MONTHYEARIR 05000334/20230112023-12-0404 December 2023 Age-Related Degradation Inspection Report 05000334/2023011 and 05000412/2023011 IR 05000334/20233012023-11-27027 November 2023 Initial Operator Licensing Examination Report 05000334/2023301 IR 05000334/20230032023-11-0606 November 2023 Integrated Inspection Report 05000334/2023003 and 05000412/2023003 IR 05000334/20234022023-09-29029 September 2023 Security Baseline Inspection Report 05000334/2023402 and 05000412/2023402 (Cover Letter Only) IR 05000334/20234012023-09-21021 September 2023 Cybersecurity Inspection Report 05000334/2023401 and 05000412/2023401 (Cover Letter Only) ML23243A9272023-09-19019 September 2023 Review of the Fall 2022 Steam Generator Tube Inspection Report IR 05000334/20230052023-08-31031 August 2023 Updated Inspection Plan for Beaver Valley Power Station Units 1 and 2 (Report 05000334/2023005 and 05000412/2023005) IR 05000334/20230022023-08-0909 August 2023 Integrated Inspection Report 05000334/2023002 and 05000412/2023002 ML23157A1072023-06-0707 June 2023 Request for Information and Notification of Conduct of IP 71111.21.N.04, Age-Related Degradation, Reference Inspection Report 05000334/2023011 and 05000412/2023011 IR 05000334/20230012023-05-0808 May 2023 Integrated Inspection Report 05000334/2023001 and 05000412/2023001 L-23-058, 180-Day Steam Generator Tube Inspection Report2023-03-27027 March 2023 180-Day Steam Generator Tube Inspection Report IR 05000334/20230102023-03-0808 March 2023 Biennial Problem Identification and Resolution Inspection Report 05000334/2023010 05000412/2023010 IR 05000334/20220062023-03-0101 March 2023 Annual Assessment Letter for Beaver Valley Power Station, Units 1 and 2 (Reports 05000334/2022006 and 05000412/2022006) IR 05000334/20220042023-02-0909 February 2023 Integrated Inspection Report 05000334/2022004 and 05000412/2022004 IR 05000334/20224012023-01-0909 January 2023 Security Baseline Inspection Report 05000334/2022401 and 05000412/2022401 (Cover Letter Only) ML22314A2682022-12-16016 December 2022 Review of the Fall 2021 2R22 Steam Generator Tube Inspection 180 Day Report IR 05000334/20220032022-11-10010 November 2022 Integrated Inspection Report 05000334/2022003 and 05000412/2022003 and Independent Spent Fuel Storage Installation Inspection Report 07201043/2022001 IR 05000334/20220052022-08-31031 August 2022 Updated Inspection Plan for Beaver Valley Power Station, Units 1 and 2 (Report 05000334/2022005 and 05000412/2022005) IR 05000334/20220022022-08-12012 August 2022 Integrated Inspection Report 05000334/2022002 and 05000412/2022002 IR 05000334/20224022022-08-12012 August 2022 Cyber Security Problem Identification and Resolution Inspection Report 05000334/2022402 and 05000412/2022402 (Cover Letter Only) IR 05000334/20220112022-06-29029 June 2022 Temporary Instruction 2515/194 Inspection Report 05000334/2022011 and 05000412/2022011 IR 05000334/20225012022-06-29029 June 2022 Emergency Preparedness Biennial Exercise Inspection Report 05000334/2022501 and 05000412/2022501 IR 05000412/20223012022-06-14014 June 2022 Initial Operator Licensing Examination Report 05000412/2022301 IR 05000334/20220102022-05-12012 May 2022 Design Basis Assurance Inspection (Programs) Inspection Report 05000334/2022010 and 05000412/2022010 IR 05000334/20224202022-05-11011 May 2022 Security Baseline Inspection Report 05000334/2022420 and 05000412/2022420 - Cover Letter IR 05000334/20220012022-05-10010 May 2022 Integrated Inspection Report 05000334/2022001 and 05000412/2022001 IR 05000334/20210062022-03-0202 March 2022 Annual Assessment Letter for Beaver Valley Power Station, Units 1 and 2 (Reports 05000334/2021006 and 05000412/2021006) IR 05000334/20210042022-02-14014 February 2022 Integrated Inspection Report 05000334/2021004 and 05000412/2021004 L-22-054, Steam Generator Inspection Report- Fall 2021 Refueling Outage2022-02-10010 February 2022 Steam Generator Inspection Report- Fall 2021 Refueling Outage IR 05000334/20210032021-11-0909 November 2021 Integrated Inspection Report 05000334/2021003 and 05000412/2021003 IR 05000334/20210112021-10-19019 