ML102980470

From kanterella
Revision as of 02:23, 11 July 2019 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
Jump to navigation Jump to search
Memorandum from Timothy O'Hara to Arthur Burritt, Inservice Inspection Activities Inspection Feeder for Salem Unit 1, Inspection Report 05000272/2010003, Revision of July 21, 2010
ML102980470
Person / Time
Site: Salem PSEG icon.png
Issue date: 07/22/2010
From: O'Hara T
Engineering Region 1 Branch 1
To: Arthur Burritt
Reactor Projects Branch 3
References
FOIA/PA-2010-0334, IR-10-003
Download: ML102980470 (29)


See also: IR 05000272/2010003

Text

UNITED STATES NUCLEAR REGULATORY

COMMISSION

REGION I 475 ALLENDALE

ROAD KING OF PRUSSIA, PA 19406-1415

July 22, 2010 n/9 "(1WL-MEMORANDUM

TO: Arthur L. Burritt, Chief Projects Branch 3 Division of Reactor Projects Richard J. Conte, Chief Engineering

Branch I Division of Reactor Safety THRU: FROM: Timothy L. OHara, Reactor Inspector Engineering

Branch 1 Division of Reactor Safety SUBJECT: INSERVICE

INSPECTION

ACTIVITIES

INSPECTION

FEEDER FOR SALEM UNIT 1, INSPECTION

REPORT 05000272/2010003, REVISION OF July 21, 2010 The enclosed feeder contains input for the subject report resulting

from inspection

of Inservice Inspection (ISI) activities

during the period from April 5, 2010 to June 28, 2010, at Salem Unit 1.The inspection

was conducted

using Inspection

Procedure

71111.08, Inservice

Inspection

Activities

and Temporary

Instruction (TI) 2515/172, Reactor Coolant System Dissimilar

Metal Butt Welds. The results of this inspection

were presented

to Mr. Ed Eilola, Salem Plant Manager, at an exit meeting on June 28, 2010.Suggested

Cover Letter Input This feeder documents

one NRC-identified

finding of very low safety significance (Green). This finding was determined

to be a violation

of an NRC requirement.

This feeder also documents

a licensee-identified

violation, which was determined

to be of very low safety significance, in section 40A7 of this report. Because these violations

are of very low safety significance

and because the issues were entered into your corrective

action process, these findings are being treated as non-cited

violations (NCVs) consistent

with Section VI.A.1 of the NRC Enforcement

Policy.Issue of Agency Concern: Buried, Safety Related Piping: Because of an ongoing issue of Agency Concern about the degradation

of buried piping, this issue is being documented

as a licensee-identified

finding in Section 40A7, in accordance

with the guidance of IMC 0612-10."/ ý`bD'_ý'

V **vt' S 2 Nospecific action is needed for this concern in light of industry initiatives

on buried piping and the NRC Buried Piping Action Plan.Since this issue, as noted below, is licensee identified, a long discussion

was not permitted

by IMC0612 format requirements.

Documenting

an issue of agency wide concern appears to only apply to minor findings, however, this issue is more than minor and licensee identified.

The following

finding of very low safety significance

was identified

by PSEG and is a violation

of 10 CFR 50, Appendix B, Criterion

III, Design Control, an NRC requirement.

PSEG did not providean

effective

protective

coating for the buried AFW piping. This issue has been evaluated

via IMC 0609, Attachment

4, Initial Screening

and Characterization

of Findings and IMC 0612, Appendix B, Issue Screening.

During a planned excavation

and inspection

of the Unit 1 AFW buried piping to SG #12 and SG#14, PSEG identified

corrosion (significantly

below minimum wall thickness

for a design pressure of 1950 psi) of the safety related, ASME Class 3, Seismic Class 1 piping. PSEG repaired or replaced the affected Unit 1 buried AFW piping before returning

the plant to operation.

Portions of the Unit 1 and Unit 2 Auxiliary

Feedwater (AFW) System piping is buried piping and has not been visually inspected

since the plant began operation

in 1977 for Unit I and since 1979 for Salem Unit 2. In April 2010, approximately

680 ft. (340 ft. of the #12 SG AFW supply and 340 ft. of the #14 SG AFW supply) of piping between the pump discharge manifold and the connection

to the Main Feedwater

piping to the affected SGs was discovered

to be corroded to below minimum wall thickness

(0.278") for the 1950 psi design pressure of the AFW System. The lowest wall thickness

measured in the affected piping was 0.077".Preliminarily, PSEG representatives

believe that there was an inadvertent

omission of coating during construction

days. PSEG plans on excavating

the Unit 2 buried piping to inspect the condition

during the next Unit 2 outage scheduled

for the spring of 2011. Although no leakage was evident for these conditions, the inspector

questioned

if periodic pressure test had been conducted

on this underground

piping and this resulted in an NRC identified

finding, as noted in this feeder, along with an operability

determination

for Unit 2 and as risk assessment

for waiting to do the above noted inspection.

This analysis resulted in a revised pipe design rating for Unit 2 down to 1275 psig.10 CFR 50, Appendix B, Criterion

11, Design Control, states, in part, "Measures

shall be established

to assure that applicable

regulatory

requirements

and the design basis ... for those structures, systems, and components

to which this appendix applies are correctly translated

into specifications, drawings, procedures, and instructions.

These measures shall include provisions

to assure that appropriate

quality standards

are specified

and included in design documents

and that deviations

from such standards

are controlled.

Measures shall also be established

for the selection

and review for suitability

of application

of materials, parts, equipment, and processes

that are essential

to the safety-related

functions

of the structures, systems and components." r ~~'P w~" ,~ ~*0 '7 3/4

3 Contrary to these requirements, PSEG did not provide engineering

evaluations, vendor certification, or testing data to demonstrate

that the specified

coating would protect the buried AFW piping for the design lifetime of the plant. Also, PSEG did not assure appropriate

quality standards

which assure that deviations

from such standards

were controlled.

Additionally, PSEG did not provide measures for the selection

and review for suitability

of the coating materials

for the buried AFW piping application, for periodic inspections

to ensure that the.applied coating was protecting

the buried AFW piping, and did not provide engineering

details I; demonstrating

the ability of the coating to protect the buried AFW piping for the design life of the , ,.plant.Ad ua This licensee identified

finding affects the mitigating

systems cornerstone

by affecting

the secondary, short term decay heat removal capability.

Because the finding did not result in loss ., of operability

or functionality

the inspector

determined

that the finding was of very low safety significance, Green. The inspector

determined

that this licensee identified

finding is more than minor, and that a Cross Cutting Aspect did not exist because the issue was not indicative

of current performance

because the condition

existed since 1977. Specifically, the section of * , piping under question was identified

with degradation

that put the system outside its originalf, /design basis (1950 psi design rating); and PSEG was required to make significant

revisions

to the system design analysis to take credit for available

margin to show that the system remained -operable.

.: " Because PSEG entered this condition

into the corrective

action process (Notification

20456999)

.: and because the issue is of very low safety significance (Green), this issue is being treated as a .. : ..licensee identified

non-cited

violation

consistent

with Section VI.A. 1 of the NRC Enforcement

',,. ,'Policy.Follow up Comments for Future PI&R Sample Because PSEG had not completed

the EQ:ACE for the corroded AFW piping, had not ! l >2 completed

the Root Cause Evaluation

for missing the IWA-5244 pressure tests, and had not completed

it's evaluation

of Notification

20462034, it was agreed that an annual PI&R sample would be completed

to review these documents

to determine

that the following

.comments/observations

have been addressed

by PSEG. It is anticipated

that this sample will >be performed

in September

2010 depending

upon PSEG completion

of the cause , determinations

and Notification

actions.The inspector

made other observations

related to the finding on the AFW pressure testing issue .-and degradation

noted in the AFW yard piping. PSEG intends to address the following observations/comments

in the cause determinations

and Notification

evaluations.*, (1) The PSEG buried piping inspection

procedure

did not document how a representative

inspection

sample is selected and did not enumerate

the basis for the inspection

sample I selection(s).

