MONTHYEARIR 05000346/20230902023-08-0101 August 2023 EA-23-002 Davis-Besse Nuclear Power Station - NRC Inspection Report No. 05000346/2023090 (Public) IR 05000346/20210922022-03-0101 March 2022 EA-21-155 Davis Besse - Final Significance Determination of White Finding, Notice of Violation and Assessment Follow Up Letter, NRC Inspection Report 50000346/2021092 ML22031A1712022-01-31031 January 2022 EA-21-105; Davis-Besse Final Determination for a Greater than Green Finding Letter and Enclosure 1 (Public) IR 05000346/20210912021-12-17017 December 2021 NRC Inspection Report (05000346/2021091) Preliminary Greater than Green Finding ML21340A2212021-12-0909 December 2021 NRC Inspection Report (05000346/2021090) Preliminary White Finding ML20275A0482020-10-0101 October 2020 EA-20-068 Davis Besse Licensee Closure Letter ML18099A0742018-04-10010 April 2018 EN-18-006, Issuance of Final Significance Determination and Notice of Violation (EA-18-008) L-16-347, Action for Confirmatory Order EA-16-0222016-12-0101 December 2016 Action for Confirmatory Order EA-16-022 ML16077A3722016-03-17017 March 2016 EA-15-215; Results of Nuclear Regulatory Commission Investigation Report 3-2015-002 IR 05000346/20144072014-10-22022 October 2014 EA-14-129 Final Significance Determination for a Security-Related Greater than Green Finding and Notice of Violation; NRC Inspection Report No. 05000346/2014407; Davis-Besse Nuclear Power Station (Cover Letter Only) ML12314A2812012-11-0808 November 2012 EA-12-179, Davis-Besse, Final Significance Determination of a Security-Related Greater than Green Finding and Notice of Violation - Cover Letter Only IR 05000346/20124052012-11-0808 November 2012 EA-12-179, Davis-Besse, Final Significance Determination of a Security-Related Greater than Green Finding and Notice of Violation - Cover Letter Only IR 05000346/20100072010-04-30030 April 2010 EA-09-332, Davis-Besse Nuclear Power Station, Notice of Violation, NRC Inspection Report No. 05000346-10-007(DRS) IR 05000346/20095032009-12-28028 December 2009 IR 05000346-09-503(DRS), on 08/04/2009 - 11/23/2009; Davis-Besse Nuclear Power Station; Event Follow-up Inspection ML0936208142009-12-28028 December 2009 IR 05000346-09-503(DRS), on 08/04/2009 - 11/23/2009; Davis-Besse Nuclear Power Station; Event Follow-up Inspection IR 05000346/20060052007-01-30030 January 2007 IR 05000346-06-005; 10/1/2006 - 12/31/2006; Davis-Besse Nuclear Power Station; Maintenance Risk Assessments and Emergent Work Control, As-Low-As-Reasonably-Achievable (ALARA) Planning and Controls ML1026701392005-02-25025 February 2005 Choice Letter - Apparent Violation of Employee Protection Requirements (Office of Investigations Report Nos. 3-2004-006 and 3-2004-018), Davis Besse ML0406411712004-03-0808 March 2004 EA-03-214, CAL No. 3-02-001, Approval to Restart the Davis-Besse Nuclear Power Station Closure of Confirmatory Action Letter, and Issuance of Confirmatory Order ML0328017062003-10-0707 October 2003 EA-03-131, Davis-Besse, Notice of Violation IR 05000346/20020162003-01-0707 January 2003 IR 05000346-02-016, IR 05000346-02-006, on 09/30-12/13/2002, Davis-Besse, Special Inspection - Substantial Potential for an Overexposure of Occupational Workers and Uncontrolled Release of Radioactive Material to the Environment 2023-08-01
[Table view] Category:Letter
MONTHYEARIR 05000346/20240022024-08-0101 August 2024 Integrated Inspection Report 05000346/2024002 IR 05000346/20244012024-07-30030 July 2024 Security Baseline Inspection Report 05000346/2024401 ML24208A0962024-07-25025 July 2024 57243-EN 57243 - Rssc Wire & Cable LLC, Dba Marmon - Part 21 Notification L-24-032, Cycle 23 and Refueling Outage 23 Inservice Inspection Summary Report2024-07-15015 July 2024 Cycle 23 and Refueling Outage 23 Inservice Inspection Summary Report L-24-063, License Amendment Request to Remove the Table of Contents from the Technical Specifications2024-07-0808 July 2024 License Amendment Request to Remove the Table of Contents from the Technical Specifications L-24-024, Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling System Evaluation Models2024-06-19019 June 2024 Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling System Evaluation Models L-23-214, Submittal of Relief Request for Impractical American Society of Mechanical Engineers Boiler and Pressure Vessel Code Section XI Examination Requirements2024-06-0505 June 2024 Submittal of Relief Request for Impractical American Society of Mechanical Engineers Boiler and Pressure Vessel Code Section XI Examination Requirements L-24-019, Unit No.1 - Report of Facility Changes, Tests, and Experiments2024-05-22022 May 2024 Unit No.1 - Report of Facility Changes, Tests, and Experiments ML24142A3532024-05-21021 May 2024 Station—Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection L-24-111, Response to Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-05-15015 May 2024 Response to Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations L-24-072, Combined Annual Radiological Environmental Operating Report and Radioactive Effluent