UNITED STATES NUCLEAR REGULATORY COMMISSION rch 1, 2017

SUBJECT:

ANNUAL ASSESSMENT LETTER FOR WATTS BAR NUCLEAR PLANT, NRC INSPECTION REPORT 05000390/2016006 AND 05000391/2016006

Dear Mr. Shea:

The NRC has completed its end-of-cycle performance review of Watts Bar Nuclear Plant (WBN)

Units 1 and 2 reviewing performance indicators (PIs), inspection results, and enforcement actions from January 1, 2016, through December 31, 2016. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility.

The NRC concluded that overall performance at your facility preserved public health and safety.

The NRC determined the performance at Watts Bar Units 1 and 2 during the most recent quarter was within the Licensee Response Column, the highest performance category of the NRCs Reactor Oversight Process (ROP) Action Matrix, because all inspection findings had very low safety significance (i.e., Green), and all PIs were within the expected range (i.e., Green).

Therefore, the NRC plans to conduct ROP baseline inspections at your facility.

In letter dated November 21, 2016, WATTS BAR NUCLEAR PLANT, UNIT 2 - FULL TRANSITION TO THE REACTOR OVERSIGHT PROCESS AND ASSESSMENT LETTER (ADAMS Accession No. ML16326A210), the NRC communicated it had transitioned the remaining reactor safety cornerstones for the Watts Bar Nuclear Plant Unit 2 to the full oversight of the ROP as described in Inspection Manual Chapter (IMC) 2515 and IMC 0305. This also represented the conclusion of the applicability of IMC 2517. The NRC determined that overall, Watts Bar Nuclear Plant Unit 2 operated in a manner that preserved public health and safety and met all cornerstone objectives. Inspection findings and traditional enforcement violations issued across all cornerstones were determined to be of very low safety significance (i.e.,

Severity Level IV or Green). Additionally, PIs for previously transitioned cornerstones indicated that your performance was within the nominal, expected range (i.e., Green). Therefore, the NRC has determined that Watts Bar Nuclear Plant Unit 2 has entered the Licensee Response Column of the ROP Action Matrix, effective as of November 21, 2016. A cross-cutting theme in the Safety Conscious Work Environment (SCWE) cross-cutting area exists, as identified in our mid-cycle letter to you dated August 31, 2016 (ADAMS Accession No.

ML16244A703). Specifically, on March 23, 2016, the NRC issued letter entitled, Chilled Work Environment for Raising and Addressing Safety Concerns at the Watts Bar Nuclear Plant (ADAMS Accession No. ML16083A479) and the NRC identified one inspection finding in the assessment period with a cross-cutting aspect of SCWE Policy, [S.1]. The NRC will continue to follow-up on the Chilling Effect Letter and SCWE theme using baseline inspection samples and focused inspections as appropriate.

The enclosed inspection plan lists the inspections scheduled through December 31, 2018. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last twelve months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.

This inspection plan does not include security-related inspections, which will be sent via separate, non-publicly available correspondence.

In addition to the ROP baseline inspections at your facility, we also plan on conducting infrequently performed inspections which include: Operator Licensing Examinations; IP 93100, Safety-Conscious Work Environment Issue of Concern Followup; and IP 92702, Follow-up On Traditional Enforcement Actions Including Violations, Deviations, Confirmatory Action Letters, Confirmatory Orders, And Alternative Dispute Resolution Confirmatory Orders. Follow-up inspections in accordance with IP 92702 will be accomplished as necessary for the follow-up to open Confirmatory Order actions, willful violations, and escalated enforcements items.

Additionally, the NRC will perform Temporary Instruction 2515/192, Inspection of the Licensees Interim Compensatory Measures Associated With the Open Phase Condition Design Vulnerabilities in Electric Power Systems, in the first quarter of 2017.

