2008/07/08-Joint StipulationML081980525 |
Person / Time |
---|
Site: |
Vermont Yankee File:NorthStar Vermont Yankee icon.png |
---|
Issue date: |
07/08/2008 |
---|
From: |
Doris Lewis, Bob Nelson, Travieso-Diaz M Entergy Nuclear Operations, Entergy Nuclear Vermont Yankee, Pillsbury, Winthrop, Shaw, Pittman, LLP |
---|
To: |
Atomic Safety and Licensing Board Panel |
---|
SECY RAS |
References |
---|
50-271-LR, ASLBP 06-849-03-LR, RAS M-129 |
Download: ML081980525 (6) |
|
|
---|
Category:Legal-Intervention Petition
MONTHYEARML1107503812011-03-10010 March 2011 Entergy'S Response to New England Coalition'S Motion for Stay and Request for Further Opportunity for Hearings ML1036300302010-12-23023 December 2010 Entergy'S Response to the Supplement to New England Coalition'S Petition for Commission Review of LBP-10-19 ML1033403292010-11-22022 November 2010 Entergy'S Answer Opposing New England Coalition'S Petition for Commission Review of LBP-10-19 ML1028002492010-09-30030 September 2010 New England Coalition'S Answer & Opposition to Entergy'S Motion to Strike Declaration of Paul Blanch ML1027204022010-09-20020 September 2010 New England Coalition'S Reply to NRC Staff and Entergy Nuclear Vermont Yankee Opposition to New England Coalition'S Motion to Reopen the Hearing & Reply to NRC Staff'S Answer to Proposed New Contention ML1026003772010-09-14014 September 2010 Entergy'S Answer Opposing New England Coalition'S Motion to Reopen ML1007403702010-03-12012 March 2010 Entergy'S Response in Opposition to New England Coalition'S Stay Request ML0922400652009-08-0303 August 2009 Entergy'S Response in Opposition to New England Coalition'S Petition for Review of LBP-09-09 ML0921202202009-07-23023 July 2009 New England Coalition'S Petition for Review of the Licensing Board'S Full Initial Decision, LBP-09-09 ML0916702632009-06-0808 June 2009 New England Coalition'S Opposition to Entergy'S Motion to Strike New England Coalition'S Reply to NRC Staff and Entergy Oppositions to Nec'S Motion to File a Timely New Contention ML0915404042009-05-26026 May 2009 Nec'S Reply to NRC Staff and Entergy Oppositions to Nec'S Motion to File a Timely New Contention ML0914203732009-05-18018 May 2009 Entergy'S Opposition to Nec'S Motion to File a Timely New Contention ML0913400192009-05-0707 May 2009 New England Coalition'S Reply to Nrc'S Staff and Entergy Answers to New England Coalition'S Motion to Hold in Abeyance Action on It'S Proposed Contention Until Issuance of NRC Staff Supplemental Safety Evaluation Report ML0912708592009-05-0101 May 2009 Entergy'S Opposition to New England Coalition'S Motion to Hold Action on Proposed Contention in Abeyance Until Issuance of NRC Staff Supplemental Safety Evaluation Report ML0908404222009-03-10010 March 2009 Final Calculations of Record for the Confirmatory Environmentally Assisted Fatigue (Cufen) Analyses on the Reactor Pressure Vessel Core Spray (CS) and Recirculation Outlet (RO) Nozzles at Vermont Yankee ML0912101052009-03-0909 March 2009 New England Coalition'S Petition for Leave Reply to Entergy Responses to New England Coalition'S Motion to Alter or Amend the Schedule in the Above Captioned Proceeding ML0907711422009-03-0909 March 2009 Entergy'S Opposition to New England Coalition'S Motion to Alter or Amend the Schedule ML0901400782009-01-0707 January 2009 Entergy'S Opposition to New England Coalition'S Motion for Reconsideration of the Licensing Board'S Partial Initial Decision ML0901400792008-12-29029 December 2008 Entergy'S Answer Opposing Motion by New York Et Al. for Leave to Submit Brief Amici Curiae ML0901602092008-12-19019 December 2008 New England Coalition'S Response to NRC Staff'S Petition for Review of the Licensing Board'S Partial Initial Decision, LBP-08-25 ML0900606092008-12-19019 December 2008 Entergy'S Answer in Support of NRC Staff'S Petition for Review of the Licensing Board'S Partial Initial Decision ML0836600342008-12-19019 December 2008 Vermont Department of Public Service Opposition to Petition for Review of Partial Initial Decision LBP-08-25 ML0836401982008-12-11011 December 2008 Entergy'S Answer