MONTHYEARML16337A2982016-11-29029 November 2016 Slides from Public Meeting with Southern Nuclear to Discuss Vogtle GSI-191 Resolution Plan and Current Status Project stage: Meeting ML16354A1212016-12-27027 December 2016 Summary of Public Meeting with SNC on Planned Submittal of Vogtle Electric Generating Plant, Units 1 and 2, License Amendment Requests and Exemptions Concerning Resolution of Generic Safety Issue 191 Project stage: Meeting ML17033A0232017-02-14014 February 2017 Request for One-Time Exception to Nuclear Reactor Regulation Office Instructions LIC-109, LIC-101, and LIC-500 Acceptance Review Criteria Project stage: Acceptance Review 2016-12-27
[Table View] |
|
---|
Category:Meeting Summary
MONTHYEARML24025A1372024-01-31031 January 2024 Summary of Observation Pre-Submittal Meeting Held with Snc., Regarding a Proposed Alternative Request - Explosively Actuated Valves for Vogtle Electric Generating Plant, Units 3 and 4 ML24019A1932024-01-30030 January 2024 Summary of January 8, 2024, Observation Pre-Submittal Meeting Held with Southern Nuclear Operating Company Regarding a Proposed LAR for Vogtle Electric Generating Plant, Units 1, 2, 3, & 4; Hatch, Units 1 & 2; Farley, Units 1 & 2 ML23356A0282023-12-27027 December 2023 December 11, 2023, Pre-Application Meeting with SNC Regarding a Proposed Fleet LAR to Revise TS 5.3.1 to Relocate Training Qualification Requirements from TS to Their Qatr/Ndqam ML23311A1302023-11-17017 November 2023 Summary of Nov. 6, 2023, - Closed Meeting Held with Southern Nuclear Operating Company, Inc., Regarding Physical Barriers Exemptions for Hatch Units 1 & 2, Farley Units 1 & 2 and Vogtle Units 1, 2, 3 & 4 (EPID L-2023-LLE-0018 & L-2023-LLE-0 ML23313A0952023-11-16016 November 2023 Summary of November 7, 2023, Observation Pre-Submittal Meeting Held with Southern Nuclear Operating Company, Inc., Regarding a Proposed License Amendment Request for Vogtle Electric Generating Plant, Units 1 and 2 ML23303A2032023-11-0101 November 2023 October 24, 2023, Summary of Comment Gathering Public Meeting on Lessons Learned from the ITAAC Hearing Process for Vogtle Units 3 and 4 ML23275A0882023-10-12012 October 2023 Summary of Meeting with Southern Nuclear Operating Company ML23272A1822023-10-11011 October 2023 Summary of September 28, 2023, Observation Pre Submittal Meeting Held with Southern Nuclear Operating Company, Inc., Regarding a Proposed License Amendment Request for Vogtle Electric Generating Plant, Units 3 and 4 ML23230A0212023-08-30030 August 2023 LAR-22-002 Technical Specification 3.8.3 Summary of 08-17-23 Public Meeting ML23187A5742023-08-22022 August 2023 Summary of June 29, 2023, Meeting with Southern Nuclear Operating Company ML23146A1542023-06-0505 June 2023 Summary of May 25, 2023, Meeting with Southern Nuclear Operating Company ML23132A0412023-05-18018 May 2023 Summary of May 11, 2023, Meeting with Southern Nuclear Operating Company ML23121A1692023-05-12012 May 2023 Summary of Meeting with Southern Nuclear Operating Company Vogtle LAR-23-006 U/3&4 More Restrictive Action for TS 3.1.9 Cvs Isolation Valves ML23115A3282023-05-10010 May 2023 Summary of Public Meeting with Southern Nuclear Operating Company to Have a Pre-Submittal Discussion of Draft License Amendment Request (LAR) for Vogtle Electric Generating Plant (VEGP) Unit 3 ML23115A0662023-05-0101 May 2023 Summary of Public Meeting with Southern Nuclear Operating Company to Have Presubmittal Meeting for Vogtle Electric Generating Plant, Unit 4 IR 05000424/20040252023-04-28028 April 2023 Public Meeting Summary - Vogtle Electric Generating Plant, Units 1, 2, 3, & 4 Docket No. 5000424, 5000425, 5200025, 5200026, Meeting Number 20230375 ML23090A1422023-04-0303 April 2023 Summary of Conference Call Regarding the Spring 2022 Steam Generator Tube Inspections ML23065A0732023-03-17017 March 2023 March 2, 2023, Summary of Meeting with Southern Nuclear Operating Company - Vogtle Electric Generating Plant, Unit 4 ML23055A0902023-03-14014 March 2023 February 16, 2023, Summary of Meeting with Southern Nuclear Operating Company ML23048A0682023-03-0101 March 2023 Summary of February 13, 2023, Observation Pre-Submittal Meeting Held with Southern Nuclear Operating Company, Inc. Regarding a Proposed License Amendment Request for Vogtle Electric Generating Plant, Units 1 