Release Report - 20232024-05-15015 May 2024 Combined Annual Radiological Environmental Operating Report and Radioactive Effluent Release Report - 2023 L-24-031, Unit No.1 - Steam Generator Tube Circumferential Crack Report - Spring 2024 Refueling Outage2024-05-14014 May 2024 Unit No.1 - Steam Generator Tube Circumferential Crack Report - Spring 2024 Refueling Outage IR 05000346/20240012024-05-0303 May 2024 Integrated Inspection Report 05000346/2024001 L-24-069, Occupational Radiation Exposure Report for Year 20232024-04-30030 April 2024 Occupational Radiation Exposure Report for Year 2023 L-24-018, Submittal of Core Operating Limits Report, Cycle 24, Revision 02024-04-16016 April 2024 Submittal of Core Operating Limits Report, Cycle 24, Revision 0 IR 05000346/20243012024-02-0202 February 2024 NRC Initial License Examination Report 05000346/2024301 IR 05000346/20230042024-01-31031 January 2024 Integrated Inspection Report 05000346/2023004 ML23313A1352024-01-17017 January 2024 Authorization and Safety Evaluation for Alternative Request RP 5 for the Fifth 10 Year Interval Inservice Testing Program ML23353A1192023-12-19019 December 2023 Operator Licensing Examination Approval Davis Besse Nuclear Power Station, January 2024 L-23-260, Corrections to the 2022 Combined Annual Radiological Environmental Operating Report and Radioactive Effluent Release Report for the Davis-Besse Nuclear Power Station2023-12-0707 December 2023 Corrections to the 2022 Combined Annual Radiological Environmental Operating Report and Radioactive Effluent Release Report for the Davis-Besse Nuclear Power Station L-23-243, Independent Spent Fuel Storage Installation - Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-12-0606 December 2023 Independent Spent Fuel Storage Installation - Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23338A3172023-12-0606 December 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000346/2024001 IR 05000346/20234032023-11-0202 November 2023 Security Baseline Inspection Report 05000346/2023403 ML23293A0612023-11-0101 November 2023 Letter to the Honorable Marcy Kaptur, from Chair Hanson Responds to Letter Regarding Follow Up on Concerns Raised by Union Representatives During the June Visit to the Davis-Besse Nuclear Power Plant L-23-215, Changes to Emergency Plan2023-10-19019 October 2023 Changes to Emergency Plan ML23237B4222023-09-28028 September 2023 Energy Harbor Nuclear Corp. - Vistra Operations Company LLC - Letter Regarding Order Approving Transfer of Licenses and Draft Conforming License Amendments ML23269A1242023-09-27027 September 2023 Request for Withholding Information from Public Disclosure IR 05000346/20234012023-09-13013 September 2023 Security Baseline Inspection Report 05000346/2023401 (Public) L-23-205, Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments2023-09-12012 September 2023 Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments L-23-172, Quality Assurance Program Manual2023-08-31031 August 2023 Quality Assurance Program Manual IR 05000346/20230112023-08-30030 August 2023 Biennial Problem Identification and Resolution Inspection Report 05000346/2023011 ML23129A1722023-08-25025 August 2023 Request for Withholding Information from Public Disclosure for Beaver Valley Power Station, Units 1 and 2; Davis Besse Nuclear Power Station, Unit 1; and Perry Nuclear Power Plant, Unit 1 IR 05000346/20230052023-08-24024 August 2023 Updated Inspection Plan for Davis-Besse Nuclear Power Station (Report 05000346/2023005) L-23-188, Energy Harbor Nuclear Corp., Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments2023-08-0707 August 2023 Energy Harbor Nuclear Corp., Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments IR 05000346/20230502023-08-0303 August 2023 Special Inspection Report 05000346/2023050 IR 05000346/20230902023-08-0101 August 2023 EA-23-002 Davis-Besse Nuclear Power Station - NRC Inspection Report No. 05000346/2023090 (Public) ML23178A2742023-08-0101 August 2023 Letter to the Honorable Marcy Kaptur from Chair Hanson Responds to Letter Regarding the License Transfer Application for the Davis-Besse Nuclear Power Station L-23-175, Submittal of Fifth Ten Year Inservice Testing Program2023-08-0101 August 2023 Submittal of Fifth Ten Year Inservice Testing Program IR 05000346/20230022023-07-27027 July 2023 Integrated Inspection Report 05000346/2023002 ML23193A7842023-07-13013 July 2023 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000346/2023402 ML23178A2422023-06-28028 June 2023 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch III ML23160A2342023-06-13013 June 2023 Confirmation of Initial License Examination IR 05000346/20235012023-06-13013 June 2023 Emergency Preparedness Biennial Exercise Inspection Report 05000346/2023501 L-23-034, 2022 Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling System Evaluation Models2023-06-13013 June 2023 2022 Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling System Evaluation Models L-23-135, Response to Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-05-31031 May 2023 Response to Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations L-23-065, Annual Financial Report2023-05-22022 May 2023 Annual Financial Report ML23124A1742023-05-17017 May 2023 Energy Harbor Fleet Vistra License Transfer - Request for Withholding Information from Public Disclosure for Commance Peak Plant, Units 1 & 2, Beaver Valley Station, Units 1 & 2, Davis Besse Station, Unit 1 and Perry Plant, Unit 1 ML23129A0112023-05-16016 May 2023 Notice of Consideration of Approval of Indirect and Direct License Transfer for Comanche Peak Plant, Units 1 & 2, Beaver Valley Station, Units 1 & 2, Davis Besse Station, Unit 1 and Perry Plant, Unit 1 (EPID L-2023-LLM-0000) (Letter) ML23131A2732023-05-15015 May 2023 Notification of NRC Supplemental Inspection 95001 and Request for Information L-23-131, Readiness for Resumption of NRC Supplemental Inspection2023-05-12012 May 2023 Readiness for Resumption of NRC Supplemental Inspection 2024-08-01
[Table view] |
Text
UNITED STATES ctober 22, 2014
SUBJECT:
FINAL SIGNIFICANCE DETERMINATION FOR A SECURITY-RELATED GREATER THAN GREEN FINDING AND NOTICE OF VIOLATION; NRC INSPECTION REPORT NO. 05000346/2014407; DAVIS-BESSE NUCLEAR POWER STATION
Dear Mr. Lieb:
This letter provides the final significance determination of the preliminary Greater than Green finding identified in our previous communication dated September 18, 2014, which included U.S. Nuclear Regulatory Commission (NRC) Inspection Report No. 05000346/2014406. This Greater than Green finding was discussed in detail in that inspection report.
In a telephone conversation with Mr. Donald Funk of NRC, Region III, on September 26, 2014, Mr. Gerry Wolf of your staff indicated that FirstEnergy Nuclear Operating Company (FENOC)
did not contest the characterization of this finding and declined the opportunity to discuss this issue in a Regulatory Conference or to provide a written response.
After considering the information developed during the inspection, the NRC has concluded that the inspection finding is of at least low to moderate security significance, and is appropriately characterized as Greater than Green. Because this issue has been determined to be beyond the licensee response column, we will use the NRC's Action Matrix to determine the most appropriate NRC response. We will notify you, by separate correspondence, of that determination.
According to NRC Inspection Manual Chapter (IMC) 0609, Attachment 2, appeal rights only apply to those licensees that have either attended a regulatory conference or submitted a written response to the preliminary determination letter.
The NRC has also determined that the condition discussed is a violation of NRC requirements, as cited in the Notice of Violation (Notice) provided in the enclosure (Non-public). In accordance with the NRC Enforcement Policy, the Notice is considered escalated enforcement action because it is associated with a Greater than Green finding.
The enclosure contains Sensitive Unclassified Non-Safeguards Information. Upon separation, this cover letter is decontrolled. You are required to respond to this letter and should follow the instructions specified in the enclosed Notice when preparing your response. If you have additional information that you believe the NRC should consider, you may provide it in your response to the Notice. The NRC will use your response, in part, to determine whether further enforcement action is necessary to ensure compliance with regulatory requirements.
For administrative purposes, this letter is issued as NRC Inspection Report No. 05000346/2014407(DRS). Additionally, apparent violation (AV)05000346/2014406-01 is now closed, and violation (VIO)05000346/2014406-01 is opened in its place.
In accordance with 10 CFR 2.390 of the NRC's Rules of Practice, a copy of this letter will be made available electronically for public inspection in the NRC Public Document Room or from the NRCs Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html. The NRC also includes significant enforcement actions on its Web site at http://www.nrc.gov/reading-rm/doc-collections/enforcement/actions/. However, because the material in the enclosure is considered security-related information, as defined in 10 CFR 2.390(d)(1), its disclosure to unauthorized individuals could present a security vulnerability. Therefore, the material in this enclosure will not be made available electronically for public inspection. If Security Related Information is necessary to provide an acceptable response, please mark your entire response Security-Related Information in accordance with 10 CFR 2.390(d)(1) and follow the instructions for withholding in 10 CFR 2.390(b)(1). In accordance with 10 CFR 2.390(b)(1)(ii), the NRC is waiving the affidavit requirements for your response.
Sincerely,
/RA Darrell J. Roberts Acting for/
Cynthia D. Pederson Regional Administrator Docket No. 50-346 License No. NPF-3 Enclosure:
Notice of Violation (non-public)
cc w/ encl: M. Bear, State Liaison Officer, Ohio Emergency Management Agency cc w/o encl: Distribution via ListServ