IR 05000391/2014606

From kanterella
Jump to navigation Jump to search
Mid-Cycle Assessment Letter Watts Bar Nuclear Plant, Unit 2 (NRC Inspection Report 05000391/2014606)
ML14247A111
Person / Time
Site: Watts Bar Tennessee Valley Authority icon.png
Issue date: 09/03/2014
From: Haag R
NRC/RGN-II/DCP/CPB3
To: Skaggs M
Tennessee Valley Authority
Michelle Adams
References
IR-2014-606
Download: ML14247A111 (12)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION

REGION II

245 PEACHTREE CENTER AVE., NE., SUITE 1200 ATLANTA, GEORGIA 30303-1257 September 3, 2014 Mr. Michael Senior Vice President Nuclear Generation Development and Construction Tennessee Valley Authority 6A Lookout Place 1101 Market Street Chattanooga, TN 37402-2801 SUBJECT: MID CYCLE ASSESSMENT LETTER WATTS BAR NUCLEAR PLANT

-

UNIT 2 (NRC INSPECTION REPORT 05000391 /2014606)

Dear Mr. Skaggs:

On August 11, 2014, the NRC staff completed its performance review of the Watts Bar Nuclear Plant Unit 2 construction project. Our technical staff reviewed inspection results for the period from July 1, 2013 through June 30, 2014. The purpose of this letter is to inform you of our assessment of your safety performance during this period and our plans for future inspections at your facility.

Overall, Watts Bar Nuclear Plant Unit 2 construction activities were conducted in a manner that complied with the Commissions rules and regulations, the conditions of your construction permit, and the Unit 2 regulatory framework commitments. Our inspections indicated that your construction and testing programs were sufficiently implemented to support ongoing construction and testing activities. Management and Quality Assurance oversight effectively monitored and assessed these activities. The corrective action program implementation activities, including initiation, classification, disposition, and trending were deemed satisfactory.

In conclusion, project performance for the most recent quarter, as well as for the previous three quarters of the assessment cycle, was acceptable based on the above inspection conclusions, the fact that all violations were classified as severity level IV or below, and that no substantive cross-cutting issues were identified. Therefore, we do not plan to expand our inspection activities beyond what is specified by Inspection Manual Chapter (IMC) 2517.

The NRC staff spent over 17,900 hours0.0104 days <br />0.25 hours <br />0.00149 weeks <br />3.4245e-4 months <br /> during the 12-month Mid-Cycle Assessment period performing inspections, assessments, public meetings, allegation follow-up, and inspection program support for WBN Unit 2. The NRC staff anticipates this level of effort will increase over the next 12-month assessment cycle as WBN Unit 2 construction and pre-operational testing activities are completed.

As a result of reviewing your construction schedule and through interaction with your staff, the enclosed inspection plan contains those projected inspection activities that we have currently identified. Many of the inspections listed in the enclosed inspection plan were scheduled based on information your staff provided to the NRC. This information involved dates for completion of construction activities that would be subject to the corresponding NRC inspections. Therefore, it is crucial that you keep us apprised of any changes to the scheduled completion dates, in order to maintain our inspection plan current. As additional details of your project schedule become available, we will plan other inspections specified in Inspection Manual Chapter 2517. Your staff will be given ample notification of changes to upcoming inspection activities or newly identified inspections as they become finalized in order to allow for the resolution of any scheduling conflicts and personnel availability. Routine inspections performed by the resident staff are not listed on the inspection plan due to their ongoing and continuous nature.

The NRC continues implementation of Inspection Manual Chapter 2513, Light Water Reactor Inspection Program Preoperational Testing and Operational Preparedness Phase. We have

not listed preoperational testing inspections in the enclosed inspection plan due to likelihood that the inspection dates will change as adjustments to your preoperational testing schedule occur.

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.pov/reading rm/adamshtml (the Public Electronic Reading Room).

Please contact me at (404) 997-4446 with any questions you may have regarding this letter or our planned inspections.

