MONTHYEARML20148U0111997-06-17017 June 1997 Confirmatory Survey of Group E Effluent Discharge Pathway Areas Fsv Nuclear Station Platteville,Co ML20133D7661996-09-16016 September 1996 Confirmatory Survey Plan for Fsv Nuclear Station Decommissioning Project ML20129A4621996-09-11011 September 1996 Rev 0 to Fsv Decommissioning Project Final Survey Requirements for Liquid Effluent Pathway ML20100L3581996-02-22022 February 1996 Proposed Tech Specs,Submitting Corrected Version of Plant Decommissioning TS Updated to Reflect All Approved Amends ML20097C2601996-01-17017 January 1996 Confirmatory Survey Activities Plan for Fsv Nuclear Station PSC Platteville,Co ML20101F2091995-09-18018 September 1995 Issue 7 to DPP 5.4.2, Odcm ML20084B8801995-05-25025 May 1995 Rev 1 to Fsv Nuclear Station Decommissioning Project Final Survey Plan for Site Release ML20084B6881995-05-10010 May 1995 Issue 5 to Fire Protection Operability Requirements (Fpor) FPOR-7, Fire Extinguishers ML20082K2461995-04-14014 April 1995 Proposed Decommissioning Tech Specs Administrative Control 5.3.1,reflecting Organizational Changes That Impact Membership of Decommissioning Safety Review Committee ML20082T2151995-04-12012 April 1995 Issue 7 to Fire Protection Operability Requirements (Fpor) FPOR-12, Fire Detectors ML20082B9411995-03-17017 March 1995 Confirmatory Survey Plan for Repower Area,Fort St Vrain, Platteville,Co ML20082C0801995-03-16016 March 1995 Proposed Confirmatory Survey Plan for Repower Area,Fort St Vrain,Platteville,Co ML20082B9821995-03-15015 March 1995 Instrumentation Comparison Plan Between Orise & Fort St Vrain ML20086S2471995-02-0909 February 1995 Decommissioning Plan for Fort St Vrain Nuclear Generating Station ML20077C7171994-11-30030 November 1994 Issue 9 to FPOR-14, Fire Protection Operability Requirements ML20078C0641994-10-12012 October 1994 Revised Fire Protection Operability Requirements,Including Issue 21 to Depp Table of Contents,Issue 2 to FPOR-22 & Issue 3 to FPOR-23 ML20081J7951994-09-15015 September 1994 Issue 5 to DPP 5.4.2, Odcm ML20063M1551994-02-17017 February 1994 Rev 0 to Fsv Nuclear Station Decommissioning Project Final Survey Plan for Site Release ML20057A6151993-08-30030 August 1993 Issue 2 to FPOR-23, Fire Water Makeup Sys ML17291B3261993-05-18018 May 1993 Proposed TS Section 2.2 Re Activated Graphite Blocks,Section 2.4 Re Channel Calibr & SR 3.2.1 Re Verification of Reactor Bldg Pressure & SR 3.2.2 Re Verification of Pressure Drop Across Each HEPA Filter ML20118B2141992-09-25025 September 1992 Proposed Decommissioning Tech Specs Replacing Radiation Safety with Nuclear Safety, Revising Applicability Requirements for Specs Dealing W/Reactor Bldg Confinement Integrity & Clarifying Items Re Unreviewed Safety Questions ML20114D6871992-09-0101 September 1992 Tritium Leach Test on H-327 Graphite ML20096H1961992-05-19019 May 1992 Decommissioning TS Deleting Section 4.2.15 Re LCO 4.2.15 Covering Pcrv Cooling Water Sys Temps ML20095B0951992-04-14014 April 1992 Proposed Tech Specs Re Organization,Review & audit-administrative Controls ML20094L2831992-03-19019 March 1992 Proposed Tech Specs Re Controls & Limits Appropriate for Decommissioning ML20086C5301991-11-15015 November 1991 Proposed Tech Spec Limiting Condition for Operation 4.2.15 Re Pcrv Cooling Water Sys Temps ML20079M4261991-10-11011 October 1991 Revised Abnormal Operating Procedures,Reflecting Deletion of Issue 9 of EP Class ML20091D7631991-10-11011 October 1991 Proposed,Revised Limiting Condition for Operation 4.2.15 Re Prestressed Concrete Reactor Vessel Cooling Water Sys Temp ML20082L9311991-08-30030 August 1991 Proposed Tech Specs Re Decommissioning ML20082H8851991-08-16016 August 1991 Issue 2 to Abnormal Operating Procedure AOP-I-2, Chemical, Petroleum & Hazardous Waste Spill Response ML20091C4141991-08-0202 August 1991 Issue 58 to Abnormal Operating Procedure