I: (2) The PSEG buried piping inspection

procedure

does not provide a threshold

criteria for .. .inspection

conditions

which must be entered into the corrective

action process for evaluation, potential

resolution

and/or tracking.:"" , ,97, ,-... ..I Y,, .: "a ',: :::" " a ,

4 (3) PSEG has not defined a design life for the new coating on the replaced buried AFW ,*....-6 piping for Unit 1. Also, PSEG has not determined

an excavation

and inspection

frequency

for , 6,6 the newly coated, replaced Unit 1 buried piping.(4) Notification

20459689 reported the failure to perform the ASME, Section Xl, paragraph

," IWA-5244 required pressure tests on the buried AFW piping for Unit 1 and Unit 2. This Notification

states, "The system pressure test boundary drawing ($2-SPT-336-0)

identifies

the piping as YARD piping not buried piping." It is not clear what PSEG is doing to ensure that : 6 : other system drawings which may contain the same YARD markings and are potentially

not being treated as buried piping and components.

,, : 4.$: *;;(5) PSEG Buried Piping Program assumes that buried piping is protected

by a coating 666 system to protect the piping from degradation/corrosion

for the design life of the plant. However, the Unit 1 AFW piping was discovered

to not have been coated or protected.

It is not clear what PSEG is doing to confirm or verify that other buried piping is protected

with an effective

coating which will protect the piping for the plant life. : '6i ;6;f: (6) PSEG agreed to provide the ASME, NIS-2 forms with ANI approval for the completion

of the repair/replacement

of the Unit 1 AFW piping. .(7) PSEG has initiated

Notification

20462034 to investigate

and confirm the basis of the )1950 psig design pressure of the AFW system. Actions included in this Notification

were in 66,6 ~progress when the inspection

ended on June 28, 2010. i66 Enclosure:

Feeder for Salem Unit 1, Inspection

Report No. 05000272/2010003, 66 '05000311/2010003 , ,) 4,........ '66664.' i,666 6 6

5 cc w/Enclosure: (VIA E-MAIL)A. Burritt, DRP L. Cline, DRP D. Schroeder, DRP, SRI -Salem Unit 1 T. O'Hara, DRS R. Hardies, NRR DRS Files 4 ~4 '>4~44~ ~~'A~"~ 4~.SUNSI Review Complete:

TLOIRJC (Reviewer's

Initials)Non-Public

Designation

Category:

MD 3.4 Non-Public

A.7 DOCUMENT NAME: g:\DRS\EB1\ohara\salem1-(2010003)(ohara)(isi-rpt)(7-21-

201 0)wbr3edits.doc

After declaring

this document An Official Agency Record" it will not be released to the Public.To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with+++ + '+, <'" +:++: :++44' '2 i "'+4 4 L + A+++ +;? '>4++++++++++>'.++ +++ i +A++ ::++ : +.+... .+ .. .+ .,+ + /', , OFFICE RI/DRS IT/DRS R1/DRS NAME TO'Hara/TLO

WSchmidt/wac

for RConte/RJC

___,,_-_____

DATE 07/21/2010

07/21/2010

07/22/2010

__________,_,__

OFFICE NAME 4 DATE ,: ,? + +++ .: +:+++++.,+

+} +, :.:.' .4, OFFICIAL RECORD COPY 4< .22 4 >44~.44~.44')'4 4 ,44444~4',

SUMMARY OF FINDINGS Reactor Safety Cornerstone:

Mitigating

Systems ne),for-iPSE',falr

o perform aL'i~i iry feedwater

syste~m (AFV discha'rge

ppn, t~y este~s on~ undppn opnnsa required by. 10 CFR 5O.55a(g)(4)

and the red nericaS~n~

of~t~ Megchanica['Engineers

Cod (S~) Section Xi 'paragra2h.

fo j6 ae Unit 2. The reqiJiredtr'6sts

are in endd o _peafce piri is sa-f ielated, MEClas's 3, i~cCIa 0 Op Ipingrf hiL erf, ace efiiency is mr e than minor becaue the con~dition

affected the EfqLýO et~_s ofneanute

~(availabilit

and rlaityof te mitigating

ssei~biesoe

~jecbve ~ ~'K 4 I"M 'Tcmi ndqie t1e9,1 ~visent"naie~P

'g, W M-Wa.m. on St rat R- stru 3M=V I IRA AKAGý he "Ann'af46Un it 2 'i-n-fe r- 1144W ni Ot -mlsivol 6081016, hodicati, f Pfoht his finding is described

in Section 1 R08.One violation

of very low safety significance, which was identified

by PSEG, was reviewed by the inspector.

Corrective

actions taken or planned by PSEG were entered into the corrective

action program. The violation

and corrective

action (notification)

tracking number is described

in Section 40A7 of this report.ii

REPORT DETAILS 1R08 Inservice

Inspection (ISI) (7111108-

1 Sample)a. Inspection

Scope The inspector

observed a selected sample of nondestructive

examination (NDE)activities

in process. Also, the inspector

reviewed the records of selected additional

samples of completed

NDE and repair/replacement

activities.

The sample selection

was based on the inspection

procedure

objectives

and risk priority of those components

and systems where degradation

would result in a significant

increase in risk of core damage.The observations

and documentation

reviews were performed

to verify that the activities

inspected

were performed

in accordance

with the American Society of Mechanical

Engineers (ASME) Boiler and Pressure Vessel Code requirements.

The inspector

reviewed the licensee's

performance

of a visual inspection (VT) of the Unit 1 reactor vessel closure head (RVCH) and the installed

upper head penetrations.

The inspector

reviewed the visual procedure, the qualifications

of the personnel

and reviewed the inspection

report documenting

the inspection

results. The inspector

also reviewed the data sheets for the penetrant

tests completed

on three of the penetration

welds of the RVCH.The inspector

reviewed records for ultrasonic

testing (UT), visual testing (VT), penetrant testing (PT) and magnetic particle testing (MT) NDE processes.

PSEG did not perform any radiographic

testing (RT) during this outage. The inspector

reviewed inspection

data sheets and documentation

for these activities

to verify the effectiveness

of the examiner, process, and equipment

in identifying

degradation

of risk significant

systems, structures

and components

and to evaluate the activities

for compliance

with the requirements

of ASME Code,Section XI.Steam Generator

Inspection

Activities

The inspectors

reviewed a sample of the Unit 1 steam generator

eddy current testing (ECT) tube examinations, and applicable

procedures

for monitoring

degradation

of steam generator

tubes to verify that the steam generator

examination

activities

were performed

in accordance

with the rules and regulations

of the steam generator examination

program, Salem Unit 1 steam generator

examination

guidelines, NRC Generic Letters, 1 OCFR50, technical

specifications

for Unit 1, Nuclear Energy Institute 97-06, EPRI PWR steam generator

examination

guidelines, and the ASME Boiler and Pressure Vessel Code Sections V and XI. The review also included the Salem Unit 1 steam generator

degradation

assessment

and steam generator

Cycle 21 and 22 operational

assessment.

The inspector

also verified the individual

certifications

for personnel

participating

in the SG ECT inspections

during the 1R20 refueling

outage.j ~,~ ~~~-4, ~,~.d, ~.~-. ,, V .~., ~.*,,s ~~ ;&.4.,

2 The inspector

reviewed PSEG's efforts in identifying

wear degradation

to the tubing in the four SGs at Unit 1. The majority of the identified

wear indications

were attributed

to anti vibration

bar (AVB) wear in the u bend regions of the four SGs. The inspector reviewed the analyses and evaluations

that determined

that a total of 14 SG tubes would be removed from service by plugging.Boris Acid Corrosion

Control Program Activities

The inspector

reviewed the PSEG boric acid corrosion

control program. The resident inspectors

observed PSEG personnel

performing

boric acid walkdown inspections, inside containment, and in other affected areas outside of containment, at the beginning of the Unit 1 refueling

outage. The inspectors

reviewed the notifications

generated

by the walkdowns

and the evaluations

conducted

by Engineering

to disposition

the notifications.

Additionally, the inspector

reviewed a sample of notifications

and corrective

actions completed

to repair the reported conditions.