to Commonwealth of Massachusetts Petition for Review of LBP-08-25 and Request for Consolidated Ruling ML0835205232008-12-10010 December 2008 Entergy'S Response in Opposition to New England Coalition'S Motion to Extend Time to File Petition for Review ML0835004492008-12-0404 December 2008 Entergy'S Motion for Clarification ML0835100872008-12-0404 December 2008 Entergy'S Opposition to New England Coalition'S Motion to Extend Time to File Motion for Reconsideration ML0824018252008-08-25025 August 2008 Vermont Yankee - NRC Staff'S Proposed Findings of Fact and Conclusion of Law and Order in the Form of an Initial Decision ML0819905482008-07-15015 July 2008 Vermont Yankee - NRC Staff Letter to Board Regarding Evidentiary Hearing Attendees ML0820501022008-07-15015 July 2008 Entergy'S Response to July 11, 2008 Board Order ML0820501012008-07-15015 July 2008 Entergy'S Reply to Responses to Licensing Board'S Questions ML0820406152008-07-15015 July 2008 Vermont Department of Public Service Response to Entergy and NRC Staff Brief on Pre-Trial Legal Issues ML0819806542008-07-15015 July 2008 Vermont Yankee - NRC Staff'S Reply Brief ML0819704842008-07-0909 July 2008 Entergy'S Answers to Licensing Board Questions ML0819202482008-07-0909 July 2008 Vermont Yankee - Nrc'S Brief in Response to Board Order ML0819805252008-07-0808 July 2008 Joint Stipulation ML0819704802008-07-0707 July 2008 Entergy'S Response to Vermont Department of Public Service Motion for Modification of the Scheduling Order to Facilitate Full Compliance with 10 C.F.R. 2.323(b) ML0818504242008-07-0202 July 2008 Vermont Yankee - NRC Staff'S Response to Vermont Department of Public Service'S Motion to Modify the Schedule ML0819100872008-06-30030 June 2008 New England Coalition, Inc'S Opposition to Entergy'S and the NRC Staff'S Motions in Limine to Exclude Rebuttal Testimony of Ulrich Witte ML0819200412008-06-30030 June 2008 Entergy'S Response in Support of Staff'S Motion in Limine to Exclude Witte Rebuttal Testimony ML0818304142008-06-23023 June 2008 Entergy'S Response in Opposition to NEC Motion to File Untimely Rebuttal Testimony by Ulrich Witte ML0817807432008-06-20020 June 2008 Filing Discussing Proprietary Documents in the Matter of Entergy Nuclear Vermont Yankee, LLC and Entergy Nuclear Operations, Inc ML0817107262008-06-19019 June 2008 Vermont Yankee - NRC Staff'S Response to Nec'S Motion to Strike NRC Staff'S Rebuttal Testimony Concerning NEC Contention 4 ML0817800972008-06-19019 June 2008 Entergy'S Response in Support of Staff'S Motion in Limine ML0816305762008-06-0505 June 2008 2008/06/05-Vermont Yankee License Renewal Proceeding: June 24 Call ML0814905522008-05-20020 May 2008 Certificate of Disclosure of Sarah Hofmann, for the Vermont Department of Public Service Certifying Current with Disclosures Pursuant to 10 C.F.R. 2.336 That Are Relevant and Not Privileged to the Contentions Now Being Considered ML0814306502008-05-15015 May 2008 Supplemental Petition by Nuclear Information and Resource Service: Jersey Shore Nuclear Watch, Inc.; Grandmothers, Mothers and More for Energy Safety: New Jersey Public Interest Research Group: New Jersey Sierra Club.. ML0814906102008-05-15015 May 2008 2008/05/15-Supplemental Petition by Collective Petitioners for Additional Investigation and Correction of Deficiencies Regarding License Renewal Reviews for Oyster Creek, Indian Point, Pilgrim, and Vermont Yankee Nuclear Power Plants ML0814306512008-05-15015 May 2008 Supplemental Petition by Nuclear Information and Resource Service: Jersey Shore Nuclear Watch, Inc.: Grandmothers, Mothers and More for Energy Safety: New Jersey Public Interest Research Group: New Jersey Sierra Club: New Jersey.. ML0816402452008-05-15015 May 2008 2008/05/15-Supplemental Petition by Listed Companies for Additional Investigation and Correction of Deficiencies Regarding License Renewal Reviews, for Oyster Creek, Indian Point, Pilgrim, and Vermont Yankee Nuclear Power Plants ML0813501902008-05-0606 May 2008 Commonwealth of Massachusetts' Notice of Intent to Participate as an Interested State 2011-03-10
