ML19208A5946 July 1979Expresses Fears Re Nuclear Power.Forwards Affidavits from Seven Workers & One Foreman of Westinghouse Re Stacking of Trays.Questions NRC Lack of Action
ML19208C49524 July 1979Advises That Deposition of D Blanch Will Not Be Taken on 790726.Deposee Has Decided Not to Testify.Miami Valley Power Project Intends to Quash Util Subpoena
ML19209B12723 August 1979Expresses Gratitude Re Efforts of Ofc of Us Marshall to Serve Subpoena on R Hofstadter.Forwards Subpoena & Fee Mileage Check
ML19254E34310 September 1979Notifies That R Hofstadter Will Not Appear as Witness on Behalf of Intervenor Miami Valley Power Project.Forwards 790910 Ltr to Hofstadter
ML19263E87014 May 1979Forwards Applicant 790514 Objections to Intervenor Miami Valley Power Project Third Set of Interrogatories & Motion for Protective Order.Responses to Interrogatories Not Objectionable
ML19270G17124 April 1979Advises That Copy of Applicants' Objections to Intervenor Miami Valley Power Project Second Set of Interrogatories & Motion for Protective Order Was Mailed on 790406
ML19282A9899 January 1979Grants Extension Until 790116 to Answer Interrogatories. Expects Timely,Responsive Answers
ML19346A18327 April 1981Requests That Thorough Investigation Be Conducted Into Facility Const
ML19346A18428 April 1981Requests That Thorough Investigation Be Conducted Into Facility Const
ML20003A14327 January 1981Confirms Agreement Re Potential Witnesses R Estes & T Herman Depositions to Be Given in Cincinnati,Oh on 810204.Witness Prof Qualifications & Other Documents to Be Provided.Related Correspondence
ML20050C0861 August 1981FOIA Request for All Records Re Zimmer Nuclear Power Plant
ML20064E31114 May 1981Confirms Info Received Re Investigation of Rejected Radiographs Supplied to Util at 810430 Meeting at Region 3 Ofc.Synopsis of Problem Discussed.Meeting W/Nrc Scheduled for 810518 Postponed.Related Info Encl
ML20071L38919 May 1983Responds to Re American Nuclear Insurers Activity at Facility.No ASME Code Work in Process Due to Stop Work Order.Hj Kaiser Continuing to Resolve Existing Nonconformances & Verification of Resolutions
ML20071P11331 May 1983Forwards Biweekly Status Rept on Independent Review of Util Project Mgt Covering Period 830507-20
ML20071P12531 May 1983Summarizes 830526 Meeting to Discuss Planned Changes to Initial Program Plan.Util Interfaces W/Reactor Control,Inc Should Be Added to Program Scope
ML20072D27710 June 1983Forwards Independent Review of Zimmer Project Mgt, Biweekly Status Rept 3,for 830521-0603
ML20072H30022 March 1983Forwards List of Initial Documents & Info Required in Anticipation That Torrey Pines Technology Will Be Confirmed as Independent Reviewer of Project Mgt.Nrc Advised of Request Via 830322 Telcon
ML20072P52230 March 1983Advises That Listed Documentation Re FSAR Chapters 13,14 & 17 & Project Procedure & QA Procedure Manuals Required by Forwarded Under Separate Cover,Supplementing Util
ML20072Q09623 March 1983Forwards Response to Inquiry Re Commitment to Supply Nuclear Fuel to American Electric Power Co.Contractual Commitments Complex & Only Indirectly Related.Commitments Have No Relationship to Project & Do Not Result in Net Revenues
ML20072Q22318 March 1983Forwards Response to NRC Request for Addl Info Re Proposal for Independent Review of Util Project Mgt.Scope of Work on Completed Independent Design & Const Reviews of San Onofre, Palo Verde,Shoreham & Waterford Encl
ML20072Q24722 March 1983Forwards Initial List of Documents/Info for Independent Review of Facility Project Mgt & QA Program
ML20073A4485 April 1983Responds to Questions Raised in Jg Keppler . Info Re Bechtel Revenues to Ga Co/Torrey Pines Technology Svcs Provided to Bechtel Encl
ML20073A5285 April 1983Confirms That No Contractual Relationships Made Between Ga Co/Torrey Pines Technology & American Electric Power Co,Inc or Subsidiaries,Other than Commitment to Supply Nuclear Fuel
ML20073B81825 March 1983Forwards 830119 Project Organization Chart & Revs Dtd May & Dec 1978 & Apr 1981,per 830324 Telcon.Other Info Will Be Available During Site Visits.W/O Encl
ML20073B9804 April 1983Forwards Rev 11 to Natl Board Tasks Rept. Rept Tracks Progress on Concerns Raised by Natl Board Interim Repts 1 & 2,Suppls 2,3,5 & 7.W/o Stated Executive Summary