Section XI Repair/Replacement

Samples: AFW System Piping, Control Air & Station Air: The inspectors

reviewed PSEG's discovery, reporting, evaluation

and the repair/replacement

of Unit 1 AFW piping that was excavated

for inspection

during the April 2010 Unit 1 refueling

outage (1R20).PSEG conducted

this inspection

in accordance

with PSEG's Buried Piping Inspection

Program. Additionally, the inspectors

reviewed the UT testing results (approximately

20,000) performed

to characterize

the condition

of the degraded Unit 1 buried AFW piping.The inspector

also reviewed the repair/replacement

work orders and the 50.59 screening and evaluation

for the AFW, CA and SA piping. The inspectors

reviewed the fabrication

of the replacement

piping, reviewed the' documentation

of the welding and NDE of the replacement

piping and reviewed the pressure tests used to certify the replacement

piping. Additionally, the inspector

reviewed the specified

replacement

coating, the application

of the replacement

coating and the backfill of the excavated

area after the*piping had been tested.The inspector

reviewed the finite element analysis (FEA) results from PSEG's past operability

analysis on the affected Unit 1 buried AFW piping completed

by the licensee in order to demonstrate

past operability

at a reduced system pressure of 1275 psig. The design pressure of the AFW system is 1950 psig.The inspector

also reviewed the UT testing results (approximately

400) performed

on

of the Unit 2_AFWpiping

in response to the conditions

observed on Unit ." _men__4]__tlleleetht_"0at_

1 piping in order to determine

if significant

degradation

existed on the Unit 2 buried AFW .,..piping.Reiectable

Indication

Accepted For Service After Analysis: The inspector

reviewed the Notification

and the UT data report of a rejectable

wall thickness

measurement

on the #11 SG Feedwater

elbow during 1 R20. The inspector reviewed the additional

wall thickness

data taken to further define the condition

and

3 reviewed the finite element analysis (FEA) which verified that sufficient

wall thickness remained to operate the component

until the next refueling

outage when it will be replaced.b. Finding The inspector

identified

the following

violation

related to ASME,Section XI testing of buried Unit I and Unit 2 buried AFW piping.introduction.

The inspector

identified

a GREEN non-cited

violation (NCV) of 10 CFR 50.55a(g)(4)

and the referenced

American Society of Mechanical

Engineers (ASME)Code,Section XI, paragraph

IWA-5244 for PSEG's failure to perform required pressure tests of buried components.

This piping is safety related, 4.0" ID, ASME Class 3, Seismic Class 1 piping.Description.

Portions of the Unit I and Unit 2 Auxiliary

Feedwater (AFW) System piping is buried piping and has not been visually inspected

since the plant began operation

in 1977 for Unit 1 and since 1979 for Salem Unit 2. In April 2010, approximately

680 ft.(340 ft. of the #12 SG AFW supply and 340 ft. of the #14 SG AFW supply) of piping between the pump discharge

manifold and the connection

to the Main Feedwater

piping to the affected SGs was discovered

to be corroded to below minimum wall thickness (0.278") for the 1950 psi design pressure of the AFW System. The discovery

was noted by PSEG during a planned excavation

implementing

their buried pipe inspection

program. The lowest wall thickness

measured in the affected piping was 0.077". PSEG plans on excavating

the Unit 2 buried piping to inspect the condition

during the next Unit 2 outage scheduled

for the spring of 2011. The affected Unit 1 piping was replaced.Although no leakage was evident for these conditions, the inspector

questioned

if periodic pressure tests had been conducted

on this underground

piping.10 CFR 50.55(a)(g)(4)(ii)

requires licensees

to follow the in-service

requirements

of the ASME Code,Section XI. Paragraph

IWA-5244 of Section Xl requires licensees

to perform es ssn buried components

to demonstrate

the structural

integrity_

of mnt[5] o, the tested piping. The pressure test required by IWA-5244 is considered

to be an et0unders larld th'at re, arrS retoV , m -s M inservice

inspection

and is part of Section XI.Section XI and IWA-5244 do not specify lihi other non-destructive

examinations (NDE) on buried components

to demonstrate

the ~obabl;' cbsser IftEfm existence

of structural

integrity.

-t n uirei 3e ° cnsayP.l

s u 3tpeln.k 6 , ; MOeti~'per" d__ Inera =° 1.L' '; 4 Thus PSEG ...

j 4did not to perform the only inservice

inspection, intended to ' ... efdemonstrate

the structural

integrity

of this safety related buried piping. ., PSEG sought relief, from the NRC, from the previous Code required pressure testing in 1988 for Unit 1 only. Relief was granted to PSEG, by the NRC,_to perform an alternate flow test in 1991 for Unit 1. However, t-ttet

n t .E e i testAung~h~2visericen~aari~

du~n~ the~ (i1901~o~6//04an&P.

!;A)-4.4.the

9l In Service insp cinIntenddvoamide

J Phuse 1 P SEG in7ciue CU Enfareen

4____ ~§fi~en~y

which~ff&6t~.

misse&~9pp___

I~reR¶i, ~cA~r rw t jfsu.~fl~rwl~~

PSEG replaced the affected buried Unit 1 piping during the refueling

outage in April/May 2010. The required pressure tests were successfully

completed

after the replacement

of the Unit 1 buried piping. Because the AFW system functioned

as required during the plant shutdown prior to the start of, 1R20 (April 2010), the system did not loose operability.

8 42Ilito p~er ct ikA h?6fo PSGretlaed

6~~t6iTtlthe

afe~ctd buredu let1piigdurteing

otaehereueing

fortag inArihg/2May

Analysis.

The req ired pre fore r t were qucrdssfullycom

tlieted af e repla t th Uit d brid i png ng. Becraus cyth ea sys em fu ctioe .as eqire odirionga

the perform the only inservice

inspection (IWA-5244), intended to provide-eviden

o demonstrate

the structural

integrity

of this safety related buried piping. , Thes oninetion

ascreened

th menperformance

d attinbyutesvin

abiMC ity9 Atacdhmenibltyo

imat he m~i~tigat

Cirnersstemorners~tine

tyodvesu'tel

afetn h ecnay hr permabilityfy

heat repova c Y Ljniii wasiurther

rOsultodpin

in a m erore niianc codeition

ducrtoac aen tined undtcctedcroion

wasthou pr ftr t15or e iirrelcesti'g

fo ilr et rcka e. tterýg 'f1 F tem ecy

ata, [1¶& inl ectbr "3Vf andtiee S EGCeq uestedghr m a&ac tionssf .. fi !je W g .-.ecte.. ... .n ... .. .. ..

5 Enforcement.

11hbatte srv61 LqsrzdwtrýrAed

ula oi6'T =r~ f~ilitcomiponents

ihare!cIassifiedas

VASME o~de, ClA~ss;, 1ls' 2ad, us nietýýfhe

rreq~imen'i-, Fa'rglra'1561IWA-52441

Bu~ried Qompon o etnXlsays, in P tha -F-o bu compbonbnts

whero ! -Yieacmntincht3j

9,1stenm pressuiretestfrbre

comp~onents

that ate isolable bmeans of valvesýshai~onsstof

1st thatV ~detris thdýrtepressttr.

loss. Atrilati!yel

t~1ýt--i ftký*, rh -iowf1-c pm_,fj2t-s. "I--------------------------

~~d~o 1 tha 0t eo'e6hae l~t~'rcMmendddetj~

addressF my Contrary to these requirements, PSEG did not perform the required pressure tests of the buried AFW piping to the #12 SG and #14 SG at Salem Unit 1 during the 2nd In Service Inspection

Interval (2/27/88 to 5/19/01) and during the 1st (5/19/01 to 6/3/04) and 2 nd (6/24/04 to 5/20/08) periods of the 3rd In Service Inspection

Interval (5/19/01 to 5/19/11).Also, contrary to these requirements, PSEG did not perform the required pressure tests of the buried piping to the #22 SG and #24 SG for Unit 2 for the 1st period (5/19/01 to 6/3/04) and 2nd period (6/24/04 to 5/20/08) of the 3rd In Service Inspection

Interval.Consequently, from 2/27/88 to 4/20/07) the required pressure tests were not performed to demonstrate

structural

integrity

on the affected buried-Unit

1 AFW piping.Because PSEG entered this condition

into the corrective

action process (Notification

20459686)

and because it is is of very low safety significance (Green), it is being treated as a non-cited

violation

consistent

with Section VI.A.1 of the NRC Enforcement

Policy.NCV 50-272/2010-??

and NCV 50-311/2010-??

