Letter Sequence RAI |
---|
|
|
MONTHYEARML0722002132007-08-23023 August 2007 ISFSI, Request for Additional Information Regarding Revision to Emergency Action Levels (TAC Nos. MD4964 Through MD4967) Project stage: RAI 2007-08-23
[Table View] |
|
---|
Category:Letter
MONTHYEARML24318C4622024-11-13013 November 2024 Emergency Plan Revision - Relocation of the Technical Support Center (TSC) - License Amendment Nos. 315 and 315 Updated Information Regarding TSC Ventilation Design IR 05000280/20240032024-11-12012 November 2024 Integrated Inspection Report 05000280-2024003 and 05000281-2024003 IR 05000338/20240032024-10-28028 October 2024 – Integrated Inspection Report 05000338-2024003 and 05000339-2024003 ML24302A2402024-10-28028 October 2024 CFR 21 Report 1-BY-BC-1-LV Battery Charger ML24302A2342024-10-23023 October 2024 Request for Project Number Related to Dominion Energy Services New Nuclear Program at North Anna Power Station ML24302A1762024-10-22022 October 2024 Core Operating Limits Report Surry 2 Cycle 33 Pattern Hot Revision 0 ML24283A0392024-10-0909 October 2024 Annual Submittal of Technical Specification Bases Changes Pursuant to Technical Specification 5.5.13.D ML24281A1372024-10-0707 October 2024 ISFSI - Submittal of Cask Registration for Spent Fuel Storage ML24283A0702024-10-0707 October 2024 Annual Submittal of Technical Specifications Bases Changes Pursuant to Technical Specification 6.4.J IR 05000280/20240102024-10-0202 October 2024 Biennial Problem Identification and Resolution Inspection Report 05000280/2024010 and 05000281/2024010 ML24270A0022024-09-25025 September 2024 Inservice Inspection Owners Activity Report (OAR) 05000338/LER-2024-001-01, Automatic Reactor Trip Due to PRNI High Negative Rate2024-09-24024 September 2024 Automatic Reactor Trip Due to PRNI High Negative Rate IR 05000338/20244202024-09-23023 September 2024 Security Baseline Inspection Report 05000338/2024420 and 05000339/2024420, Cover Letter ML24243A0872024-09-20020 September 2024 Response to EPA Comments Regarding the Final Site Specific Supplement to the Generic Eist for License Renewal North Anna Power Station, Units 1 and 2 IR 05000338/20244022024-09-17017 September 2024 Security Baseline Inspection Report 05000338/2024402 and 05000339/2024402 ML24248A1712024-09-0303 September 2024 Proposed License Amendment Request - Temporary Service Water Supply to the Component Cooling Heat Exchangers ML24215A2622024-08-28028 August 2024 Transmittal Letter for Subsequent Renewed License IR 05000338/20240052024-08-27027 August 2024 Updated Inspection Plan for North Anna Power Station, Units 1 and 2 (Report 05000338/2024005 and 05000339/2024005) IR 05000280/20240052024-08-26026 August 2024 Updated Inspection Plan for Surry Power Station, Units 1 and 2 (Report 05000280/2024005 and 05000281-2024005), Rev 1 ML24219A2372024-08-23023 August 2024 Issuance of Amendment Nos. 319 and 319, Adoption of TSTF-577, Rev. 1, Revised Frequencies for Steam Generator Tube Inspection, ML24207A0402024-08-21021 August 2024 Summary of July 17, 2024, Public Meeting - TS 3.7/3.14 AOT for SW Piping Maintenance 05000339/LER-2024-001-01, Loss of Generator Field for 2J Eog During 2-PT-82.282024-08-20020 August 2024 Loss of Generator Field for 2J Eog During 2-PT-82.28 ML24234A0742024-08-15015 August 2024 Notification of Deviation from Pressurized Water Reactor Owners Group (PWROG) Letter OG-23-63, NEI 03-08 Needed Guidance: PWR Thermal Shield Flexure Inspection Requirements ML24164A0012024-08-12012 August 2024 Proposed Alternative Relief Request V-1 Inservice Testing of Pressure Isolation Valves (EPID l-2023-LLR-0060) ML24221A1862024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Eastern Band of Cherokee Indians ML24221A1882024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Monacan Indian Nation ML24221A1872024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Eastern Shawnee Tribe of Oklahoma ML24221A1852024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Delaware Tribe of Indians ML24221A1842024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Delaware Nation, Oklahoma ML24221A1832024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Chickahominy Indian Tribe-Eastern Division ML24221A1822024-08-0808 August 2024 Tribal Section 106 Letters - North Anna - Chickahominy Indian Tribe ML24221A1812024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Catawba Indian Nation ML24208A0142024-08-0808 August 2024 Tribal Section 106 Letters-North Anna-Absentee-Shawnee Tribe of Indians of Oklahoma ML24206A0062024-08-0808 August 2024 Notice of Availability of the Final Environmental Impact Statement for the North Anna Nuclear Power Station Unit Numbers 1 and 2 Subsequent License Renewal (Docket Numbers: 50-338 and 50-339) ML24206A0052024-08-0808 August 2024 SLR