Sincerely, IRN Robert C. Haag, Chief Construction Projects Branch 3 Division of Construction Projects Docket No. 50-391 Construction Permit No: CPPR-92 Enclosure:

Watts Bar Unit 2 Scheduled Inspection Items List cc w/encl: Mr. R. R. Baron, Senior Manager Mr. Gordon P. Arent Nuclear Construction Quality Assurance Director, Licensing WBN Unit Two Watts Bar Nuclear Plant Watts Bar Nuclear Plant Tennessee Valley Authority Tennessee Valley Authority P.O. Box 2000 P.O. Box 2000 Spring City, Tennessee 37381 Spring City, Tennessee 37381 Mr. 0. J. Zeringue, General Manager Mr. Joseph Shea, Vice President Engineering and Construction Nuclear Licensing WBN Unit Two Tennessee Valley Authority Watts Bar Nuclear Plant 1101 Market Street Tennessee Valley Authority 3R Lookout Place P.O. Box 2000 Chattanooga, TN 37402-2801 Spring City, Tennessee 37381 Mr. E. J. Vigluicci Mr. R. A. Hruby, General Manager Assistant General Counsel Technical Services Tennessee Valley Authority WBN Unit Two 400 West Summit Hill Drive Watts Bar Nuclear Plant 6A West Tower Tennessee Valley Authority Knoxville, Tennessee 37402 P.O. Box 2000 Spring City Tennessee 37381 Mr. Lawrence E. Nanney, Director Tennessee Department of Environmental Mr. James ODell, Manager Health & Conservation Licensing and Industry Affairs Division of Radiological Health WBN Nuclear Plant 3rd Floor, L&C Annex Tennessee Valley Authority 401 Church Street P.O. Box 2000 Nashville, TN 37243-1 532 Spring City, Tennessee 37381 Mr. Kevin Walsh Mr. Joseph P. Grimes Site Vice President Chief Nuclear Officer Watts Bar Nuclear Plant and Executive Vice President Tennessee Valley Authority Tennessee Valley Authority P.O. Box 2000 1101 Market Place Spring City, Tennessee 37381 3R Lookout Place Chattanooga, Tennessee 37402-2801 County Mayor P.O. Box 156 County Executive Decatur, Tennessee 37322 375 Church Street Suite 215 Ms. Ann P. Harris Dayton, Tennessee 37321 Public 341 Swing Loop Mr. Sean Connors Rockwood, TN 37854 Plant Manager, WBN Nuclear Plant Tennessee Valley Authority P.O. Box 2000 Spring City, Tennessee 37381 cc email distribution w/encl:

Greg Scott Ten nessee Valley Authority Electronic Mail Distribution Watts Bar Unit 2 Licensing Tennessee Valley Authority Electronic Mail Distribution

REQ Watts Bar Unit 2 Ca Scheduled Inspection Items List I

71 Items

Scheduled Type Item # Tide Inspection TMI Il.D.3 Valve position indication 09/08/2014 GL 79-36 Adequacy of station electric distribution systems voltages 09/08/2014 GL 06-02 Grid reliability and impact on plant risk and operability of offsite power 09/08/2014 TI 2515/174 Hydrogen igniter backup power 09/08/2014 TI 2515/165 Offsite power and impact on plant risk 09/08/2014 SER SSERAppHH NRC staff will verify installation of acoustic-monitoring system for the 09/08/2014 Item 74 power-operated relief valve (PORV) position indication in WBN U2 before fuel load (Section 7.8.1)

TI 2512/021 Equipment Seismic CAP 09/15/2014 TMI Il.B.2 Plant shielding 10/06/2014 GL 89-04 Guidelines on developing acceptable inservice testing programs 10/06/2014 TI 2515/110, Ri SR check valves. GL 89-04 10/06/2014 TI 2515/1 14 GL 89-04, Inservice Testing 10/06/2014 CDR 83-48 Installation of flow switch & sensing lines 10/06/2014 Wednesday, September 03, 2014 Page 1 of.6 IEflCIOSU re

Scheduled Type Item # Title lIzspLc SER SSER App HH Confirm adequacy of updates for plant data displays and dose 10/06/2014 Item 41 assessment models prior to issuance of Unit 2 CL (Section 13.3.2.9)

SER SSER App HH NRC staff will confirm availability & operability of ERDS for U2 prior to 10/06/2014 Item 38 issuance of U2 CL (SSER 22, Section 13.3.2.6)