As described in Watts Bar Nuclear Plant Unit 2 Reactor Oversight Process (ROP) Transition Plan (ADAMS Accession No. ML15096A204), because the PIs for Initiating Events indicators IE01and IE03; and Mitigating Systems indicators MS06, MS07, MS08, MS09, and MS10 are not yet valid for Unit 2; those PIs will be subject to augmented inspections until declared fully valid.

In accordance with Title 10 of the Code of Fedral Regulations (10 CFR) 2.390 of the NRCs Agency Rules of Practice and Procedure, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). Please contact me at (404) 997-4415 with any questions you have regarding this letter.

Sincerely,

/RA/

Alan Blamey, Chief Reactor Projects Branch 6 Division of Reactor Projects Docket No.: 50-390, 391 License No.: NPF-90, 96 Enclosure:

Watts Bar Inspection/Activity Plan 03/01/2017 - 12/31/2018 cc: Distribution via ListServ SUBJECT: ANNUAL ASSESSMENT LETTER FOR WATTS BAR NUCLEAR PLANT, NRC INSPECTION REPORT 05000390/2016006 AND 05000391/2016006 March 1, 2017 DISTRIBUTION:

M. Kowal, RII S. Price, RII OE Mail RIDSNRRDIRS PUBLIC RidsNrrPMWattsBarResource ROPassessment Resource ROPreports Resource Institute of Nuclear Power Operations (INPO)

ADAMS Accession Number: ML17060A160 OFFICE RII:DRP RII:DRP NAME JSeat ABlamey DATE 2/23/2017 2/24/2017 Official Agency Record

Page 1 of 3 Watts Bar 02/28/2017 07:04:37 Inspection / Activity Plan Report 22 03/01/2017 - 12/31/2018 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site CDBI - COMPONENT DESIGN BASES INSPECTION 1 1, 2 01/06/2017 04/28/2017 IP 7111121 Component Design Bases Inspection ISI - UNIT 1 IN-SERVICE INSPECTION 1 1 03/27/2017 03/31/2017 IP 7111108P Inservice Inspection Activities - PWR RP - RP OCCUPATIONAL INSPECTION WEEK 1 2 1, 2 03/27/2017 03/31/2017 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1, 2 03/27/2017 03/31/2017 IP 71124.02 Occupational ALARA Planning and Controls 1, 2 03/27/2017 03/31/2017 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 1, 2 03/27/2017 03/31/2017 IP 71124.04 Occupational Dose Assessment 1, 2 03/27/2017 03/31/2017 IP 71124.05 Radiation Monitoring Instrumentation 1, 2 03/27/2017 03/31/2017 IP 71151 Performance Indicator Verification SGISI - UNIT 1 SG IN-SERVICE INSPECTION 1 1 04/03/2017 04/07/2017 IP 7111108P Inservice Inspection Activities - PWR RP - RP OCCUPATIONAL INSPECTION WEEK 2 3 1 04/17/2017 04/21/2017 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1 04/17/2017 04/21/2017 IP 71124.02 Occupational ALARA Planning and Controls 1 04/17/2017 04/21/2017 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 1 04/17/2017 04/21/2017 IP 71124.04 Occupational Dose Assessment 1 04/17/2017 04/21/2017 IP 71124.05 Radiation Monitoring Instrumentation 1 04/17/2017 04/21/2017 IP 71151 Performance Indicator Verification EQI - DESIGN BASES ASSURANCE INSPECTION (PROGR 4 1, 2 05/08/2017 05/12/2017 IP 7111121N Component Design Bases Inspection (Programs)

1, 2 06/05/2017 06/09/2017 IP 7111121N Component Design Bases Inspection (Programs)

1, 2 06/19/2017 06/23/2017 IP 7111121N Component Design Bases Inspection (Programs)

