MONTHYEARML1107503812011-03-10010 March 2011 Entergy'S Response to New England Coalition'S Motion for Stay and Request for Further Opportunity for Hearings ML1036300302010-12-23023 December 2010 Entergy'S Response to the Supplement to New England Coalition'S Petition for Commission Review of LBP-10-19 ML1033403292010-11-22022 November 2010 Entergy'S Answer Opposing New England Coalition'S Petition for Commission Review of LBP-10-19 ML1028002492010-09-30030 September 2010 New England Coalition'S Answer & Opposition to Entergy'S Motion to Strike Declaration of Paul Blanch ML1027204022010-09-20020 September 2010 New England Coalition'S Reply to NRC Staff and Entergy Nuclear Vermont Yankee Opposition to New England Coalition'S Motion to Reopen the Hearing & Reply to NRC Staff'S Answer to Proposed New Contention ML1026003772010-09-14014 September 2010 Entergy'S Answer Opposing New England Coalition'S Motion to Reopen ML1007403702010-03-12012 March 2010 Entergy'S Response in Opposition to New England Coalition'S Stay Request ML0922400652009-08-0303 August 2009 Entergy'S Response in Opposition to New England Coalition'S Petition for Review of LBP-09-09 ML0921202202009-07-23023 July 2009 New England Coalition'S Petition for Review of the Licensing Board'S Full Initial Decision, LBP-09-09 ML0916702632009-06-0808 June 2009 New England Coalition'S Opposition to Entergy'S Motion to Strike New England Coalition'S Reply to NRC Staff and Entergy Oppositions to Nec'S Motion to File a Timely New Contention ML0915404042009-05-26026 May 2009 Nec'S Reply to NRC Staff and Entergy Oppositions to Nec'S Motion to File a Timely New Contention ML0914203732009-05-18018 May 2009 Entergy'S Opposition to Nec'S Motion to File a Timely New Contention ML0913400192009-05-0707 May 2009 New England Coalition'S Reply to Nrc'S Staff and Entergy Answers to New England Coalition'S Motion to Hold in Abeyance Action on It'S Proposed Contention Until Issuance of NRC Staff Supplemental Safety Evaluation Report ML0912708592009-05-0101 May 2009 Entergy'S Opposition to New England Coalition'S Motion to Hold Action on Proposed Contention in Abeyance Until Issuance of NRC Staff Supplemental Safety Evaluation Report ML0908404222009-03-10010 March 2009 Final Calculations of Record for the Confirmatory Environmentally Assisted Fatigue (Cufen) Analyses on the Reactor Pressure Vessel Core Spray (CS) and Recirculation Outlet (RO) Nozzles at Vermont Yankee ML0912101052009-03-0909 March 2009 New England Coalition'S Petition for Leave Reply to Entergy Responses to New England Coalition'S Motion to Alter or Amend the Schedule in the Above Captioned Proceeding ML0907711422009-03-0909 March 2009 Entergy'S Opposition to New England Coalition'S Motion to Alter or Amend the Schedule ML0901400782009-01-0707 January 2009 Entergy'S Opposition to New England Coalition'S Motion for Reconsideration of the Licensing Board'S Partial Initial Decision ML0901400792008-12-29029 December 2008 Entergy'S Answer Opposing Motion by New York Et Al. for Leave to Submit Brief Amici Curiae ML0901602092008-12-19019 December 2008 New England Coalition'S Response to NRC Staff'S Petition for Review of the Licensing Board'S Partial Initial Decision, LBP-08-25 ML0900606092008-12-19019 December 2008 Entergy'S Answer in Support of NRC Staff'S Petition for Review of the Licensing Board'S Partial Initial Decision ML0836600342008-12-19019 December 2008 Vermont Department of Public Service Opposition to Petition for Review of Partial Initial Decision LBP-08-25 