AOP-L, Loss of Instrument Air Header ML20024H3341991-05-10010 May 1991 Nonproprietary Rev 2 to FSV-P-SCP-100, Fort St Vrain Initial Radiological Site Characterization Program Program Description ML20072V5291991-04-12012 April 1991 Revised Defueling Emergency Response Plan,Including Section 1 Definitions,Section 2 Scope & Applicability,Section 3 Summary of Fsv Derp,Section 4 Emergency Classifications & Section 5 Emergency Organization ML20070V6871991-03-20020 March 1991 Issue 55 to Abnormal Operating Procedure AOP-R, Loss of Access to Control Room ML20072S0521991-03-15015 March 1991 Public Version of Revised Crisis Mgt Implementing Procedures,Including Rev 9 to CMIP-11, Classification of Emergency for McGuire Nuclear Station & Rev 11 to CMIP-12, Classification of Emergency for Oconee Nuclear Station ML20066J1171991-02-15015 February 1991 Issue 56 to Intro Section of Abnormal Operating Procedure (Aop),Issue 58 of AOP-A,Issue 58 to AOP-B,Issue 56 of AOP D-1 & Issue 2 of RERP-TRANSPORTATION ML20066A3781990-12-21021 December 1990 Proposed Decommissioning Tech Specs Re Reactor Bldg Integrity,Reactor Bldg Ventilation Exhaust Sys,Radiation Monitoring Instrumentation & Pcrv Shielding Water Tritium Concentration ML20059L5891990-09-14014 September 1990 Proposed Tech Specs Changing Design Features Section 6.1 to Permit Removal of CRD & Orifice Assemblies from Core Regions Defueled in Support of Plant Closure Activities ML20058N1071990-08-10010 August 1990 Issue 56 to AOP-I, Discussion of Fire ML20042F3151990-04-26026 April 1990 Proposed Tech Specs Re Defueling ML20006B7921990-01-25025 January 1990 Proposed Tech Specs Re Administrative Title Changes to Section 7.1 ML19332E8901989-12-0404 December 1989 Proposed Tech Specs Re Reactivity Control & Control Rod Pair Position Requirements During Shutdown ML19332F3561989-12-0404 December 1989 Proposed Tech Specs Re Limiting Condition for Operations 4.7.3, Fuel Storage Wells & 4.7.5, Instrumentation. ML19332C8151989-11-21021 November 1989 Proposed Tech Specs Revising Items 2.D.(1) & 2.D.(4) Re Max Power Level & Early Shutdown,Respectively ML20064B2111989-11-0909 November 1989 Fort St Vrain Cycle 4 RT-500L Test Rept ML19324B6961989-10-30030 October 1989 Proposed Tech Specs Re Reactor Core & Reactivity Control ML19327B1321989-10-13013 October 1989 Proposed Tech Specs,Reflecting Deleted Limiting Conditions of Operations 4.1.2 Through 4.1.6,deleted Surveillance Requirements 5.1.1,5.1.2,5.1.3 & 5.1.5 & Newly Added Reactivity Control Section ML19351A3271989-10-13013 October 1989 Proposed Tech Specs 6.1 Re Defueling Phase Document Design Features ML20248G4731989-10-0101 October 1989 Proposed Tech Specs Re End of Operations ML20248G4461989-09-30030 September 1989 Proposed Tech Specs Re Chlorine Detection & Alarm Sys & Control Room Emergency Ventilation Sys 1997-06-17
[Table view] Category:TEST/INSPECTION/OPERATING PROCEDURES
MONTHYEARML20148U0111997-06-17017 June 1997 Confirmatory Survey of Group E Effluent Discharge Pathway Areas Fsv Nuclear Station Platteville,Co ML20133D7661996-09-16016 September 1996 Confirmatory Survey Plan for Fsv Nuclear Station Decommissioning Project ML20129A4621996-09-11011 September 1996 Rev 0 to Fsv Decommissioning Project Final Survey Requirements for Liquid Effluent Pathway ML20097C2601996-01-17017 January 1996 Confirmatory Survey Activities Plan for Fsv Nuclear Station PSC Platteville,Co ML20101F2091995-09-18018 September 1995 Issue 7 to DPP 5.4.2, Odcm ML20084B8801995-05-25025 May 1995 Rev 1 to Fsv Nuclear Station Decommissioning Project Final Survey Plan for Site Release ML20084B6881995-05-10010 May 1995 Issue 5 to Fire Protection Operability Requirements (Fpor) FPOR-7, Fire Extinguishers ML20082T2151995-04-12012 April 1995 Issue 7 to Fire Protection Operability Requirements (Fpor) FPOR-12, Fire Detectors ML20082B9411995-03-17017 March 1995 Confirmatory