40A2 Identification

and Resolution

of Problems (71152)a. Inspection

Scope The inspectors

reviewed a sample of corrective

action reports (notifications), listed in Attachment

2 which involved in-service

inspection

related issues, to ensure that issues are being promptly identified, reported and resolved.b. Findings No findings of significance

were identified.

40A5 Temporary

Instruction (TI) 2515/172 a. Inspection

Scope The Temporary

Instruction (TI), 2515/172 provides for confirmation

that owners of pressurized-water

reactors (PWRs) have implemented

the industry guidelines

of the Materials

Reliability

Program (MRP) -139 regarding

nondestructive

examination

and evaluation

of certain dissimilar

metal welds in the RCS containing

nickel based Alloys 600/82/182.

6 During 1R20 PSEG inspected

the dissimilar

metal weld on the 1" reactor vessel drain piping with no detected indications.

Salem Unit 1 has dissimilar

metal welds in the eight reactor coolant system piping to reactor vessel nozzle safe end welds. No additional

inspections

or MSIP applications

were performed

during 1R20.This TI requires documentation

of specific questions

in an inspection

report. The questions

and responses

for the IR 05000272/2010003

section 40A5 are included in this report as Attachment "B-I".b. Findings No findings of significance

were identified.

40A6 Meetings, includinq

Exit The inspectors

presented

the ISI inspection

and TI 2515/172 inspection

results to Mr. Ed Eilola, Salem Plant Manager, and other members of the PSEG staff at the conclusion

of the inspection

at an exit meeting on June 28, 2010 for Salem Unit 1. The licensee acknowledged

the conclusions

and observations

presented.

Some proprietary

information

was reviewed during this inspection

and was properly destroyed.

No proprietary

information

is contained

in this report.40A7 Licensee Identified

Violations

The following

violation

of NRC requirements

was identified

by PSEG. It was determined

to have very low significance (Green) and to meet the criteria of Section VI of the NRC Enforcement

Policy, NUREG-1600, for being dispositioned

as a non-cited

violation.

The

finding of very l.w safcy .igifi.a...

was identified

by PSEG. The finding is a violation

of 10 CFR 50, Appendix B, Criterion

III, Design Control that-requires

in part that measures shall be established

to assure that applicable

regulatory

requirements

and'design

bases are correctly

translated

into specifications, drawings, and instructions

and that these measures shall include provisions

to assure the proper selection

and review for suitability

of application

of materials, parts, equipment, and processes.

During pipe excavation

and inspections

conducted

as part of PSEGs buried piping program PSEG identified

that it did not provide an effective

protective

coating for the buried_section of AFW piping on Unit 1.PSEG identified

general corrosion

that reduced the wall thickness

of the safety related piping to less than the design minimum wall thickness

of 0.278" for the system design pressure of 1950 psig. The lowest measured wall thickness

was 0.077". An FEA for the degraded piping was able to demonstrate

past operabili

at a reduced operating pressure of 1275 psiorto gt~i r rhai A'1so w~ smtgatn s te~illlt f short erma decay heat removal.capability.The__na__gwas__emlet6be

Green_Ioss of.operabli 661RY,* -o .".O N .I.-.-- -------------------------.I.- -.-.-- ------------------------------------------------------------------

7 Because PSEG entered this condition

into the corrective

action process (Notification

20456999)

and because the issue is of very low safety significance (Green), this issue is being treated as a non-cited

violation

consistent

with Section VI.A.1 of the NRC Enforcement

Policy. NCV 50-27212010003-??

4; , ..~4 A K2. &~242PA-2 2 ~ 2~j ~~'2 2;,~22~j2 4 22~'22'22.

27~ '2-2~ 2-242 ~ 2><22.44~2~4~2~2~2.1/2'"2 4 '4'4P- '2-2-., 42'<4~42 44k 2 24~m 42>2 .4-44222 2244-2 2~ '~'~ 2,2 2 2~222~22 4'424 2,4 222

A-1 ATTACHMENT

SUPPLEMENTAL

INFORMATION

KEY CONTACTS Licensee Personnel:

~: ~Howard Berrick, PSEG Pat Fabian, PSEG Mohammad Ahmed, PSEG Tony Oliveri, PSEG Tom Roberts, PSEG Ali Fakhar, PSEG Len Rajkowski, PSEG Dave Mora, PSEG Edley Giles, PSEG Walter Sheets, PSEG Bob Montgomery, PSEG Jim Mellchiona, PSEG Bill Mattingly, PSEG Pat Van Horn, PSEG Jim Barnes, PSEG Justin Werne, PSEG Rick Villar, PSEG Matthew Murray, PSEG'4 44" LIST OF DOCUMENTS

REVIEWED Notifications:

20457869, Control Air Piping Leak*20462034, Basis AFW Discharge

Line Design Pressure*20461785, Untimely retrieval

of Design Documents*

20461255, U2 Containment

Liner Blisters*20459259, U2 Containment

Liner Blisters*20459689, failure to do IWA-5244 pressure tests*20456999, Guided Wave (GW) pipe wall loss 20% to 44%*, in Equipment

Apparent Cause Evaluation (EQ;ACE) Charter 20457854, see Equipment

Apparent Cause Evaluation (EQ: ACE) Charter 20457869, Air Line Leak, in Equipment

Apparent Cause Evaluation

EQ: ACE Charter 20458147, see Equipment

Apparent Cause Evaluation (EQ: ACE) Charter 20458148, see Equipment

Apparent Cause Evaluation (EQ: ACE) Charter 20458568, see Equipment

Apparent Cause Evaluation (EQ: ACE) Charter 20458554, 11 CA HDR Line In Fuel Xfer Area Degraded*20458761, 1R20 CA Buried Pipe Coating Repair*20458925, 1 R20 SA Buried Pipe Coating Repair*.20457262, (88) 1R20 AF Buried Pipe Inspection

Results*20460624, Need Heat Trace on AF lines in FFT Area 20457877, UI Containment

Liner Corrosion

at 78' El.*i 4~AV '~<

flt.< *> y(. *t.. -(4 ~ ~4W~'i A-2 20459259, Ul Corrosion

on Containment

Liner*20459303, #14 AF pipe damaged penetration

seal*20459304, #12 AF pipe damaged penetration

seal*20459454, Request for Additional

UT Data, 4/18/10 (due to 0.077" reading)*20344017, Inspect steel liner in 1R19 20235636, NRC noted water running down containment

wall 20459189, Question on location of RFO-14 location of a PZR shell weld 20290560, Replace section of 15B FWH shell-S1-R18

20457879, (184) 1R20 FAC(N18) 14# elbow below Tmin 20456828, (66) valve has visible boron buildup 1 R20 20459232, Heavy Dry White Boron VIv Packing (1 R20)20456834, Heavy Dry White Boron VIv Packing (1 R20)20456840, Medium Dry White Boron VIv Packing (1 R20)20456839, Medium Dry. White Boron Vlv Packing (1R20)20389147, Recordable

ISI Indications

on CVC Tank 20344017, Inspect Steel Liner in 1R19 @ Containment

Sump 20235636, NRC Noted Water Running Down Containment

Wall 20392631, ARMA From ISI Program Audit 2008 20460624, Need Heat Trace on AF lines in FTT Area 20333050, Response to NRC NOV EA-07-149 20322039, 2 nd Interval ISI NRC Violation 20397518, A1CVC-1CV180

Chk VIv Stuck Open -PI&R review 20444514, Boric Acid Leak from Drain Line -PI&R review 20445314, boron leak -PI&R review 20448241, Minor Packing Leak -BAC -PI&R review 20435861, 21SJ313 Has Boric Acid Leakage -PI&R review 20417331, Boric Acid Leak at 11 CV156 -PI&R review 20411151, Tubing leak on 1SS653 -PI&R review 20414343, 12 Charging Pump seal inj. Line -PI&R review 20395346, 12 Bat PP Seal Leak -PI&R review 20450330, Containment