ML0836401982008-12-11011 December 2008 Entergy'S Answer to Commonwealth of Massachusetts Petition for Review of LBP-08-25 and Request for Consolidated Ruling ML0835205232008-12-10010 December 2008 Entergy'S Response in Opposition to New England Coalition'S Motion to Extend Time to File Petition for Review ML0835004492008-12-0404 December 2008 Entergy'S Motion for Clarification ML0835100872008-12-0404 December 2008 Entergy'S Opposition to New England Coalition'S Motion to Extend Time to File Motion for Reconsideration ML0824018252008-08-25025 August 2008 Vermont Yankee - NRC Staff'S Proposed Findings of Fact and Conclusion of Law and Order in the Form of an Initial Decision ML0819905482008-07-15015 July 2008 Vermont Yankee - NRC Staff Letter to Board Regarding Evidentiary Hearing Attendees ML0820501022008-07-15015 July 2008 Entergy'S Response to July 11, 2008 Board Order ML0820501012008-07-15015 July 2008 Entergy'S Reply to Responses to Licensing Board'S Questions ML0820406152008-07-15015 July 2008 Vermont Department of Public Service Response to Entergy and NRC Staff Brief on Pre-Trial Legal Issues ML0819806542008-07-15015 July 2008 Vermont Yankee - NRC Staff'S Reply Brief ML0819704842008-07-0909 July 2008 Entergy'S Answers to Licensing Board Questions ML0819202482008-07-0909 July 2008 Vermont Yankee - Nrc'S Brief in Response to Board Order ML0819805252008-07-0808 July 2008 Joint Stipulation ML0819704802008-07-0707 July 2008 Entergy'S Response to Vermont Department of Public Service Motion for Modification of the Scheduling Order to Facilitate Full Compliance with 10 C.F.R. 2.323(b) ML0818504242008-07-0202 July 2008 Vermont Yankee - NRC Staff'S Response to Vermont Department of Public Service'S Motion to Modify the Schedule ML0819100872008-06-30030 June 2008 New England Coalition, Inc'S Opposition to Entergy'S and the NRC Staff'S Motions in Limine to Exclude Rebuttal Testimony of Ulrich Witte ML0819200412008-06-30030 June 2008 Entergy'S Response in Support of Staff'S Motion in Limine to Exclude Witte Rebuttal Testimony ML0818304142008-06-23023 June 2008 Entergy'S Response in Opposition to NEC Motion to File Untimely Rebuttal Testimony by Ulrich Witte ML0817807432008-06-20020 June 2008 Filing Discussing Proprietary Documents in the Matter of Entergy Nuclear Vermont Yankee, LLC and Entergy Nuclear Operations, Inc ML0817107262008-06-19019 June 2008 Vermont Yankee - NRC Staff'S Response to Nec'S Motion to Strike NRC Staff'S Rebuttal Testimony Concerning NEC Contention 4 ML0817800972008-06-19019 June 2008 Entergy'S Response in Support of Staff'S Motion in Limine ML0816305762008-06-0505 June 2008 2008/06/05-Vermont Yankee License Renewal Proceeding: June 24 Call ML0814905522008-05-20020 May 2008 Certificate of Disclosure of Sarah Hofmann, for the Vermont Department of Public Service Certifying Current with Disclosures Pursuant to 10 C.F.R. 2.336 That Are Relevant and Not Privileged to the Contentions Now Being Considered ML0814306502008-05-15015 May 2008 Supplemental Petition by Nuclear Information and Resource Service: Jersey Shore Nuclear Watch, Inc.; Grandmothers, Mothers and More for Energy Safety: New Jersey Public Interest Research Group: New Jersey Sierra Club.. ML0814906102008-05-15015 May 2008 2008/05/15-Supplemental Petition by Collective Petitioners for Additional Investigation and Correction of Deficiencies Regarding License Renewal Reviews for Oyster Creek, Indian Point, Pilgrim, and Vermont Yankee Nuclear Power Plants ML0814306512008-05-15015 May 2008 Supplemental Petition by Nuclear Information and Resource Service: Jersey Shore Nuclear Watch, Inc.: Grandmothers, Mothers and More for Energy Safety: New Jersey Public Interest Research Group: New Jersey Sierra Club: New Jersey.. ML0816402452008-05-15015 May 2008 2008/05/15-Supplemental Petition by Listed Companies for Additional Investigation and Correction of Deficiencies Regarding License Renewal Reviews, for Oyster Creek, Indian Point, Pilgrim, and Vermont Yankee Nuclear Power Plants ML0813501902008-05-0606 May 2008 Commonwealth of Massachusetts' Notice of Intent to Participate as an Interested State 2011-03-10
[Table view] Category:Responses and Contentions
MONTHYEARML1107503812011-03-10010 March 2011 Entergy'S Response to New England Coalition'S Motion for Stay and Request for Further Opportunity for Hearings ML1036300302010-12-23023 December 2010 Entergy'S Response to the Supplement to New England Coalition'S Petition for Commission Review of LBP-10-19 ML1033403292010-11-22022 November 2010 Entergy'S Answer Opposing New England Coalition'S Petition for Commission Review of LBP-10-19 ML1028002492010-09-30030 September 2010 New England Coalition'S Answer & Opposition to Entergy'S Motion to Strike Declaration of Paul Blanch ML1027204022010-09-20020 September 2010 New England Coalition'S Reply to NRC Staff and Entergy Nuclear Vermont Yankee Opposition to New England Coalition'S Motion to Reopen the Hearing & Reply to NRC Staff'S Answer to Proposed New Contention ML1026003772010-09-14014 September 2010 Entergy'S Answer Opposing New England Coalition'S Motion to Reopen ML1007403702010-03-12012 March 2010 Entergy'S Response in Opposition to New England Coalition'S Stay Request ML0922400652009-08-0303 August 2009 Entergy'S Response in Opposition to New England Coalition'S Petition for Review of LBP-09-09 ML0921202202009-07-23023 July 2009 New England Coalition'S Petition for Review of the Licensing Board'S Full Initial Decision, LBP-09-09 ML0916702632009-06-0808 June 2009 New England Coalition'S Opposition to Entergy'S Motion to Strike New England Coalition'S Reply to NRC Staff and Entergy Oppositions to Nec'S Motion to File a Timely New Contention ML0915404042009-05-26026 May 2009 Nec'S Reply to NRC Staff and Entergy Oppositions to Nec'S Motion to File a Timely New Contention ML0914203732009-05-18018 May 2009 Entergy'S Opposition to Nec'S Motion to File a Timely New Contention ML0913400192009-05-0707 May 2009 New England Coalition'S Reply to Nrc'S Staff and Entergy Answers to New England Coalition'S Motion to Hold in Abeyance Action on It'S Proposed Contention Until Issuance of NRC Staff Supplemental Safety Evaluation Report ML0912708592009-05-0101 May 2009 Entergy'S Opposition to New England Coalition'S Motion to Hold Action on Proposed Contention in Abeyance Until Issuance of NRC Staff Supplemental Safety Evaluation Report ML0908404222009-03-10010 March 2009 Final Calculations of Record for the Confirmatory Environmentally Assisted Fatigue (Cufen) Analyses on the Reactor Pressure Vessel Core Spray (CS) and Recirculation Outlet (RO) Nozzles at Vermont Yankee ML0912101052009-03-0909 March 2009 New England Coalition'S Petition for Leave Reply to Entergy Responses to New England Coalition'S Motion to Alter or Amend the Schedule in the Above Captioned Proceeding ML0907711422009-03-0909 March 2009 Entergy'S Opposition to New England Coalition'S Motion to Alter or Amend the Schedule ML0901400782009-01-0707 January 2009 Entergy'S Opposition to New England Coalition'S Motion for Reconsideration of the Licensing Board'S Partial Initial Decision ML0901400792008-12-29029 December 2008 Entergy'S Answer Opposing Motion by New York Et Al. for Leave to Submit Brief Amici Curiae ML0901602092008-12-19019 December 2008 New England Coalition'S Response to NRC Staff'S Petition for Review of the Licensing Board'S Partial Initial Decision, LBP-08-25 ML0900606092008-12-19019 December 2008 Entergy'S Answer in Support of NRC Staff'S Petition for Review of the Licensing Board'S Partial Initial Decision ML0836600342008-12-19019 December 2008 Vermont Department of Public Service Opposition to Petition for Review of Partial Initial Decision LBP-08-25 ML0836401982008-12-11011 December 2008 Entergy'S Answer to Commonwealth of Massachusetts Petition for Review of LBP-08-25 and Request for Consolidated Ruling ML0835205232008-12-10010 December 2008 Entergy'S Response in Opposition to New England Coalition'S Motion to Extend Time to File Petition for Review ML0835004492008-12-0404 December 2008 Entergy'S Motion for Clarification ML0835100872008-12-0404 December 2008 Entergy'S Opposition to New England Coalition'S Motion to Extend Time to File Motion for Reconsideration ML0824018252008-08-25025 August 2008 Vermont Yankee - NRC Staff'S Proposed Findings of Fact and Conclusion of Law and Order in the Form of an Initial Decision ML0819905482008-07-15015 July 2008 Vermont Yankee - NRC Staff Letter to Board Regarding Evidentiary Hearing Attendees ML0820501022008-07-15015 July 2008 Entergy'S Response to July 11, 2008 Board Order ML0820501012008-07-15015 July 2008 Entergy'S Reply to Responses to Licensing Board'S Questions ML0820406152008-07-15015 July 2008 Vermont Department of Public Service Response to Entergy and NRC Staff Brief on Pre-Trial Legal Issues ML0819806542008-07-15015 July 2008 Vermont Yankee - NRC Staff'S Reply Brief ML0819704842008-07-0909 July 2008 Entergy'S Answers to Licensing Board Questions ML0819202482008-07-0909 July 2008 Vermont Yankee - Nrc'S Brief in Response to Board Order ML0819805252008-07-0808 July 2008 Joint Stipulation ML0819704802008-07-0707 July 2008 Entergy'S Response to Vermont Department of Public Service Motion for Modification of the Scheduling Order to Facilitate Full Compliance with 10 C.F.R. 2.323(b) ML0818504242008-07-0202 July 2008 Vermont Yankee - NRC Staff'S Response to Vermont Department of Public Service'S Motion to Modify the Schedule ML0819100872008-06-30030 June 2008 New England Coalition, Inc'S Opposition to Entergy'S and the NRC Staff'S Motions in Limine to Exclude Rebuttal Testimony of Ulrich Witte ML0819200412008-06-30030 June 2008 Entergy'S Response in Support of Staff'S Motion in Limine to Exclude Witte Rebuttal Testimony ML0818304142008-06-23023 June 2008 Entergy'S Response in Opposition to NEC Motion to File Untimely Rebuttal Testimony by Ulrich Witte ML0817807432008-06-20020 June 2008 Filing Discussing Proprietary Documents in the Matter of Entergy Nuclear Vermont Yankee, LLC and Entergy Nuclear Operations, Inc ML0817107262008-06-19019 June 2008 Vermont Yankee - NRC Staff'S Response to Nec'S Motion to Strike NRC Staff'S Rebuttal Testimony Concerning NEC Contention 4 ML0817800972008-06-19019 June 2008 Entergy'S Response in Support of Staff'S Motion in Limine ML0816305762008-06-0505 June 2008 2008/06/05-Vermont Yankee License Renewal Proceeding: June 24 Call ML0814905522008-05-20020 May 2008 Certificate of Disclosure of Sarah Hofmann, for the Vermont Department of Public Service Certifying Current with