August 2003 Monthly Operating Report for Cooper Nuclear Station
ML032591117
Person / Time
Site: Cooper Entergy icon.png
Issue date: 09/11/2003
From: Jason Christensen
Nebraska Public Power District (NPPD)
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
GL-97-002, NLS2003099
Download: ML032591117 (5)


Text

N Nebraska Public Power District Alwos Adthe n you need us NLS2003099 September 11, 2003 U. S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, D.C. 20555-0001

Subject:

Monthly Operating Report for August 2003, Docket No. 50-298 The purpose of this letter is to provide the Cooper Nuclear Station Monthly Operating Report for August 2003. In accordance with the guidance provided by Generic Letter 97-02, this report includes an Operating Data Report and Unit Shutdown Report for the month of August. In accordance with Technical Specification 5.6.4, this report also includes documentation of challenges to the safety/relief valves.

Should you have any comments or require additional information regarding this report, please contact Paul Fleming at (402) 825-2774.

Sincerely, J Christensen Plant Manager

/cb Enclosure cc: NRC Regional Administrator W. J. Fehrman NRC Senior Resident Inspector W. D. Shanks ANI Library C. C. Warren J. M. Cline B. Lewis A. L. Dostal G. W. Griffith J. W. Dutton S. Moffitt R. L. Gumm INPO Records Center Records COOPER NUAR STATION P.O. Box 98 / Brovnile, NE 68321-0098 Tekphone: (402) 825-3811 / Fac (402) 825-5211 www.nppd.com Il L: -a

APPENDIX A OPERATING DATA REPORT DOCKET NO. 050-0298 UNIT NAME Cooper Nuclear Station DATE 911112003 COMPLETED BY Rodrick Wilson TELEPHONE (402) 825-5135 Reporting Period: August 2003 This Month Yr-to-Date Cumulative I. Design Electrical Rating (Net MWe). 778.0 N/A N/A The nominal net electrical output of the unit specified by the utility and used for the purpose of plant design.

2. Maximum Dependable Capacity (Net MWe): 764.0 N/A N/A The gross electrical output as measured at the output terminals of the turbine-generator during the most restrictive seasonal conditions minus the normal station service loads.
3. Number of Hours the Reactor Was Critical. 744.0 3,772.6 196295.7 The total number of hours during the gross hours of the reporting period that the reactor was critical.
4. Number of Hours the Generator Was On Line. 744.0 3544.5 193415.1 (Also called Service Hours). The total number of hours during the gross hours of the reporting period that the unit operated with the breakers closed to the station bus.

The sum of the hours the generator was on line plus the total outage hours should equal the gross hours in the reporting period.

5. Unit Reserve Shutdown Hours. 0.0 0.0 0.0 The total number of hours during the gross hours of the reporting period that the unit was removed from service for economic or similar reasons but was available for operation
6. Net Electrical Energy (MWH). 549216 0 2580779.0 131242451.0 The gross electrical output of the unit measured at the output terminals of the tusbine-generator minus the normal station service loads during the gross hours of the reporting period, expressed in mega-watt hours. Negative quantities should not be used.

9/11/2003 1:14 FM

APPENDIX B UNIT SHUTDOWNS DOCKET NO. 050-0298 UNIT NAME Cooper Nuclear Station DATE 9/11/2003 COMPLETED BW Rodrick Wilson TELEPHONE (40Z) 825-5 3-REPORT MONTH August 2003 No. Date Type Durton(Hor) Reason () Method Of Shutting CAUSE/CORRECTIVE ACTIONS COMMENTS No. Date TypFOREDDrto Hur) RaoI Dow COM2NT S: SCHEDULED t 5 9 5

.1. 1 1 A .1. 1

SUMMARY

None (1) Reason:

A -Equipment Failure (Explain)

B. Maintenance or Test C - Refuelling D - Replatory Restriction E .Operator Traning/License Examination F -Administrative G -Operational Error (Explain)

H -Other (Explain)

(2)Method:

I -Manual 2 -Manual Trip/Scram 3 -Automatic Trip/Scram 4 Continnation 5 -Other (Explain) 9/11/2003 1:14 PM

APPENDIX C SAFETY/RELIEF VALVE CHALLENGES AUGUST 2003 There were no challenges to the safety/relief valves during the month of August.

I ATTACHMENT 3 LIST OF REGULATORY COMMITMENTSl Correspondence Number: NLS2003099 The following table identifies those actions committed to by Nebraska Public Power District (NPPD) in this document. Any other actions discussed in the submittal represent intended or planned actions by NPPD. They are described for information only and are not regulatory commitments. Please notify the Licensing & Regulatory Affairs Manager at Cooper Nuclear Station of any questions regarding this document or any associated regulatory commitments.

