No. 26), Reactor Coolant System (RCS)
2. ITAAC 2.1.03.09b (Index No. 83), Reactor System (RXS)
3. ITAAC 2.2.01.06b (Index No. 103), Containment System (CNS)
4. ITAAC 2.2.03.07b (Index No. 172), Passive Core Cooling System (PXS)
5. ITAAC 2.2.04.07b (Index No. 233), Steam Generator System (SGS)
6. ITAAC 2.2.05.06a (Index No. 263), Main Control Room Emergency Habitability System (VES)
7. ITAAC 2.3.02.06b (Index No. 296), Chemical and Volume Control System (CVS)
8. ITAAC 2.3.06.07b (Index No. 368), Normal Residual Heat Removal System (RNS)
9. ITAAC 2.3.07.06a (Index No. 399), Spent Fuel Pool Cooling System (SFS)
10. ITAAC 2.3.10.11a (Index No. 878), Liquid Radwaste System (WLS)
11. ITAAC 2.3.13.06b (Index No. 467), Primary Sampling System (PSS)
12. ITAAC 2.5.02.05a (Index No. 527), Protection and Safety Monitoring System (PMS)
13. ITAAC 2.6.01.03a (Index No. 582), Main ac Power System (ECS)
14. ITAAC 2.7.01.06a (Index No. 687), Nuclear Island Nonradioactive Ventilation System (VBS)

The NRC staff commented that documentation explaining how the ITAAC proposed for deletion are redundant to the remaining ITAAC has not been identified in the proposed LAR. In addition, the justification proposed by SNC is partly based on similarities in uncompleted ITAAC notifications and associated work packages. The staff stated that this would typically be an insufficient basis for justifying the proposed changes. A readily reviewable LAR proposing deletions to ITAAC based on redundancy would specify the redundant ITAAC, explain why these ITAAC contain the same requirements or when completed accomplish the same purposes as the ITAAC proposed to be deleted, and provide adequate explanation or analysis supporting that statement.

The presentation proceeded to the second category of changes proposed in the draft LAR, which is the proposal to consolidate 18 electrical cable, raceway color coding, and separation ITAAC into the three Containment, Auxiliary Building Non-Radiation, and Auxiliary Building Radiation, ITAAC for VEGP Unit 4 as show below:

Containment ITAAC - Unconsolidated Containment ITAAC - Consolidated ITAAC 3.3.00.07aa (Index No. 789)

ITAAC 3.3.00.07ba (Index No. 792)

ITAAC 3.3.00.07d.ii.a (Index No. 800)

ITAAC 3.3.00.07d.ii.a (Index No. 800)

ITAAC 3.3.00.07d.iii.a (Index No. 803)

ITAAC 3.3.00.07d.iv.a (Index No. 806)

ITAAC 3.3.00.07d.v.a (Index No. 809)

Auxiliary Building Non-Radiation ITAAC - Auxiliary Building Non-Radiation ITAAC -

Unconsolidated Consolidated ITAAC 3.3.00.07ab (Index No. 790)

ITAAC 3.3.00.07bb (Index No. 793)

ITAAC 3.3.00.07d.ii.b (Index No. 801)

ITAAC 3.3.00.07d.ii.b (Index No. 801)

ITAAC 3.3.00.07d.iii.b (Index No. 804)

ITAAC 3.3.00.07d.iv.b (Index No. 807)

ITAAC 3.3.00.07d.v.b (Index No. 810)

Auxiliary Building Radiation ITAAC - Auxiliary Building Radiation ITAAC -

Unconsolidated Consolidated ITAAC 3.3.00.07ac (Index No. 791)

ITAAC 3.3.00.07bc (Index No. 794)

ITAAC 3.3.00.07d.ii.c (Index No. 802)

ITAAC 3.3.00.07d.ii.c (Index No. 802)

ITAAC 3.3.00.07d.iii.c (Index No. 805)

ITAAC 3.3.00.07d.iv.c (Index No. 808)

ITAAC 3.3.00.07d.v.c (Index No. 811)

The staff summarized its understanding of the consolidation changes as follows: for each case of the consolidation, the unconsolidated design commitments; inspections, tests, and analyses (ITAs); and acceptance criteria would be moved in their entirety with no changes to the consolidated ITAAC. SNC confirmed this understanding was correct. The draft LAR does note, however, that for ITAAC Index No. 805, there is one apparent error in the acceptance criterion number ii.c). The proposed revision to consolidated ITAAC Index No. 802 corrects this number to iii.c). SNC estimated the current submittal date would be August 31, 2022, with the current proposed approval date of January 7, 2023, but the submittal date might change due to feedback received at this meeting.

Following completion of the presentation by SNC and comments by NRC staff, members of the public were asked for comment. The members of the public who were in attendance offered no comments or questions. The staff did not receive any verbal meeting feedback or completed Public Meeting Feedback forms.

Please direct any inquiries to me at 301-415-7270 or Cayetano.Santos@nrc.gov.

Sincerely, Signed by Santos, Cayetano on 09/09/22 Cayetano Santos Jr., Senior Project Manager Vogtle Project Office Office of Nuclear Reactor Regulation Docket No.52-026

Enclosure:

As stated cc: Listserv

LIST OF ATTENDEES AUGUST 25, 2022, PUBLIC MEETING WITH SOUTHERN NUCLEAR OPERATING COMPANY Name Organization Cayetano (Tanny) Santos William (Billy) Gleaves Christopher Welch Michael Webb Victor Hall Phil OBryan James Gaslevic Garry Armstrong NRC/Office of Nuclear Reactor Regulation Tom Fredette Bill Roggenbrodt Sheila Ray Thomas Scarbrough Stewart Bailey Morton Wendell Mike Waters NRC/Office of Nuclear Security and Incident Ken Mott

Response

George Khouri Bradley Davis Robert Mathis NRC/Region II Omar Lopez-Santiago Nicole Coovert Julie Ezell NRC/Office of General Counsel Amy Chamberlain Kelli Roberts Neil Haggarty Eddie Grant Southern Nuclear Operating Company Peter LeJeune Keith Dorsey Keith Drudy Ray Fu Kevin Little Members of the Public Wade McKenzie Michael Hiller Enclosure

ML22243A030 OFFICE NRR/VPO/VPOB NRR/VPO/VPOB NRR/DEX/ELTB NRR/DEX/EEOB NAME WGleaves WG RButler RB WMorton WM MWaters MW DATE Aug 31, 2022 Aug 31, 2022 Sep 8, 2022 Sep 8, 2022 OFFICE R-II/DRP/RPB4 NRR/VPO/VPOB NRR/VPO/VPOB SBailey NAME VHall VH CSantos CS YLi for YL DATE Sep 9, 2022 Sep 9, 2022 Sep 9, 2022