ML22318A007

From kanterella
Jump to navigation Jump to search
Integrated Inspection Report 05000390/2022003 and 05000391/2022003
ML22318A007
Person / Time
Site: Watts Bar  Tennessee Valley Authority icon.png
Issue date: 11/14/2022
From: Wesley Deschaine
Division Reactor Projects II
To: Jim Barstow
Tennessee Valley Authority
References
IR 2022003
Download: ML22318A007 (16)


See also: IR 05000390/2022003

Text

November 14, 2022

Mr. Jim Barstow

Vice President Nuclear Regulatory

Affairs & Support Services

Tennessee Valley Authority

1101 Market Street, LP 4A-C

Chattanooga, TN 37402-2801

SUBJECT: WATTS BAR NUCLEAR PLANT - INTEGRATED INSPECTION REPORT

05000390/2022003 AND 05000391/2022003

Dear Jim Barstow:

On September 30, 2022, the U.S. Nuclear Regulatory Commission (NRC) completed an

inspection at Watts Bar Nuclear Plant. On October 24, 2022, the NRC inspectors discussed the

results of this inspection with Mr. Anthony Williams and other members of your staff. The results

of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

The Regional Administrator has authorized staff to use IP 50001, Steam Generator

Replacement Inspection, to inspect Watts Bar Unit 2 Steam Generator Replacement because

the steam generator replacement inspection is an infrequent inspection and outside of the

routine reactor oversight program (ROP) baseline inspections.

This letter, its enclosure, and your response (if any) will be made available for public inspection

and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document

Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public

Inspections, Exemptions, Requests for Withholding.

Sincerely,

Signed by Deschaine, Wesley

on 11/14/22

Wesley D. Deschaine, Chief

Reactor Projects Branch 5

Division of Reactor Projects

Docket Nos. 05000390 and 05000391

License Nos. NPF-90 and NPF-96

Enclosure:

As stated

cc w/ encl: Distribution via LISTSERV

ML22318A007

X Non-Sensitive X Publicly Available

X SUNSI Review

Sensitive Non-Publicly Available

OFFICE RII/DRP

NAME W. Deschaine

DATE 11/14/22

U.S. NUCLEAR REGULATORY COMMISSION

Inspection Report

Docket Numbers: 05000390 and 05000391

License Numbers: NPF-90 and NPF-96

Report Numbers: 05000390/2022003 and 05000391/2022003

Enterprise Identifier: I-2022-003-0020

Licensee: Tennessee Valley Authority

Facility: Watts Bar Nuclear Plant

Location: Spring City, TN 37381

Inspection Dates: July 01, 2022 to September 30, 2022

Inspectors: N. Childs, Senior Project Engineer

P. Cooper, Senior Reactor Inspector

N. Karlovich, Resident Inspector

K. Kirchbaum, Operations Engineer

M. Magyar, Reactor Inspector

N. Peterka, Fuel Facility Inspector

M. Riley, Senior Project Engineer

D. Simpkins, Sr. Tech Training Program Specialist

J. Steward, Senior Resident Inspector

D. Turpin, Resident Inspector

Approved By: Wesley D. Deschaine, Chief

Reactor Projects Branch 5

Division of Reactor Projects

Enclosure

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees

performance by conducting an integrated inspection at Watts Bar Nuclear Plant, in accordance

with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for

overseeing the safe operation of commercial nuclear power reactors. Refer to

https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

2

PLANT STATUS

Unit 1 began the inspection period at 100 percent rated thermal power (RTP). On July 21, Unit

1 was reduced to 98 percent power due to condenser vacuum and returned to 100 percent RTP

on July 28. On August 2, 2022, Unit 1 was briefly reduced to 70 RTP to repair D common

station service transformer (CSST) and returned to 100 RTP on the same day. The unit

remained at or near RTP for the entire inspection period.