and 2 ML23037A0032023-02-0606 February 2023 Summary of February 2, 2023, Public Meeting with Southern Nuclear Operating Company ML23012A0512023-01-17017 January 2023 January 11, 2023, Summary of Public Meeting with Southern Nuclear Operating Company (SNC) Regarding Vogtle Emergency Technical Specification Amendment ML22349A2142023-01-0303 January 2023 Summary of December 8, 2022, Public Meeting with Southern Nuclear Operating Company ML22336A0812022-12-0505 December 2022 Summary of December 1, 2022, Observation Pre-Submittal Meeting Held with Southern Nuclear Operating Company, Inc., Regarding a Proposed License Amendment Request for Vogtle Electric Generating Plant, Units 1 and 2 ML22335A4922022-12-0202 December 2022 Summary of Observation Pre-Submittal Meeting Held with Southern Nuclear Operating Company, Inc., Regarding a Proposed License Amendment Request for Vogtle Electric Generating Plant, Units 1 and 2 ML22319A0132022-11-30030 November 2022 Summary of a Public Meeting with Southern Nuclear Operating Company on November 10, 2022 ML22322A1672022-11-28028 November 2022 Summary of 11/15/2022 Public Meeting on Lessons Learned ML22271A0182022-10-0404 October 2022 Summary of Public Meeting with SNC on Lessons Learned Final ML22257A2362022-09-19019 September 2022 Summary of September 13, 2022, Partially Open and Partially Closed Pre-Submittal Meeting Held with SNC, Regarding a Proposed OLM License Amendment Request for Vogtle Electric Generating Plant, Units 1 and 2 ML22243A0302022-09-0909 September 2022 Summary of a Public Meeting with Southern Nuclear Operating Company on August 25, 2022 ML22145A6052022-06-0202 June 2022 Summary of May 24, 2022, Public Meeting with SNC, Regarding a Proposed Alternative Request for Performance-Based Leakage Test Frequencies for the Refueling Water Tank Suction Check Valves for Vogtle, Units 1 & 2 ML22145A4492022-05-27027 May 2022 Summary of May 23, 2022, Public Meeting with SNC, Regarding a Proposed License Amendment Request to Change Technical Specification 3.8.1 and Implement TSTF-163 for Vogtle Electric Generating Plant, Units 1 and 2 ML22131A3422022-05-18018 May 2022 Summary of Public Meeting with Southern Nuclear Operating Company, Inc., Regarding a Proposed License Amendment Requests to Implement Alternate Source Term, TSTF-51, TSTF-471, and TSTF-490 for Vogtle, Units 1 & 2 (EPID No. L-2022-LRM-0033 ML22132A0102022-05-17017 May 2022 Meeting of Public Meeting with Southern Nuclear Operating Company, Inc., Regarding Proposed Accident Tolerant Fuel License Amendment Request and Exceptions for Vogtle Electric Generating Plant, Units 1 and 2 ML22123A0652022-05-0202 May 2022 Public Meeting Summary Vogtle Electric Generating Plant, Units 1, 2, 3, & 4 Docket No. 50-424, 50-425, 52-025, 52-026, Meeting Number 20220330 ML22098A1292022-04-26026 April 2022 Summary of March 31, 2022 Public Meeting with Southern Nuclear Operating Company ML22095A2292022-04-11011 April 2022 Summary of Conference Call Regarding the Spring 2022 Steam Generator Tube Inspections ML22077A5432022-04-0404 April 2022 Summary of Meeting with Southern Nuclear Operating Co ML22028A0462022-02-0101 February 2022 MTS - Meeting Summary - Pre-Submittal Meeting on January 27, 2022 - Vogtle ATF LAR and Exemption ML21337A0032021-12-0707 December 2021 Summary of Vogtle Readiness Group Public Meeting on December 2, 2021 ML21322A1502021-12-0202 December 2021 Summary of November 10, 2021 Public Meeting with Southern Nuclear Operating Company ML21316A0692021-11-22022 November 2021 November 4, 2021 Summary of Public Meeting with Southern Nuclear Operating Company ML21313A1172021-11-18018 November 2021 Summary of Public Meeting with Southern Nuclear Operating Company, Inc., Regarding a Proposed License Amendment Request to Change the Technical Specification Related to Technical Specification 5.5.16 for Joseph M. Farley Nuclear Plant ML21238A1622021-09-10010 September 2021 Summary of Public Meeting with Southern Nuclear Operating Company, Inc., Regarding a Proposed License Amendment Request to Change the Technical Specification Related to Main Steam Isolation Valves for Vogtle Electric Generating Plant ML21225A5532021-08-31031 August 2021 August 13,2021, Public Meeting Summary with Southern Nuclear Operating Regarding Proposed LAR to Revise Technical Specifications Related to Reactor Trip System & Engineered Safety Feature Actuation System Instrumentation for Vogtle 1&2 (L-2 ML21230A0102021-08-24024 August 2021 Summary of Public Meeting with Southern Nuclear Operating Company on August 12, 2021 ML21154A2772021-07-20020 July 2021 Summary of a Public Meeting with Southern Nuclear Operating Company on May 27, 2021 ML21194A0402021-07-20020 July 2021 Summary of June 24, 2021 Public Meeting with SNC ML21190A0622021-07-16016 July 2021 Summary of July 8 2021 Public Meeting to Discuss Late-Filed Allegation Process for Vogtle Electric Generating Plant Units 3 and 4 2024-01-31