Survey Plan for Repower Area,Fort St Vrain, Platteville,Co ML20082C0801995-03-16016 March 1995 Proposed Confirmatory Survey Plan for Repower Area,Fort St Vrain,Platteville,Co ML20082B9821995-03-15015 March 1995 Instrumentation Comparison Plan Between Orise & Fort St Vrain ML20086S2471995-02-0909 February 1995 Decommissioning Plan for Fort St Vrain Nuclear Generating Station ML20077C7171994-11-30030 November 1994 Issue 9 to FPOR-14, Fire Protection Operability Requirements ML20078C0641994-10-12012 October 1994 Revised Fire Protection Operability Requirements,Including Issue 21 to Depp Table of Contents,Issue 2 to FPOR-22 & Issue 3 to FPOR-23 ML20081J7951994-09-15015 September 1994 Issue 5 to DPP 5.4.2, Odcm ML20063M1551994-02-17017 February 1994 Rev 0 to Fsv Nuclear Station Decommissioning Project Final Survey Plan for Site Release ML20057A6151993-08-30030 August 1993 Issue 2 to FPOR-23, Fire Water Makeup Sys ML20079M4261991-10-11011 October 1991 Revised Abnormal Operating Procedures,Reflecting Deletion of Issue 9 of EP Class ML20082H8851991-08-16016 August 1991 Issue 2 to Abnormal Operating Procedure AOP-I-2, Chemical, Petroleum & Hazardous Waste Spill Response ML20091C4141991-08-0202 August 1991 Issue 58 to Abnormal Operating Procedure AOP-L, Loss of Instrument Air Header ML20024H3341991-05-10010 May 1991 Nonproprietary Rev 2 to FSV-P-SCP-100, Fort St Vrain Initial Radiological Site Characterization Program Program Description ML20072V5291991-04-12012 April 1991 Revised Defueling Emergency Response Plan,Including Section 1 Definitions,Section 2 Scope & Applicability,Section 3 Summary of Fsv Derp,Section 4 Emergency Classifications & Section 5 Emergency Organization ML20070V6871991-03-20020 March 1991 Issue 55 to Abnormal Operating Procedure AOP-R, Loss of Access to Control Room ML20072S0521991-03-15015 March 1991 Public Version of Revised Crisis Mgt Implementing Procedures,Including Rev 9 to CMIP-11, Classification of Emergency for McGuire Nuclear Station & Rev 11 to CMIP-12, Classification of Emergency for Oconee Nuclear Station ML20066J1171991-02-15015 February 1991 Issue 56 to Intro Section of Abnormal Operating Procedure (Aop),Issue 58 of AOP-A,Issue 58 to AOP-B,Issue 56 of AOP D-1 & Issue 2 of RERP-TRANSPORTATION ML20058N1071990-08-10010 August 1990 Issue 56 to AOP-I, Discussion of Fire ML20154M4361988-09-0909 September 1988 Rev a to EE-FP-0005, Evaluation of Cable Trays Outside of Congested Cable Area ML20154L8751988-05-26026 May 1988 Simulation Facility Program Plan ML20154L8911988-03-31031 March 1988 Rev 2 to Guidance for Development of Simulation Facility to Meet Requirements of 10CFR55.45 ML20148Q4681988-03-31031 March 1988 Rev 2 to Guidance for Development of Simulation Facility to Meet Requirements of 10CFR55.45 ML20150E3141988-03-18018 March 1988 Issue 1 to Procedure SR 5.4.1.3.8.abcd-R1, Steam Line Rupture Detection/Isolation Sys (Slrdis) Calibr & Testing for Panel I-93543 ML20150E2901987-12-31031 December 1987 Issue 5 to Procedure SR 5.3.4b1-A Loop I Shutdown Cooling Power Operated Valve Test ML20238E3541987-08-0707 August 1987 Rev a to EE-ISI-002, Condensate Line Erosion Insp Program ML20236N8681987-08-0505 August 1987 Exercise Manual Fort St Vrain Nuclear Generating Station Nrc/Fema Graded Exercise 870805 ML20235Y7861987-07-29029 July 1987 Issue 2 to MAP-4, Maint Dept Personnel Experience, Qualification & Training Requirements ML20237J6921987-06-0909 June 1987 Issue 6 to MQCIM-1, Maint QC Insp Program. Annotated Page to Rev 4 to Updated FSAR Encl ML20235Y7731987-05-25025 May 1987 Training Mgt Procedure Index ML20237J7151987-05-0101 May 1987 Issue 12 to Q-18, QA Monitoring & Audit Program ML20215H9731987-04-30030 April 1987 Revised Buckle Users Manual:Creep Collapse of Thin-Walled Circular Cylindrical Shells Subj to Radial Pressure & Thermal Gradients ML20215H6101987-04-10010 April 1987 Program