Liner Corrosion

-PI&R review 20385733, Severe Corrosion

on FP Valve -PI&R review 20438320, (217) Op Eval. Of Containment

Corrosion

-PI&R review 20387897, Significant

outlet pipe corrosion

-PI&R review 20397225, MIC Corrosion

Causing Through Wall Leak -PI&R review 20436836, Repair Cracks in Battery Cells -PI&R review 20392145, Update U1 ISI Relief Request Book -PI&R review 20449447, Update Salem Unit 1 ISI 10 Yr Plan -PI&R review 20449744, Update Salem Unit 1 Containment

ISI 10 Yr Plan -PI&R review 20449442, Update Salem Unit 2 Containment

ISI 10 Yr Plan -PI&R review 20449554, Salem U2 RFO18 ISI Scope -PI&R review 20416605, INPO PSIRV Alloy 600 Program -PI&R review 20404057, Unit 2 ISI (MSIP) -PI&R review 20392631, ARMA FROM ISI PROGRAM AUDIT 2008 -PI&R review 20388065, Water leaking in decon room -PI&R review 20439023, 23 CFCU Head Leakage -PI&R review 20439022, SW Header Leakage 23 CFCU -PI&R review 20389148, 1R19 ISI Weld Exam Limitations

-PI&R review 20416605, INPO PSIRV Alloy 600 Program -PI&R review 20449442, Update Salem 2 Containment

ISI 10 yr. Plan -PI&R review 20449554, Salem Unit 2 RFO18 ISI Scope -PI&R review 4 4 w~.44, A'((9, 4,~ ~'4 ".4 4<, 4'../ '>~44944 444~'.. ~4~44( (~,"-'4 4 44 4 .4'4,4 4~4, 4'4'

A-3 C" 20449747, Update Salem 2 ISI 10 Yr. Plan -PI&R review 20401542, Perform ISI BMV Exam on RPV Upper Head -PI&R review 20449063, SA Ul Service Inspec- ISI & U1 TI 2515 -PI&R review 20389147, Recordable

ISI Indications

on CVC Tank -PI&R review 20392145, Update Ul ISI Relief Request Book -PI&R review 20449744, Update Salem U1 Containment

ISI 10 Yr. Plan -PI&R review 20409943, NRC RIS 2009-04 SG Tube Insp Rqmts -PI&R review 20459851, Section Xl Exams Limited to 90% or Less -PI&R review 20450520, Recoat Affected Areas of Liner 2R18 -PI&R review 20457388, Excavation

Issues -PI&R review*Denotes this Notification

was generated

as a result of this inspection

Section XI Repair/Replacement

Samples: Y1A~i ~~; '4h:;;* <'1'~" '1~4~< ~'4', ~&r~Y~ >~k" ~1/2& >.& 'W.O. 60079414,14" Carbon Steel Elbow FAC indication

below minimum wall W.O. 60084266, Salem Ul AF Buried Piping Inspection

W.O. 60089561, 80101381:

Replace Aux FW U/G Piping W.O. 60064104, Repair 15B FWH Area W.O. 60084375, BACC Program repair to 1PS1 W.O. 60089612, BACC Program repair to SlCVC-14CV392

W.O. 60089615, BACC Program repair to S1SJ-13SJ25

W.O. 60089848, 80101382 Advanced Work Authorization

  1. 2 FTTA Replace Aux. Feedwater Pipe W.O. 60089561, 80101381 Advanced Work Authorization

-Replace Aux. FW U/G Piping, 4/9/10 Non-Code Repair W.O. 60089848, Repair Non-nuclear, safety related CA Pipe, Unit 1 FTTA W.O. 60089757, Test Non-nuclear, safety related CA Pipe Repair, Unit 1 FTTA Miscellaneous

Work Orders: '&4<4,.-<~4< 4~'V ,~7 4~ -.~4 ,4 7 , ,,',." W.O. 60089917, Penetrations

for CA & SA Lines, 4/23/10 W.O. 941017262, Activity 04, Excavate and Examine Auxiliary

Feedwater

Piping, W.O. 941017262, Activity 03, Excavate and Examine Auxiliary

Feedwater

Piping, W.O. 941017262, Activity 02, Excavate and Examine Auxiliary

Feedwater

Piping, W.O. 941017262, Activity 01, Excavate and Examine Auxiliary

Feedwater

Piping, W.O. 60089561, Flush New AFW piping 12 and 14 Unit 2, 12/94 Unit 2, 12/94 Unit 2, 12/94 Unit 2, 12/94 I~ 4 ~'Drawings & Sketches: 205236A8761-54, Salem Nuclear Generating

Station, Unit No. 1, Auxiliary

Feedwater Salem Unit 1 Aux Feed Piping, Allan Johnson, 4/10/10 80101381 RO, Buried Pipe, Replaced AFW Piping Arrangement

207483A8923-1

1, Salem Nuclear Generating

Station, Unit No. 1 -Reactor Containment

Auxiliary

Feedwater, Plans & Sections -Elev. 78' 10" & 100' 0", Mechanical

Arrangement, Revision 8, 9/31/86 C""~, ~K:

A-4 207483A8923-28, Sheet I of 4, Salem Nuclear Generating

Station, Unit No. 1 -Reactor Containment

Auxiliary

Feedwater, Plans & Sections -Elev. 84',Mechanical

Arrangement, Revision 8, 9/31/86 207483A8923-31, Sheet 2 of 4, Salem Nuclear Generating

Station, Unit No. 1 -Reactor Containment

Auxiliary

Feedwater, Plans & Sections -Elev. 84', Mechanical

Arrangement, Revision 8, 9/31/86 207483A8923-28, Sheet 3 of 4, Salem Nuclear Generating

Station, Unit No. 1 -Reactor Containment

Auxiliary

Feedwater, Plans & Sections -Elev. 84', Mechanical

Arrangement, Revision 8, 9/31/86 207483A8923-30, Salem Nuclear Generating

Station, Unit No. 1 -Reactor Containment

Auxiliary

Feedwater, Plans & Sections -Elev. 84',Mechanical

Arrangement, Revision 8, 9/31/86 207610A8896-12, Salem Nuclear Generating

Station, Unit No. 1 -Auxiliary

Building & Reactor Containmnet

Compressed

Air Piping, Aux. Building El. 84 East & React. Contain. El. 78, Mechanical

Arrangement, Revision 8, 9/31/86 Design Change Packages/Equivalent

Change Packages 80101382, Revision 2, Replace Salem Unit 1 AFW Piping from the UnitMechanical

Penetration

Area El. 78'-0" to the Unit 1 Fuel Transfer Tube Area El. 100'-0" 80101381, Revision 1, Replace in-kind the Salem Unit 1 AF Piping that runs underground

from the Unit 1 Fuel Transfer Tube Area to the Unit 1 Main Steam Outer Penetration

Area Y~,~ ~;<~ ~50.59 Applicability

Reviews, Screenings

& Evaluations

80101382;

Salem Unit 1 12/14 AF Piping Reroute; 4/24/10 System & Program Health Reports & Self-Assessments:

Salem Boric Acid Corrosion

Control Program Focused Area Self-Assessment, 1/2010 70106830, Salem $1R20 NRC ISI Inspection

Check-In Self Assessment

70095327, Salem Boric Acid Corrosion

Control Program Focused Area Self-Assessment, 4/29/09 Pro-gram Documents PSEG Nuclear Salem Units 1 & 2, Alloy 600 Management

Plan, Long Term Plan (LTP), Revision 2, Integrated

Strategic

Plan For Long Term Protection

from Primary Water Stress Corrosion

Cracking (PWSCC), 10/15/09 ASME, Section X1,1998 Edition, 2000 Addenda, IWA-5244 Buried Components