[Table view] Category:Responses and Contentions
MONTHYEARML1107503812011-03-10010 March 2011 Entergy'S Response to New England Coalition'S Motion for Stay and Request for Further Opportunity for Hearings ML1036300302010-12-23023 December 2010 Entergy'S Response to the Supplement to New England Coalition'S Petition for Commission Review of LBP-10-19 ML1033403292010-11-22022 November 2010 Entergy'S Answer Opposing New England Coalition'S Petition for Commission Review of LBP-10-19 ML1028002492010-09-30030 September 2010 New England Coalition'S Answer & Opposition to Entergy'S Motion to Strike Declaration of Paul Blanch ML1027204022010-09-20020 September 2010 New England Coalition'S Reply to NRC Staff and Entergy Nuclear Vermont Yankee Opposition to New England Coalition'S Motion to Reopen the Hearing & Reply to NRC Staff'S Answer to Proposed New Contention ML1026003772010-09-14014 September 2010 Entergy'S Answer Opposing New England Coalition'S Motion to Reopen ML1007403702010-03-12012 March 2010 Entergy'S Response in Opposition to New England Coalition'S Stay Request ML0922400652009-08-0303 August 2009 Entergy'S Response in Opposition to New England Coalition'S Petition for Review of LBP-09-09 ML0921202202009-07-23023 July 2009 New England Coalition'S Petition for Review of the Licensing Board'S Full Initial Decision, LBP-09-09 ML0916702632009-06-0808 June 2009 New England Coalition'S Opposition to Entergy'S Motion to Strike New England Coalition'S Reply to NRC Staff and Entergy Oppositions to Nec'S Motion to File a Timely New Contention ML0915404042009-05-26026 May 2009 Nec'S Reply to NRC Staff and Entergy Oppositions to Nec'S Motion to File a Timely New Contention ML0914203732009-05-18018 May 2009 Entergy'S Opposition to Nec'S Motion to File a Timely New Contention ML0913400192009-05-0707 May 2009 New England Coalition'S Reply to Nrc'S Staff and Entergy Answers to New England Coalition'S Motion to Hold in Abeyance Action on It'S Proposed Contention Until Issuance of NRC Staff Supplemental Safety Evaluation Report ML0912708592009-05-0101 May 2009 Entergy'S Opposition to New England Coalition'S Motion to Hold Action on Proposed Contention in Abeyance Until Issuance of NRC Staff Supplemental Safety Evaluation Report ML0908404222009-03-10010 March 2009 Final Calculations of Record for the Confirmatory Environmentally Assisted Fatigue (Cufen) Analyses on the Reactor Pressure Vessel Core Spray (CS) and Recirculation Outlet (RO) Nozzles at Vermont Yankee ML0912101052009-03-0909 March 2009 New England Coalition'S Petition for Leave Reply to Entergy Responses to New England Coalition'S Motion to Alter or Amend the Schedule in the Above Captioned Proceeding ML0907711422009-03-0909 March 2009 Entergy'S Opposition to New England Coalition'S Motion to Alter or Amend the Schedule ML0901400782009-01-0707 January 2009 Entergy'S Opposition to New England Coalition'S Motion for Reconsideration of the Licensing Board'S Partial Initial Decision ML0901400792008-12-29029 December 2008 Entergy'S Answer Opposing Motion by New York Et Al. for Leave to Submit Brief Amici Curiae ML0901602092008-12-19019 December 2008 New England Coalition'S Response to NRC Staff'S Petition for Review of the Licensing Board'S Partial Initial Decision, LBP-08-25 ML0900606092008-12-19019 December 2008 Entergy'S Answer in Support of NRC Staff'S Petition for Review of the Licensing Board'S Partial Initial Decision ML0836600342008-12-19019 December 2008 Vermont Department of Public Service Opposition to Petition for Review of Partial Initial Decision LBP-08-25 ML0836401982008-12-11011 December 2008 Entergy'S Answer to Commonwealth of Massachusetts Petition for Review of LBP-08-25 and Request for Consolidated Ruling ML0835205232008-12-10010 December 2008 Entergy'S Response in Opposition to New England Coalition'S Motion to Extend Time to File Petition for Review ML0835004492008-12-0404 December 2008 Entergy'S Motion for Clarification ML0835100872008-12-0404 December 2008 Entergy'S Opposition to New England Coalition'S Motion to Extend Time to File Motion for Reconsideration