Unit 2 began the inspection period at Mode 1 following the refueling outage and returned to 100

RTP on July 5, 2022. On August 2, 2022, Unit 1 was reduced to 70 RTP to repair D CSST and

returned to 100 RTP on the same day. The unit remained at or near RTP for the entire

inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in

effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with

their attached revision histories are located on the public website at http://www.nrc.gov/reading-

rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared

complete when the IP requirements most appropriate to the inspection activity were met

consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection

Program - Operations Phase. The inspectors performed activities described in IMC 2515,

Appendix D, Plant Status, observed risk significant activities, and completed on-site portions of

IPs. The inspectors reviewed selected procedures and records, observed activities, and

interviewed personnel to assess licensee performance and compliance with Commission rules

and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (3 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following

systems/trains:

(1) Emergency Diesel Generator (EDG) 2A on August 12, 2022.

(2) Unit 1 and 2 125V DC System Channel I, II, and IV on August 24, 2022

(3) Safety Injection Pump (SI) 1A on September 21, 2022

Complete Walkdown Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated system configurations during a complete walkdown of the

Essential Raw Cooling System (ERCW) on August 17, 2022.

3

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (5 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a

walkdown and performing a review to verify program compliance, equipment functionality,

material condition, and operational readiness of the following fire areas:

(1) Diesel Generator Building (Elevation 742' and 760.5') on July 22, 2022.

(2) Auxiliary Building Rooms (Elevation 692' - Charging Pump Rooms and Pipe Chases)

on Aug 5, 2022.

(3) Auxiliary Building Corridor (Elevation 692) on August 5, 2022.

(4) Transformer Yard (Elevation 729') on August 15, 2022.

(5) Control Building (Elevation 692', 708', 729', and 755') on August 12, 2022.

Fire Brigade Drill Performance Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated the onsite fire brigade training and performance during two

unannounced fire drills one on July 13 in the Control Building Cable Spreading Room

and on August 9 in the Unit 1 Turbine Driven Auxiliary Feedwater Pump area.

71111.06 - Flood Protection Measures

Inspection Activities - Internal Flooding (IP Section 03.01) (2 Samples)

The inspectors evaluated internal flooding mitigation protections in the:

(1) Intake Pump Station (IPS) A train rooms

(2) 480V / Motor Control Center (MCC) board rooms

71111.08P - Inservice Inspection Activities (PWR)

PWR Inservice Inspection Activities Sample (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated pressurized water reactor non-destructive testing by

reviewing the following examinations from March 7 - July 25, 2022:

1. Ultrasonic Testing (UT)

a. RSG-3-H-SE, Primary Nozzle to Safe End, Class 1 (reviewed)

b. RSG-3-C-SE, Primary Nozzle to Safe End, Class 1 (reviewed)

c. 3065 FW-1, RCS Hot Leg Elbow to RSG Nozzle Safe End, Class 1

(reviewed)

d. 3065 FW-2, RCS Crossover Leg Elbow to RSG Nozzle Safe End,

Class 1 (reviewed)

2. Radiographic Testing (RT)

a. 3065 FW-1, RCS Hot Leg Elbow to RSG Nozzle Safe End, Class 1

(reviewed)

b. 3065 FW-2, RCS Crossover Leg Elbow to RSG Nozzle Safe End,

Class 1 (reviewed)

3. Penetrant Testing (PT)

a. 3065 FW-1, RCS Hot Leg Elbow to RSG Nozzle Safe End, Class 1

(reviewed)

4

b. 3065 FW-2, RCS Crossover Leg Elbow to RSG Nozzle Safe End,

Class 1 (reviewed)

4. Visual Testing (VT)

a. R-033, Reactor Vessel Closure Head, Code Case N-729-6 (reviewed)

The Inspectors evaluated the licensees boric acid corrosion control program

performance.

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01)

(1 Sample)

(1) The inspectors observed and evaluated licensed operator performance in the Main

Control Room during a dual unit downpower to 70% power, swap of electrical buses

and return to 100% power on August 2, 2022.

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) The inspectors observed and evaluated the following licensed operator requalification

simulator scenarios: crew A on July 20, 2022, and crew A on August 17, 2022. Both

observations make up one sample.

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (3 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the

following planned and emergent work activities to ensure configuration changes and

appropriate work controls were addressed:

(1) Risk assessment for (week of) August 1, 2022, with the D CSST failure on 7/31 and

swaps to A CSST.

(2) Risk assessment for (week of) July 11, 2022, with the B MCR Chiller out of service for

maintenance.

(3) Risk assessment for maintenance feed to D CSST swap on the 6.9KV shutdown

Boards, on September 15, 2022.

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (1 Sample)

The inspectors evaluated the licensee's justifications and actions associated with the

following operability determinations and functionality assessments:

(1) CR 1793858 - Shutdown Board 1B-B secondary block maintenance, on

August 3, 2022.

5

71111.18 - Plant Modifications

Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02)

(1 Sample)

The inspectors evaluated the following temporary or permanent modifications:

(1) Temporary modification WBN-2-2022-068-001, Removal of Unit 2 Loop 1 T Cold 2

RTD from scan in Eagle 21 on July 19, 2022.

71111.19 - Post-Maintenance Testing

Post-Maintenance Test Sample (IP Section 03.01) (6 Samples)

The inspectors evaluated the following post-maintenance testing activities to verify system

operability and/or functionality:

(1) 1-SI-62-901-A, 1A-A Centrifugal Charging Pump (CCP) Quarterly Performance Test,

following preventative maintenance, on July 5, 2022, (WO 122055915).

(2) 2-SI-63-901-B, Safety Injection Pump 2B-B Quarterly Performance Test, after

preventative maintenance was performed under WOs 122517428 and 122517424.

(3) 2-SI-3-907-B, Valve Position Indication Verification (Train B) Auxiliary Feedwater

(AFW) System, after replacement of 2-FSV-003-0359-B, Auxiliary Feedwater Pump

2B-B recirculation flow solenoid valve, under WO 122419369.

(4) N-VT-4, In-service Visual Examination after replacement of the High Pressure Fire

Water (HPFW) strainer outlet isolation valves (WBN-0-ISV-026-0553, WBN-0-ISV-

026-0549, WBN-0-ISV-026-0575, and WBN-0-ISV-026-0582), under WOs

113642168, 120411298, 120716471, and 120919948.

(5) 1-SI-61-901-A, Valve Full Stroke Exercising During Plant Operation Ice Condenser

System (Train A), WO 122610129 on August 23, 2022.

(6) 0-TI-50.045, 2B-B Diesel Starting Air System Quarterly Check Valve Test, WO 122610225 on August 23, 2022.

71111.22 - Surveillance Testing

The inspectors evaluated the following surveillance testing activities to verify system operability

and/or functionality:

Surveillance Tests (other) (IP Section 03.01) (4 Samples)

(1) Surveillance Instruction 1-SI-63-51, 18-Month Channel Calibration RWST Level,

Channel II Loop 1-LPL-63-51, on July 13, 2022 (WO 122561234)

(2) Surveillance Instruction 0-SI-82-11-B, Monthly Diesel Generator Start and Load Test

DG 1B-B, on August 11, 2022 (WO 122609865)

(3) Surveillance Instruction 1-SI-61-6, Weekly Ice Condenser Intermediate Deck Doors

Visual Inspection, on September 13, 2022 (WO 122658134).

(4) Surveillance Instruction 1-SI-74-901-B, Residual Heat Removal Pump 1B-B Quarterly

Performance Test, on August 24, 2022 (WO 122610132)

6

Inservice Testing (IP Section 03.01) (1 Sample)

(1) Surveillance Instruction 2-SI-63-901-A, Safety Injection Pump 2A-A Quarterly

Performance Test, on August 31,2022, (WO 122610433)

OTHER ACTIVITIES - BASELINE

71152A - Annual Follow-up Problem Identification and Resolution

Annual Follow-up of Selected Issues (Section 03.03) (1 Sample)

The inspectors reviewed the licensees implementation of its corrective action program

related to the following issues:

(1) Corrective actions and referenced calculations associated with the as-left open

running loads for the Unit 2 RCS loop 4 to RHR inlet bypass isolation valve, 2-MVOP-

074-0009-B, not meeting acceptance criteria on September 28 and 29, 2022.