Disclosures Pursuant to 10 C.F.R. 2.336 That Are Relevant and Not Privileged to the Contentions Now Being Considered ML0814306502008-05-15015 May 2008 Supplemental Petition by Nuclear Information and Resource Service: Jersey Shore Nuclear Watch, Inc.; Grandmothers, Mothers and More for Energy Safety: New Jersey Public Interest Research Group: New Jersey Sierra Club.. ML0814906102008-05-15015 May 2008 2008/05/15-Supplemental Petition by Collective Petitioners for Additional Investigation and Correction of Deficiencies Regarding License Renewal Reviews for Oyster Creek, Indian Point, Pilgrim, and Vermont Yankee Nuclear Power Plants ML0814306512008-05-15015 May 2008 Supplemental Petition by Nuclear Information and Resource Service: Jersey Shore Nuclear Watch, Inc.: Grandmothers, Mothers and More for Energy Safety: New Jersey Public Interest Research Group: New Jersey Sierra Club: New Jersey.. ML0816402452008-05-15015 May 2008 2008/05/15-Supplemental Petition by Listed Companies for Additional Investigation and Correction of Deficiencies Regarding License Renewal Reviews, for Oyster Creek, Indian Point, Pilgrim, and Vermont Yankee Nuclear Power Plants ML0813501902008-05-0606 May 2008 Commonwealth of Massachusetts' Notice of Intent to Participate as an Interested State 2011-03-10
[Table view] |
Text
DOCKETED USNRC December 4, 2008 (12:36pm)
OFFICE OF SECRETARY December 4, 2008 RULEMAKINGS AND ADJUDICATIONS STAFF UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION Before the Atomic Safety and Licensing Board In the Matter of
)
Entergy Nuclear Vermont Yankee, LLC ) Docket No. 50-271-LR and Entergy Nuclear Operations, Inc. ) ASLBP No. 06-849-03-LR
)
(Vermont Yankee Nuclear Power Station) )
ENTERGY'S MOTION FOR CLARIFICATION Pursuant to 10 C.F.R. § 2.323(a),' Entergy Nuclear Vermont Yankee, LLC and Entergy Nuclear Operations, Inc. (collectively "Entergy") respectfully request clarification of an apparent inconsistency in the schedule set forth in the Atomic Safety and Licensing Board's ('.'Board")
Partial Initial Decision LBP-08-25 issued on November 24, 2008 ("Decision"). The apparent inconsistency relates to the schedule for further actions following Entergy's submittal of confirmatory environmentally assisted fatigue ("CUFen") calculations for the Core Spray ("CS")
and Reactor Recirculation ("RR") outlet nozzles at the Vermont Yankee Nuclear Power Station.
The nature of the apparent inconsistency is as follows. At one point in its Decision, the Board states:
Assuming Entergy still wishes to pursue this license renewal, it must (1) recalculate the CUFen analyses for the CS and RR outlet nozzles, in accordance with the ASME Code, NUREG[/CR-]6583 and 5704, and all other regulatory guidance, (2) resubmit these results to the NRC Staff and serve them on the other parties herein, and (3) either demonstrate that the TLAAs [Time Limited Aging Analyses] are less than unity or submit an adequate AMP [Aging Management Plan] for these components. At that point we presume (but do not 10 C.F.R. § 2.323(a) provides: "(a) Presentation and disposition. All motions must be addressed to the Commission or other designated presiding officer. A motion must be made no later than ten (10) days after the occurrence or circumstance from which the motion arises. All written motions must be filed with the Secretary and served on all parties to the proceeding."
and cannot order) that the NRC Staff will evaluate Entergy's submissions.
Presumably NEC [New England Coalition] Will do the same.
