MONTHYEARIR 05000272/20244032024-09-25025 September 2024 and Salem Nuclear Generating Station, Units 1 and 2, Cybersecurity Inspection Report 05000354/2024403, 05000272/2024403, and 05000311/2024403 (Cover Letter Only) IR 05000272/20244022024-09-23023 September 2024 and Salem Nuclear Generating Station, Units 1 and 2 - Security Baseline Inspection Report 05000354/2024402, 05000272/2024402, and 05000311/2024402 (Cover Letter Only) ML24267A1082024-09-23023 September 2024 Submittal of the Reactor Vessel Material Surveillance Program Capsule Technical Report IR 05000272/20240052024-08-29029 August 2024 Updated Inspection Plan for Salem Nuclear Generating Station, Units 1 and 2 (Report 05000272/2024005 and 05000311/2024005) IR 05000272/20240022024-07-30030 July 2024 Integrated Inspection Report 05000272/2024002 and 05000311/2024002 LR-N24-0012, Application to Revise Technical Specifications and 10 CFR 50.12 Exemption Request to Implement Optimized ZIRLO Fuel Rod Cladding2024-07-24024 July 2024 Application to Revise Technical Specifications and 10 CFR 50.12 Exemption Request to Implement Optimized ZIRLO Fuel Rod Cladding ML24145A1772024-07-15015 July 2024 and Salem Nuclear Generating Station, Unit Nos. 1 and 2 - Issuance of Amendment Nos. 236, 349, and 331 Modify Exclusion Area Boundary IR 05000272/20245012024-06-12012 June 2024 and Salem Nuclear Generating Station, Units 1 and 2 - Emergency Preparedness Biennial Exercise Inspection Report 05000354/2024501, 05000272/2024501 and 05000311/2024501 ML24099A1572024-05-29029 May 2024 Issuance of Amendment Nos. 348 and 330 Permanent Extension of Type a and Type C Containment Leak Rate Test Frequencies ML24150A0032024-05-28028 May 2024 Request for Exemptions from 10 CFR 50.82(a)(8)(i)(A) and 10 CFR 50.75(h)(1)(iv) and Proposed Amendment to the Decommissioning Trust Agreement LR-N24-0041, Stations, Revisions to Emergency Plan Document Nc EP-EP-ZZ-01102, Rev. 28, Emergency Coordinator Response2024-05-22022 May 2024 Stations, Revisions to Emergency Plan Document Nc EP-EP-ZZ-01102, Rev. 28, Emergency Coordinator Response IR 05000272/20240102024-05-16016 May 2024 Fire Protection Team Inspection Report 05000272/2024010 and 05000311/2024010 LR-N24-0038, Pressure Boundary Leakage Through a Reactor Coolant Pump Thermal Barrier Heat Exchanger2024-05-0909 May 2024 Pressure Boundary Leakage Through a Reactor Coolant Pump Thermal Barrier Heat Exchanger IR 05000272/20240012024-05-0707 May 2024 Integrated Inspection Report 05000272/2024001 and 05000311/2024001 LR-N24-0039, Steam Generator Tube Inspection Report - Twenty-ninth Refueling Outage2024-05-0606 May 2024 Steam Generator Tube Inspection Report - Twenty-ninth Refueling Outage LR-N24-0034, 2023 Annual Radioactive Effluent Release Report (ARERR)2024-04-30030 April 2024 2023 Annual Radioactive Effluent Release Report (ARERR) LR-N24-0035, 2023 Annual Radiological Environmental Operating Report (AREOR)2024-04-30030 April 2024 2023 Annual Radiological Environmental Operating Report (AREOR) LR-N24-0024, Response to Request for Additional Information Associated with License Amendment Request (LAR) to Modify the Salem and Hope Creek Exclusion Area Boundary2024-04-26026 April 2024 Response to Request for Additional Information Associated with License Amendment Request (LAR) to Modify the Salem and Hope Creek Exclusion Area Boundary LR-N24-0011, Supplemental Information to License Amendment Request (LAR) to Modify the Salem and Hope Creek Exclusion Area Boundary2024-04-0505 April 2024 Supplemental Information to License Amendment Request (LAR) to Modify the Salem