12/13/2006 FENOC Slides from Perry Public Meeting to Discuss Results of NRC Confirmatory Action Letter Followup Inspections
ML063490024
Person / Time
Site: Perry FirstEnergy icon.png
Issue date: 12/13/2006
From: Pearce B
FirstEnergy Nuclear Operating Co
To:
Office of Nuclear Reactor Regulation
References
Download: ML063490024 (15)


Text

Perry Nuclear Power Plant December 13, 2006 Public Meeting CAL Follow Up Inspections 2 CAL Follow Up Inspections Perry Nuclear Power Plant Perry Nuclear Power Plant Bill Pearce Site Vice President 3 CAL Follow Up Inspections Introduction Introduction NRC Inspection Issues -

Barry Allen and Mike Wayland Status of Performance Improvement Initiative (PII), Status of Confirmatory Action Letter (CAL) Commitments and Key Actions Going Forward-Fred Cayia Closing Remarks 4 CAL Follow Up Inspections NRC Inspection Issues NRC Inspection Issues Barry Allen Director , Site Operations Mike Wayland Director, Maintenance 5 CAL Follow Up Inspections NRC Inspection Issue

-Fuse Removal NRC Inspection Issue

-Fuse RemovalOctober 23, 2006 -Additional fuse was pulled, making one of the two Division 1 Diesel Generator ventilation

fans inoperable (CR 06-8702) Apparent Causes

-Equipment labeling

-Clearance lacked sufficient detail

-Workersmade incorrect assumptions 6 CAL Follow Up Inspections Actions Taken

-Fuse reinstalled

  • Job walked down with operations management and workers

-Interim action

  • Night order issued to enhance expectations for fuse removal

-Workers re-trained, remediated, and prepared cause analysis

-Labels installed on wiring

-Lessons learned shared

-Section clock reset NRC Inspection Issue

-Fuse Removal NRC Inspection Issue

-Fuse Removal 7 CAL Follow Up Inspections NRC Inspection Issue

-Airlock Equalizer Valve NRC Inspection Issue

-Airlock Equalizer Valve Work performed to correct containment airlock equalizer valve mechanism without adequate work

instructions (CR 06-10130) Apparent Causes

-Weak supervisor oversight

  • Supervisor did not recognize the need to stop work and revise work package before proceeding

-Lack of familiarity with the Fix-it Now (FIN) process 8 CAL Follow Up Inspections NRC Inspection Issue

-Airlock Equalizer Valve NRC Inspection Issue

-Airlock Equalizer Valve Actions-Valve stem is replaced

-Stand-down to train FIN te am members on FIN process restrictions

-Limits placed on who ca n authorize FIN work orders

-Workers not specifically traine d in FIN process are not used for FIN work

-Section clock reset

-Training gap analysis to be performed to determine knowledge deficiency

-Evaluate a sample of FIN work orders for extent of condition 9 CAL Follow Up Inspections Status of PII, Status of CAL Commitments and Key Actions Going Forward Status of PII, Status of CAL Commitments and Key Actions Going Forward Fred Cayia Director, Performance Improvement 10 CAL Follow Up Inspections Status of Perry Performance Improvement Initiative (PII)

Status of Perry Performance Improvement Initiative (PII) PII actions for each focus area completed

-Corrective Action Program Implementation Improvement

-Excellence in Human Performance

-Training to Improve Performance

-Effective Work Management

-Employee Engagement and Communication

-Operational Focused Organization PII Closure Reports for each focus area approved 11 CAL Follow Up Inspections Status of PII Status of PII Demonstrated sustained improvement in Corrective Action Program and Human Performance Continuous improvement actions reflected in Excellence

Plan Periodic performance assessments to ensure continuous

improvement

-Oversight-Metrics-Benchmarking / Self-assessment 12 CAL Follow Up Inspections Status of CAL Commitments Status of CAL Commitments CAL Commitments completed

-Resolution of IP 95002 follow-up issues

-Corrective Action Program Implementation improvement

-Human Performance improvement

-Emergency Preparedness improvement Enhancements to key maintenance procedures on schedule for completion Letter requesting CAL Closure to be submitted 13 CAL Follow Up Inspections Key Actions Going Forward Key Actions Going Forward PII improved capability to perform critical self-assessments Self-assessments and benchmarking support continuous improvement in Corrective Action Program and Human

Performance Plans for 2007

-Focused self-assessments

-Snapshot self-assessments

-Fleet-coordinated assessments The results of these assessments will be added to the excellence plans.

14 CAL Follow Up Inspections Closing Remarks Closing Remarks Bill Pearce Site Vice President Perry Nuclear Power Plant December 13, 2006 Public Meeting CAL Follow Up Inspections