ML20073J11631 March 1983Submits Listing of Initial Tasks Re Consulting Efforts Concerning Suspension of Facility Const.Addl Tasks & Recommendations May Be Suggested as Work Develops or New Areas Are Identified
ML20073J82813 April 1983Forwards App a of Bechtel Corp 821108 Proposal Outlining Scope of Survey Activities in Preparation of Independent Mgt Review of Project
ML20073J92212 April 1983Forwards NRC Transcript of 830328 Public Meeting in Cincinnati,Oh Re Util Selection of Torrey Pines Technology to Perform Mgt Assessment of Project.W/O Encl
ML20076A8109 August 1983Forwards Biweekly Status Rept on Independent Review of Facility Project Mgt Covering Period 830716-29
ML20076A9888 August 1983Forwards Rev 20 to Natl Board Tasks Rept
ML20076J54219 August 1983Forwards Aug 1983 Final Rept, Independent Review of Zimmer Project Mgt. W/O Encl
ML20076J75424 June 1983Forwards Biweekly Status Rept 4 on Independent Review of Project Mgt for 830604-17.Total of 7,252 Manhours Expended on Review
ML20076M37212 July 1983Forwards Biweekly Status Rept on Independent Review of Facility Project Mgt for 830618-0701
ML20076M69313 July 1983Revises Re Bechtel Study Draft Rept on Mgt of Util.Bechtel Should Retain Rept & Arrange Meeting W/Torrey Pines Technology
ML20077E33622 July 1983Forwards Biweekly Status Rept 6 on Independent Review of Zimmer Project Mgt for 830702-15
ML20077H7544 August 1983Discusses Telcon W/R Warnick of Region 3 Re Contents of Rept on Facility.Contents Will Be Discussed Following Release of Rept on 830812,per NRC Protocol Requirements
ML20077J48211 August 1983Protests Cincinnati Environ Advisory Council Rejection of M Prather to Serve on Council.Prather Should Be Appointed or T Carpenter,Representing Miami Valley Power Project,Should Be Eliminated
ML20078A57129 August 1983Forwards Rev 21 to 830819 Natl Board Tasks Rept, Assembled for Tracking Progress on Concerns Raised by Suppls 2,3,5 & 7 to Natl Board Interim Repts 1 & 2. Executive Summary Attached to Highlight Changes Made Since 830805 Rev 20 Rept
ML20078C38119 September 1983Forwards Rev 23 to Natl Board Tasks Rept, Dtd 830916. Rept Assembled for Tracking Progress on Concerns Raised by Natl Board Interim Repts 1,2, Suppls 2,3,5,7 & 13.Executive Summary Highlights Changes Made Since Rev 22
ML20078D45112 September 1983Comments on Implementation of Recommended Independent Design Review.Design Verification Should Be Conducted in Parallel W/Verification of Const Quality
ML20078J5727 October 1983Forwards Natl Board Interim Rept 15 Covering Audit Team Activities for Sept 1983
ML20079K19717 January 1984Forwards Natl Board of Boiler & Pressure Vessel Inspectors Interim Rept 18 Covering Natl Board Audit Team Activities at Facility for Dec 1983.Concurs W/Recommendations.Task NBT-4 Closed
ML20079P96824 January 1984Forwards 840124 Telegram Appealing Dismissal of J E Abson Claim Against Hj Kaiser Co,Per Dept of Labor 840120 Ruling
ML20079R1499 June 1983Submits 830606 Request for Documents Re Kaiser Engineers, Inc Qa/Qc Personnel
ML20080G36730 August 1983Requests Clarification of Statements in Torrey Pines Technology Final Rept GA-C17173, Independent Review of Zimmer Project Mgt Re Recommendations on Independent Design Review
ML20080R3753 October 1983Forwards Rev 24 to Natl Board Tasks Rept. Rept Assembled for Tracking Progress on Concerns Raised by Natl Board Interim Repts 1 & 2,Suppls 2,3,5,7 & 13
ML20081B76023 November 1982Submits Revised Proposal for Providing Completion Svcs for Facility.Rev to Proposal,Originally Submitted on 821108, Responds to Commission 821122 Order to Show Cause.List of Independent Review Team Members Encl
ML20081B76529 December 1982Suppls in Response to Jg Keppler 821228 Request, Directed to Util,Re Bechtel Mgt Role.Soderholm Involvement Discussed
ML20081B7688 November 1982Forwards Description of Steps to Be Taken to Identify Necessary Organizational & Procedural Action,Resumes of Phase I Team Members,Summarizes of Bechtel Nuclear Experience & Contract Forms.Info Deleted
ML20082F59714 November 1983Forwards 831109 Nat Board Interim Rept 16 Re Audit & Surveillance Activities at Facility.Author Concurs W/Natl Board Audit Team Recommendations.Task NBT-4 Re Util Takeover of Partial Piping Sys Closed