August 31, 2016
SUBJECT:
MID-CYCLE ASSESSMENT LETTER - WATTS BAR NUCLEAR PLANT UNIT 2 (NRC INSPECTION REPORT 05000391/2016611)
Dear Mr. Skaggs:
On August 10, 2016, the U. S. Nuclear Regulatory Commission (NRC) staff completed its performance review of the Watts Bar Nuclear Plant (WBN) Unit 2 construction project. Our technical staff reviewed inspection results for the period from July 1, 2015, through June 30, 2016. The purpose of this letter is to inform you of our assessment of your safety performance during this period and our plans for future inspections at your facility.
During the assessment period, WBN Unit 2 construction and testing activities were generally conducted in a manner that complied with the Commissions rules and regulations, the conditions of your construction permit, operating license, and the Unit 2 regulatory framework commitments. Our inspections indicated that your construction and testing programs were sufficiently implemented to support ongoing construction and testing activities. Management and Quality Assurance oversight effectively monitored and assessed these activities. In conclusion, project performance for the most recent quarter, as well as for the previous three quarters of the assessment cycle, was acceptable. We plan to continue with our inspection activities of Unit 2 testing in accordance with Inspection Manual Chapter (IMC) 2517.
The NRC identified a cross-cutting theme in the Safety Conscious Work Environment (SCWE)
cross-cutting area. Specifically, on March 23, 2016, the NRC issued a Chilling Effect Letter for Watts Bar. Since this is the first assessment cycle with this cross-cutting theme, the NRC will inspect SCWE using baseline inspection samples during inspections conducted under the Reactor Oversight Process.
On April 23, 2015, the NRC issued the Reactor Oversight Process Transition Plan for Watts Bar Nuclear Plant, Unit 2 (Agencywide Documents Access and Management System (ADAMS)
Accession No. ML15096A204). In accordance with this plan, upon completion of our inspection activities of your preoperational and startup testing programs, the NRC will assess current plant performance, provide the results of the assessment and our plans for inspection to you, and begin full implementation of the Reactor Oversight Process at Watts Bar Unit 2. In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). Please contact me at (404) 997-4606 with any questions you may have regarding this letter or our planned inspections.
Sincerely,
/RA/
Daniel W. Rich, Chief
Reactor Projects Branch 8
Division of Reactor Projects
Docket No. 50-391 License No. NPF-96
cc: See next page
_________________________
SUNSI REVIEW COMPLETE FORM 665 ATTACHED OFFICE RII:DRP RII: DCP
SIGNATURE JBB5 DWR1
NAME J. Baptist D. Rich
DATE 8/4/2016 8/31/2016 9/ /2016 9/ /2016 9/ /2016 9/ /2016 9/ /2016 E-MAIL COPY?
YES NO YES NO YES NO YES NO YES NO YES NO YES NO cc:
Mr. Gordon P. Arent Director, Licensing Watts Bar Nuclear Plant Tennessee Valley Authority P.O. Box 2000 Spring City, TN 37381
Mr. Paul Simmons, Vice President WBN Unit Two Project Watts Bar Nuclear Plant Tennessee Valley Authority P.O. Box 2000 Spring City, TN 37381
Mr. Sean Connors Plant Manager, WBN Nuclear Plant Tennessee Valley Authority P.O. Box 2000 Spring City, TN 37381
Mr. Joseph Shea, Vice President Nuclear Licensing Tennessee Valley Authority 1101 Market Street 3R Lookout Place Chattanooga, TN 37402-2801
Mr. S. A. Vance Assistant General Counsel Tennessee Valley Authority 400 West Summit Hill Drive 6A West Tower Knoxville, TN 37902
Mr. Kevin Walsh Site Vice President Watts Bar Nuclear Plant Tennessee Valley Authority P.O. Box 2000 Spring City, TN 37381
Mr. G. E. Pry Director, Plant Support Watts Bar Nuclear Plant Tennessee Valley Authority P.O. Box 2000 Spring City, TN 37381
Mr. E. D. Schrull Manager, Fleet Licensing Tennessee Valley Authority 1101 Market Street, LP 5A-C Chattanooga, TN 37402-2801
Debra G. Shults, Director Tennessee Department of Environment and Conservation (TDEC)
Division of Radiological Health William R. Snodgrass Tennessee Tower 15th Floor 312 Rosa L. Parks Avenue Nashville, TN 37243
Meigs County Mayor 17214 State Hwy 58 N.
Decatur, TN 37322
Rhea County Executive 375 Church Street Suite 215 Dayton, TN 37321
Ms. Ann P. Harris Public 341 Swing Loop Rockwood, TN 37854
cc email distribution:
Watts Bar 2 Licensing Tennessee Valley Authority Electronic Mail Distribution Letter to Michael from Daniel W. Rich dated August 31, 2016.
SUBJECT:
MID-CYCLE ASSESSMENT LETTER - WATTS BAR NUCLEAR PLANT UNIT 2 (NRC INSPECTION REPORT 05000391/2016611)
DISTRIBUTION:
Region II Regional Coordinator, OEDO B. Beasley, NRR R. Schaaf, NRR C. Haney, RII L. Gibson, RII EICS A. Blamey, RII DRP J. Nadel, RII WBN Unit 1 SRI OE Mail ConE_Resource@nrc.gov PUBLIC