Mid Cycle Assessment Letter for Watts Barr Nuclear Plant Unit 1, NRC Inspection Report 05000390/2016005
ML16244A703
Person / Time
Site: Watts Bar Tennessee Valley Authority icon.png
Issue date: 08/31/2016
From: Alan Blamey
Reactor Projects Region 2 Branch 6
To: James Shea
Tennessee Valley Authority
References
IR 2016005
Download: ML16244A703 (5)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION ust 31, 2016

SUBJECT:

MID CYCLE ASSESSMENT LETTER FOR WATTS BAR NUCLEAR PLANT UNIT 1, NRC INSPECTION REPORT 05000390/2016005

Dear Mr. Shea:

On August 10, 2016, the NRC completed its mid-cycle performance review of Watts Bar Nuclear Plant (WBN) Unit 1. The NRC reviewed the most recent quarterly performance indicators (PIs)

in addition to inspection results and enforcement actions from July 1, 2015, through June 30 2016. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility.

The NRC determined that overall, Watts Bar Unit 1 operated in a manner that preserved public health and safety and met all cornerstone objectives. The NRC determined the performance at the Watts Bar Nuclear Plant Unit 1 during the most recent quarter was within the Licensee Response Column of the NRCs Reactor Oversight Process (ROP) Action Matrix because all inspection findings had very low (i.e., green) safety significance, and all PIs indicated that your performance was within the nominal, expected range (i.e., green). Therefore, the NRC plans to conduct ROP baseline inspections at your facility.

The NRC also identified a cross-cutting theme in the Safety Conscious Work Environment (SCWE) cross-cutting area. Specifically, on March 23, 2016, the NRC issued a Chilling Effect Letter for Watts Bar and the NRC identified one inspection findings in the assessment period with a cross-cutting aspect of S.1 SCWE Policy. The NRC will follow-up on the SCWE theme using baseline inspection sample because this is the first assessment cycle in which the cross-cutting theme was identified.

The enclosed inspection plan lists the inspections scheduled through June 30, 2018. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last nine months of the inspection plan are tentative and may be revised at the mid-cycle performance review. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include security related inspections, which will be sent via separate, non-publicly available correspondence. In addition to the ROP baseline inspections at your facility, we also plan on conducting infrequently performed inspections which include: Inspection Procedure (IP) 43004, Inspection of Commercial-Grade Dedication Programs, and Operator Licensing Examinations. The NRC will continue to evaluate the effectiveness of TVAs oversight and management of operations during Unit 2 startup and transition to dual unit operattion. This will include inspections and reviews addressing the organizational and operational challenges associated with the integration of both Watts Bar units.

The NRC staff completed Temporary Instruction 2515/191, Inspection of the Implementation of Mitigation Strategies and Spent Fuel Pool Instrumentation Orders and Emergency Preparedness Communication/Staffing/Multi-Unit Dose Assessment Plans at Watts Bar on January, 16 2016 to confirm full implementation of orders Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events and Order EA-12-051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation. The results of the inspection can be found in inspection report 05000390/2015609 and 05000391/2015616.

In Staff Requirements Memorandum - SECY 16-0009, Recommendations Resulting from the Integrated Prioritization and Re-Baselining of Agency Activities, the Commission approved the NRC staff recommendation to discontinue the formal mid-cycle assessment process beginning in calendar year 2017. This will be the final mid-cycle assessment letter. The staff will continue to conduct quarterly assessment meetings and communicate changes in the assessment of licensee performance in accordance with the guidance in Inspection Manual Chapter 0305, Operating Reactor Assessment Program.

In accordance with 10 CFR 2.390 of the NRCs Agency Rules of Practice and Procedure, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Please contact me at (404) 997-4415 with any questions you have regarding this letter.

Sincerely,

/RA/

Alan Blamey, Chief Reactor Projects Branch 6 Division of Reactor Projects Docket No.: 50-390 License No.: NPF-90 Enclosure: Watts Bar Inspection/Activity Plan (09/01/2016 - 06/30/2018)

cc: Distribution via ListServ

_________________________ SUNSI REVIEW COMPLETE FORM 665 ATTACHED OFFICE RII:DRP RII:DRP SIGNATURE CRK1 AJB3 NAME C. Kontz A. Blamey DATE 8/5/2016 8/31/2016 8/ /2016 8/ /2016 8/ /2016 8/ /2016 8/ /2016 E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NO