and Hope Creek Exclusion Area Boundary IR 05000272/20240112024-04-0101 April 2024 and Salem Nuclear Generating Station, Units 1 and 2 - Plant Modification and Annual Problem Identification and Resolution Inspection Report 05000354/2024011, 05000272/2024011, and 05000311/2024011 LR-N24-0028, and Salem Generating Station - Notice of Intent to Pursue Subsequent License Renewal2024-03-28028 March 2024 and Salem Generating Station - Notice of Intent to Pursue Subsequent License Renewal LR-N24-0021, and Salem Generating Station, Units 1 and 2 - Guarantees of Payment of Deferred Premiums2024-03-20020 March 2024 and Salem Generating Station, Units 1 and 2 - Guarantees of Payment of Deferred Premiums ML24071A2132024-03-12012 March 2024 Senior Reactor and Reactor Operator Initial License Examinations LR-N24-0020, Generation Station and Salem Generating Station, Units 1 & 2 - Annual Property Insurance Status Report2024-03-0707 March 2024 Generation Station and Salem Generating Station, Units 1 & 2 - Annual Property Insurance Status Report LR-N24-0022, Spent Fuel Cask Registration2024-02-29029 February 2024 Spent Fuel Cask Registration IR 05000272/20230062024-02-28028 February 2024 Annual Assessment Letter for Salem Nuclear Generating Station, Units 1 and 2 (Reports 05000272/2023006 and 05000311/2023006 IR 05000272/20244012024-02-26026 February 2024 and Salem Nuclear Generating Station, Units 1 and 2 - Security Baseline Inspection Report 05000354/2024401, 05000272/2024401 and 05000311/2024401 (Cover Letter Only) LR-N24-0009, In-Service Inspection Activities2024-02-0505 February 2024 In-Service Inspection Activities IR 05000272/20230042024-02-0505 February 2024 Integrated Inspection Report 05000272/2023004 and 05000311/2023004 ML24009A1022024-01-26026 January 2024 – Exemption from Select Requirements of 10 CF Part 73 (EPID L-2023-LLE-0045 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) IR 05000272/20234012024-01-22022 January 2024 Material Control and Accounting Program Inspection Report 05000272/2023401 and 05000311/2023401 ML24004A1542024-01-0808 January 2024 Notification of Conduct of a Fire Protection Team Inspection LR-N23-0079, Special Report 23-02-00 Pursuant to the Requirements of Salem Unit 1 Technical Specification 3.3.3.7, Action 10, for the Unit 1 Main Steam Line Rad Monitor Inoperable for Greater than Seven Days2023-12-0707 December 2023 Special Report 23-02-00 Pursuant to the Requirements of Salem Unit 1 Technical Specification 3.3.3.7, Action 10, for the Unit 1 Main Steam Line Rad Monitor Inoperable for Greater than Seven Days LR-N23-0077, Loss of Coolant Accident Peak Cladding Temperature Margin Tracking - Annual Report 2023 & 30 Day Report for Salem Unit 1 Upflow Conversion2023-11-29029 November 2023 Loss of Coolant Accident Peak Cladding Temperature Margin Tracking - Annual Report 2023 & 30 Day Report for Salem Unit 1 Upflow Conversion ML23270C0072023-11-29029 November 2023 Notice of Proposed Amendment to Decommissioning Trust Agreement ML23324A3072023-11-17017 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML24250A0582023-11-14014 November 2023 PSEG to Marine Mammal Stranding Center, Salem Sea Turtle Stranding Response Services IR 05000272/20230032023-11-13013 November 2023 Integrated Inspection Report 05000272/2023003 and 05000311/2023003 LR-N23-0072, Core Operating Limits Report Cycle 302023-11-0101 November 2023 Core Operating Limits Report Cycle 30 IR 05000272/20230102023-10-12012 October 2023 Biennial Problem Identification and Resolution Inspection Report O5000272/2023010 and 05000311/2023010 IR 