Updated Inspection Plan for Dresden Nuclear Power Station, Units 2 and 3 (Report 05000237/2017005 and 05000249/2017005)
ML17240A266
Person / Time
Site: Dresden  Constellation icon.png
Issue date: 08/28/2017
From: Jamnes Cameron
Reactor Projects Region 3 Branch 4
To: Bryan Hanson
Exelon Generation Co, Exelon Nuclear
References
IR 2017005
Download: ML17240A266 (5)


Text

August 28, 2017

SUBJECT:

UPDATED INSPECTION PLAN FOR DRESDEN NUCLEAR POWER STATION , UNIT S 2 AND 3 (REPORT 05000237/201 7005 AND 05000249/201 7005)

Dear Mr. Hanson

The enclosed inspection plan lists the inspections scheduled through June 30 , 20 19 for Dresden Nuclear Power Station

. The U.S. Nuclear Regulatory Commission (NRC)

provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issue Routine inspections performed by resident inspectors are not included in the inspection pla The inspections listed during the last twelve months of the inspection plan are tentative and may be revise The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any change This inspection plan does not include the plan for security-related inspections, which will be sent via separate, non-publicly available correspondenc NRC inspectors will be performing Temporary Instruction 2515/191, "Inspection of the Implementation of Mitigation Strategies and Spent Fuel Pool Instrumentation Orders and Emergency Preparedness Communication/Staffing/Multi-Unit Dose Assessment Plans," at your site from November 27, 2017

, until December 1, 201 In March 2018 NRC inspectors will review your design basis using inspection procedure 711121M, "Design Bases Assurance Inspection (Teams)."

In addition Phase 4 of Post-Approval License Renewal inspection will be performed from February 25, 2019

, until March 1, 20 19 , in accordance with Inspection Procedure 71003, "Post-Approval Site Inspection for License Renewal

."

B. Hanson - 2 - This letter and its enclosure will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, "Public Inspections, Exemptions, Requests for Withholding."

Please contact me a t 630-829-9833 with any questions you have regarding this lette

Sincerely,

/RA/ Jamnes Cameron, Chief Branch 4 Division of Reactor Projects Docket Nos. 50-237; 50-249 License Nos. DPR-19; DPR-25 Enclosure: