July 7, 2011 MEETING

SUMMARY

MN No: 11-019 LICENSEE: DOMINION NUCLEAR CONNECTICUT, INC.

FACILITY: MILLSTONE POWER STATION

SUBJECT:

SUMMARY

OF MAY 25, 2011, MEETING WITH THE CONNECTICUT NUCLEAR ENERGY ADVISORY COUNCIL (NEAC)

On May 25, 2011, at 6:30 p.m., a public meeting was conducted at the Waterford Town Hall, Waterford, CT, between the Nuclear Regulatory Commission (NRC) and NEAC to discuss the implementation of the Reactor Oversight Process and to answer questions regarding the Millstone Nuclear Power Plant performance for calendar year 2010.

The NRC presented and discussed its assessment of the safety performance of Millstone for the period from January 1 through December 31, 2010. The NRC presentation included a discussion of the NRCs 2010 Millstone performance assessment results and U.S. nuclear plant safety in light of Japan events. As part of the meeting, the NRC provided NEAC with an overall assessment of plant performance and with specific information concerning selected inspection findings.

The public observed the meeting and was offered the opportunity to communicate with the NRC regarding Dominions performance at Millstone and the role of the agency in ensuring safe plant operations.

The NRC's assessment letter can be found in ADAMS with an accession number of ML110620174. The meeting notice, with the attached agenda, can be found in ADAMS with accession number ML111250122, and the NRC meeting slides can be found in ADAMS with accession number ML111880064. The Attachment provides a list of individuals that attended the meeting as well as the slides used during the presentation. ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html.

Sincerely,

/RA/

Donald E. Jackson, Chief Projects Branch 5 Division of Reactor Projects

Attachment:

Meeting Attendees

MEETING

SUMMARY

MN No: 11-019 LICENSEE: DOMINION NUCLEAR CONNECTICUT, INC.

FACILITY: MILLSTONE POWER STATION

SUBJECT:

SUMMARY

OF MAY 25, 2011, MEETING WITH THE CONNECTICUT NUCLEAR ENERGY ADVISORY COUNCIL (NEAC)

On May 25, 2011, at 6:30 p.m., a public meeting was conducted at the Waterford Town Hall, Waterford, CT, between the Nuclear Regulatory Commission (NRC) and NEAC to discuss the implementation of the Reactor Oversight Process and to answer questions regarding the Millstone Nuclear Power Plant performance for calendar year 2010.

The NRC presented and discussed its assessment of the safety performance of Millstone for the period from January 1 through December 31, 2010. The NRC presentation included a discussion of the NRCs 2010 Millstone performance assessment results and U.S. nuclear plant safety in light of Japan events. As part of the meeting, the NRC provided NEAC with an overall assessment of plant performance and with specific information concerning selected inspection findings.

The public observed the meeting and was offered the opportunity to communicate with the NRC regarding Dominions performance at Millstone and the role of the agency in ensuring safe plant operations.

The NRC's assessment letter can be found in ADAMS with an accession number of ML110620174. The meeting notice, with the attached agenda, can be found in ADAMS with accession number ML111250122, and the NRC meeting slides can be found in ADAMS with accession number ML111880064. The Attachment provides a list of individuals that attended the meeting as well as the slides used during the presentation. ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html.

Sincerely,

/RA/

Donald E. Jackson, Chief Projects Branch 5 Division of Reactor Projects Attachments: Meeting Attendees Distribution: (see attached page)

SUNSI Review Complete: DEJ (Reviewer=s Initials) ML111880644 DOC NAME: G:\DRP\BRANCH5\Annual Assessment Meetings\2010 EOC\Meeting Summaries\Millstone NEAC Meeting Summary.doc After declaring this document AAn Official Agency Record@ it will be released to the Public.

To receive a copy of this document, indicate in the box: C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy OFFICE RI/DRP RI/DRP NAME TSetzer/dej for DJackson/dej DATE 07/07/11 07/07/11 OFFICIAL RECORD COPY

2 Distribution:

W. Dean, ORA D. Lew, ORA D. Roberts, DRP J. Clifford, DRP D. Jackson, DRP T. Setzer, DRP D. Dodson, DRP E. Keighley S. Shaffer, DRP B. Haagensen. DRP J. Krafty, DRP C. Kowalyshyn, OA

A-1 LIST OF ATTENDEES MILLSTONE POWER STATION MEETING WITH THE CONNECTICUT NUCLEAR ENERGY ADVISORY COUNCIL (NEAC)

MAY 25, 2011 NAME ORGANIZATION Sharon Berry Waterford Resident Nancy Burton CCAM

Attachment