Special Rept:On 890603,two Out of Three Diesel Fire Pumps Were Inoperable for Less than 12 H.Caused by Diesel Fire Pump Day Tank Outlet Valve Being Closed Instead of Fill Valve During Performance Test 1158.Test Revised
ML20244E594
Person / Time
Site: Monticello Xcel Energy icon.png
Issue date: 06/16/1989
From: Parker T
NORTHERN STATES POWER CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
NUDOCS 8906210004
Download: ML20244E594 (2)


Text

. _ _ ..

. D Northem States Power Company 414 Nicollet Mall Minneapolis, Minnesota 55401-1927 Telephone (612) 330-5500 June 16, 1989 Tech Spec 3.13'.B.3.b Director of Nuclear Reactor Regulation US Nuclear Regulatory Commission .

Attn: Document Control Desk i Washington D.C. 20555 MONTICELLO NUCLEAR GENERATING PLANT Docket No. 50-263 License No. DPR-22 l

l k

Special Report j 2 of 3 Fire Purns Inoperable l This special report is being submitted per Technical Specification l 3.13.B.3.b. Technical Specification 3.13.B.3.b requires that, "With the l

fire system otherwise inoperable provide a special report to the Commission i within 14 days outlining the actions taken and the plans and schedule for I restoring the system to operable status".

On Saturday, June 3, 1989 at approximately 0500 the diesel fire pump operability test #1158 was completed in preparation for isolating the screenwash/ fire pump for repacking. During the performance of test #1158 the diesel fire pump day tank outlet valve was closed instead of the diesel fire pump day tank fill valve as the procedure states. This isolated the fuel supply to the diesel fire pump, making it inoperable. At 0525, the isolation for the screenwash/ fire pump was complete making it inoperable.

A t- 1358 it was discovered that the wrong valve had been closed. The diesel

, ump day tank outlet valve was opened and the fill valve verified c 1. The diesel fire pump was declared operable at 1500 when the ops bility test of the diesel fire pump was completed. Therefore, the two fire pumps were inoperable for less than 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />.

A backup fire suppression water system was not established since the time between discovery of the diesel fire pump inoperablity and restoration to an operable condition was less than 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.

m h

s y

,  : o Northem States Power Company Director of NRR June 16, 1989 Page 2 To prevent this from reoccurring the following actions have been taken:

1. The diesel fire pump day tank outlet velve is now seal wired open.
2. The Diesel Fire Fump Operability Test #1158 has been reviewed and revised to include valve numbers and valve tag names to any step which requires manipulation of a valve.

Please contact me if you require additional information.

M Thomas M Parker Manager Nuclear Support Services cc: Regional Administrator-III, NRC NRR Project Manager, NRC Resident Inspector, NRC G Charnoff