Text

July 7, 2011 MEETING

SUMMARY

MN No:

11-018 LICENSEE:

DOMINION NUCLEAR CONNECTICUT, INC.

FACILITY:

MILLSTONE POWER STATION

SUBJECT:

SUMMARY

OF THE MAY 25, 2011, ANNUAL ASSESSMENT PUBLIC MEETING On May 25, 2011, from 2:00 p.m. to 4:00 p.m., the Nuclear Regulatory Commission (NRC) conducted an Annual Assessment Public Meeting at the Waterford Town Hall in Waterford, CT.

The NRC conducted the meeting to discuss the NRCs assessment of the safety performance of Millstone Power Station for the calendar year 2010.

A notice of the public meeting was issued on May 5, 2011, and was posted on the NRCs external (public) web page (ADAMS Accession No. ML111250109).

The NRC presented and discussed its assessment of the safety performance of Millstone Power Station for the period of January 1 through December 31, 2010, as documented in our letter dated March 4, 2011 (ADAMS Accession No. ML110620174). The NRC presentation (ADAMS Accession No. ML111880033) included a discussion of the NRCs 2010 Millstone performance assessment results and U.S. nuclear plant safety in light of Japan events. Additional information relative to the NRC's Annual Assessment Process and the safety performance of Millstone Power Station can be found on the NRC's web site at:

www.nrc.gov/NRR/OVERSIGHT/ASSESS/index.html.

The Attachment provides a list of local officials, Dominion employees and members of the public that attended the open house and were offered the opportunity to question the NRC regarding Dominions performance and the role of the agency in ensuring safe plant operations.

Sincerely,

/RA/

Donald E. Jackson, Chief Projects Branch 5 Division of Reactor Projects

Attachment:

List of Attendees

July 7, 2011 MEETING

SUMMARY

MN No:

11-018 LICENSEE:

DOMINION NUCLEAR CONNECTICUT, INC.

FACILITY:

MILLSTONE POWER STATION

SUBJECT:

SUMMARY

OF THE MAY 25, 2011, ANNUAL ASSESSMENT PUBLIC MEETING On May 25, 2011, from 2:00 p.m. to 4:00 p.m., the Nuclear Regulatory Commission (NRC) conducted an Annual Assessment Public Meeting at the Waterford Town Hall in Waterford, CT.

The NRC conducted the meeting to discuss the NRCs assessment of the safety performance of Millstone Power Station for the calendar year 2010.

A notice of the public meeting was issued on May 5, 2011, and was posted on the NRCs external (public) web page (ADAMS Accession No. ML111250109).

The NRC presented and discussed its assessment of the safety performance of Millstone Power Station for the period of January 1 through December 31, 2010, as documented in our letter dated March 4, 2011 (ADAMS Accession No. ML110620174). The NRC presentation (ADAMS Accession No. ML111880033) included a discussion of the NRCs 2010 Millstone performance assessment results and U.S. nuclear plant safety in light of Japan events. Additional information relative to the NRC's Annual Assessment Process and the safety performance of Millstone Power Station can be found on the NRC's web site at:

www.nrc.gov/NRR/OVERSIGHT/ASSESS/index.html.

The Attachment provides a list of local officials, Dominion employees and members of the public that attended the open house and were offered the opportunity to question the NRC regarding Dominions performance and the role of the agency in ensuring safe plant operations.

Sincerely,

/RA/

Donald E. Jackson, Chief Projects Branch 5 Division of Reactor Projects Attachments:

List of Attendees Distribution:

W. Dean, ORA D. Lew, ORA D. Roberts, DRP J. Clifford, DRP D. Jackson, DRP T. Setzer, DRP D. Dodson, DRP S. Shaffer, DRP B. Haagensen. DRP J. Krafty, DRP C. Kowalyshyn, OA SUNSI Review Complete: DEJ (Reviewer=s Initials)

ML111880531 After declaring this document An Official Agency Record it will be released to the Public.

Adams Accession No:

Document Name: G:\\DRP\\BRANCH5\\ANNUAL ASSESSMENT MEETINGS\\2010 EOC\\MEETING SUMMARIES\\MILLSTONE 2011 AA MEETING

SUMMARY

.DOC To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy OFFICE RI/DRP lhp RI/DRP RI/DRP NAME TSetzer/dej for DJackson/dej DATE 07/07/11 07/07/11 OFFICAL RECORD COPY

A-1 LIST OF ATTENDEES MILLSTONE POWER STATION ANNUAL ASSESSMENT MEETING NAME ORGANIZATION Nancy Burton CCAM Sherri Vogt Cong Courtney Denny Hicks NEAC Bill Sheehan NEAC Tom Cleary Dominion Dennis Holt Dominion Dr. Ed Wild State of Connecticut Kevin Hennesey Dominion Helen LaForge FEMA Attachment