05000272/20234022023-10-12012 October 2023 and Salem Nuclear Generating Station, Units 1 and 2 - Security Baseline Inspection Report 05000354/2023402, 05000272/2023402 and 05000311/2023402 (Cover Letter Only) LR-N23-0045, and Peach Bottom Atomic Power Station, Units 2 and 3 - Notice of Proposed Amendment to Decommissioning Trust Agreement2023-09-0808 September 2023 and Peach Bottom Atomic Power Station, Units 2 and 3 - Notice of Proposed Amendment to Decommissioning Trust Agreement ML23249A2612023-09-0606 September 2023 License Amendment Request to Modify the Salem and Hope Creek Exclusion Area Boundary IR 05000272/20230052023-08-31031 August 2023 Updated Inspection Plan for Salem Nuclear Generating Station, Units 1 and 2 (Reports 05000272/2023005 and 05000311/2023005) ML23233A0762023-08-21021 August 2023 Requalification Program Inspection ML23192A8212023-08-14014 August 2023 and Salem Nuclear Generating Station, Unit Nos. 1 and 2 - Issuance of Amendment Nos. 234, 347, and 329 Revise Technical Specifications to Delete Meteorological Tower Location IR 05000272/20230022023-08-0909 August 2023 Integrated Inspection Report 05000272/2023002 and 05000311/2023002 LR-N23-0055, Special Report 272/23-01-00, Pursuant to the Requirements of Technical Specification 3.3.3.1, Action 23, for the Vent Noble Gas Rad Monitor Inoperable for Greater than Seven Days2023-08-0303 August 2023 Special Report 272/23-01-00, Pursuant to the Requirements of Technical Specification 3.3.3.1, Action 23, for the Vent Noble Gas Rad Monitor Inoperable for Greater than Seven Days IR 05000354/20230022023-08-0303 August 2023 Integrated Inspection Report 05000354/2023002 and Independent Spent Fuel Storage Installation Inspection Report 07200048/2023001 LR-N23-0054, In-Service Inspection Activities2023-07-26026 July 2023 In-Service Inspection Activities 2024-09-25
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML24060A0492024-02-28028 February 2024 NRR E-mail Capture - Final Exhb RAI for Hope Creek, Salem 1 and 2 Amendment to Modify Exclusion Area Boundary ML22333A9022022-11-29029 November 2022 NRR E-mail Capture - Final Iolb RAI - Salem 1 and 2 LAR to Revise TS to Extend Allowed Outage Time for Inoperable EDG ML22318A1062022-11-14014 November 2022 Information Request for Quadrennial Baseline Comprehensive Engineering Team Inspection; Notification to Perform Inspection 05000272/2023011 and 05000311/2023011 ML22290A2202022-10-17017 October 2022 NRR E-mail Capture - Final RAI - Salem 1 and 2 LAR to Revise TS to Extend Allowed Outage Time for Inoperable EDG ML22055A0702022-02-22022 February 2022 NRR E-mail Capture - Final RAI - Salem 1-Relief Request Associated with Fourth Inservice Inspection (ISI) Interval Limited Examinations (L-2021-LLR-0085) ML21256A1902021-09-10010 September 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding License Transfer Application ML21144A2132021-05-24024 May 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding License Transfer Application ML21068A4142021-03-0909 March 2021 NRR E-mail Capture - Final RAI for Salem Unit 1 LAR to Revise and Relocate Pressurizer Overpressure Protection System Limits to Pressure and Temperature Limits Report ML21043A1442021-02-11011 February 2021 NRR E-mail Capture - Salem - Final RAI Alternative for Examination of ASME Section XI, Category B-B, Item Number B2.11and B2.12 (L-2020-LRR-0103) ML21021A2592021-01-21021 January 2021 NRR E-mail Capture - Final RAI - Salem 1 - Steam Generator Tube Inspection Report ML20281A5172020-10-13013 October 2020 Notification of Conduct of a Fire Protection Team Inspection