October 2021 Temporary Instruction 2515/194 Inspection Report 05000334/2021011 and 05000412/2021011 IR 05000334/20210102021-09-29029 September 2021 Triennial Fire Protection Inspection Report 05000334/2021010 and 05000412/2021010 IR 05000334/20210052021-09-0101 September 2021 Updated Inspection Plan for the Beaver Valley Power Station, Units 1 and 2 (Report 05000334/2021005 and 05000412/2021005) IR 05000334/20214022021-08-18018 August 2021 Security Baseline Inspection Report 05000334/2021402 and 05000412/2021402 IR 05000334/20214012021-08-12012 August 2021 Material Control and Accounting Program Inspection Report 05000334/2021401 and 05000412/2021401 (Cover Letter Only) IR 05000334/20210022021-08-11011 August 2021 Integrated Inspection Report 05000334/2021002 and 05000412/2021002 IR 05000334/20210012021-05-13013 May 2021 Integrated Inspection Report 05000334/2021001 and 05000412/2021001 IR 05000334/20214032021-05-13013 May 2021 Cyber Security Problem Identification and Resolution Inspection Report 05000334/2021403 and 05000412/2021403 (Cover Letter Only) ML21097A1142021-04-19019 April 2021 Review of Steam Generator Tube Inspection Report for the Spring 2020 Refueling Outage IR 05000334/20213012021-04-0101 April 2021 Initial Operator Licensing Examination Report 05000334/2021301 IR 05000334/20210122021-03-24024 March 2021 Biennial Problem Identification and Resolution Inspection Report 05000334/2021012 and 05000412/2021012 IR 05000334/20210132021-03-0404 March 2021 Nuclear Regulatory Commission Investigation Report No. 1-2019-010 and Inspection Report 05000334/2021013 and 05000412/2021013 IR 05000334/20200062021-03-0303 March 2021 Annual Assessment Letter for Beaver Valley Power Station, Units 1 and 2 (Reports 05000334/2020006 and 05000412/2020006) IR 05000334/20200042021-02-12012 February 2021 Integrated Inspection Report 05000334/2020004 and 05000412/2020004 IR 05000334/20205012020-11-23023 November 2020 Emergency Preparedness Biennial Exercise Inspection Report 05000334/2020501 and 05000412/2020501 IR 05000334/20200032020-11-13013 November 2020 Integrated Inspection Report 05000334/2020003 and 05000412/2020003 IR 05000334/20200112020-10-26026 October 2020 Design Basis Assurance Inspection (Teams) Inspection Report 05000334/2020011 and 05000412/2020011 IR 05000334/20204012020-10-0505 October 2020 Security Baseline Inspection Report 05000334/2020401 and 05000412/2020401 (Cover Letter Only) IR 05000334/20200052020-08-31031 August 2020 Updated Inspection Plan (Inspection Report 05000334/2020005 and 05000412/2020005) IR 05000334/20200022020-08-13013 August 2020 Integrated Inspection Report 05000334/2020002 and 05000412/2020002 2023-09-29
[Table view] Category:Letter
MONTHYEARML24025A0922024-01-25025 January 2024 Requalification Program Inspection L-23-267, Submittal of Discharge Monitoring Report (Npdes), Permit No. PA00256152023-12-18018 December 2023 Submittal of Discharge Monitoring Report (Npdes), Permit No. PA0025615 IR 05000334/20230112023-12-0404 December 2023 Age-Related Degradation Inspection Report 05000334/2023011 and 05000412/2023011 L-23-229, Request for Additional Information Regarding the Spring 2023 Generic Letter 95-05 Voltage-Based Alternate Repair Criteria and Steam Generator F-Star Reports2023-11-29029 November 2023 Request for Additional Information Regarding the Spring 2023 Generic Letter 95-05 Voltage-Based Alternate Repair Criteria and Steam Generator F-Star Reports IR 05000334/20233012023-11-27027 November 2023 Initial Operator Licensing Examination Report 05000334/2023301 L-23-247, Discharge Monitoring Report (NPDES) Permit No. PA00256152023-11-17017 November 2023 Discharge Monitoring Report (NPDES) Permit No. PA0025615 IR 05000334/20230032023-11-0606 November 2023 Integrated Inspection Report 05000334/2023003 and 05000412/2023003 L-23-227, Discharge Monitoring Report (NPDES) Permit No. PA0025615 for Third Quarter 20232023-10-20020 October 2023 Discharge Monitoring Report (NPDES) Permit No. PA0025615 for Third Quarter 2023 ML23279A0612023-10-0505 October 2023 Paragon Energy Solutions LLC, Part 21 Final Report