Final EIS Letter to Achp ML24163A3002024-08-0808 August 2024 Request for Relief Request N1-I5-NDE-007 Inservice Inspection Alternative ML24221A1912024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Rappahannock Tribe, Inc ML24221A1892024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Nansemond Indian Nation ML24221A1902024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Pamunkey Indian Tribe ML24221A1922024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Tuscarora Nation of New York ML24221A1942024-08-0808 August 2024 Tribal Section 106 Letters-North Anna-United Keetoowah Band of Cherokee Indians in Oklahoma ML24221A1932024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Upper Mattaponi Tribe ML24241A0692024-08-0606 August 2024 ISFSI, Submittal of Cask Registration for Spent Fuel Storage IR 05000338/20240022024-08-0202 August 2024 Integrated Inspection Report 05000338/2024002 and 05000339/2024002 IR 05000280/20240022024-08-0101 August 2024 Integrated Inspection Report 05000280/2024002 and 05000281/2024002 05000280/LER-2024-001, Troubleshooting Initiated Unknown Turbine Trip Feature in Control System2024-07-30030 July 2024 Troubleshooting Initiated Unknown Turbine Trip Feature in Control System ML24206A0432024-07-26026 July 2024 Feis - Letter to the Applicant 05000338/LER-2024-001, Automatic Reactor Trip Due to PRNI High Negative Rate2024-07-25025 July 2024 Automatic Reactor Trip Due to PRNI High Negative Rate ML24206A0902024-07-24024 July 2024 Owners Activity Report ML24165A2782024-07-17017 July 2024 Issuance of Amendment Nos. 318 and 318, Reclassification of Regulatory Guide 1.97 Variable for Low Head Safety Injection 2024-09-03
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML24141A2862024-05-22022 May 2024 Information Request for the Cyber Security Baseline Inspection, Notification to Perform Inspection 05000280/2024403 and 05000281- 2024403 IR 05000280/20244032024-05-22022 May 2024 Information Request for the Cyber Security Baseline Inspection, Notification to Perform Inspection 05000280/2024403 and 05000281- 2024403 ML24102A0682024-04-10010 April 2024 IST (z)(2) Hardship RR V-1 RCS Cold Leg, Lh Safety Injection Check Valves ML24087A0112024-03-23023 March 2024 NRR E-mail Capture - Draft RAIs for Reactor Coolant Pump (RCP) Relief Request (L-2024-LLR-0022) ML24065A2532024-03-0505 March 2024 RAI Issuance Surry RR IST P-1 P-2 ML23318A1172023-11-13013 November 2023 NRR E-mail Capture - Formal Issuance of RAIs for North Anna Technical Support Center (TSC) License Amendment Request (LAR) (L-2023-LLA-0006) ML23257A2092023-09-14014 September 2023 NRR E-mail Capture - Formal Issuance of 2nd Round RAIs for Surry Units 1&2 and North Anna Units 1&2 Emergency Plans LAR ML23243A9862023-08-31031 August 2023 NRR E-mail Capture - Draft RAIs for EP Staff Augmentation Times LAR (L-2022-LLA-0166) ML23219A1602023-08-0707 August 2023 003 Radiation Safety Baseline Inspection Information Request ML23187A1122023-07-0606 July 2023 TSC Relocation LAR RAIs ML23171B0522023-06-20020 June 2023 NRR E-mail Capture - RAI for Review of Appendix F to DOM-NAF-2-P (Redacted) ML23081A5282023-04-26026 April 2023 Request for Additional Information - North Anna Subsequent License Renewal Application Environmental Review ML23075A0232023-03-15015 March 2023 NRR E-mail Capture - RAI - License Amend Req (LAR) to Revise Tech Spec (Ts) 3.6.8 Limiting Condition for Operation to Remove Refueling Water Chemical Addition Tank and Replace the Containment Sump Buffer North Anna, 1 and 2 (L-2022-LLA-0162 ML23068A0242023-03-0808 March 2023 RAI Issuance Fuel Handling Trolley LAR ML23060A0932023-03-0101 March 2023 NRR E-mail Capture - Formal Issuance of RAIs for Surry/North Anna Emergency Plans LAR ML23059A2282023-02-28028 February 2023 NRR E-mail Capture - Draft RAIs for Containment Buffer Change to Natb (L-2022-LLA-0162) ML23054A2412023-02-23023 February 2023 NRR E-mail Capture - Formal Issuance of RAIs for Surry Turbine Building Tornado Reclassification ML23046A1172023-02-0202 February 2023 002 Radiation Safety Baseline Inspection Information Request ML23018A1642023-01-17017 January 2023 Formal Issuance of RAIs for Surry ISI Alternative for SG Welds, 30 Day Calendar Response Period (Email) ML22349A2102022-12-15015 December 2022 Formal 43-day Request for Additional Information Issuance for Surry Turbine Building License Amendment Request ML22339A1582022-11-30030 November 2022 Requalification Inspection Notification Letter ML22258A2202022-09-13013 September 2022 FFD RFI ML22251A1292022-09-0909 September 2022 Request for Additional Information Related to Response to Generic Letter 2004-04 ML22242A0452022-08-23023 August 2022 NRR E-mail Capture - Dominion GL 04-02 Response Draft RAIs (L-2017-LRC-0000) ML22223A1192022-08-14014 August 2022 