Page 1 of 2 Watts Bar 08/31/2016 08:08:16 Inspection / Activity Plan Report 22 09/01/2016 - 06/30/2018 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site ISFSI - ISFSI DRY RUN AND INITIAL LOADING 2 1 08/29/2016 09/02/2016 IP 60854.1 Preoperational Testing of Independent Spent Fuel Storage Facility Installation at Operating Plants 1 09/12/2016 09/16/2016 IP 60854.1 Preoperational Testing of Independent Spent Fuel Storage Facility Installation at Operating Plants 1 09/19/2016 09/24/2016 IP 60854.1 Preoperational Testing of Independent Spent Fuel Storage Facility Installation at Operating Plants PI&R - PROBLEM IDENTIFICATION AND RESOLUTION 5 1, 2 09/12/2016 09/15/2016 IP 71152B Problem Identification and Resolution 1, 2 10/31/2016 11/04/2016 IP 71152B Problem Identification and Resolution EP - EP PROGRAM INSPECTION 5 1 11/14/2016 11/18/2016 IP 7111402 Alert and Notification System Testing 1 11/14/2016 11/18/2016 IP 7111403 Emergency Preparedness Organization Staffing and Augmentation System 1 11/14/2016 11/18/2016 IP 7111404 Emergency Action Level and Emergency Plan Changes 1 11/14/2016 11/18/2016 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies 1 11/14/2016 11/18/2016 IP 71151 Performance Indicator Verification OL RQ - REQUAL INSP 2 1 11/28/2016 12/02/2016 IP 7111111B Licensed Operator Requalification Program ISI - UNIT 1 IN-SERVICE INSPECTION & RVH EXAM 2 1 03/27/2017 03/31/2017 IP 7111108P Inservice Inspection Activities - PWR RP - RP OCCUPATIONAL INSPECTION WEEK 1 2 1 03/27/2017 03/31/2017 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1 03/27/2017 03/31/2017 IP 71124.02 Occupational ALARA Planning and Controls 1 03/27/2017 03/31/2017 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 1 03/27/2017 03/31/2017 IP 71124.04 Occupational Dose Assessment 1 03/27/2017 03/31/2017 IP 71124.05 Radiation Monitoring Instrumentation 1 03/27/2017 03/31/2017 IP 71151 Performance Indicator Verification SGISI - UNIT 1 SG IN-SERVICE INSPECTION 1 1 04/03/2017 04/07/2017 IP 7111108P Inservice Inspection Activities - PWR RP - RP OCCUPATIONAL INSPECTION WEEK 2 3 1 04/17/2017 04/21/2017 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1 04/17/2017 04/21/2017 IP 71124.02 Occupational ALARA Planning and Controls 1 04/17/2017 04/21/2017 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 1 04/17/2017 04/21/2017 IP 71124.04 Occupational Dose Assessment 1 04/17/2017 04/21/2017 IP 71124.05 Radiation Monitoring Instrumentation 1 04/17/2017 04/21/2017 IP 71151 Performance Indicator Verification This report does not include INPO and OUTAGE activities. Enclosure This report shows only on-site and announced inspection procedures.

Page 2 of 2 Watts Bar 08/31/2016 08:08:16 Inspection / Activity Plan Report 22 09/01/2016 - 06/30/2018 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site TFPI - TRIENNIEL FIRE PROTECTION INSPECTION 5 1 09/18/2017 09/22/2017 IP 7111105T Fire Protection [Triennial]

1 10/02/2017 10/06/2017 IP 7111105T Fire Protection [Triennial]

ISI - UNIT 2 IN-SERVICE INSPECTION 1 2 10/23/2017 10/27/2017 IP 7111108P Inservice Inspection Activities - PWR SGISI - UNIT 2 SG IN-SERVICE INSPECTION 1 2 10/30/2017 11/03/2017 IP 7111108P Inservice Inspection Activities - PWR EP - EP EXERCISE 3 1 11/13/2017 11/17/2017 IP 7111401 Exercise Evaluation 1 11/13/2017 11/17/2017 IP 7111404 Emergency Action Level and Emergency Plan Changes 1 11/13/2017 11/17/2017 IP 7111408 Exercise Evaluation - Scenario Review 1 11/13/2017 11/17/2017 IP 71151 Performance Indicator Verification MODS - PLANT MODIFICATIONS INSPECTION 3 1, 2 04/16/2018 04/20/2018 IP 7111117T Evaluations of Changes, Tests, and Experiments and Permanent Plant Modifications 1, 2 04/30/2018 05/04/2018 IP 7111117T Evaluations of Changes, Tests, and Experiments and Permanent Plant Modifications HS - TRIENNIAL HEAT SINK PERFORMANCE 1 1, 2 06/04/2018 06/04/2018 IP 7111107T Heat Sink Performance This report does not include INPO and OUTAGE activities. Enclosure This report shows only on-site and announced inspection procedures.