Letter Sequence Other |
---|
|
|
MONTHYEARML0613200182006-05-0202 May 2006 Revision to the Request for Amendment to the Technical Specifications (TS) - Deletion of Requirement Related to NRC Approval of Engineering Evaluation for Elevated Relief Valve Discharge Pipe Temperature Project stage: Request ML0618400322006-08-0404 August 2006 Issuance of License Amendment 222 Deletion of Requirement Related to NRC Approval of Engineering Evaluation for Elevated Relief Valve Discharge Pipe Temperature Project stage: Approval ML0622301672006-08-0404 August 2006 Tech Spec Pages for Amendment 222 Deletion of Requirement Related to NRC Approval of Engineering Evaluation for Elevated Relief Valve Discharge Pipe Temperature Project stage: Other 2006-05-02
[Table View] |
Tech Spec Pages for Amendment 222 Deletion of Requirement Related to NRC Approval of Engineering Evaluation for Elevated Relief Valve Discharge Pipe TemperatureML062230167 |
Person / Time |
---|
Site: |
Pilgrim |
---|
Issue date: |
08/04/2006 |
---|
From: |
NRC/NRR/ADRO/DORL/LPLI-1 |
---|
To: |
|
---|
References |
---|
TAC MC7053 |
Download: ML062230167 (3) |
|
|
---|
Category:Letter
MONTHYEARML24240A1692024-09-18018 September 2024 Cy 2023 Summary of Decommissioning Trust Fund Status IR 05000293/20240022024-08-21021 August 2024 NRC Inspection Report No. 05000293/2024002 PNP 2024-030, Update Report for Holtec Decommissioning International Fleet Decommissioning Quality Assurance Program Rev. 3 and Palisades Transitioning Quality Assurance Plan, Rev 02024-08-0202 August 2024 Update Report for Holtec Decommissioning International Fleet Decommissioning Quality Assurance Program Rev. 3 and Palisades Transitioning Quality Assurance Plan, Rev 0 ML24151A6482024-06-0303 June 2024 Changes in Reactor Decommissioning Branch Project Management Assignments for Some Decommissioning Facilities ML24129A1042024-05-26026 May 2024 Preapplication Readiness Assessment Plan for the Holtec Decommissioning International License Termination Plan ML24136A2382024-05-14014 May 2024 Annual Radiological Environmental Operating Report for 2023 ML24135A3212024-05-14014 May 2024 Annual Radioactive Effluent Release Report, January 1 Through December 31, 2023 IR 05000293/20240012024-05-0707 May 2024 NRC Inspection Report No. 05000293/2024001 L-24-009, HDI Annual Occupational Radiation Exposure Data Reports - 20232024-04-29029 April 2024 HDI Annual Occupational Radiation Exposure Data Reports - 2023 L-24-010, Request for Preapplication Readiness Assessment of the Draft License Termination Plan2024-04-22022 April 2024 Request for Preapplication Readiness Assessment of the Draft License Termination Plan L-24-007, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations – Holtec Decommissioning International, LLC (HDI)2024-03-29029 March 2024 Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations – Holtec Decommissioning International, LLC (HDI) IR 05000293/20230032024-02-29029 February 2024 NRC Inspection Report Nos. 05000293/2023003 and 05000293/2023004 L-24-002, Late LLRW Shipment Investigation Report Pursuant to 10 CFR 20, Appendix G2024-02-0202 February 2024 Late LLRW Shipment Investigation Report Pursuant to 10 CFR 20, Appendix G ML23342A1182024-01-0909 January 2024 Independent Spent Fuel Storage Installation Security Inspection Plan L-23-019, Proof of Financial Protection 10 CFR 140.152023-12-18018 December 2023 Proof of Financial Protection 10 CFR 140.15 ML23334A1822023-11-30030 November 2023 Biennial Report for the Defueled Safety Analysis Report Update, Technical Specification Bases Changes, 10 CFR 50.59 Evaluation Summary, and Regulatory Commitment Change Summary – November 2021 Through October 2023 L-23-012, Master