TI 2512/026 Instrument Lines CAP 10/20/2014 GL 89-19 Request for actions related to resolution of unresolved safety issue A- 10/20/2014 47, Safety implication of control systems in LWR nuclear power plants, pursuant to 1OCFR5O.54(f)

GL 96-01 Testing of safety-related circuits 10/20/2014 TI 2515/139 GL 96-01, Testing of SR logics circuits 10/20/2014 IP 71111.07 Heat Sink Performance - Subissue: ERCW testing (02.02.d.5) 10/20/2014 SER SSER App HH NRC staff should verify the ERCW dual unit flow balance confirms that 10/20/2014 Item 90 ERCW pumps meet all specified performance requirements & have sufficient capability to supply all required ERCW normal & accident flows for dual unit operation OTHER Fire Protection Program Inspection 10/20/2014 P 80210 Environmental Protection 10/27/2014 BL 79-24 Frozen lines 11/03/2014 VIO 87-19-02 Failure to preseve equipment installed in north/south valve rooms 11/03/2014 CDR 86-24 Inadequate flexibility of instrument tubing attached to steel containmt 11/03/2014 vessel CDR 94-04 Potential freezing of main steam pressure transmitter sense line 11/03/2014 Wednesday, September 03, 2014 Page 2 of 6

Scheduled Type Item # Title !IlSpeCtWII OTHER Fire Protection Program Inspection 11/04/2014 P 73051 nservice Inspection Program 11/10/2014 IP 73052 Inservice Inspection Procedures 11/10/2014 IP 73053 Preservice Inspection Observation 11/10/2014 IP 71111.07 Heat Sink Performance 11/17/2014 IP 71111.07 Heat Sink Performance - Subissue: CCS HX B heat transfer test 11/17/2014 (02.02.b. 1)

IP 71111.07 Heat Sink Performance Subissue: Intake inspections, system

- 11/17/2014 controls, and system chemistry (02.02.d.2&4)

SER SSER App HH Resolve reasoning for not upgrading MSIV solenoid valves to Category 11/17/2014 Item 23 1 TI 2512/036 Environmental Qualification SP 12/01/2014 GL 04-02 Potential impact of debris blockage on emergency recirculation during 12/01/2014 design basis accidents at PWRs TI 2515/87 MPAA-17: RG 1.97 12/01/2014 TI 2515/166, Ri Containment sump blockage 12/01/2014 CDR 87-10 Failure of Category C devices may adversely affect Category A 12/01/2014 devices SER SSER App HH Perform detailed inspection/evaluation prior to fuel load on EQ 12/01/2014 Item 16 program compliance with 1OCFR5O.49 requirements (Section 3.11.2)

Wednesday, September 03, 2014 Page 3 of 6

Scheduled Type Ileni # Title ln,pectio,i SER SSER App HH Verify accuracy of WBN U2 EQ list prior to fuel load (Section 3.11.2.1) 12/01/2014 Item 17 IP 79501 LWR Water Chemistry Control And Chemical Analysis Audits 12/01/2014 IP 79502 Plant Systems Affecting Plant Water Chemistry 12/01/2014 IP 84525 Quality Assurance and Confirmatory Measurements for In Plant 12/01/2014 Radiochemical Analysis (Preoperational And Supplemental)

P 71130 Security Operational Readiness Inspection 12/08/2014 IP 35742 QA Program (Document Control) 12/08/2014 BL 96-02 Movement of heavy loads over spent fuel. over fuel in reactor, or over 12/15/2014 safety-related equipment SER SSER App HH Verify completion of DCNs of 125V dc vital battery system prior to 12/15/2014 Item 33 issuance of Unit 2 OL (Section 8.3.2.3)

BL 80-04 Analysis of PWR main steam line break with continuous feedwater 01/05/2015 addition BL 03-02 Leakage from RPV lower head penetrations and reactor coolant 01/05/2015 pressure boundary integrity (PWR5)

TMI ll.E.1.2 Auxiliary feedwater system initiation and flow 01/05/2015 GL 88-14 Instrument air supply system problems affecting safety-related 01/05/2015 equipment TI 2500/19 Licensees actions taken to implement USI A-26: Transient protection 01/05/2015 TI 2515/120 MPA Item A-22, Station Blackout Rule 01/05/2015 Wednesday, September 03, 2014 Page 4 of 6