Re Potential Defect with Eaton Jd and Hjd Series Molded Case Circuit Breakers (Mccbs) ML23198A3592023-10-0202 October 2023 Issuance of Amendment Nos. 322 and 212 Analytical Methodology to the Core Operating Limits Report for a Full Spectrum Loss of Coolant Accident (EPID L-2022-LLA-0129) - Nonproprietary IR 05000334/20234022023-09-29029 September 2023 Security Baseline Inspection Report 05000334/2023402 and 05000412/2023402 (Cover Letter Only) ML23237B4222023-09-28028 September 2023 Energy Harbor Nuclear Corp. - Vistra Operations Company LLC - Letter Regarding Order Approving Transfer of Licenses and Draft Conforming License Amendments ML23269A1242023-09-27027 September 2023 Request for Withholding Information from Public Disclosure IR 05000334/20234012023-09-21021 September 2023 Cybersecurity Inspection Report 05000334/2023401 and 05000412/2023401 (Cover Letter Only) ML23263A0192023-09-20020 September 2023 Operator Licensing Examination Approval ML23243A9272023-09-19019 September 2023 Review of the Fall 2022 Steam Generator Tube Inspection Report ML23249A1842023-09-18018 September 2023 Authorization and Safety Evaluation for Alternative Request No. 2-TYP-4-RV-06 L-23-208, Submittal of Discharge Monitoring Report Cnpdes), Permit No. PA00256152023-09-14014 September 2023 Submittal of Discharge Monitoring Report Cnpdes), Permit No. PA0025615 L-23-167, Twenty-Third Refueling Outage Inservice Inspection Summary Report2023-09-13013 September 2023 Twenty-Third Refueling Outage Inservice Inspection Summary Report L-23-205, Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments2023-09-12012 September 2023 Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments IR 05000334/20230052023-08-31031 August 2023 Updated Inspection Plan for Beaver Valley Power Station Units 1 and 2 (Report 05000334/2023005 and 05000412/2023005) L-23-172, Quality Assurance Program Manual2023-08-31031 August 2023 Quality Assurance Program Manual ML23129A1722023-08-25025 August 2023 Request for Withholding Information from Public Disclosure for Beaver Valley Power Station, Units 1 and 2; Davis Besse Nuclear Power Station, Unit 1; and Perry Nuclear Power Plant, Unit 1 IR 05000334/20230022023-08-0909 August 2023 Integrated Inspection Report 05000334/2023002 and 05000412/2023002 ML23219A0592023-08-0707 August 2023 Steam Generator Inspection Reports - Spring 2023 Spring Refueling Outrage L-23-188, Energy Harbor Nuclear Corp., Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments2023-08-0707 August 2023 Energy Harbor Nuclear Corp., Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments L-23-179, Submittal of Discharge Monitoring Report, (NPDES) Permit No. PA00256152023-07-18018 July 2023 Submittal of Discharge Monitoring Report, (NPDES) Permit No. PA0025615 ML23188A0982023-07-17017 July 2023 Correction to the Safety Evaluation Issued Related to Amendment Nos. 321 and 211 Consolidate Fuel Decay Time Technical Specifications in a New Limiting Condition for Operation Titled Decay Time ML23188A0672023-07-10010 July 2023 Project Manager Assignment L-23-165, Discharge Monitoring Report (NPDES) Permit No. PA00256152023-06-26026 June 2023 Discharge Monitoring Report (NPDES) Permit No. PA0025615 L-23-139, Response to Request for Additional Information Regarding Fall 2022 180-Day Steam Generator Tube Inspection Report2023-06-13013 June 2023 Response to Request for Additional Information Regarding Fall 2022 180-Day Steam Generator Tube Inspection Report ML23157A1072023-06-0707 June 2023 Request for Information and Notification of Conduct of IP 71111.21.N.04, Age-Related Degradation, Reference Inspection Report 05000334/2023011 and 05000412/2023011 ML23143A0272023-05-23023 May 2023 Licensed Operator Positive Fitness-For-Duty Test L-23-055, Submittal of the Updated Final Safety Analysis Report, Revision 342023-05-23023 May 2023 Submittal of the Updated Final Safety Analysis Report, Revision 34 ML23102A1472023-05-22022 May 2023 Issuance of Amendment Nos. 321 and 211 Consolidate Fuel Decay Time Technical Specifications in a New Limiting Condition for Operation Titled Decay Time