NLS2002143, November 2002 Monthly Operating Report for Cooper

From kanterella
Jump to navigation Jump to search
November 2002 Monthly Operating Report for Cooper
ML023520516
Person / Time
Site: Cooper Entergy icon.png
Issue date: 12/12/2002
From: Hutton J
Nebraska Public Power District (NPPD)
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
NLS2002143
Download: ML023520516 (5)


Text

H Nebraska Public Power District Nebraska's Energy Leader NLS2002143 December 12, 2002 U. S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, D.C. 20555-0001

Subject:

Monthly Operating Report for November 2002, Docket No. 50-298 Enclosed for your information and use is the Cooper Nuclear Station Monthly Operating Report for November 2002. In accordance with the guidance provided by Generic Letter 97-02, this report includes an Operating Data Report and Unit Shutdown Report for the month ofNovember. In accordance with Technical Specification 5.6.4, this report also includes documentation ofchallenges to the safety/relief valves.

Should you have any comments or require additional information regarding this report, please contact Paul Fleming at (402) 825-2774.

Sincerely, PamesWA. Hutton

/Plant Managger

/cb Enclosure cc: NRC Regional Administrator W. R. Mayben NRC Senior Resident Inspector W. D. Shanks ANI Library D. L. Wilson J. M. Cline B. Lewis A. L. Dostal G. W. Griffith J. W. Dutton D. T. McNeil R. L. Gumm INPO Records Center Records Cooper Nuclear Station P.0. Box 98/Brownville, NE 68321-0098 Telephone: (402) 825-3811 / Fax: (402) 825-5211 http //www nppd corn

APPENDIX A OPERATING DATA REPORT DOCKET NO. 050-0298 UNIT NAME Cooper Nuclear Station DATE 12/1212002 COMPLETED BY Rodrick Wilson TELEPHONE (402) 825-5135 Reporting Period: Noember 2002 This Month Yr -to-Date Cumulative Design Electrical Rating (Net MWe) 7780 NIA N/A 1.

The nominal net electrical output of the unit specified by the utility and used for the purpose of plant design 7640 NA N/A 2 Maximum Dependable Capacity (Net MWe)

The gross electrical output as measured at the output terminals of the turbine generator during the most restrictive seasonal conditions minus the normal station service loads 7200 78900 191779 I 3 Number of Hours the Reactor Was Critical The total number of hours during the gross hours of the reporting period that the reactor was critical 7054 7771 8 189126 6 4 Number ofIlours the Generator Was On Line (Also called Service [fours) The total number of hours during the gross hours of the reporting period that the unit operated with the breakers closed to the station bus The sum of the hours the generator was on line plus the total outage hours should equal the gross hours in the reporting period.

5 Unit Reserve Shutdown Hlours 00 00 00 The total number of hours during the gross hours of the reporting period that the unit was removed from service for economic or similar reasons but was aailable for operation 5092340 57569430 128100464 0 6 Net Electrical Energy (MWH)

The gross electrical output of the unit measured at the output terminals of the turbine-generator minus the normal station sen ice loads during the gross hours of the reporting period, expressed in mega watt hours Negative quanitties should not be used 12/13/2002 1 22 Ai

APPENDIX B UNIT SHUTDOWNS DOCKET NO. 050-0298 UNIT NAME Cooper Nuclear Station DATE 12/12/2002 COMPLETED BY Rodrick Wilson TELEPHONE (402) 825-5135 REPORT MONTH November 2002

SUMMARY

None (1) Reason:

A - Equipment Failure (Explain)

B - Maintenance or Test C - Refueling D - Regulatory Restriction E - Operator Training/License Examination F - Administrative G - Operational Error (Explain)

If - Other (Explain)

(2) Method:

I - Manual 2 - Manual Trip/Scram 3 - Automatic Trip/Scram 4 - Continuation 5 - Other (Explain) 12/13/2002 7:23 AM

APPENDIX C SAFETY/RELIEF VALVE CHALLENGES NOVEMBER 2002 There were no challenges to the safety/relief valves during the month of November.

I ATTACHMENT 3 LIST OF REGULATORY COMMITMENTS Correspondence Number: NLS2002143 I The following table identifies those actions committed to by Nebraska Public Power District I (NPPD) in this document. Any other actions discussed in the submittal represent intended or planned actions by NPPD. They are described for information only and are not regulatory commitments. Please notify the NL&S Manager at Cooper Nuclear Station of any questions regarding this document or any associated regulatory commitments.

COMMITTED DATE COMMITMENT OR OUTAGE None I-1-

  • 1-

+

I PROCEDURE 0.42 1 REVISION 11 PAGE 13 OF 16 1