Plan for Integrated Validation of NUREG-0737 Initiatives ML20215H6031987-04-10010 April 1987 SOAP-2,Issue 1 of Guidelines for Preparation of Emergency Procedures ML20215H5951987-04-10010 April 1987 Procedures Generation Package:Public Svc Co of Colorado Fort St Vrain Nuclear Generating Station ML20150E3041987-03-20020 March 1987 Issue 1 to Procedure SR 5.4.1.3.8.abcd-R2, Steam Line Rupture Detection/Isolation Sys (Slrdis) Calibr & Testing for Panel I-93544 ML20237J7231987-02-20020 February 1987 Issue 5 to QAAP-1, Planning & Scheduling Fort St Vrain QA Audits ML20212B3081987-02-15015 February 1987 Issue 7 to Procedure G-9, Controlled Work Procedures ML20210E3001987-02-0303 February 1987 Revised Administration Procedures Consisting of Issue 7 to G-3, Action Request-Preparation & Processing, Issue 21 to G-2, Fort St Vrain Procedure Sys & Issue 6 to G-6, Compliance w/10CFR21 Requirements ML20210A7571987-01-30030 January 1987 Fort St Vrain 1987 Power Ascension Plan ML20237J7421987-01-19019 January 1987 QA Audit QAA-502-87-01, Audit Plan - QA Program for Transport of Radioactive Matls ML20212B2851986-10-24024 October 1986 Issue 10 to Procedure Q-3, Design Control Sys ML20238E3461986-10-0202 October 1986 Rev C to EE-ISI-0001, Extraction Steam Lines & Turbine Vent & Drain Lines Erosion Insp Program 1997-06-17
[Table view] |
Text
.* PUBLIC SERVICE COMPANY OF COLORADO G-2
!ssue 3 FORT ST. VRAIN NUCLEAR GENERATING STATICN :: age . cf 6 i-MoA ) tofBroro 7:TLE: FSV PROCECURE SYSTEMS Tw w. C . a,,. .ulLE D COFY VEr5f "J E STATUS hugs 10 U'E ecRC
' 'D
- 8. 77&,
c~A ~
%bn EFFECTiv6 REVIEW P0nc 3 91 DEC 181980 DATE 12. - 21. $O 1.0 PURPOSE This procedure describes the system of procedures and procedure controls used to govern activities and maintain required disciplines at the FSV Nuclear Generating Station.
2.0 APPLICABILITY This procedure applies to all FSV related procedures identified in Attachment G-2A.
3.0 GENERAL a) Procedures become effective five working days after the date issued.
b) All new or major revisions of procedures are required to conform to the format outlined in Attachment G-28.
c) In the event of procedural conflicts, Level I procedures take precedence over Level II and III procedures.
d) When procedure changes are required, the entire procedure will be reissued. A' revised Table of Contents for the affected manual will be reissued together with each new or revised procedure. The Table of Contents will indicate the procedure number, title, issue number and effective date.
e) Responsibility for initiating, revising and assuring adequacy and currentness of the procedures listed by Attachment G-2A is assigned by the " Responsible for" column thereon.
f) All levels of FSV Station and Project personnel are responsible for assuring compliance with authorized procedures, or for initiating action to obtain appropriate procedure changes if compliance is not possible.
k g) Deviations to procedures must be processed and authorized as outlined by paragraph 4.4.
G703030510 870220 PDR ADOCK 05000267 G PDR
PUZLIC SERVICE COMPANY OF COLORADO ')'"""i FCRT ST. VRAIN NUCLEAR GENERATING STAflCN , .
h) Supervisory personnel will be informed of all new and revised procedures and procedure ceviations. Supervisory personnel are responsible to inform personnel under tneir direction of those procedures, procecure changes and procedure deviations tnat affect their work.
4.0 P:0CEDURE 4.1 PROCEDURE INITIATION 4.1.1 Proposed new procedures, procedure changes and procedure cancellations are initiated as follows:
a) Proposals developed within an organization (NP, NPO or QA) are initiated and coordinated in accordance with paragraph 4.2.1 of this procedure.
b) Proposals developed by other organizations are submitted to the " Responsible For" party utilizing a Procedure Change Action Request (PCAR) issued in accorc.tnce with Procedure G-3.