L-23-065, Annual Financial Report2023-05-22022 May 2023 Annual Financial Report ML23135A7872023-05-19019 May 2023 Summary of Conference Calls Regarding the Spring 2023 Steam Generator Tube Inspections L-23-137, Discharge Monitoring Report (NPDES) Permit No. PA00256152023-05-18018 May 2023 Discharge Monitoring Report (NPDES) Permit No. PA0025615 ML23124A1742023-05-17017 May 2023 Energy Harbor Fleet Vistra License Transfer - Request for Withholding Information from Public Disclosure for Commance Peak Plant, Units 1 & 2, Beaver Valley Station, Units 1 & 2, Davis Besse Station, Unit 1 and Perry Plant, Unit 1 L-23-125, Cycle 24 Core Operating Limits Report2023-05-17017 May 2023 Cycle 24 Core Operating Limits Report ML23124A3882023-05-16016 May 2023 Summary of Regulatory Audit in Support of License Amendment Request to Revise Technical Specification 5.6.3, Core Operating Limits Reports (COLR) and TS 4.2.1 Fuel Assemblies ML23129A0112023-05-16016 May 2023 Notice of Consideration of Approval of Indirect and Direct License Transfer for Comanche Peak Plant, Units 1 & 2, Beaver Valley Station, Units 1 & 2, Davis Besse Station, Unit 1 and Perry Plant, Unit 1 (EPID L-2023-LLM-0000) (Letter) L-23-132, Response to NRC Regulatory Issue Summary 2023-01 Preparation and Scheduling of Operator Licensing Examinations2023-05-10010 May 2023 Response to NRC Regulatory Issue Summary 2023-01 Preparation and Scheduling of Operator Licensing Examinations IR 05000334/20230012023-05-0808 May 2023 Integrated Inspection Report 05000334/2023001 and 05000412/2023001 L-23-129, Response to Request for Additional Information for 10 CFR 50.55a Request 2-TYP-4-RV-06 for Alternative Repair Methods for Reactor Pressure Vessel Head Penetrations2023-05-0505 May 2023 Response to Request for Additional Information for 10 CFR 50.55a Request 2-TYP-4-RV-06 for Alternative Repair Methods for Reactor Pressure Vessel Head Penetrations ML23118A3812023-04-28028 April 2023 10 CFR 50.55a Request 2-TYP-4-RV-06 for Alternative Repair Methods for Reactor Pressure Vessel Head Penetrations L-23-115, Submittal of 2022 Annual Radioactive Effluent Release Report, 2022 Annual Radiological Environmental Operating Report, and 2022 Annual Environmental Operating Report (Non-Radiological2023-04-27027 April 2023 Submittal of 2022 Annual Radioactive Effluent Release Report, 2022 Annual Radiological Environmental Operating Report, and 2022 Annual Environmental Operating Report (Non-Radiological L-23-126, Discharge Monitoring Report (Npdes), Permit No. PA00256152023-04-22022 April 2023 Discharge Monitoring Report (Npdes), Permit No. PA0025615 CP-202300181, ISFSI, Beaver Valley, Units 1 and 2, ISFSI, Davis-Besse, Unit 1, ISFSI, Perry, Unit 1, ISFSI, Corrected Affidavit for Application for Order Consenting to Transfer of Licenses and Conforming License Amendments2023-04-20020 April 2023 ISFSI, Beaver Valley, Units 1 and 2, ISFSI, Davis-Besse, Unit 1, ISFSI, Perry, Unit 1, ISFSI, Corrected Affidavit for Application for Order Consenting to Transfer of Licenses and Conforming License Amendments ML23107A2502023-04-18018 April 2023 Requalification Program Inspection 2024-01-25
[Table view] |
Text
July 11, 2019 Mr. Rod L. Penfield Site Vice President FirstEnergy Nuclear Operating Company Beaver Valley Power Station Mail Stop P-BV-SSEB P.O. Box 4, Route 168 Shippingport, PA 15077
SUBJECT:
BEAVER VALLEY POWER STATION, UNIT 2 - REVIEW OF STEAM GENERATOR TUBE INSPECTION REPORT FOR THE FALL 2018 REFUELING OUTAGE (EPID L-2019-LRO-0000)
Dear Mr. Penfield:
By letters dated January 31, 2019, and March 28, 2019 (Agencywide Documents Access and Management System (ADAMS) Accession Nos. ML19035A607 and ML19087A050, respectively), FirstEnergy Nuclear Operating Company (FENOC) submitted information summarizing the results of the fall 2018 steam generator (SG) tube inspections performed at Beaver Valley Power Station (Beaver Valley), Unit 2. The inspections were performed during Refueling Outage 20. The information was submitted in accordance with Beaver Valley Technical Specification 5.6.6.2, Unit 2 SG Tube Inspection Report.