OAR-i, Owner's Activity Report, #S1RFO19, 1/15/09 r~t

A-5 Procedures

DETAILED AND GENERAL, VT-1 AND VT-3 VISUAL EXAMINATION

OF ASME CLASS MC AND CC CONTAINMENT

SURFACES AND COMPONENTS

SHRA -AP.ZZ -8805(Q) -Revision 4, 8/31/06; Boric Acid Corrosion

Management

Program ER -AP -331, Revision 4, Boric Acid Corrosion

Control (BACC) Program ER -AP -331 -1001, Revision 2, Boric Acid Corrosion

Control (BACC) Inspection

Locations, Implementation

And inspection

Guidelines

ER -AP -331 -1002, Revision 3, Boric Acid Corrosion

Control (BACC) Program Identification, Screening, and Evaluation

ER -AP -331 -1003, Revision 1, RCS Leakage Monitoring

And Action Plan ER -AP -331 -1004, Revision 2, Boric Acid Corrosion

Control (BACC) Program Training and Qualification

ER -AA -330 -001, Revision 7, SECTION XI PRESSURE TESTING LS -AA -125, Revision 13; Corrective

Action Program (CAP) Procedure LS -AA -120, Revision 8; Issue Identification

And Screening

Process SH.RA-IS.ZZ-0005(Q)-Revision

6; VT-2 Visual Examination

Of Nuclear Class 1, 2 and 3 Systems SH.RA-IS.ZZ-0150(Q)

-Revision 8, 10/19/04;

Nuclear Class 1, 2, 3 and MC Component Support Visual Examination

OU-AP-335-043, Revision 0; BARE METAL VISUAL EXAMINATION (VE) OF CLASS I PWR COMPONENTS

CONTAINING

ALLOY 600/82/182

AND CLASS 1 PWR REACTOR VESSEL UPPER HEADS OU-AA-335-015, Revision 0; VT 2 -VISUAL EXAMINATION

Areva NP, Inc., Engineering

Information

Record 51-9118973-000;

Qualified

Eddy Current Examination

Techniques

for Salem Unit 1 Areva Steam Generators, 10/15/09 AREVA NP 03-9123233, Revision 000, 10/13/09;

Salem Unit 2 RVCH Flange Repair SC.MD-GP.ZZ-0035(Q)

-Revision 9, PRESSURE TESTING OF NUCLEAR CLASS 2 AND 3 COMPONENTS

AND SYSTEMS, 02/02/10 SH.MD-GP.ZZ-0240(Q)

-Revision 10, SYSTEM PRESSURE TEST AT NORMAL OPERATING PRESSURE AND TEMPERATURE, 7/29/09 S2.OP-AF-0007(Q)-Revision

20, 12/23/09;

INSERVICE

TESTING AUXILIARY

FEEDWATER VALVES, MODE 3 ER-AA-5400-1002, Revision 1, BURIED PIPING EXAMINATION

GUIDE Specification

No. S-C-MPOO-MGS-0001;

Piping Schedule SPS54, Auxiliary

Feedwater, Revision 6 PSEG Test Procedure

10-H-8-R1, Unit 2 Auxiliary

Feedwater

2100/2150

Hydro; 9/21/78 NDE Examination

Reports & Data Sheets>~~r~rJ~ ~;9~ ~ j 003753, VT-10-113, PRV nozzle sliding support 003754, VT-10-114, RPV nozzle sliding support 006325, UT-10-041, PZR longitudinal

shell weld J (100%)007500, UT-10-132, PZR surge line nozzle (100%)007901, UT-10-028, 13 SG lower head to tubesheet

weld (67%)006073, VE-10-026, CRDM TO VESSEL PENETRATION

WELD, 4/12/10 008001, VE-10-027, 31-RCN-1 130-IRS 008026, VE-1 0-028, 29-RCN-1 130-IRS 009070, VE-10-030, 12-STG Channel Head Drain (100%)033300, UT-10-027, 4-PS-1131-27

(100%)033200, UT-10-029, 4-PS-1 131-26 (100%)9 $

A-6 033100, UT-1 0-032, 4-PS-1 131-25 (100%)032300, UT-10-033, 4-PS-1131-17

(100%)031700, UT-1 0-040, 4-PS-1 131-12 (100%)032600, UT-10-034, 4-PS-1 131-20 (100%)047600, UT-1 0-045, 29-RC-1 140-3 (100%)051200, UT-1 0-048, 29-RC- 1120-3 (100%)203901, UT-10-047, 32-MSN-2111-1

(100%)204001, UT-10-046, 16-BFN-2111-1

(70.64%)210586, UT-10-025, 14-BF-2141-19

(100%)210588, UT-10-024, 14-BF-2141-20

(100%)836300, IWE: VT-10-338, PNL-S1-343-1

836400, IWE: VT-10-333, ALK-Sl-100-tubing

840000, IWE: Vert Leak Channels 1 -14 006073, VE-10-026, RPV Upper Head Inspection

006051, PT-1 0-004, CRDM Housing Weld Exams, penetrations

  1. 66, 67, and 72 Salem Unit 1, VT-2, Visual Examination

Record, 12/14 AF FTTA, W.O. 60089848, 4/26/10 (VT)Salem Unit 1, VT-2, CA Repair Snoop Test, W.O. 60089575, 4/27/10 Salem Unit 1, UT, W.O. 60084266, Yard AF, 4/18/10 Salem Unit 2, UT, W.O.60089851, Exam of containment

liner Salem Unit 1, UT 1-SGF-31-L2

FW elbow below min. wall Salem Unit 1, UT, W.O. 30176541, 1-SGF-31-L2

FW elbow below min. wall Salem Unit 1, UT, W.O. 60084266, AFW Order 50113214, ST 550D, Surveillance:

ISI Perform PORV Check Order 50118090, ST 550D, Surveillance:

OPS Perform PORV Check W.O. 60089848, VT-2 Visual Examination

Record, 12/14 AFW in FTTA, 4/26/10 W.O. 941017262, Activity 02; Salem Unit 2, Excavate and Examine Auxiliary

Feedwater

Piping, 12/2/94 W.O. 60084266, UT Unit 1 AFW (thinnest

area), 4/20/10 UT Analysis, Component

1-SGF-31-L2

(14" FW Elbow below Minimum wall), 4/10/10 W.O. 60089851, Unit 2 Containment

Liner blister UT measurements, 4/21/10 W.O. 60086175, Unit 1 Containment

corrosion

78' elevation W.O. 60084266, Unit 1 AFW piping UT measurements, 4/12/10 W.O. 30176541, Unit 1 AFW piping UT measurements, 4/12/10 W.O. 60084266, Unit 1 AFW piping UT measurements, 4/7/10 W.O. 60084266, Unit 1 AFW piping UT measurements, 4/5/10 W.O. 60084266, Unit 1 AFW pipe UT measurements

at supports, 4/18/10 W.O. 30176541, Unit 1 CA piping UT measurements

in FTTA 401600, VE-04-198;

Hope Creek system pressure test CST to HPCI/RCIC

and Core Spray, 11/5/04 VT-2, Salem Unit 1 AF 12 & 14 Pressure Test, 4/25/10 W.O. 60089661, UT measurements, Unit 2 AFW Piping #24 in FTTA, 4/25/10 W.O. 60089661, UT measurements, Unit 2 AFW Piping #22 in FTTA, 4/26/10 2 T~~2~4,<A~. ,~.#-..41-4- ,>2 41

A-7 Eddy Current Testing Personnel

Qualification

Records A2421 88731 80500 B5127 B5128 B2576 F3961 C1560 D7895 D9573 D6502 H2039 K5380 M9460 E0427 M6664 84260 A3502 J9815 P5436 M6042 B8589 84014 G2573 V8530 W3368 M4305 84052 K6975 G391 0 H0268 L3025 P1465 B8079 G1756 C8071 6410058746

B5371 H2131 2909965330076

C2028 C4596 C3340 D3858 H6267 H0282 14048 J 1978 2010983302133

P6459 R0830 Ri1164 S0608 2509981330193

K5858 1007951330114

L9168 L4332 F7460 F0037 317943330158

6206070744

6507061922

1803983330125

2709977301226

P5304 P4006 R4201 R6452 R8002 S7752 T8251 V3197 R4142 R6279 G3380 83720 R6900 A9608 N2574 13805.T2170 N4815 M0945 P2963 M9715 K1 903 D5318 W6070 M5096 J1945 L4588 C8042 N5330 L8267 F3453 T5616 R931 1 G4943 C5542 F0075 F6623 F3453 G4943 G1311 H7791 J9141 M0950 M2665 M7006 M9459 M7007 M9082 N7035 N9952 R9311I S9098 T5616 T5565 W2639 W7912 2224222'24~'22 4'222.2 22 2'22' '1 22~ .2222, 24222~22.