Decommissioning Trust Agreement Changes for Indian Point Nuclear Generating Units 1, 2 and 3, Pilgrim Nuclear Power Station, Palisades Nuclear Plant and the Non-Qualified Trust for Big Rock Point2023-11-13013 November 2023 Master Decommissioning Trust Agreement Changes for Indian Point Nuclear Generating Units 1, 2 and 3, Pilgrim Nuclear Power Station, Palisades Nuclear Plant and the Non-Qualified Trust for Big Rock Point ML23306A0992023-11-0202 November 2023 and Indian Point Energy Center, Notification of Changes in Schedule in Accordance with 10 CFR 50.82(a)(7) IR 05000293/20234012023-08-31031 August 2023 NRC Inspection Report No. 05000293/2023401 & 2023001 (Cover Letter Only) IR 05000293/20230022023-08-0404 August 2023 NRC Inspection Report No. 05000293/2023002 L-23-008, Correction to Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations Holtec Decommissioning International, LLC (HDI)2023-05-23023 May 2023 Correction to Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations Holtec Decommissioning International, LLC (HDI) ML23135A2152023-05-15015 May 2023 Annual Radioactive Effluent Release Report, January 1 Through December 31, 2022 ML23136A7792023-05-15015 May 2023 Annual Radiological Environmental Operating Report, January 1 Through December 31, 2022 L-23-004, HDI Annual Occupational Radiation Exposure Data Reports - 20222023-04-24024 April 2023 HDI Annual Occupational Radiation Exposure Data Reports - 2022 L-23-003, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2023-03-31031 March 2023 Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations ML23088A0382023-03-29029 March 2023 Stations 1, 2, & 3, Palisades Nuclear Plant, and Big Rock Point - Nuclear Onsite Property Damage Insurance ML23069A2782023-03-13013 March 2023 Request for Scoping Comments Concerning the Environmental Review of Monticello Nuclear Generating Plant, Unit 1 Subsequent License Renewal Application ML22361A1022023-02-24024 February 2023 Reactor Decommissioning Branch Project Management Changes for Some Decommissioning Facilities and Establishment of Backup Project Manager for All Decommissioning Facilities IR 05000293/20220042023-02-15015 February 2023 NRC Inspection Report No. 05000293/2022004 ML22356A0712023-01-31031 January 2023 Issuance of Exemption for Pilgrim Nuclear Power Station ISFSI Regarding Annual Radioactive Effluent Release Report - Cover Letter ML22347A2782022-12-21021 December 2022 Independent Spent Fuel Storage Installation Security Inspection Plan Dated December 21, 2022 L-22-042, Oyster, Pilgrim, Indian Point, Palisades and Big Rock Point - Proof of Financial Protection 10 CFR 140.152022-12-14014 December 2022 Oyster, Pilgrim, Indian Point, Palisades and Big Rock Point - Proof of Financial Protection 10 CFR 140.15 L-22-041, Supplemental Information to Enhance Exemption Request Detail for Pilgrim ISFSI Annual Radioactive Effluent Release Report Due Date Extension2022-12-0909 December 2022 Supplemental Information to Enhance Exemption Request Detail for Pilgrim ISFSI Annual Radioactive Effluent Release Report Due Date Extension IR 05000293/20220032022-11-18018 November 2022 NRC Inspection Report No. 05000293/2022003 L-22-036, Decommissioning Trust Fund Agreement2022-11-0808 November 2022 Decommissioning Trust Fund Agreement ML22276A1762022-10-24024 October 2022 Decommissioning International Proposed Revisions to the Quality Assurance Program Approval Forms for Radioactive Material Packages ML22266A1922022-09-23023 September 2022 and Pilgrim Nuclear Power Station - Request to Withdraw Prior Submissions from NRC Consideration ML22272A0352022-09-22022 September 2022 S. Lynch-Benttinen Letter Regarding U.S. Citizen Intent to Sue U.S. Fish