RP Inspection Document Request Letter Final ML22110A2052022-04-19019 April 2022 Formal Issuance of RAIs for Post LOCA Buffer Change LAR ML22083A2102022-03-24024 March 2022 NRR E-mail Capture - Draft RAI - Relief Request N2-14-LMT-003 Fourth Ten Year Inservice Inspection Interval ML22067A1622022-03-0909 March 2022 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection ML22012A0572022-01-11011 January 2022 Issuance of RAIs for Surry Unit 1, Spring 2021 Steam Generator Tube Inspection ML21327A3652021-11-23023 November 2021 NRR E-mail Capture - Draft RAI for TSTF-577 LAR ML21322A0962021-11-18018 November 2021 Final Request for Additional Information Set 5 - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - Email ML21322A0992021-11-18018 November 2021 Final Request for Additional Information Set 5 - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - Enclosure ML21256A0672021-09-13013 September 2021 Final Request for Confirmation of Information Set 2 - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - Email ML21256A0692021-09-13013 September 2021 Final Request for Confirmation of Information Set 2 - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - Request for Confirmation of Information ML21238A0942021-08-25025 August 2021 Draft Request for Additional Information Set Z - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - Email ML21238A0982021-08-25025 August 2021 Draft Request for Additional Information Set Z - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - Enclosure ML21225A5022021-08-13013 August 2021 Request for Additional Information for North Anna Power Station, Units 1 and 2, Surry Power Station, Units 1 and 2, and Millstone Power Station, Units 2 and 3, Appendix E of Fleet Report Com-Naf-2 (EPID:L02021-LLT-0000) Public Version ML21196A1012021-07-15015 July 2021 Notification of an NRC Fire Protection Team Inspection (FPTI) (NRC Inspection Report 05000280/2021011 and 05000281/2021011) and Request for Information (RFI) ML21195A2442021-07-13013 July 2021 NRR E-mail Capture - Draft RAI Appendix E to Topical Report DOM-NAF-2 Qualification of the Framatome BWU-I CHF Correlation in the Dominion Energy VIPRE-D Computer Code ML21188A1632021-07-0707 July 2021 Final Request for Additional Information Set 4 - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - Email ML21188A1652021-07-0707 July 2021 Final Request for Additional Information Set 4 - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - Enclosure ML21174A1952021-06-23023 June 2021 Safety RAIs - Set Y - Draft - Enclosure ML21166A3512021-06-15015 June 2021 Safety RAIs - Set 4 - Draft ML21123A2972021-05-0303 May 2021 Final Request for Additional Information Set 3 - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - E-mail ML21123A2982021-05-0303 May 2021 Final Request for Additional Information Set 3 - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - Enclosure ML21102A3122021-04-12012 April 2021 NRR E-mail Capture - Surry, Units 1 & 2 - Final RAI for the LOCA AST LAR ML21091A0032021-04-0101 April 2021 Final Request for Additional Information Set 2 - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - Enclosure 1 - RAIs ML21091A0042021-04-0101 April 2021 SLRA Safety Review - Withdrawn Requests for Information (EPID No. L-2020-SLR-0000) - Enclosure 2 ML21076A4622021-03-17017 March 2021 NRR E-mail Capture - Draft RAI for Versatile Internals and Component Program for Reactors Vipre Code Review (L-2021-LLT-0000) ML21075A0032021-03-12012 March 2021 Emergency Preparedness Exercise Inspection Request for Information for - Brunswick, Catawba, North Anna, Oconee, Vogtle 1 & 2 2024-05-22
[Table view] |
Text
August 23, 2007 Mr. David A. Christian Senior Vice President and Chief Nuclear Officer Virginia Electric and Power Company Innsbrook Technical Center 5000 Dominion Boulevard Glen Allen, VA 23060-6711
SUBJECT:
NORTH ANNA POWER STATION, UNIT NOS. 1 AND 2, AND INDEPENDENT SPENT FUEL STORAGE INSTALLATIONS (ISFSIs), SURRY POWER STATION, UNIT NOS. 1 AND 2, AND ISFSls, REQUEST FOR ADDITIONAL INFORMATION (RAI) REGARDING REVISIONS TO EMERGENCY ACTION LEVELS (TAC NOS. MD4964, MD4965, MD4966, MD4967)
Dear Mr. Christian:
By letter dated March 28, 2007, Virginia Electric and Power Company (the licensee), submitted proposed revisions to the emergency action levels (EALs) for the North Anna Power Station, Unit Nos. 1 and 2 and ISFSIs, and Surry Power Station, Unit Nos. 1 and 2 and ISFSIs. The proposed revisions would implement a new scheme based on Nuclear Energy Institute (NEI) 99-01, Revision 4, Methodology for Development of Emergency Action Levels. The Nuclear Regulatory Commission (NRC) staff is reviewing the submittal and has determined that additional information is required to complete its evaluation. The NRC staffs RAI is enclosed.