ML18267A1712018-09-21021 September 2018 NRR E-mail Capture - Final RAI from PRA Branch: Revise Technical Specifications to Increase Inverter AOT Extension (L-2018-LLA-0140) ML18264A0122018-09-20020 September 2018 NRR E-mail Capture - Final RAI from I&C Branch: Revise Technical Specifications to Increase Inverter AOT Extension (L-2018-LLA-0140) ML18250A3132018-09-0606 September 2018 NRR E-mail Capture - Final RAI: Revise Technical Specifications to Increase Inverter AOT Extension (L-2018-LLA-0140) ML18171A3212018-06-20020 June 2018 NRR E-mail Capture - Final RAI: Revise Technical Specifications to Adopt TSTF-411 and 418 (L-2017-LLA-0442) ML18094B0832018-04-0505 April 2018 Enclosurequest for Additional Information (Letter to P. Duke RAI Regarding Entergy Operations, Inc.'S Decommissioning Funding Plan Update for Salem and Hope Creek, and Peach Bottom ISFSIs Docket Nos. 72-48 and 72-29) ML18067A1482018-03-0808 March 2018 Enclosurequest for Additional Information (Letter to P. R. Simpson Request for Additional Information Regarding Exelon Generating Company, Llc'S Decommissioning Funding Plan Update for Independent Spent Fuel Storage Installation) ML17212B1152017-07-31031 July 2017 Request for Additional Information - Salem Units 1 and 2 - Containment Fan Coil Unit Allowed Outage Time Amendment Request (CACs MF9364 and MF9365) ML17199A1122017-07-18018 July 2017 Request for Additional Information - Salem Units 1 and 2 - Accident Monitoring Instrumentation License Amendment Request (CAC Nos. MF8859 & MF8860) ML17192A1672017-07-11011 July 2017 Request for Additional Information - Salem Unit 1 - Steam Generator Tube Inspection Report ML17115A4032017-05-0909 May 2017 Request for Additional Information Regarding Relief Request SC-14R-171 - Use of Code Cases N-695-1 and N-696-1 ML16321A4642016-11-21021 November 2016 and Salem Nuclear Generating Station, Unit Nos. 1 and 2 - Request for Additional Information Regarding License Amendment Request to Remove Certain Training Requirements ML16218A0052016-08-11011 August 2016 Request for Additional Information Concerning Request for an Extension to Enforcement Guidance Memorandum 12-001 ML16195A4492016-07-14014 July 2016 Request for Additional Information Regarding Chilled Water System Modifications ML16188A4152016-07-0707 July 2016 Request for Additional Information Aging Management Program Plan for Reactor Vessel Internals ML16124A5802016-05-0303 May 2016 and Salem Nuclear Generating Station, Unit Nos. 1 and 2 - Redacted - Request for Additional Information Review of Security Plan Revision 17 Changes ML16013A1592016-02-17017 February 2016 Request for Additional Information Regarding Chilled Water System Modifications ML15287A1412015-11-0202 November 2015 Request for Additional Information License Amendment Request Regarding Replacement of Source Range and Intermediate Range Neutron Monitoring Systems ML15287A1052015-11-0202 November 2015 Request for Additional Information License Amendment Request to Isolate Unborated Water Sources and Use Gamma-Metrics Post-Accident Neutron Monitors During Mode 6 (Refueling) (CAC Nos. MF5831 & MF5832) ML15299A3832015-10-29029 October 2015 Supplemental Information Needed for Acceptance of Requested Licensing Action Amendment Request Regarding Chilled Water System Modification ML15069A1812015-03-31031 March 2015 Request for Additional Information Aging Management Program Plan for Reactor Vessel Internals (TAC Nos. MF5149 and MF5150) ML15075A2602015-03-24024 March 2015 Request for Additional Information Spring 2014 Steam Generator Tube Inspections ML15055A3772015-03-10010 