Discusses Status of Corrective Action Re Electrical Hanger Installation.Progress in Constructed Hanger Documentation & Field Const Work Controls Has Been Made,But Resolution of Design & Const Items Prior to Apr 1981 Is Needed
ML20008E753
Person / Time
Site: Clinton Constellation icon.png
Issue date: 02/25/1981
From: Koch L
ILLINOIS POWER CO.
To: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
References
1605, U-0220, NUDOCS 8103090565
Download: ML20008E753 (1)


Text

1605 ILLINDIS POWER COMPANY '

f'1 (9,_,3 _L l 500 SOUTH 27TH STREET. DECATUR, ILUNOIS 62525 February 25, 1981 m '

?!

[ t Mr. James C. Keppler lcM MAR 0 01981 -

Director, Region III ,

Office of Inspection and Enforcement 3'- co tsson /

U.S. Nuclear Regulatory Commission \ ,  ;' ,/

799 Roosevelt Road '\.

Glen Ellyn, IL 60137

Dear Mr. Keppler:

Clinton Power Station Docket 50-461/CPPR-137 Potential Reportable Deficiency Electrical Hanger Installation My letter, U-0208 of December 19, 1980, describes progress being made to implement corrective action associated with the electrical hanger installation at Clinton. Since my last letter, we have made further progress in documenting constructed hanger details and in controlling field construction work. However, we have not reached the point of submitting a final report since certain design and construction items are still being resolved and carried out.

We expect to submit a final report on this matter at the end of April 1981. ,

Sincerely, e

l/

. och Vice President AJB/ph cc: H. H. Livermore, NRC Resident Inspector

. yDirector, Office of I&E, USNRC, Washington, D.C., 20013 f

Director-Quality Assurance 810809 0 M

$