and Wildlife and NOAA Fisheries Representing the Endangered Species (Na Right Whale) Which Will Be Adversely Affected by Holtec International Potential Actions ML22269A4202022-09-22022 September 2022 Citizen Lawsuit ML22241A1122022-08-29029 August 2022 Request for Exemption from 10 CFR 72.212(a)(2), (b)(2), (b)(3), (b)(4), (B)(5)(i), (b)(11), and 72.214 for Pilgrim ISFSI Annual Radioactive Effluent Release Report IR 05000293/20220022022-08-12012 August 2022 NRC Inspection Report No. 05000293/2022002 ML22215A1772022-08-0303 August 2022 Decommissioning International (HDI) Proposed Revisions to the Quality Assurance Program Approval Forms for Radioactive Material Packages ML22221A2592022-08-0101 August 2022 LTR-22-0217-1-NMSS - Town of Duxbury Letter Opposing the Irradiated Water Release from Pilgrim (Docket No. 05000293) ML22206A1512022-08-0101 August 2022 NRC Office of Investigations Case Nos. 1-2022-002 & 1-2022-006 ML22175A1732022-07-28028 July 2022 LTR-22-0153-1 - Response Letter to D. Turco, Cape Downwinders, from A. Roberts, NRC, Regarding Holtec-Pilgrim Plans to Dump One Million Gallons of Radioactive Waste Into Cape Cod Bay ML22193A1662022-07-28028 July 2022 LTR-22-0154-1 - Heather Govern, VP, Clean Air and Water Program, Et Al., Letter Regarding Radioactive Wastewater Disposal from the Pilgrim Nuclear Power Station (Docket No. 05000293) ML22154A4882022-06-0101 June 2022 Letter from Conservation Law Foundation Regarding Irradiated Water Release from Pilgrim ML22154A1622022-05-26026 May 2022 Letter and Email from Save Our Bay/Diane Turco Regarding Irradiated Water Release from Pilgrim ML22136A2602022-05-16016 May 2022 Submittal of Annual Radiological Environmental Operating Report for January 1 Through December 31, 2021 ML22136A2572022-05-16016 May 2022 Submittal of Annual Radioactive Effluent Release Report for January 1 Through December 31, 2021 2024-09-18
[Table view] Category:Technical Specifications
MONTHYEARML20328A2972020-12-0101 December 2020 Amendment No. 253 - Non-Safeguards Version ML19276C4202020-01-0202 January 2020 Issuance of Amendment No. 252, Request to Remove Cyber Security Plan Requirements for the Permanently Defueled Condition ML19235A0502019-08-27027 August 2019 Issuance of Amendment No. 249 Order Approving Direct Transfer of Renewed Facility Operating License and ISFSI General License and Conforming Amendment ML17163A1812017-05-25025 May 2017 Supplemental to Technical Specifications Proposed Change - Administrative Controls for Permanently Defueled Condition ML17053A4682017-02-14014 February 2017 Technical Specifications Proposed Change - Administrative Controls for Permanently Defueled Condition ML16363A2662017-01-10010 January 2017 Correction to Amendment No. 234 Change in Technical Specification Measurement Frequency from 18 Months to 24 Months ML16250A2232016-10-28028 October 2016 Issuance of Amendments Proposed Changes to Emergency Plan to Revise Training for the on - Shift Chemistry Technician ML15114A0212015-05-0606 May 2015 Issuance of Amendment Regarding the Minimum Critical Power Ratio License Amendment Request ML14272A0702015-03-12012 March 2015 Issuance of Amendment 242 Re Revision to Technical Specification 2.1, Safety Limits to Resolve Pressure Regulator Fail-Open Transient ML14295A6852014-10-31031 October 2014 Issuance of Amendment Regarding Heavy Loads to Facilitate Dry Storage Handling Operations ML14259A3812014-09-11011 September 2014 Supplement to Proposed License Amendment Request to Modify Technical Specification 4.3.4, Heavy Loads to Facilitate Dry Storage Handling Operations ML13108A2172013-04-0505 April 2013 Proposed License Amendment: Revision to Technical Specification 2.1, Safety Limits