March 2015 and Salem Nuclear Generating Station, Unit Nos. 1 and 2, Request for Additional Information Request to Update Appendix B to Renewed Facility Operating License DPR-70, DPR-75 and NPF-57 ML14197A6192014-07-24024 July 2014 and Salem Nuclear Generating Station, Units 1 and 2 - Request for Additional Information Regarding Cyber Security Plan Milestone 8 Implementation Schedule (Tac Nos. MF3384, MF3385 and MF3386) ML14168A2422014-06-28028 June 2014 Request for Additional Information Regarding Flooding Hazard Reevaluation ML14135A2912014-06-0202 June 2014 RAI Regarding Request for Relief SC-I4R-140 from American Society of Mechanical Engineers Boiler & Pressure Vessel Code, Section XI Requirements Regarding the Reactor Vessel Head Flange Seal Leak Detection ML14086A6362014-04-30030 April 2014 Request for Additional Information Regarding Core Operating Limits Report ML14066A2952014-03-0606 March 2014 Licensed Operator Positive Fitness-For-Duty-Test (FY14) ML13330A5672013-11-22022 November 2013 Request for Additional Information: Salem Units 1 and 2 - Relief Request SC-14R-133 Repair of Service Water Piping (TAC MF1375 & 1376) ML13304B4182013-11-0101 November 2013 Request for Additional Information Associated with Near-Term Task Force Recommendation 2.3, Seismic Walkdowns ML13304B9362013-10-29029 October 2013 Request for Additional Information: Salem Units 1 and 2 - Relief Request SC-14R-133 Repair of Service Water Piping (TAC MF1375 & 1376) ML13270A4142013-10-17017 October 2013 Interim Staff Evaluation and Request for Additional Information Regarding the Overall Integrated Plan for Implementation of Order EA-12-051, Reliable Spent Fuel Pool Instrumentation (TAC Nos. MF0913 and Mf ML13249A0112013-09-0505 September 2013 Weko Seal Relief Request RAI ML13196A3382013-07-15015 July 2013 2013 Decommissioning Fund Report RAI ML13192A2322013-07-11011 July 2013 Draft Request for Additional Information Overall Integrated Plan in Response to Order EA-12-051, Reliable Spent Fuel Pool Instrumentation. ML13186A1672013-07-11011 July 2013 Request for Additional Information Overall Integrated Plan for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) ML13179A3032013-06-28028 June 2013 RAIs for Salem Regarding Response to Order EA-12-051 (SFP Instrumentation) ML13137A4882013-06-0505 June 2013 Request for Additional Information Relief Request SC-l4R-133 ML13149A0862013-06-0505 June 2013 Request for Additional Information Decommissioning Funding Status Report ML13102A2752013-04-25025 April 2013 Request for Additional Information Change to PSEG Emergency Plan to Remove the Backup R45 Plant Vent Radiation Monitor Indications 2024-02-28
[Table view] |
Text
March 21, 2005 Mr. William Levis Senior Vice President &
Chief Nuclear Officer PSEG Nuclear - X15 P.O. Box 236 Hancocks Bridge, NJ 08038
SUBJECT:
SALEM NUCLEAR GENERATING STATION, UNIT NO. 2, REQUEST FOR ADDITIONAL INFORMATION REGARDING STEAM GENERATOR TUBE INSPECTION CONDUCTED DURING 2003 REFUELING OUTAGE (TAC NOS. MC2264 AND MC2265)
Dear Mr. Levis:
By letters dated November 17, 2003, February 19, and March 19, 2004 (located in the Agencywide Documents Access and Management System (ADAMS) under accession numbers ML033290440, ML040620694, and ML040760608, respectively), PSEG Nuclear LLC, the licensee for Salem Nuclear Generating Station, Unit No. 2 (Salem), submitted reports summarizing the steam generator tube inspections conducted at Salem during the 2003 refueling outage. Additionally, a summary of conference calls concerning these inspections are in ADAMS under accession number ML040800008.