ML0824018252008-08-25025 August 2008 Vermont Yankee - NRC Staff'S Proposed Findings of Fact and Conclusion of Law and Order in the Form of an Initial Decision ML0819905482008-07-15015 July 2008 Vermont Yankee - NRC Staff Letter to Board Regarding Evidentiary Hearing Attendees ML0820501022008-07-15015 July 2008 Entergy'S Response to July 11, 2008 Board Order ML0820501012008-07-15015 July 2008 Entergy'S Reply to Responses to Licensing Board'S Questions ML0820406152008-07-15015 July 2008 Vermont Department of Public Service Response to Entergy and NRC Staff Brief on Pre-Trial Legal Issues ML0819806542008-07-15015 July 2008 Vermont Yankee - NRC Staff'S Reply Brief ML0819704842008-07-0909 July 2008 Entergy'S Answers to Licensing Board Questions ML0819202482008-07-0909 July 2008 Vermont Yankee - Nrc'S Brief in Response to Board Order ML0819805252008-07-0808 July 2008 Joint Stipulation ML0819704802008-07-0707 July 2008 Entergy'S Response to Vermont Department of Public Service Motion for Modification of the Scheduling Order to Facilitate Full Compliance with 10 C.F.R. 2.323(b) ML0818504242008-07-0202 July 2008 Vermont Yankee - NRC Staff'S Response to Vermont Department of Public Service'S Motion to Modify the Schedule ML0819100872008-06-30030 June 2008 New England Coalition, Inc'S Opposition to Entergy'S and the NRC Staff'S Motions in Limine to Exclude Rebuttal Testimony of Ulrich Witte ML0819200412008-06-30030 June 2008 Entergy'S Response in Support of Staff'S Motion in Limine to Exclude Witte Rebuttal Testimony ML0818304142008-06-23023 June 2008 Entergy'S Response in Opposition to NEC Motion to File Untimely Rebuttal Testimony by Ulrich Witte ML0817807432008-06-20020 June 2008 Filing Discussing Proprietary Documents in the Matter of Entergy Nuclear Vermont Yankee, LLC and Entergy Nuclear Operations, Inc ML0817107262008-06-19019 June 2008 Vermont Yankee - NRC Staff'S Response to Nec'S Motion to Strike NRC Staff'S Rebuttal Testimony Concerning NEC Contention 4 ML0817800972008-06-19019 June 2008 Entergy'S Response in Support of Staff'S Motion in Limine ML0816305762008-06-0505 June 2008 2008/06/05-Vermont Yankee License Renewal Proceeding: June 24 Call ML0814905522008-05-20020 May 2008 Certificate of Disclosure of Sarah Hofmann, for the Vermont Department of Public Service Certifying Current with Disclosures Pursuant to 10 C.F.R. 2.336 That Are Relevant and Not Privileged to the Contentions Now Being Considered ML0814306502008-05-15015 May 2008 Supplemental Petition by Nuclear Information and Resource Service: Jersey Shore Nuclear Watch, Inc.; Grandmothers, Mothers and More for Energy Safety: New Jersey Public Interest Research Group: New Jersey Sierra Club.. ML0814906102008-05-15015 May 2008 2008/05/15-Supplemental Petition by Collective Petitioners for Additional Investigation and Correction of Deficiencies Regarding License Renewal Reviews for Oyster Creek, Indian Point, Pilgrim, and Vermont Yankee Nuclear Power Plants ML0814306512008-05-15015 May 2008 Supplemental Petition by Nuclear Information and Resource Service: Jersey Shore Nuclear Watch, Inc.: Grandmothers, Mothers and More for Energy Safety: New Jersey Public Interest Research Group: New Jersey Sierra Club: New Jersey.. ML0816402452008-05-15015 May 2008 2008/05/15-Supplemental Petition by Listed Companies for Additional Investigation and Correction of Deficiencies Regarding License Renewal Reviews, for Oyster Creek, Indian Point, Pilgrim, and Vermont Yankee Nuclear Power Plants ML0813501902008-05-0606 May 2008 Commonwealth of Massachusetts' Notice of Intent to Participate as an Interested State 2011-03-10
[Table view] |
Text
tIA 8 a DOCKETED USNRC July 14, 2008 (8:00am)OFFICE OF SECRETARY RULEMAKINGS AND ADJUDICATIONS STAFF July 8, 2008 UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION Before the Atomic Safety and Licensing Board In the Matter of))))Entergy Nuclear Vermont Yankee, LLC and Entergy Nuclear Operations, Inc.Docket No. 50-271-LR ASLBP No. 06-849-03-LR
)(Vermont Yankee Nuclear Power Station) )JOINT STIPULATION Pursuant to para. 7 of the Atomic Safety and Licensing Board's ("Board")