222 '2 2222.~&~>222422222'

~22&142 22 2222 2' 2222224 ~2.242,2 S~422~ ~2 ~ 4~ ~ 2 242.~4. 242~ '4- '2 22 4~ 24f2~2 2~2 2244 22 2222~2'. %.22~~ ~2~2 2~2~222 '~K2~2~" >2~2' ~212 222,1 2 '2'222 22 2' 224224222242

2222>' 222 22,1222 K>422 74222242.24442422242

242 '722' 22 ,2222~ .4.2222~722 24'"" 2 2.2 42 2, 22<2 *2 K.2..2222 2 2.22 22: ,2 22

A-8 Engineerinq

Analyses & Calculations

& Standards Calculation

6SO-1882, Revision 1, 8/30/96; Qualification

of Safety-Related

Buried Commodities

For Tornado Missle and Seismic Evaluation

Calculation

No. S-C-AF-MDC-1

789; Salem Auxiliary

Feedwater

Thermal Hydraulic

Flow Model, 10/4/00 70087436, Steam Generator

Degradation

& Operational

Assessment

Validation, Salem Unit 1 Refueling

Outage 18 (1R18) & Cycles 19/20, 9/2008 51-9052270-000, Update -Salem Unit 1 SG Operational

Assessment

At 1R18 For Cycles 19 and 20, 10/1/08 51-9048311-002, Salem Unit 1 SG Condition

Monitoring

For 1R18 And Preliminary

Operational

Assessment

For Cycles 19 and 20, 10/30/07 701086998-0050, Maximum Pressure in Underground

Auxiliary

Feedwater

Piping 60089575-130, Past Operability

Determination

for the leak in the one inch air line to air operated valves in Unit 1 South Penetration

Area 70109233/20459231;

Boric Acid evaluation

of leakage from S1CVC-1CV277

70109232/20459230;

Boric Acid evaluation

of leakage from S1CVC-1 CV2 70109230/20459228;

Boric Acid evaluation

of leakage from S2RC-1PS1 70109234/20459232;

Boric Acid evaluation

of leakage from S1 SJ-13SJ25 70108698/30, Operating

Experience

Report for degraded Unit 1 AFW piping 51-9135923-000, AREVA; Salem unit 1 SG Condition

Monitoring

For 1R20 and Preliminary

Operational

Assessment

For Cycles 21 And 22, 4/20/10 SA-SURV-2010-001, Revision 1; Risk Assessment

of Missed. Surveillance

-Auxiliary Feedwater

discharge

line underground

piping pressure testing, 4/23/10 CQ9503151526;

SCI-94-0877,'EXCAVATED

AUXILIARY

PIPING WALKDOWN/DISPOSITION

OF COATING REQUIREMENTS;

12/16/94 Specification

No. S-C-M600-NDS-019, COATINGS INTERIOR/EXTERIOR

SURFACES CARBON STEEL SERVICE WATER PIPING, NO. 12 COMPONENT

COOLING HEAT EXCHANGER

ROOM AUXILIARY

BUILDING (ELEVATION

84)Structural

Integrity

Associates, Inc. Calculation

File No. 1000494.301, Evaluation

of Degraded Underground

Auxiliary

Feedwater

Piping (Between Unit 1 FTTA and OPA), 4/23/10 Technical

Evaluation

60089575-0140, Acceptability

of CA Piping in the Fuel Transfer Area, 4/29/10 Technical

Evaluation

60089848-0960, Auxiliary

Feedwater

Piping Missle Barrier Exclusion, 4/29/10 Structural

Integrity

Associates, Inc. Calculation

File No. 1000498.301, Evaluation

of Thinned Feedwater

Elbow, 4/22/10 Technical

Evaluation

70108698-0050, Maximum Pressure in Underground

Auxiliary

Feedwater Piping, 4/29/10 SPECIFICATION

NO. S-C-MPOO-MGS-0001, Piping Schedule SPS54 AUXILIARY FEEDWATER, Revision 6 OpEval. #10-005, Salem Unit 2 Operability

Evaluation, Received 5/18/10 Technical

Evaluation

60084266-105-20, Alternative

Exterior Coatings for Buried Piping, AF, CA, SA and Pipe Supports Under W.O. 60084266, 4/2/10 Technical

Evaluation

H-1-EA-PEE-1871, Hope Creek Service Piping Coatings Alternatives, 80075587, Revision 0, 10/15/04 PSEG Nuclear, LLC, Technical

Standard, Coating Systems and Color Schedules, Revision 5, 4/3/06.~.,~4 4 7w* .,. <AZ. -Y...7w.

A-9 Weld Records -AFW Piping Repair (W.O. #'s 60084266, 60089561, 60089798, 60089848)Multiple Weld History Record: 74626 Multiple Weld History Record: 74556 Multiple Weld History Record: 74557 Multiple Weld History Record: 74558 Multiple Weld History Record: 74559 Multiple Weld History Record: 74560 Multiple Weld History Record: 74561 Multiple Weld History Record: 74562 Multiple Weld History Record: 74563 Multiple Weld History Record: 74564 Multiple Weld History Record: 74565 Multiple Weld History Record: 74566 Multiple Weld History Record: 74567 Multiple Weld History Record: 74627 Multiple Weld History Record: 74569 Multiple Weld History Record: 74599 Multiple Weld History Record: 74623 Multiple Weld History Record: 74600 Multiple Weld History Record: 74630 Multiple Weld History Record: 74622 Multiple Weld History Record: 74578 Multiple Weld History Record: 74596 Multiple Weld History Record: 74601 Multiple Weld History Record: 74602 Multiple Weld History Record: 74603 Multiple Weld History Record: 74604 Multiple Weld History Record: 74605 Multiple Weld History Record: 74598 Multiple Weld History Record: 74606 Multiple Weld History Record: 74607 Multiple Weld History Record: 74608 Multiple Weld History Record: 74609 Multiple Weld History Record: 74610 Multiple Weld History Record: 74611 Multiple Weld History Record: 74612 Multiple Weld History Record: 74613 Multiple Weld History Record: 74614 Multiple Weld History Record: 74615 Multiple Weld History Record: 74597 Multiple Weld History Record: 74616 Multiple Weld History Record: 74579 Multiple Weld History Record: 74580 Multiple Weld History Record: 74581 Multiple Weld History Record: 74582 Multiple Weld History Record: 74583 Multiple Weld History Record: 74595 Multiple Weld History Record: 74584 Multiple Weld History Record: 74585 Multiple Weld History Record: 74586 I,

A-10 Multiple Weld History Record: 74587 Multiple Weld History Record: 74588 Multiple Weld History Record: 74589 Multiple Weld History Record: 74590 Multiple Weld History Record: 74591 Multiple Weld History Record: 74592 Multiple Weld History Record: 74593 Multiple Weld History Record: 74577 Multiple Weld History Record: 74625 Multiple Weld History Record: 74574 Multiple Weld History Record: 74624 Multiple Weld History Record: 74573 Multiple Weld History Record: 74572 Multiple Weld History Record: 74570 Multiple Weld History Record: 74571 Multiple Weld History Record: 74623 Multiple Weld History Record: 74622 Multiple Weld History Record: 74621 Multiple Weld History Record: 74537 Multiple Weld History Record: 74538 Multiple Weld History Record: 74537 Welder Stamp Number: P-664 Welder Stamp Number: P-65 Welder Stamp Number: P-466 Welder Stamp Number: P-57 Welder Stamp Number: E-64 Welder Stamp Number: P-710 Welder Stamp Number: P-207 Welder Stamp Number: P-666 Welder Stamp Number: P-708 Welder Stamp Number: E-89 Welder Stamp Number: P-84 Welder Stamp Number: P-228 Surface Exam Record: 60089561-0041