If the CUFen analyses are (1) done in accordance with the above stated guidance and the basic approach used in the Confirmatory CUFen Analysis for the FW
[Feedwater] nozzle, (2) contain no significantly different scientific or technical judgments, and (3) demonstrate values less than unity, then this adjudicatory proceeding terminates. If not, NEC may file a new or amended contention challenging the adequacy of the CUFen calculation, or, if Entergy chooses to proceed under the AMP route, NEC may revitalize dormant Contention.2 (as to the adequacy of Entergy's AMP). In light of these possible eventualities, our ruling today can only be a partial initial decision, and this ASLB proceeding will remain open until 45 days after Entergy performs the confirmatory CUFen analyses on the CS and RR nozzles, the NRC Staff approves them, and Entergy serves NEC and Vermont with full written results of such analyses. If no motion involving any such new, amended, or revitalized contention is filed by the 45th day, the adjudicatory proceeding on these matters shall be terminated.
Decision at 67-68 (emphasis added). However, in the "Conclusions" section of the Decision, the Board states:
Accordingly, the Board rules that our authorization to issue the license renewal is contingent upon; and the license renewal application cannot be granted unless and until, Entergy completes the confirmatory CUFen analyses on the core spray and reactor recirculation nozzles with satisfactory results without using the simplified Green's function methodology and makes those analyses available for review by the NRC Staff and the other parties herein. The record will be held open with regards to Contentions 2A and 2B, and Contention 2 will be held in abeyance until 45 days after those events occur.
Id. at 151-52, emphasis added.
The earlier quote suggests that the instant proceeding will remain open until 45 days after Entergy performs the calculations, the NRC Staff ("Staff") approves them, and Entergy serves on the other parties the results of the calculations. The quote in the Decision's Conclusion, however, states that the proceeding will remain open for 45 days after Entergy performs the calculations and serves them on the Staff and the other parties, without requiring Staff approval during the 45-day period.
2
Entergy respectfully requests that the Board issue an Order' addressing this scheduling issue. In our view, the schedule set forth in the Decision's Conclusion is the appropriate one.
The Board recognizes that-it "presume[s] (but do[es] not and cannot order) that.the NRC Staff will evaluate Entergy's submissions." Decision, slip op. at 67. Whether and on what schedule the Staff will review and approve the new calculations cannot be either dictated or predicted by the Board or -the parties. Keeping.the proceeding open for an indefinite period of time would be inconsistent with the orderly conduct and ultimate conclusion of this proceeding, and would be detrimental to Entergy's right to obtaining a timely final decision on its license renewal application.
In addition, it is beyond dispute thatthe "focus of a hearing on a proposed licensing action is the adequacy of the application to support the licensing action, not the nature of the NRC Staff s review." Dominion Nuclear Connecticut, Inc. (Millstone Power Station, Unit 3),
CLI-08-17, 68 N.R.C. _ (2008), slip op. at 8; Pa'ina Hawaii, LLC, CLI-08-3, 67 N.R.C. 151, 168 n.73 (2008). Any deficiencies that another party may wish to raise with respect to Entergy's new calculations must be based on the adequacy of the calculations themselves and not on whether the Staff approves them. 2 Accordingly, there should be no need to await the Staff s approval of the calculations for contentions to be filed challenging them.
CONCLUSION For the above-stated reasons, Entergy respectfully requests that the Board clarify the schedule for closing this proceeding and that it rule that the proceeding will remain open for 45 days after Entergy performs the confirmatory CS and RR nozzle calculations and serves them on 2 Indeed, the New England Coalition was able to gain admittance of a new Contention 2B that challenged Entergy's CUFen "confirmatory analysis" of the feedwater nozzle, even though that analysis had been found acceptable by the NRC Staff. See Final Safety Evaluation Report (February 2008) Staff Exh. 1, Section 4.3.3.2 at 4-43; Order (Granting Motion to Amend NEC Contention 2A) (April 24, 2008).
3
the Staff and the other parties, so that any contentions challenging such calculations must be submitted within that 45 dayperiod.