[Table view] |
Text
FACILITY:
SUBJECT:
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 December 27, 2016 Southern Nuclear Operating
- Company, Inc. Vogtle Electric Generating Plant, Units 1 and 2 SUMMARY OF NOVEMBER 29, 2016, PUBLIC MEETING WITH SOUTHERN NUCLEAR OPERATING COMPANY ON PLANNED SUBMITIAL OF VOGTLE ELECTRIC GENERATING PLANT, UNITS 1 AND 2, LICENSE AMENDMENT AND EXEMPTION REQUESTS CONCERNING RESOLUTION OF GENERIC SAFETY ISSUE 191 (CAC NOS. MF8488 AND MF8489) On November 29, 2016, a Category 1 public meeting was held between the U.S. Nuclear Regulatory Commission (NRC) and representatives of Southern Nuclear Operating Company (SNC or the licensee) at NRC Headquarters, One White Flint North, 11555 Rockville Pike, Rockville, Maryland.
The purpose of the meeting was for SNC to provide an overview of its planned risk-informed license amendment request (LAR) involving the resolution of GSl-191, "Assessment of Debris Accumulation on Pressurized Water Reactor (PWR) Sump Performance,"
for the Vogtle Electric Generating Plant, Units 1 and 2 (VEGP). The meeting notice and agenda, dated November 15, 2016, are available in the Agencywide Documents Access and Management System (ADAMS) at Accession No. ML 16320A073.
A list of participants is enclosed.
The licensee's presentation slides used at the meeting are available in ADAMS at Accession No. ML 16337 A298. The licensee described the information that it plans to include in its risk-informed submittal.
SNC described the features and plant operations that are relevant to the planned license amendment and exemption
- requests, which included overall layout of VEGP, strainer arrangement, and plant response.
SNC provided an overview of the layout and content of the planned submittal.
During its presentation, the licensee addressed the following topics:
- Hybrid loss-of-coolant accident frequency methodology sensitivity
- Credit for containment accident pressure
- Fiber quantity required for chemical head loss
- Partially submerged breaks
- Sensitivity and uncertainty quantification SNC asked the NRC staff for feedback on the methods it plans to use to address specific technical issues and to identify potential gaps in the submittal.
The NRC staff informed the licensee that the following needs to be addressed in its submittal:
- Justification for conservatism in flashing and de-gas calculations.
- Justification for the assumed minimum bed thickness at which chemical head loss may occur.
- Description of all five key principles for risk-informed submittals, including monitoring.
- If planning to seek "credit" for other previously reviewed and approved risk-informed licensing
- actions, explain the applicability of the disposition of findings and observations to the planned submittal.
- Indication (e.g., tabulated) of weld locations subject to multiple degradation mechanisms or nearing bounding quantity of debris.
- Discussion of the use of Argonne National Laboratory equations for solubility versus the equations from the University of New Mexico.
- Description of any additional weld inspections to the ones included in the in-service inspection program.
The list above is not all inclusive of the information that needs to be included in the planned submittal.
The list only includes the potential gaps that the NRC staff was able to identify from the licensee's presentation.
During its presentation, the licensee highlighted the timing of its planned submittal relative to Westinghouse Electric Company's WCAP-17788, "Comprehensive Analysis and Test Programs for GSl-191 Closure (PA-SEE-1090),"
which is a topical report (TR) currently being reviewed by the NRC (ADAMS Package Accession No. ML 15210A667).