In addition to this report, the U.S. Nuclear Regulatory Commission (NRC) staff summarized a conference call regarding the fall 2018 steam generator tube inspections at Beaver Valley, Unit 2, in a letter dated November 28, 2018 (ADAMS Accession No. ML18325A023).
The NRC staff has completed its review of FENOCs submittals, as documented in the enclosed evaluation. The NRC staff concludes that FENOC has provided the information required by the technical specifications and that no additional followup is required at this time. This completes the NRC staffs efforts for EPID L-2019-LRO-0000.
R. Penfield If you have any questions, please contact me at 301-415-1603 or Carleen.Parker@nrc.gov.
Sincerely,
/RA/
Carleen J. Parker, Project Manager Plant Licensing Branch I Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-412
Enclosure:
Review of the Fall 2018 Steam Generator Tube Inspection Report cc: Listserv
OFFICE OF NUCLEAR REACTOR REGULATION REVIEW OF THE FALL 2018 STEAM GENERATOR TUBE INSPECTION REPORT FIRSTENERGY NUCLEAR OPERATING COMPANY BEAVER VALLEY POWER STATION, UNIT 2 DOCKET NO. 50-412
1.0 INTRODUCTION
By letters dated January 31, 2019, and March 28, 2019 (Agencywide Documents Access and Management System (ADAMS) Accession Nos. ML19035A607 and ML19087A050, respectively), FirstEnergy Nuclear Operating Company (the licensee) submitted information summarizing the results of the fall 2018 steam generator (SG) tube inspections performed at Beaver Valley Power Station (Beaver Valley), Unit 2. The inspections were performed during Refueling Outage 20. The information was submitted in accordance with Beaver Valley Technical Specification 5.6.6.2, Unit 2 SG Tube Inspection Report.
In addition to this report, the U.S. Nuclear Regulatory Commission (NRC) staff summarized a conference call regarding the fall 2018 SG tube inspections at Beaver Valley, Unit 2, in a letter dated November 28, 2018 (ADAMS Accession No. ML18325A023).
2.0 BACKGROUND
Beaver Valley, Unit 2, is a 3-loop plant with Westinghouse Model 51M SGs. Each SG contains 3,376 mill-annealed Alloy 600 tubes with a nominal outside diameter of 0.875 inches and a nominal wall thickness of 0.050 inches. The tubes are supported by a number of carbon steel tube support plates and Alloy 600 anti-vibration bars. The tubes were roll-expanded at both ends for the full depth of the tubesheet. The portion of tubes from about 3 inches above the top of the tubesheet to about 1 inch above the tube ends was shot-peened on both the hot-leg and cold-leg side of the SG prior to operation. In addition, the U-bend region of the small radius tubes was in-situ stress relieved prior to operation.
3.0 EVALUATION The licensee provided the scope, extent, methods, and results of its SG tube inspections in the documents referenced above. In addition, the licensee described corrective actions such as tube plugging and sleeving taken in response to the inspection findings.
After reviewing the information provided by the licensee, the NRC staff has the following comments and observations:
Five tubes surrounding two foreign objects (a small wire and gasket) in SG A were removed from service. A stabilizer was installed in each tube before plugging both ends of each tube. No tube wear was detected because of these foreign objects.
Based on the 481 sleeves in service and the assumed per-sleeve leak rates in WCAP-15919, Revision 2, Steam Generator Tube Repair for Westinghouse Designed Enclosure
Plants with 7/8 Inch Inconel 600 Tubes Using Leak Limiting Alloy 800 Sleeves (0.000543 gallons per hour (gph) at normal operating conditions and 0.000863 gph during main steam or feedwater line break conditions), the assumed total leak rates for normal operating conditions and accident conditions are 6.27 gallons per day (gpd) and 9.96 gpd, respectively.
No tubes required in situ pressure testing.
Based on a review of the information provided, the NRC staff concludes that the licensee provided the information required by its technical specifications. In addition, the NRC staff concludes that there are no technical issues that warrant followup action at this time since the inspections appear to be consistent with the objective of detecting potential tube degradation, and the inspection results appear to be consistent with industry operating experience at similarly designed and operated units.
Principal Contributor: Andrew Johnson Date: July 11, 2019
ML19177A020 *by memo dated OFFICE DORL/LPL1/PM DORL/LPL1/LA DMLR/MCCB/BC* DORL/LPL1/BC DORL/LPL1/PM NAME CParker LRonewicz SBloom JDanna CParker DATE 07/08/2019 07/08/2019 06/24/2019 07/10/2019 07/11/2019