ISI - UNIT 2 IN-SERVICE INSPECTION 1 2 10/23/2017 10/27/2017 IP 7111108P Inservice Inspection Activities - PWR SGISI - UNIT 2 SG IN-SERVICE INSPECTION 1 2 10/30/2017 11/03/2017 IP 7111108P Inservice Inspection Activities - PWR EP - EP EXERCISE 3 1, 2 12/11/2017 12/15/2017 IP 7111401 Exercise Evaluation 1, 2 12/11/2017 12/15/2017 IP 7111404 Emergency Action Level and Emergency Plan Changes 1, 2 12/11/2017 12/15/2017 IP 7111408 Exercise Evaluation - Scenario Review 1, 2 12/11/2017 12/15/2017 IP 71151 Performance Indicator Verification This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

Enclosure

Page 2 of 3 Watts Bar 02/28/2017 07:04:37 Inspection / Activity Plan Report 22 03/01/2017 - 12/31/2018 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site MODS - PLANT MODIFICATIONS INSPECTION 3 1, 2 03/19/2018 03/23/2018 IP 7111117T Evaluations of Changes, Tests, and Experiments and Permanent Plant Modifications HS - TRIENNIAL HEAT SINK PERFORMANCE 1 1, 2 06/04/2018 06/04/2018 IP 7111107T Heat Sink Performance OL EXAM - INITIAL LICENSE EXAM PREP 3 1 08/06/2018 08/10/2018 V23516 WATTS BAR / SEPTEMBER 2018 INITIAL EXAM AT POWER FACILITIES RP - RP PUBLIC INSPECTION 2 1, 2 08/06/2018 08/10/2018 IP 71124.06 Radioactive Gaseous and Liquid Effluent Treatment 1, 2 08/06/2018 08/10/2018 IP 71124.07 Radiological Environmental Monitoring Program 1, 2 08/06/2018 08/10/2018 IP 71151-OR01 Occupational Exposure Control Effectiveness 1, 2 08/06/2018 08/10/2018 IP 71151-PR01 RETS/ODCM Radiological Effluent Occurrences OL EXAM - INITIAL LICENSE EXAM 3 1 09/03/2018 09/21/2018 V23516 WATTS BAR / SEPTEMBER 2018 INITIAL EXAM AT POWER FACILITIES RP - RAD HAZARD AND TRANSPORTATION 2 1, 2 09/10/2018 09/14/2018 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1, 2 09/10/2018 09/14/2018 IP 71124.08 Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation ISI - UNIT 1 IN-SERVICE INSPECTION 1 1 09/17/2018 09/21/2018 IP 7111108P Inservice Inspection Activities - PWR SGISI - UNIT 1 SG IN-SERVICE INSPECTION 1 1 09/24/2018 09/28/2018 IP 7111108P Inservice Inspection Activities - PWR PI&R - PROBLEM IDENTIFICATION AND RESOLUTION 4 1, 2 10/22/2018 10/26/2018 IP 71152 Problem Identification and Resolution 1, 2 11/05/2018 11/09/2018 IP 71152B Problem Identification and Resolution EP - EP PROGRAM INSPECTION 5 1, 2 11/12/2018 11/16/2018 IP 7111402 Alert and Notification System Testing 1, 2 11/12/2018 11/16/2018 IP 7111402 Alert and Notification System Testing 1, 2 11/12/2018 11/16/2018 IP 7111403 Emergency Preparedness Organization Staffing and Augmentation System 1, 2 11/12/2018 11/16/2018 IP 7111404 Emergency Action Level and Emergency Plan Changes 1, 2 11/12/2018 11/16/2018 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies 1, 2 11/12/2018 11/16/2018 IP 71151-EP01 Drill/Exercise Performance 1, 2 11/12/2018 11/16/2018 IP 71151-EP02 ERO Readiness 1, 2 11/12/2018 11/16/2018 IP 71151-EP03 Alert & Notification System Reliability This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

Page 3 of 3 Watts Bar 02/28/2017 07:04:37 Inspection / Activity Plan Report 22 03/01/2017 - 12/31/2018 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site OL RQ - REQUAL INSPECTION 2 1, 2 11/12/2018 11/16/2018 IP 7111111B Licensed Operator Requalification Program This report does not include INPO and OUTAGE activities.