ML12115A107

From kanterella
Revision as of 00:13, 29 June 2019 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
Jump to navigation Jump to search
04/19/2012 Summary of Public Meeting to Discuss Annual Assessment of Safety Performance at Milstone for 2011
ML12115A107
Person / Time
Site: Millstone  Dominion icon.png
Issue date: 04/23/2012
From: Bellamy R
NRC/RGN-I/DRP/PB5
To:
Shared Package
ML12058A411 List:
References
Download: ML12115A107 (2)


Text

April 23, 2012 MEETING

SUMMARY

LICENSEE: DOMINION NUCLEAR CONNECTICUT, Inc.

FACILITY: MILLSTONE POWER STATION

SUBJECT:

SUMMARY

OF PUBLIC MEETING

On Thursday, April 19, 2012, at 5:30 p.m., the U. S. Nuclear Regulatory Commission (NRC)

conducted a public open-house at the Waterford Town Hall in Waterford, CT. The NRC conducted the open-house to discuss its assessment of the safety performance at Millstone Power Station (Millstone) for 2011.

A notice of the open-house was issued on April 2, 2012, and was posted on the NRC's external (public) Web page. The meeting notice can be found in the NRC's Agencywide Documents Access and Management System (ADAMS) with Accession No. ML12093A083. ADAMS is accessible from the NRC web page at:

http://www.nrc.gov/reading-rm/adams.html.

The NRC presented poster boards and was available to discuss its assessment of the safety performance of Millstone for the period of January 1 through December 31, 2011, as documented in our letter dated March 5, 2012 (ADAMS Accession No. ML12061A240). The NRC poster boards included background on the Reacto r Oversight Process (ROP). Additional information relative to the NRC's annual asse ssment process and the safety performance of Millstone can be found on the NRC's web site at:

www.nrc.gov/NRR/OVERSIGHT/ASSESS/index.html.

Members of the public and media attended the open-house and were offered the opportunity to question the NRC regarding Millstone's performance and the role of the agency in ensuring safe plant operations.

/RA/ Ronald R. Bellamy, Chief Projects Branch 5

Division of Reactor Projects

ML12061A240). The NRC poster boards included background on the Reacto r Oversight Process (ROP). Additional information relative to the NRC's annual asse ssment process and the safety performance of Millstone can be found on the NRC's web site at: www.nrc.gov/NRR/OVERSIGHT/ASSESS/index.html. Members of the public and media attended the open-house and were offered the opportunity to question the NRC regarding Millstone's performance and the role of the agency in ensuring safe

plant operations.

/RA/ Ronald R. Bellamy, Chief Projects Branch 5

Division of Reactor Projects

Enclosures:

None

Distribution: (via email) R. Bellamy T. Setzer E. Keighley J. DeBoer S. Shaffer, SRI B. Haagensen, RI J. Krafty, RI C. Kowalyshyn, Admin RidsNRRPMResource DOC NAME: G:\DRP\BRANCH5\Annual Assessment Meetings\2011 EOC\Millstone 2011 Annual Assessment Meeting Summary.docx ADAMS Accession No.: ML12115A107 SUNSI Review Non-Sensitive Sensitive Publicly Available Non-Publicly Available OFFICE RI/DRP RI/DRP NAME TSetzer RBellamy DATE 04/20/12 04/23/12