Initial Scheduling Order dated November 17, 2006, as modified by the Board during the prehearing telephone conference held on June 24, 2008 (Tr. 656-57), Applicants Entergy Nuclear Vermont Yankee, LLC and Entergy Nuclear Operations, Inc. (collectively "Entergy"), the NRC Staff, and intervenor New England Coalition, Inc. ("NEC") hereby agree to stipulate to the following facts.NEC CONTENTIONS 2A AND 2B 1. Section 4.3.3 of the License Renewal Application for VY ("Application")
presents Entergy's initial assessment of the effects of the reactor coolant environment on fatigue life for nine plant-specific locations of six reactor components at VY selected in accordance NUREG/CR-6260 and the NRC Staff s "GALL Report".2. The initial CUF s computed by Entergy for VY are tabulated in Table 4.3.3 of the en Application.
As that Table shows, seven of the nine locations had CUF s greater than en unity, and therefore greater than the specified criterion of the ASME Code.3. To address these results, the Application states (Application, Section 4.3.3 at 4.3-7) that, prior to entering the period of extended operation, for each location that may exceed a CUF of 1.0 when considering environmental effects, VY will implement one of three possible courses of action, including "further refinement of the fatigue analyses to lower the predicted CUFs to less than 1.0." 4. Entergy engaged SIA to performn-refined analyses to calculate the CUFs, F ens and CUFen s for all nine locations of interest in accordance with the approach described in the GALL Report.5. Final versions of fifteen refined calculations were issued in August and December 2007.6. To resolve certain NRC Staff concerns, Entergy proposed, and the NRC Staff accepted, that Entergy perform a confirmatory CUF analysis of the feedwater nozzle using en methods that would be acceptable to the NRC.7. The Staff imposed a license condition requiring similar confirmatory analyses for two other nozzles, the recirculation outlet nozzle and the core spray nozzle. Those confirmatory analyses will become the "analyses of record" for those two locations.
Entergy is to submit these analyses to the Staff no later than two years prior to the start of the period of extended operation, in March 2012.NEC CONTENTION 3 8. In 2002, steam dryer cracking and damage to components and supports for the main steam and feedwater lines were observed at the Quad Cities Unit 2 nuclear power plant.Loose parts were shed by the dryer due to metal fatigue failure of the dryer caused by flow-induced vibration.
- 9. The Quad Cities 2 experience raised a concern that a loss of physical integrity of the dryer could result in the release and migration of loose dryer sections or parts to other components and could thus have adverse impact on safety-related equipment.
- 10. The existence of cracks on the surface of a steam dryer needs to be identified and evaluated before the cracks progress to the point where they could cause a loss of physical integrity of the dryer, resulting in loose parts.I
- 11. In its License Renewal Application, Entergy addresses aging management of the VY steam dryer as follows: Cracking due to flow-induced vibration in the stainless steel steam dryers is managed by the BWR Vessel-Internals Program. The BWR Vessel Internals Program currently incorporates the guidance of GE-SIL-644, Revision 1. VYNPS will evaluate BWRVIP-139 once it is approved by the staff and either include its recommendations in the VYNPS BWR Vessel Internals Program or inform the staff of VYNPS's exceptions to that document.License Renewal Application, § 3.1.2.2.11 "Cracking due to Flow-Induced Vibration."-
- 13. GE-SIL-644 recommends that BWR licensees institute a program for the long term monitoring and inspection of their steam dryers. It provides inspection and monitoring guidelines.
- 14. The monitoring component of the proposed VY steam dryer management program consists of assessing the status of the steam dryer by the plant operators and VY's technical staff through the continuous monitoring of certain plant parameters.