The Nuclear Regulatory Commission staff has been reviewing the inspection results and analysis and has determined that additional information is required in order to complete our review. Please provide your response to the enclosed within 30 days from the date of this letter.
If you have any questions regarding this matter, please contact me at (301) 415-1494.
Sincerely,
/RA/
Daniel S. Collins, Sr. Project Manager, Section 2 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-311
Enclosure:
Request for Additional Information cc w/encl: See next page
Salem Nuclear Generating Station, Unit Nos. 1 and 2 cc:
Mr. Michael H. Brothers Lower Alloways Creek Township Vice President - Nuclear Assessments c/o Mary O. Henderson, Clerk PSEG Nuclear Municipal Building, P.O. Box 157 P.O. Box 236 Hancocks Bridge, NJ 08038 Hancocks Bridge, NJ 08038 Dr. Jill Lipoti, Asst. Director Mr. Patrick S. Walsh Radiation Protection Programs Vice President - Eng/Tech Support NJ Department of Environmental PSEG Nuclear - N28 Protection and Energy P.O. Box 236 CN 415 Hancocks Bridge, NJ 08038 Trenton, NJ 08625-0415 Mr. Thomas P. Joyce Brian Beam Site Vice President - Salem Board of Public Utilities PSEG Nuclear 2 Gateway Center, Tenth Floor P.O. Box 236 Newark, NJ 07102 Hancocks Bridge, NJ 08038 Regional Administrator, Region I Ms. Christina L. Perino U.S. Nuclear Regulatory Commission Director - Regulatory Assurance 475 Allendale Road PSEG Nuclear - N21 King of Prussia, PA 19406 P.O. Box 236 Hancocks Bridge, NJ 08038 Senior Resident Inspector Salem Nuclear Generating Station Mr. George H. Gellrich U.S. Nuclear Regulatory Commission Plant Support Manager Drawer 0509 PSEG Nuclear Hancocks Bridge, NJ 08038 P.O. Box 236 Hancocks Bridge, NJ 08038 Mr. Carl J. Fricker Plant Manager Jeffrie J. Keenan, Esquire PSEG Nuclear - N21 PSEG Nuclear - N21 P.O. Box 236 P.O. Box 236 Hancocks Bridge, NJ 08038 Hancocks Bridge, NJ 08038 Ms. R. A. Kankus Joint Owner Affairs PECO Energy Company Nuclear Group Headquarters KSA1-E 200 Exelon Way Kennett Square, PA 19348
Mr. William Levis Senior Vice President &
Chief Nuclear Officer PSEG Nuclear - X15 P.O. Box 236 Hancocks Bridge, NJ 08038
SUBJECT:
SALEM NUCLEAR GENERATING STATION, UNIT NO. 2, REQUEST FOR ADDITIONAL INFORMATION REGARDING STEAM GENERATOR TUBE INSPECTION CONDUCTED DURING 2003 REFUELING OUTAGE (TAC NOS. MC2264 AND MC2265)
Dear Mr. Levis:
By letters dated November 17, 2003, February 19, and March 19, 2004 (located in the Agencywide Documents Access and Management System (ADAMS) under accession numbers ML033290440, ML040620694, and ML040760608, respectively), PSEG Nuclear LLC, the licensee for Salem Nuclear Generating Station, Unit No. 2 (Salem), submitted reports summarizing the steam generator tube inspections conducted at Salem during the 2003 refueling outage. Additionally, a summary of conference calls concerning these inspections are in ADAMS under accession number ML040800008.