The " Responsible For" organization will finalize the proposal and coordinate the review in accordance with paragraph 4.2.1 of this procedure.
4.1.2 When requirements for a procedure generation or revision are identified, the following logic shall be applied to categorize the procedure.
a) Issue as Level I If the procedure concerns administrative policy, rules and/or regulations applicable to all personnel assigned to or visiting the Station; or, establishes instructions for the orderly accomplishment of activities involving two or more organizations.
b) Issue as Level II If the procedure is required to provide detailed administrative instructions, applicable only to the affected department.
c) Issue as Level III If the procedure is required to provide specific instructions to individuals assigned responsiblity for performing physical tasks b involving operating, maintaining, or protecting the Plant.
PUBLIC SERVICE COMPANY OF COLORADO 3-2 FORT ST. VRAIN Nt.; CLEAR GENERATING STATICN g
4.2 PROCEDURE CCCRD:NATICN 4.2.1 The " Responsible For" ::erson(s) is responsible for assuring no conflict with Level I procecures exists, and for coordinating tne proposed new or revised procedure draft with the " Authorized by" parties. A Cocument Coorcination and Concurrence Form (OCCF), is prepared in accorcance with Attachment G-2C and attached to each new proposal.
Copies are sent to the " Authorized by" parties for review.
4.2.2 The " Authorized by" party (f es) is (are) required to sign and date the OCCF to indicate that tne propcsed change is "OK as is", or to provide comment concerning further revisions required to permit concurrence. The OCCF and attacnments are returned to the " Responsible For" organization by the "Date Due" indicated on the OCCF. Comments considered to be " Mandatory" are so identified.
4.2.3 The " Responsible For" party must coordinate the resolution of " Mandatory" comments documented by the " Authorized by" parties. Impasse situations are referred to the next higher level of management for resolutions.
4.3 PROCEDURE APPROVAL / REVIEW / DISTRIBUTION 4.3.1 Approvals required to authorize procedure issuance, use or cancellation are identified in the
" Authorized by" column of Attachment G-2A.
4.3.2 The procedure is forwarded together with signed DCCF(s) to the " Authorized by" party (ies). If authorization for procedure cancellation is being requested, it shall be so noted on the procedure cover sheet.
4.3.3. Note: NPD procedures-(ENG'S and SDCC'S) are exempt from paragraphs 4.3.4 thru 4.3.6. See 4.3.7 for NPD procedure processing requirements.
4.3.4 The approved procedure and signed copies of related l
DCCF(s) are forwarded to Technical Services for review to verify compatibility with existing procedures, and to determine if Plant Operations Review Committee (PORC) review is required. If required per Technical Specification AC 7.4.(a),
the procedure is submitted to PORC.
b 4.3.5 If incompatibility with existing procedures is identified, Technical Services will, when l
N PUBLIC SERVICE COMPANY OF COLORADO j FORT ST. VRAIN NUCLEAR GENERATING STATICN
- appropriate, place the procecure "On Holc" and initiate appropriate requests for procedure changes.
4.3.6 Following review, the authori:ed procedure master is forwarded to Station Clerical. Station Clerical applies the " Effective Date", uodates the appropriate manual Table of Contents and reproduces and distributes the procedure and Tacle of Contents in accordance with Procedure P-9. The CCCF's will be transmitted to the FSV Records Center.
4.3.7 Review and approval of NPD procedures (ENG'S and 50CC'S) will be performed in accorcance with NPO procedures. Upon completion of the review and approval, the " Effective Date" will be applied to the procedure, the Table of Contents for the appropriate manual will be updated and the procedure and the Table of Contents will be reproduced and distributed in accordance with Procedure P-9. The OCCF's will be transmitted to the FSV Records Center.
4.4 PROCEDURE DEVIATIONS 4.4.1 Temporary changes and deviations to procedures are permitted as follows:
a) The intent of the procedure cannot be changed.
b) The proposed change or deviation must be documented and approved on the Procedure Deviation Report Form (POR), Attachment G-20 in accordance with this procedure.
c) POR's are sequentially numbered with the year preceeding the number eq: 80-001. POR numoers are issued by the Shift Supervisor.
d) Station clerical will issue copies of POR's and the POR Status Index to all supervisors and the FSV Record Center.
e) Approvals required for POR's are identified in Attach. G-20, page 3.
L
.