Scheduled Type lieu: # Title I,u.j,ecIioui TI 2515/1 52, Ri BL 2003-02, RPV nozzles 01/05/2015 Fl 86-10-03 U2 instrument air preop test 01/05/2015 CDR 86-il Lack of thermal qualification for Systems 43 & 90 piping 01/05/2015 TI 2515/i 71 Verification of site specific implementation of B.5.b Phase 2 & 3 01/05/2015 mitigating strategies SER SSER App HH Confirm adequacy of emergency facilities/equipment to support dual 01/05/2015 Item 40 unit operations prior to issuance of Unit 2 CL (Section 13.3.2.8)

SER SSER App HH NRC staff will verify test procedures & qualification testing for auxiliary 01/05/2015 Item 75 feedwater initiation & control & flow indication are completed in WBN U2 before fuel load (Section 7.8.2)

TI 2512/041 Radiation Monitoring System SP 01/12/2015 TMI ll.F.1.2.a Noble gas 01/12/2015 TMI lI.F.1.2.c Containment high range monitoring 01/12/2015 BL 88-il PZR surge line thermal stratification 02/02/2015 IP 42451 Maintenance Procedures 02/02/2015 TI 2512/037 Master Fuse List SP 02/09/2015 URI 87-i 9-06 Nonsafety-related cable in close proximity to safety-related cable in 02/09/2015 electrical panels TI 2512/020 Electrical Issues CAP - Subissue: Cable separation and electrical 02/09/2015 isolation Wednesday, September 03, 2014 Page 5 of 6

Scheduled Type Item # Title TI 2512/038 Mechanical Equipment Qualification SP 02/16/2015 TMI l.C.7 NSSS vendor revision of procedures 03/09/2015 BL 80-06 Emergency safety feature reset controls 04/06/2015 Wednesday, September 03, 2014 Page 6 of 6 available, we will plan other inspections specified in Inspection Manual Chapter 2517. Your staff will be given ample notification of changes to upcoming inspection activities or newly identified inspections as they become finalized in order to allow for the resolution of any scheduling conflicts and personnel availability. Routine inspections performed by the resident staff are not listed on the inspection plan due to their ongoing and continuous nature.

The NRC continues implementation of Inspection Manual Chapter 2513, Light Water Reactor Inspection Program Preoperational Testing and Operational Preparedness Phase. We have

not listed preoperational testing inspections in the enclosed inspection plan due to likelihood that the inspection dates will change as adjustments to your preoperational testing schedule occur.

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading rm/adams.html (the Public Electronic Reading Room).

Please contact me at (404) 997-4446 with any questions you may have regarding this letter or our planned inspections.

Sincerely, IRA)

Robert C. Haag, Chief Construction Projects Branch 3 Division of Construction Projects Docket No. 50-391 Construction Permit No: CPPR-92 Enclosure:

Watts Bar Unit 2 Scheduled Inspection Items List cc: (See next page)

  • PUBLICLY AVAILABLE n NON-PUBLICLY AVAILABLE D SENSITIVE * NON-SENSITIVE ADAMS: * Yes ACCESSION NUMBER: ML14247A111 * SUNSI REVIEW COMPLETE OFFICE RII:DCP SIGNATURE CJE NAME CEven DATE 9/3/2014 E-MAIL COPY? YES NO OFFICIAL RECORD COPV DOCUMENT NAME: G:\CCI\DCP\CPB3\WATTS BAR 2\ASSESSMENT\2014 MID CYCLE\WBN2-MID-CYCLE LETTER 2014 REV 1.DOcX

Letter to Michael from Robert C. Haag dated September 3, 2014.

SUBJECT: WATTS BAR NUCLEAR PLANT UNIT 2 CONSTRUCTION - NRC INSPECTION REPORT 05000391/2014606 Distribution w/encl:

Region II Regional Coordinator, OEDO (E. Quinones)

J. Quichocho, NRR J. Poole, NRR A. Hon, NRR J. Bartley, RIl DRP T. Nazario, Rh Watts Bar Unit 2 SRI E. Patterson, Rh, WBN Unit 2, RI R. Monk, RhI Watts Bar Unit 1 SRI S. Price, Rh ConE Resource@nrc.Qov PUBLIC