The questions which make up the request were discussed with licensee staff on August 6, 2007. As discussed during the teleconference, the EAL submittal for each plant site was evaluated in parallel and RAIs were generated accordingly. The response should address the RAIs on a site-specific basis. Each licensee should address the RAI applicable to their site, revise the EAL and/or provide more information in the EAL Basis, and revise the Difference/Deviation Matrix as applicable. A revised Difference/Deviation Matrix and Redline/Strikeout copy shall be provided in the licensee's response. Also, a complete, clean, EAL Basis Document shall be provided as an attachment to the licensee's response.
D. Christian You are requested to provide a response to the RAI within 30 days.
Sincerely,
/RA/
R. A. Jervey, Project Manager Plant Licensing Branch II-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-338, 50-339, 50-280, 50-281,72-002, 72-016,72-055 and 72-056
Enclosure:
RAI cc w/encl: See next page
ML072200213 OFFICE NRR/LPL2-1/PM NRR/LPL2-1/PM NRR/LPD2-1/LA NSIR/BC NRR/LPL2-1/BC NAME RJervey:nc SLingam MOBrien EWeiss EMarinos DATE 8/20/07 8/20/07 8/20/07 8/21/07 8/23/07 REQUEST FOR ADDITIONAL INFORMATION (RAI) REGARDING- NORTH ANNA POWER STATION, UNIT NOS. 1 AND 2, AND INDEPENDENT SPENT FUEL STORAGE INSTALLATIONS (ISFSIs), SURRY POWER STATION, UNIT NOS. 1 AND 2, AND ISFSls, REVISIONS TO EMERGENCY ACTION LEVELS (TAC NOS. MD4964, MD4965, MD4966, MD4967)
Pages 1 -12 Enclosure
North Anna Power Station, Units 1 & 2, Surry Power Station, Units 1 & 2, cc:
Mr. David A. Christian Senior Resident Inspector Senior Vice President North Anna Power Station and Chief Nuclear Officer U. S. Nuclear Regulatory Commission Virginia Electric and Power Company P. O. Box 490 Innsbrook Technical Center Mineral, Virginia 23117 5000 Dominion Boulevard Glen Allen, VA 23060-6711 Mr. Daniel G. Stoddard Site Vice President Mr. C. Lee Lintecum North Anna Power Station County Administrator Virginia Electric and Power Company Louisa County Post Office Box 402 Post Office Box 160 Mineral, Virginia 23117-0402 Louisa, Virginia 23093 Dr. Robert B. Stroube, MD, MPH Ms. Lillian M. Cuoco, Esq. State Health Commissioner Senior Counsel Office of the Commissioner Dominion Resources Services, Inc. Virginia Department of Health Building 475, 5 th floor Post Office Box 2448 Rope Ferry Road Richmond, Virginia 23218 Waterford, Connecticut 06385 Mr. Donald E. Jernigan Dr. W. T. Lough Site Vice President Virginia State Corporation Commission Surry Power Station Division of Energy Regulation Virginia Electric and Power Company Post Office Box 1197 5570 Hog Island Road Richmond, Virginia 23218 Surry, Virginia 23883-0315 Old Dominion Electric Cooperative Senior Resident Inspector 4201 Dominion Blvd. Surry Power Station Glen Allen, Virginia 23060 U. S. Nuclear Regulatory Commission 5850 Hog Island Road Mr. Chris L. Funderburk, Director Surry, Virginia 23883 Nuclear Licensing & Operations Support Dominion Resources Services, Inc. Chairman Innsbrook Technical Center Board of Supervisors of Surry County 5000 Dominion Blvd. Surry County Courthouse Glen Allen, Virginia 23060-6711 Surry, Virginia 23683 Office of the Attorney General Commonwealth of Virginia 900 East Main Street Richmond, Virginia 23219