to Resolve Pressure Regulator Fail-Open (PRFO) Transient Reported by General Electric Nuclear Energy in Accordance with 10 CFR 21.21(d) CNRO-2012-00009, Entergy Responses to Request for Additional Information Regarding Changes to the Quality Assurance Program Manual & Associated Plant Technical Specifications Re Staff Qualifications2012-11-20020 November 2012 Entergy Responses to Request for Additional Information Regarding Changes to the Quality Assurance Program Manual & Associated Plant Technical Specifications Re Staff Qualifications ML12005A1982011-12-29029 December 2011 Cycle-Specific License Amendment Request for Rod Worth Minimizer (RWM) Bypass Allowance to Allow Reactor Startup ML0731004782007-11-0505 November 2007 Technical Specifications, Issuance of Amendment Control Rod Operability, Scram Insertion Time, and Control Rod Accumulator Requirements ML0726101972007-09-18018 September 2007 Technical Specifications, Adoption of Technical Specification Task Force (TSTF) Change TSTF-372, the Addition of Limiting Condition for Operation (LCO) 3.0.8 on the Inoperability of Snubbers ML0726102002007-05-17017 May 2007 Technical Specifications, Corrected Page II (Fixed Administrative Error) ML0715605422007-04-25025 April 2007 Tech Spec Pages for Amendment 228 Single Control Rod Withdrawal Allowances ML0714303052007-04-25025 April 2007 Technical Specifications, Limiting Conditions for Operation ML0708603592007-03-26026 March 2007 Technical Specifications, Issuance of License Amendment 226 Adoption of Technical Specification Task Force (TSTF) Change TSTF-484 Use of TS 3.10.1 for Scram Time Testing Activities. ML0708603392007-02-22022 February 2007 Technical Specifications, Modify the TSs to Extend the Use of the Current Pressure-Temperature Limits as Specified in TS Figures 3.6.1, 3.6.2, and 3.6.3 Through the End of Operating Cycle 18 ML0702302932007-01-15015 January 2007 Proposed Change to Applicability of Pilgrim'S Pressure - Temperature Curves as Described in Technical Specification Figures 3.6.1, 3.6.2, and 3.6.3, Revision 1 ML0631303512006-11-0202 November 2006 Application for Technical Specification (TS) Change to Add LCO 3.0.8 on the Inoperability of Snubbers (and Adoption of TS Bases for LCO 3.0.8) Using the Consolidated Line Item Improvement Process (CLIIP) ML0626405822006-09-20020 September 2006 Tech Spec Pages for Amendment 225 Regarding Revised Reactor Coolant System Leakage Detection Instrumentation Requirements and Actions ML0626202402006-09-14014 September 2006 Technical Specification Pages Re Relocation of Technical Specifications Structural Integrity Requirements to Final Safety Analysis Report ML0624904892006-08-30030 August 2006 Technical Specification Amendment Request to Relocate Specifications Not Meeting the Criteria of 10 CFR 50.36(c)(2)(ii), Revision 1, ML0622800132006-08-0909 August 2006 Tech Spec Pages for Amendment 223 Regarding Administrative Changes and Relocation of Certain Technical Specification Responsibilities ML0622301672006-08-0404 August 2006 Tech Spec Pages for Amendment 222 Deletion of Requirement Related to NRC Approval of Engineering Evaluation for Elevated Relief Valve Discharge Pipe Temperature ML0618704692006-06-30030 June 2006 Technical Specifications Amendment Request to Revise the Surveillance Requirements for the High Pressure Coolant Injection (HPCI) and Reactor Core Isolation Cooling (RCIC) Systems ML0613000952006-05-0505 May 2006 Correction to Amendment No. 221 Revised Rod Worth Minimizer Bypass Allowances - Technical Specifications ML0610702152006-04-13013 April 2006 Technical Specification Page, Deletes the Main Steam Isolation Valve Twice Per Week Partial Stroke Testing Surveillance Specified