The licensee stated that the submittal relies on some of the methods described in the TR and that it planned to provide its submittal to the NRC prior to the NRC staff completing review of the TR. SNC stated that it plans to submit the license amendment and exemption requests in the first quarter of calendar year 2017 and to request NRC approval by June 2018. The NRC staff informed the licensee of NRC practice concerning submittals that rely on information in a TR that is currently under review for generic use. Specifically, the NRC staff should not accept a requested licensing action for review until the generic review is completed.
The NRC staff informed SNC that it had three options to avoid non-acceptance of its planned license amendment and exemption requests:
(1) Delay its planned submittal until the review of WCAP-17788 is complete; (2) Include the methods described in WCAP-17788 directly into its planned submittal; or (3) Provide a plant-specific justification, describing an urgent need that cannot wait until review of WCAP-17788 is completed.
With regard to the third option, the NRC staff informed the licensee that it could provide a plant-specific justification prior to its planned submittal for consideration by the NRC staff. During the meeting, the licensee described how it plans to consider safety margin and operating margin with regard to the evaluation of plant modifications, if the planned license amendment and exemption requests are approved by the NRC. The NRC staff asked the licensee if it planned to request NRC approval of the licensee's method for evaluating plant modifications that could affect GSl-191 "inputs" as part of the licensee's planned submittal.
In response, the licensee stated that it was not planning to request NRC approval, but to make the staff aware of its planned approach to evaluating plant modifications that could affect GSl-191 "inputs." The NRC staff did not make any regulatory decisions during the meeting.
Members of the public were in attendance by telephone conference.
No comments from the public were received during the meeting.
A public meeting feedback form was received.
Please direct any inquiries to me at 301-415-2871 or Michael.Marshall@nrc.gov.
Docket Nos. 50-424 and 50-425
Enclosure:
List of Participants cc w/encl: Distribution via Listserv Michael L. Marshall, Jr., Senior Project Manager Plant Licensing Branch 1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation LIST OF PARTICIPANTS NOVEMBER 29, 2016. MEETING WITH SOUTHERN NUCLEAR OPERATING COMPANY ON PLANNED SUBMITTAL OF VOGTLE ELECTRIC GENERATING PLANT. UNITS 1 AND 2 LICENSE AMENDMENT AND EXEMPTION REQUESTS CONCERNING RESOLUTION OF GENERIC SAFETY ISSUE 191 Ernie Kee Enercon Owen Scott SNC Patrick Romine Enercon Philli Grissom SNC Michael Marshall Michael Markle NRC Vic Cusumano NRC Steve Smith NRC Paul Klein NRC Matt Yoder NRC Mehdi Reisi Fard NRC CJ Fon NRC John Tsao NRC The NRC staff did not make any regulatory decisions during the meeting.
Members of the public were in attendance by telephone conference.
No comments from the public were received during the meeting.
A public meeting feedback form was received.
Please direct any inquiries to me at 301-415-2871 or Michael.Marshall@nrc.gov.
IRA/ Michael L. Marshall, Jr., Senior Project Manager Plant Licensing Branch 1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-424 and 50-425
Enclosure:
List of Participants cc w/encl: Distribution via Listserv DISTRIBUTION:
PUBLIC RidsACRS_MailCTR Resource RidsNrrPMVogtle Resource RidsNrrLALRonewicz Resource RidsNrrDssSsib Resource RidsNrrDssStsb Resource RidsNrrDeEpnb Resource RidsNrrDssSnpb Resource TWertz, NRR LPL 1 R/F RidsNrrDorlLpl2-1 Resource CJFong, NRR RidsRgn2MailCenter Resource RidsNrrDraApla Resource RidsNrrDlrRarb Resource RidsNrrDeEmcb Resource RidsNrrDeEsgb Resource JBowen, OEDO ADAMS Accession Nos.: ML 16354A121 M r N r ML 16320A073 H d t ML 16337A298 ee ing o ice: an ou s: OFFICE DORL/LPL 1/PM DORL/LPL2-1
/PM DORL/LPL 1/LA NAME MMarshall MOrenak LRonewicz DATE 12/27/2016 12/27/2016 12/27/2016 OFFICE DRNAPLA/TL
/BC DORL/LPL 1 /PM NAME CFong MMarkley MMarshall DATE 12/22/2016 12/27/2016 12/27/2016 OFFICIAL RECORD COPY MMarshall, NRR ARussell, NRR CPfefferkorn, NRR SSmith, NRR PKlein, NRR MYoder, NRR MReisi Fard, NRR JTsao, NRR CTilton, NRR *b *1 1y e-ma1 DSS/SSIB/BC*
VCusumano 12/23/2016