71153 - Follow Up of Events and Notices of Enforcement Discretion

Personnel Performance (IP Section 03.03) (1 Sample)

(1) The inspectors evaluated a dual unit downpower to 70%, swap of electrical buses

and return to 100% power and licensees performance on August 2, 2022.

OTHER ACTIVITIES - TEMPORARY INSTRUCTIONS, INFREQUENT AND ABNORMAL

50001 - Steam Generator Replacement Inspection

During the Watts Bar Unit 2 Spring 2022 refueling outage, all four of the Westinghouse model

D3 (Alloy 600) original steam generators (OSGs) were replaced with Westinghouse Model

68AXP (Alloy 690) replacement steam generators (RSGs). This inspection report documents

inspection activities required by inspection procedure (IP) 50001, Steam Generator

Replacement Inspection, that were completed during the third quarter of 2022 and provides an

overall summary of inspection activities completed during the first, second, and third quarters of

2022. The table below identifies and correlates specific IP 50001 inspection requirements

examined over the first, second, and third quarters of 2022, with the corresponding quarterly

reports in which the inspection activities were completed.

IP 50001 Requirement Quarterly Integrated

Section Report(s)

02.02.a.1 Verify that selected design changes and modifications to 2022-001

systems, structures, and components (SSCs) described in 2022-002

the updated final safety analysis report (UFSAR) reviewed 2022-003

for compliance with 10 CFR 50.59.

02.02.a.2 Review key design aspects and modifications for the 2022-001

RSGs and other modifications associated with steam 2022-002

generator (SG) replacement. Include design reviews for 2022-003

7

temporary containment opening.

02.02.b Review engineering design, modification, testing, and 2022-001

analysis associated with SG lifting and rigging.

02.02.c Review radiation protection program controls, planning, 2022-002

and preparation.

02.02.d Review security considerations associated with vital and 2022-001

protected area barriers and plans to minimize any adverse

impact on the operating unit and common systems.

02.03.a Review special procedures for welding and non- 2022-002

destructive examination (NDE); training and qualifications 2022-003

for welding and NDE personnel; NDE results and work

packages for selected welds; completion of pre-service

NDE requirements for welds; and completion of baseline

eddy current examination of new SG tubes.

02.03.b Review activities associated with lifting and rigging. 2022-001

2022-002

02.03.c Observe portions of old and new SG cutting, movement, 2022-001

and reconnection inside and outside containment. 2022-002

02.03.d Major structural modifications to facilitate SG replacement 2022-002

and review condition of old SG hold down bolts for 2022-003

degradation.

02.03.e Inspect activities associated with containment access and 2022-002

restoration of temporary containment opening and 2022-003

containment leakage testing.

02.03.f Inspect establishment of operating conditions including 2022-001

defueling, RCS drain down, system isolation and safety 2022-002

tagging; implementation of radiation protection controls;

foreign material exclusion (FME) controls associated with

the primary and secondary side of the SGs and in related

RCS openings; and installation, use, and removal of

temporary services.

02.03.g Review radiological safety plans for temporary storage or 2022-002

disposal of retired SGs and components.

02.04 Conduct SG post-installation inspections and verifications 2022-003

in accordance with the inspection plan including,

containment leak testing, RCS leakage testing, and SG

secondary side leakage testing.

Steam Generator Replacement Inspection (6 Samples)

8

(1) Design Changes and Modifications to Systems, Structures, and Components - 10

CFR 50.59 Review (Sections 02.02.a.1 and 02.02.a.2)

The inspectors reviewed design documentation for restoration of the shield building

dome after replacement of the Unit 2 steam generators to verify that the acceptance

criteria for the restoration, as specified in the design documentation, were met.

(2) Welding and Non-Destructive Examination (NDE) Activities (Section 02.03.a)

In accordance with the guidance of IP 71111.08, the inspectors reviewed the

following nondestructive examination (NDE) documentation associated with the

fabrication and preservice examinations of the steam generator (SG) replacement

project.