in Technical Specification 4.7.A.2.b.1.c ML0610702042006-04-13013 April 2006 Technical Specification Page Re Revised Rod Worth Minimizer Bypass Allowances ML0610908322006-04-12012 April 2006 Proposed License Amendment to Change Technical Specification 3.6.A.2, Pressure-Temperature Limit Curves ML0610701672006-04-12012 April 2006 Tech Spec Pages for Amendment 219 Regarding Single Recirculation Loop Operation ML0611402652006-04-10010 April 2006 Technical Specification Pages Re Revised Applicability for Containment Oxygen and Differential Pressure Limits ML0524301522005-08-29029 August 2005 Technical Specification Pages Re Surveillance Frequency Improvements ML0521400792005-07-29029 July 2005 Technical Specifications, Revised Action for Scram Discharge Volume Vent and Drain Valves ML0515204742005-05-24024 May 2005 Technical Specifications Amendment Request to Revise Primary Containment Oxygen Concentration and Drywell-to-Suppression Chamber Differential Pressure Applicability Requirements ML0515204582005-05-24024 May 2005 Technical Specifications Amendment Request for Rod Worth Minimizer (RWM) Bypass Allowances ML0515204732005-05-24024 May 2005 Request for Amendment to the Technical Specifications to Delete Requirement Related to NRC Approval of Engineering Evaluation for Elevated Safety Relief Valve Discharge Pipe Temperature ML0512200952005-04-28028 April 2005 Technical Specifications, Eliminates Secondary Containment Operability Requirements When Handling Sufficiently Decayed Irradiated Fuel or Performing Core Alterations ML0510400322005-04-12012 April 2005 Technical Specifications, Revision to Surveillance Requirement Frequency for Containment and Suppression Pool Spray Headers and Nozzles ML0509004102005-03-30030 March 2005 Technical Specifications, Allows One-time Extension of Appendix J Type a Integrated Leakage Rate Test Interval ML0507601772005-03-16016 March 2005 Tech Spec Pages for Amendment No. 211, Revise Reactor Vessel Hydrostatic and Leak Testing Requirements ML0503800052005-02-0202 February 2005 Tech Spec Page for Amendment 210 Changes to Technical Specifications Table 3.2.C-1 ML0500701552005-01-0505 January 2005 Technical Specification Pages for Amendment No. 209 to License No. DPR-35 ML0423206092004-08-17017 August 2004 Technical Specifications, Issuance of Amendment Re.: Multiple Control Rod Removal, Limiting Condition for Operation 3/4.10.D ML0420502772004-07-22022 July 2004 Tech Spec Pages for Amendment 206 Elimination of Requirements for Hydrogen Analyzers ML0403307902004-01-30030 January 2004 License Amendment, Tech Spec Pages ML0332100752003-11-14014 November 2003 Revised TS Page 5.0-7, Eliminating Requirements for Post-Accident Sampling System 2020-12-01
[Table view] |
Text
B. Technical Specifications The Technical Specifications contained in Appendix A, as revised through Amendment No. 222 , are hereby incorporated in the license. The licensee shall operate the facility in accordance with the Technical Specifications.
C. Records ENO shall keep facility operating records in accordance with the requirements of the Technical Specifications.
D. Equalizer Valve Restriction - DELETED E. Recirculation Loop Inoperable - DELETED F. Fire Protection ENO shall implement and maintain in effect all provisions of the approved fire protection program as described in the Final Safety Analysis Report for the facility and as approved in the SER dated December 21, 1978 as supplemented subject to the following provision:
ENO may make changes to the approved fire protection program without prior approval of the Commission only if those changes would not adversely affect the ability to achieve and maintain safe shutdown in the event of a fire.