- CERTIFICATION As required by 10 C.F.R. § 2.323(b), counsel for Entergy certifies that he has consulted with the other parties in connection with this Motion. NEC does not oppose Entergy's filing of the Motion but does not concur with Entergy's position on its substance. The NRC Staff, the Vermont Department of Public Service and the Commonwealth of Massachusetts do not oppose the filing of the Motion, but reserve the right to evaluate and respond to the Motion as appropriate. The State of New Hampshire has taken no position on the Motion.
Respectfully Submitted, David R. Lewis Matias F. Travieso-Diaz Blake J. Nelson PILLSBURY WINTHROP SHAW PITTMAN LLP 2300 N Street, N.W.
Washington, DC .20037-1128 Tel. (202) 663-8000 Counsel for Entergy Dated: December 4, 2008
.4
UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION Before the Atomic Safety and Licensing Board In the Matter of )
)
Entergy Nuclear Vermont Yankee, LLC ) Docket No. 50-271-LR and Entergy Nuclear Operations, Inc. ) ASLBP No. 06-849-03-LR
)
(Vermont Yankee Nuclear Power Station) )
CERTIFICATE OF SERVICE I hereby certify that copies of the foregoing "Entergy's Motion for Clarification" were served on the persons listed below by deposit in the U.S. Mail, first class, postage prepaid, and where indicated by an asterisk by electronic mail, this 4th day of December, 2008;
- Administrative Judge *Administrative Judge Alex S. Karlin, Esq., Chairman Dr. Richard E. Wardwell Atomic Safety and Licensing Board Atomic Safety and Licensing Board Mail Stop T-3 F23 Mail Stop T-3 F23 U.S. Nuclear Regulatory Commission U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 Washington, D.C. 20555-0001 ask2(d@nrc. gov rew(nrc. gov
- Administrative Judge *Secretary Dr. William H. Reed Att'n: Rulemakings and Adjudications Staff 1819 Edgewood Lane Mail Stop 0-16 C l Charlottesville, VA 22902 U.S. Nuclear Regulatory Commission whrcvilleo~embarqmail.com Washington, D.C. .20555-0001 secy@nrc.gov, hearingdocket(nirc.gov
- Office of Commission Appellate Adjudication Atomic Safety and Licensing Board Mail Stop 0-16 C1 Mail Stop T-3 F23 U.S. Nuclear Regulatory Commission U.S. Nuclear Regulatory Commission*
Washington, D.C. 20555-0001 Washington, D.C. 20555-0001 OCAAmailO~nrc.gov
0 1
- Lloyd Subin, Esq. *Sarah Hofmnann, Esq.
- Mary Baty, Esq. Director of Public Advocacy
- Jessica A. Bielecki, Esq. Department of Public Service
- .Susan L. Uttal, Esq. 112 State Street - Drawer 20 Office of the General Counsel Montpelier, VT 05620-2601 Mail Stop O-15-D21 Sarah.hofinannA~state.vt.us U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 LBS3 (ýnrc.gov; mcb 1 gnrc.ov; jessica.bielecki(dnrc.gov; susan.uttal(anrc.gov
- Anthony Z. Roisman, Esq. *Ronald A. Shems, Esq.
National Legal Scholars Law Firm *Karen Tyler, Esq.
84 East Thetford Road Shems, Dunkiel, Kassel & Saunders, PLLC Lyme, NH 03768 9 College Street aroismanOnationalleialscholars.com Burlington, VT 05401 rshems(a),sdkslaw.com ktyler(asdkslaw.com
- Peter L. Roth, Esq. *Zachary Kahn, Esq.
Office of the New Hampshire Attorney General Atomic Safety .and Licensing Board Panel 33 Capitol Street Mail Stop T-3 F23 Concord, NH 03301 U.S. Nuclear Regulatory Commission Peter.rothAdoJ .nh.gov Washington, D.C. 20555-0001 zachary.kahn(iinrc.gov
Assistant Attorney General Office of the Attorney General One Ashburton Place, 1 8 th Floor Boston, MA 02108 Matthew.Brock(iistate.ma.us David R. Lewis 2