COMMITTED DATE COMMITMENT OR OUTAGE None I PROCEDURE 0.42 1 REVISION 13 l PAGE 14 OF 16

Text

N Nebraska Public Power District Alwos Adthe n you need us NLS2003099 September 11, 2003 U. S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, D.C. 20555-0001

Subject:

Monthly Operating Report for August 2003, Docket No. 50-298 The purpose of this letter is to provide the Cooper Nuclear Station Monthly Operating Report for August 2003. In accordance with the guidance provided by Generic Letter 97-02, this report includes an Operating Data Report and Unit Shutdown Report for the month of August. In accordance with Technical Specification 5.6.4, this report also includes documentation of challenges to the safety/relief valves.

Should you have any comments or require additional information regarding this report, please contact Paul Fleming at (402) 825-2774.

Sincerely, J Christensen Plant Manager

/cb Enclosure cc: NRC Regional Administrator W. J. Fehrman NRC Senior Resident Inspector W. D. Shanks ANI Library C. C. Warren J. M. Cline B. Lewis A. L. Dostal G. W. Griffith J. W. Dutton S. Moffitt R. L. Gumm INPO Records Center Records COOPER NUAR STATION P.O. Box 98 / Brovnile, NE 68321-0098 Tekphone: (402) 825-3811 / Fac (402) 825-5211 www.nppd.com Il L: -a

APPENDIX A OPERATING DATA REPORT DOCKET NO. 050-0298 UNIT NAME Cooper Nuclear Station DATE 911112003 COMPLETED BY Rodrick Wilson TELEPHONE (402) 825-5135 Reporting Period: August 2003 This Month Yr-to-Date Cumulative I. Design Electrical Rating (Net MWe). 778.0 N/A N/A The nominal net electrical output of the unit specified by the utility and used for the purpose of plant design.

2. Maximum Dependable Capacity (Net MWe): 764.0 N/A N/A The gross electrical output as measured at the output terminals of the turbine-generator during the most restrictive seasonal conditions minus the normal station service loads.
3. Number of Hours the Reactor Was Critical. 744.0 3,772.6 196295.7 The total number of hours during the gross hours of the reporting period that the reactor was critical.
4. Number of Hours the Generator Was On Line. 744.0 3544.5 193415.1 (Also called Service Hours). The total number of hours during the gross hours of the reporting period that the unit operated with the breakers closed to the station bus.

The sum of the hours the generator was on line plus the total outage hours should equal the gross hours in the reporting period.

5. Unit Reserve Shutdown Hours. 0.0 0.0 0.0 The total number of hours during the gross hours of the reporting period that the unit was removed from service for economic or similar reasons but was available for operation
6. Net Electrical Energy (MWH). 549216 0 2580779.0 131242451.0 The gross electrical output of the unit measured at the output terminals of the tusbine-generator minus the normal station service loads during the gross hours of the reporting period, expressed in mega-watt hours. Negative quantities should not be used.

9/11/2003 1:14 FM

APPENDIX B UNIT SHUTDOWNS DOCKET NO. 050-0298 UNIT NAME Cooper Nuclear Station DATE 9/11/2003 COMPLETED BW Rodrick Wilson TELEPHONE (40Z) 825-5 3-REPORT MONTH August 2003 No. Date Type Durton(Hor) Reason () Method Of Shutting CAUSE/CORRECTIVE ACTIONS COMMENTS No. Date TypFOREDDrto Hur) RaoI Dow COM2NT S: SCHEDULED t 5 9 5

.1. 1 1 A .1. 1

SUMMARY

None (1) Reason:

A -Equipment Failure (Explain)

B. Maintenance or Test C - Refuelling D - Replatory Restriction E .Operator Traning/License Examination F -Administrative G -Operational Error (Explain)

H -Other (Explain)

(2)Method:

I -Manual 2 -Manual Trip/Scram 3 -Automatic Trip/Scram 4 Continnation 5 -Other (Explain) 9/11/2003 1:14 PM

APPENDIX C SAFETY/RELIEF VALVE CHALLENGES AUGUST 2003 There were no challenges to the safety/relief valves during the month of August.

I ATTACHMENT 3 LIST OF REGULATORY COMMITMENTSl Correspondence Number: NLS2003099 The following table identifies those actions committed to by Nebraska Public Power District (NPPD) in this document. Any other actions discussed in the submittal represent intended or planned actions by NPPD. They are described for information only and are not regulatory commitments. Please notify the Licensing & Regulatory Affairs Manager at Cooper Nuclear Station of any questions regarding this document or any associated regulatory commitments.

COMMITTED DATE COMMITMENT OR OUTAGE None I PROCEDURE 0.42 1 REVISION 13 l PAGE 14 OF 16