- 15. With respect to dryer inspections during plant refueling outages, the details of the visual inspection program to be implemented are set forth in the section of GE-SIL-644 devoted to BWR-3 steam dryers, which is Appendix C, pp. 15-16. The dryer inspections are to be performed in accordance with the VY BWRVIP Program Plan, VY-RPT-06-00006 (Exhibit E3-12) and GE-SIL-644, Revision 1.NEC CONTENTION 4 16. The FAC Program that Entergy proposes to implement during the license renewal period includes the following activities: (a) conducting an analysis to determine critical locations; (b) performing baseline inspections to determine the extent of thinning at these 2 locations; and (c) performing follow-up inspections to confirm the predictions, or repairing or replacing components as necessary.
- 17. Section B. 1.13 of the License Renewal Application for VY ("Application")
indicates that-theVY program for addressing flow accelerated corrosion
("FAC") of steel piping and components is comparable to the program described in the NRC guidance document"Generic Aging Lessons Learned (GALL) Report -- Tabulation of Results," NUREG-1801, Vol. 2, Rev. 1 (Sep. 2005) ("NUREG-1801"),Section XI.M17, Flow Accelerated Corrosion.
Application at B-47.Entergy has been authorized by the NRC Staff and NEC to submit this Joint Stipulation on its own behalf as well as theirs.Respectfully Submitted, DAi Mat4K. Travie /-Diaz Blake J. Nelson PILLSBURY WINTHROP SHAW PITTMAN LLP 2300 N Street, NW Washington, DC 20037-1122 Tel. (202) 663-8000 Counsel for Entergy Dated: July 8, 2008 3 UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION Before the Atomic Safety and Licensing Board In the Matter of Entergy Nuclear Vermont Yankee, LLC and Entergy Nuclear Operations, Inc.(Vermont Yankee Nuclear Power Station)))))))Docket No. 50-271 -LR ASLBP No. 06-849-03-LR CERTIFICATE OF SERVICE I hereby certify that copies of "Joint Stipulation" were served on the persons listed below by deposit in the U.S. Mail, first class, postage prepaid, and where indicated by an asterisk by electronic mail, this 8th day of July, 2008.*Administrative Judge Alex S. Karlin, Esq., Chairman Atomic Safety and Licensing Board Mail Stop T-3 F23 U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 ask2@(dnrc.gov
- Administrative Judge William H. Reed 1819 Edgewood Lane Charlottesville, VA 22902 whrcvillea~embarcimail.com
- Administrative Judge Dr. Richard E. Wardwell Atomic Safety and Licensing Board Mail Stop T-3 F23 U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 rew(dnrc.gov
- Secretary Att'n: Rulemakings and Adjudications Staff Mail Stop 0-16 C I U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 secy@nrc.gov, hearingdocket@ldnrc.
gov Atomic Safety and Licensing Board Mail Stop T-3 F23 U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001
- Office of Commission Appellate Adjudication Mail Stop 0-16 C I U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 OCAAmailgi-nrc.gov
- Lloyd Subin, Esq.*Mary Baty, Esq.* Jessica A. Bielecki, Esq.*Susan L. Uttal, Esq.Office of the General Counsel Mail Stop O-15-D21 U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 LBS3@nrc.gov; mcbl @nrc.gov;jessica.bielecki(Ziýnrc.gov; susan.uttalgnrc.gov
- Sarah Hofmann, Esq.Director of Public Advocacy Department of Public Service 112 State Street -Drawer 20 Montpelier, VT 05620-2601 Sarah.hofinann&
state.vt.us
- Ronald A. Shems, Esq.*Karen Tyler, Esq.Shems, Dunkiel, Kassel & Saunders, PLLC 9 College Street Burlington, VT 05401 rshems@sdkslaw.
corn ktyler@sdkslaw.com
- Marcia Carpenter, Esq.Atomic Safety and Licensing Board Panel Mail Stop T-3 F23 U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 mxc7@(nrc.gov
- Diane Curran, Esq.Harmon, Curran, Spielberg, & Eisenberg, L.L.P.1726 M Street N.W., Suite 600 Washington, D.C. 20036 dcurrana~harmoncurran.com
- Peter L. Roth, Esq.Office of the New Hampshire Attorney General 33 Capitol Street Concord, NH 03301 Peter.rothgdoj.nh.gov
- Lauren Bregman, Law Clerk Atomic Safety and Licensing Board U.S. Nuclear Regulatory Commission Mail Stop: T-3 F23 Washington, D.C. 20555-0001 Lauren. Bregmangnrc.
gov* Matthew Brock Assistant Attorney General Office of the Attorney General One Ashburton Place, 1 8 th Floor Boston, MA 02108 Matthew.BrockOistate.ma.us B J. Nelso~n 2