Surface Exam Record: 60089848-0001

Surface Exam Record: 60089848-0001

Surface Exam Record: 60089561-0041

Surface Exam Record: 60089561-0860

~.4 v4~9'Miscellaneous

Documents Salem Unit 1 & Salem Unit 2 Technical

Specification, 3.4.11 STRUCTURAL

INTEGRITY, ASME CODE CLASS 1, 2 AND 3 COMPONENTS

Electric Power Research Institute (EPRI), Steam Generator

Integrity

Assessment

Guidelines, Technical

Report 1012987, Revision 2, July 2006 NRC Letter dated 3/11/91; FIRST TEN-YEARINSPECTION

INTERVAL, INSERVICE INSPECTION

PROGRAM RELIEF REQUEST, SALEM NUCLEAR GENERATING

STATION, UNIT 1 (TAC NOS. 66013 AND 71101)PSEG Nuclear, Salem Unit 1 & 2 Alloy 600 Management

Plan, Long Term Plan (LTP), Revision 2, 10/15/09 Salem Unit 1 -Buried Piping Risk Ranking

A-11 MPR Associates

Report, Technical

Input To Operability

of Potential

Containment

Liner Corrosion, Revision 0, 10/30/09 Transmittal

of Design Information

  1. S-TODI-2010-0005, 4/20/2010 Transmittal

of Design Information

  1. S-TODI-2010-0004, 4/16/2010 OQ950315126, PSEG Itr. Dated 12/16/94;

Excavated

Auxiliary

Feedwater

Piping Walkdown/Disposition

of Coating Requirements

PSEG letter LR-N07-0224

dated 9/13/2007;

REPLY TO NOTICE OF VIOLATION

EA-07-149 UNTAGGING

WORKLIST 4274446,14

AF Underground

Piping 1 R20, 4/30/10 UNTAGGING

WORKLIST 4274351, 12 AF Underground

Piping 1R20, 4/30/10 LIST OF ACRONYMS ASME BAST CEA CEDM CFR EDG EPRI EQ;ACE EQ ER FEA FTTA IMC IP IR LER LOCA MT MSIP NCV Notification

NRC NDE OE PDI PI&R PSEG PWSCC PQR RCS RT PT SDP SE American Society of Mechanical

Engineers Boric Acid Storage Tank Control Element Assembly Control Element Drive Mechanism Code of Federal Regulations

Emergency

Diesel Generator Electric Power Research institute Equipment

Apparent Cause Evaluation

Environmental

Qualification

Engineering

Request Finite Element Analysis Fuel Transfer Tube Area Inspection

Manual Chapter Inspection

Procedure NRC Inspection

Report Licensee Event Report Loss of Coolant Accident Magnetic Particle Testing Mechanical

Stress Improvement

Process Non-cited

Violation Corrective

Action Notification

Nuclear Regulatory

Commission

Nondestructive

Examination

Operating

Experience

Performance

Demonstration

Initiative

Problem Identification

and Resolution

Public Service Electric & Gas, LLC Primary Water Stress Corrosion

Cracking Procedure

Qualification

Record (Welding Procedures)

Reactor Coolant System Radiographic

Test (Radiography)

Dye Penetrant

Testing Significance

Determination

Process Safety Evaluation

Ky~~K~K ~K?" K ~"K k'-

SG SI SSC TS UT UFSAR VT WPS A-12 Steam Generator Stress Improvement

Structure, System, and Component Technical

Specifications

Ultrasonic

Test Updated Final Safety Analysis Report Visual Examination

Weld Procedure

Specification

v4~:~fl~~~>y.~4

4'4' '?~A-13 INSPECTION

SAMPLE COMPLETION

STATUS PROCEDURE

MINIMUM CURRENT RPS PROCEDURE

RPS or TI REQUIRED INSPECTION

TOTAL STATUS UPDATED SAMPLES SAMPLES SAMPLES OPEN (O) (Y) (N)Annual (A) TO DATE CLOSED (C)Biennial (B)7111108 (G) 1 Y 2515/172 1 YES 4'$~~$*4~$4>

4~V'W 4.'-K "~k~$ ~&: K.U' ~'$4 '4>4'> K'K>'*4~$$4$4 4.'4~>'>'*A' A>.'

A -14 , Attachment

B-1 TI 172 MSIP Documentation

Questions

Salem Unit I Introduction:

The Temporary

Instruction (TI), 2515/172 provides for confirmation

that owners of pressurized-water

reactors (PWRs) have implemented

the industry guidelines

of the Materials

Reliability

Program (MRP) -139 regarding

nondestructive

examination

and evaluation

of certain dissimilar

metal welds in the RCS containing

nickel based Alloys 600/82/182.

This TI requires documentation

of specific questions

in an inspection

report.The questions

and responses

for MSIP for the IR 05000311/2009005

section 40A5 are included in this Attachment "B-i".In summary the Salem Units 1 and 2 have MRP-139 applicable

Alloy 600/82/182

RCS welds in the four hot and four cold leg piping to reactor pressure vessel nozzle connections

for each plant.For Unit 1 during the 1R20 refueling

outage in April 2010 PSEG inspected

one dissimilar

metal'weld, a SG channel head drain line weld. No indications

were reported from this inspection.

PSEG plans on replacing

this valve, and the dissimilar

metal weld, during refueling

outage 1 R22.TI 2515/172 reauires the followina

a uestions to be answered for MRP-139 MSIP inspections:

  • 7w<<I~ K I ~'A~fr ~V.-'A: &V,,-'A,."A 'A'~A~$" ,'~ ~"#--'~"""V ~K$~2':~"A"'~

Question 1: For each mechanical

stress improvement

used by the licensee during the Salem U1 1 R20 outage, was the activity performed

in accordance

with a documented

qualification

report for stress improvement

processes

and in accordance

with demonstrated

procedures?

Response Question 1: No MSIP activities

were conducted

on UI during 1R20.Question d.l: Are the nozzle, weld, safe end, and pipe configurations, as applicable, consistent

with the configuration

addressed

in the stress improvement (SI) qualification

report?Response-

Question d.l: No MSIP activities

were conducted

on U1 during 1R20.Question d.2.: Does the SI qualification

report address the location radial loading is applied, the applied load, and the effect that plastic deformation

of the pipe configuration

may have on the ability to conduct volumetric

examinations?

Response Question d.2: No MSIP activities

were conducted

on U1 during 1 R20.Question d.3.: Do the licensee's

inspection

procedure

records document that a volumetric

examination

per the ASME Code,Section XI, Appendix VIII was performed

prior to and after the application

of the MSIP?Response:

Question d.3.: No MSIP activities

were conducted

on U1 during 1 R20.

A-1 5 Question d.4.: Does the SI qualification

report address limiting flaw sizes that may be found during pre-SI and post-SI inspections

and that any flaws identified

during the volumetric

examination

are to be within the limiting flaw sizes established

by the SI qualification

report?Response:

Question d.4.: No MSIP activities

were conducted

on U1 during 1 R20.Question d.5.: Was the MSIP performed

such that deficiencies

were identified, dispositioned, and resolved?Response Question d.5.: No MSIP activities

wereconducted

on U1 during 1 R20.5'>Y2~ 4: 5<', YI~~42>5 55 5~' 5'~'55'5 5

I think that we missed the point here. As defined in MC 0612 a performance

deficiency

is an issue that is the result of a licensee not meeting a requirement

or standard where the cause was reasonably

within the licensee's

ability to forsee and correct, and therefore

should have been prevented.

PSEG did not meet the CFR because they did not perform the testing, not the other way around. What was the result/the

impact on the safety of the public by not performing

the required testing? It is necessary

to define thise result in order to evaluate the significance

-that is why the definition

is written that way. Not using the following

words exactly one suggestion

for defining the result would be -due to the condition

of the pipe and coating identified

during the excavation, it is clear that the failure to perform required testing would have ultimately

resulted a loss of structural

integrity

for the pipe impacting

the operability

of the affected AFW trains.This does not meet the MC 0612 documentation

requirements.

Needs to address all the screening

criteria.

A more appropriate

statement

would be something

like this. The inspectors

determined

the issue was of very low safety significance (Green) because the finding was not a design or qualification

deficiency, did not result in an actual loss of safety function, and was not potentially

risk significant

for external events.