G. Physical Protection The licensee shall fully implement and maintain in effect all provisions of the Commission-approved physical security, training and qualification, and safeguards contingency plans including amendments made pursuant to provisions of the Miscellaneous Amendments and Search Requirements revisions to 10 CFR 73.55 (51 FR27817 and 27822) and to the authority of 10 CFR 50.90 and 10 CFR 50.54(p). The combined set of plans, which contain Safeguards Information protected under 10 CFR 73.21, is entitled: "Pilgrim Nuclear Power Station Physical Security, Training and Qualification, and Safeguards Contingency Plan, Revision 0" submitted by letter dated October 13, 2004.
Amendment 244, 24-6, 246, 24-7, 2-14,
LIMING CONDITIONS FOR OPERATION SURVEILLANCE REQUIREMENTS 3.6 PRIMARY SYSTEM BOUNDARY (Cont) 4.6 PRIMARY SYSTEM BOUNDARY (Cont)
- c. With no required leakage D. Safety and Relief Valves detection systems Operable, be in Cold Shutdown within 1. Testing of safety and relief/safety 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />. valves shall be in accordance with 3.13.
D. Safety and Relief Valves
- 2. At least one of the relief/safety valves
- 1. During reactor power operating shall be disassembled and inspected conditions and prior to reactor startup each refueling outage.
from a Cold Condition, or whenever reactor coolant pressure is greater 3. Whenever the safety relief valves are than 104 psig and temperature required to be operable, the greater than 3400F, both safety discharge pipe temperature of each valves and the safety modes of all safety relief valve shall be logged relief valves shall be operable. The daily.
nominal setpoint for the relief/safety valves shall be selected between 4. Instrumentation shall be calibrated 1095 and 1115 psig. All relief/safety and checked as indicated in Table valves shall be set at this nominal 4.2.F.
setpoint +/- 11 psi. The safety valves shall be set at 1240 psig +/- 13 psi.
- 2. If Specification 3.6.D.1 is not met, an orderly shutdown shall be initiated and the reactor coolant pressure shall be below 104 psig within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.
NOTE Technical Specifications 3.6.D.3 -
3.6.D.5 apply to the two Stage Target Rock relief valves.
- 3. If the temperature of any safety relief discharge pipe exceeds 212°F during normal reactor power operation for a period of greater than 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />, an engineering evaluation shall be performed justifying continued operation for the corresponding temperature increases.
Amendment No. 2, 66,88, 133, 139,*1, 9 222 3/4.6-6
LIMITING CONDITIONS FOR OPERATION SURVEILLANCE REQUIREMENTS 3.6 PRIMARY SYSTEM BOUNDARY (Cont) 4.6 PRIMARY SYSTEM BOUNDARY (Cont)
D. Safety Relief Valves (Con't)
- 4. Any safety relief valve whose discharge pipe temperature exceeds 212OF for 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> or more shall be removed at the next cold shutdown of 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> or more, tested in the as-found condition, and recalibrated as necessary prior to reinstallation.
- 5. The limiting conditions of operation for the instrumentation that monitors tail pipe temperature are given in Table 3.2-F.
E. Jet Pumps
- 1. Whenever the reactor is in the Startup or Run Modes, all jet pumps shall be Operable. If it is determined that a jet pump is inoperable, the reactor shall be in Hot Shutdown within 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />. E. Jet Pumps NOTES
- 1. Not required to be performed until 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> after the associated recirculation loop is in operation.
- 2. Not required to be performed until 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> after >25% Rated Thermal Power.
Whenever there is recirculation flow with the reactor in the Startup or Run Modes, jet pump operability shall be checked daily by verifying at least one of the following criteria (1, 2, or 3) is satisfied for each operating recirculation loop:
- 1. Recirculation pump flow to speed ratio differs by < 5% from established patterns, and jet pump loop flow to recirculation pump speed ratio differs by < 5% from established patterns.
- 2. Each jet pump diffuser to lower plenum differential pressure differs by < 20% from established patterns.
- 3. Each jet pump flow differs by < 10% from established patterns.
Amendment No. 46,66, 71, 93, 13, 205,21*, 222 314.6-7