The Nuclear Regulatory Commission staff has been reviewing the inspection results and analysis and has determined that additional information is required in order to complete our review. Please provide your response to the enclosed within 30 days from the date of this letter.
If you have any questions regarding this matter, please contact me at (301) 415-1494.
Sincerely,
/RA/
Daniel S. Collins, Sr. Project Manager, Section 2 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-311
Enclosure:
Request for Additional Information DISTRIBUTION:
PUBLIC DCollins TOwusu ACRS OGC ECoby, RGN-I PDI-2 R/F ADAMS Accession Number: ML050190178 OFFICE PDI-2/GE PDI-2/PM PDI-2/LA PDI-2/SC NAME TOwusu DCollins CRaynor DRoberts DATE 3/7/05 3/7/05 3/4/05 3/14/05 OFFICIAL RECORD COPY
REQUEST FOR ADDITIONAL INFORMATION REGARDING STEAM GENERATOR TUBE INSPECTION CONDUCTED DURING THE 2003 REFUELING OUTAGE SALEM GENERATING STATION, UNIT NO. 2 DOCKET NO. 50-311 By letters dated November 17, 2003, February 19, and March 19, 2004 (located in the Agencywide Documents Access and Management System (ADAMS) under accession numbers ML033290440, ML040620694, and ML040760608, respectively), PSEG Nuclear LLC, the licensee for Salem Nuclear Generating Station, Unit No. 2 (Salem), submitted reports summarizing the steam generator (SG) tube inspections conducted at Salem during the 2003 (13th) refueling outage (2R13). Additionally, a summary of conference calls concerning these inspections are in ADAMS under accession number ML040800008.
The Nuclear Regulatory Commission staff has been reviewing the inspection results and analysis and has determined that the following additional information is required in order to complete our review.
- 1. A population of bobbin coil anti-vibration bar (AVB) wear indications were inspected with a rotating probe. These examinations verified that the reported indications displayed a volumetric response and were not crack-like. Please clarify the scope of the rotating probe examinations at locations with AVB wear. That is, of the 601 AVB wear indications detected during 2R13, how many were inspected with a rotating probe?
- 2. Provide and discuss the results of your rotating probe examinations performed at the dents and the U-bend regions of the tubes.
- 3. On page 8 of Enclosure 4 to your February 19, 2004 letter, it was indicated that nine tubes in SG 23 were preventively plugged due to small anomalous signals. This statement matches data in the table on page 3 of Enclosure 4 to your February 19, 2004 letter. However, the table on page 8 indicates that eight tubes in SG 23 and one tube in SG 24 had anomalous signals. Please clarify.
- 4. Several crack-like indications have been found at dented locations during recent inspections at Salem Unit No. 2. Both axially and circumferentially-oriented crack-like indications have been detected. As of refueling outage 12, there were approximately 21,000 dents at tube supports and approximately 900 dings in the free span portion of the tube. Of the 21,000 dents, approximately 33% were greater than 5 volts. Of the 900 dings, approximately 19% are greater than 5 volts. During 2R13, not all dents or dings greater than 5 volts were inspected with a rotating probe, although all dents at the lower tube supports greater than 1 volt on the hot-leg were inspected. Given that (1) temperature and stress affect a tubes susceptibility to cracking (i.e., a larger dent at a lower temperature may be as susceptible to stress corrosion cracking as a smaller dent at a higher temperature), and (2) that the bobbin coil is not considered qualified for detecting degradation at dented/dinged locations when the dent/ding exceeds 5 volts, Enclosure
please discuss the basis for concluding that the structural and leakage integrity performance criteria were met during Cycle 13 and will continue to be met throughout subsequent cycles.
Include in this response how the integrity of dented/dinged locations exceeding 5 volts that were not inspected with a rotating probe during 2R13 were assessed. These locations potentially have undetected degradation that may have been growing since the last rotating probe inspection. Provide the technical basis for any assumptions in your analysis.
Enclosure