ASME Section III radiography, magnetic particle, and ultrasonic examination

of the tubesheet and primary head weld

ASME Section XI ultrasonic examinations of the tubesheet and primary head

weld

Eddy Current examination for the SG tubes

The inspectors also reviewed welding and NDE associated with the reconnection of

the steam generator (SG) to the reactor coolant system. These items are

documented in section 71111.08P of this report.

(3) Old and New SG Cutting, Movement, and Reconnection Inside and Outside

Containment (Section 02.03.c)

Observations of reconnection activities were completed in the second quarter of

2022. During this inspection period, the inspectors reviewed welding and NDE

associated with the reconnection of the steam generator (SG) to the reactor coolant

system. These items are documented in section 71111.08P of this report.

(4) Major Structural Modifications to Facilitate SG Replacement (Section 02.03.d)

As required by IP 50001, Section 02.03.d, the inspectors reviewed documentation

associated with the inspection of the SG hold down bolts to verify that any

degradation identified was appropriately addressed.

(5) Containment Access and Restoration of Temporary Containment Opening and

Containment Leakage Testing (Section 02.03.e.)

The inspectors reviewed results of quality control acceptance testing performed on

materials (cement, fine and coarse aggregate, water, and admixtures) selected for

batching of the concrete. The inspectors also reviewed the concrete mix data to

ensure that selected trial mix met concrete design strength requirements, and that

Quality Control (QC) acceptance criteria specified in the procedures for the concrete

were based on the trial mixes.

The inspectors reviewed related concrete testing and sampling activities to assure

compliance with American Concrete Institute (ACI) and American Society for the

Testing of Materials (ASTM) codes.

(6) SG Post-Installation Verification and Testing (Section 02.04)

As required by IP 50001, Section 02.04, the inspectors performed selective

documentation reviews, consistent with the safety significance, of the following

9

areas: snubber pre-service testing; containment leak testing; RCS leakage testing;

SG secondary side leakage testing; and calibration and testing of instrumentation for

both the primary (RCS) and secondary side (feedwater and main steam) systems

affected by the SG replacement.

93100 - Safety-Conscious Work Environment Issue of Concern Followup

Safety-Conscious Work Environment Issue of Concern Followup (1 Sample)

(1) NRC qualified safety culture assessors performed a limited assessment of the safety

conscious work environment (SCWE) in the Chemistry Department at Watts Bar in

accordance with IP 93100, Safety Conscious Work Environment Issue of Concern

Follow-up. The objectives of the assessment were to: (1) determine whether actions

taken by Tennessee Valley Authority improved the work environment in the Chemistry

Department; (2) determine if employees are currently reluctant to raise safety or

regulatory issues; and (3) determine if employees are currently being discouraged

from raising safety or regulatory issues.

The team interviewed all available employees (25) from the Chemistry and Radiation

Protection Departments, which consisted of technicians, chemists, supervisors,

managers, and the employee concern program (ECP) manager. In general, at the

time of the inspection, the team determined that many employees in the chemistry

department are hesitant to raise safety concerns through multiple avenues out of fear

of retaliation or have the perceptions that nothing will be done with their concerns if

they do raise them. The team noted that some will not use the ECP; some are

hesitant to talk to the NRC; and while they are sometimes willing to write condition

reports (CRs), they have an overall perception that nothing will be done with the CRs

once they write them. The team heard that the amount of turnover and churn among

the staff and supervisors is causing tremendous strain on the organization. The team

also reviewed TVAs responses to the GLINT assessment, the USA Alliance nuclear

safety culture assessment and responses to NRC Requests for Information, which all

identified the Chemistry Department as an area of concern and have determined that

corrective actions are new and have not yet been effective at fixing the previously

identified work environment issues within the Chemistry Department. In addition, the

team determined that the corrective actions are not comprehensive enough to

address the work environment issues within the department.

The NRC determined that there is a chilled work environment in the Chemistry

Department, meaning individuals are hesitant to raise nuclear safety concerns for fear

of retaliation and perceive that Chemistry supervision is retaliating against chemistry

employees for bringing up concerns. The NRC reviewed the NRC allegation manual

guidance, Section 5.2.i.6(a)(2), to determine if a chilling effect letter (CEL) is

warranted at this time. The NRC concluded that the CEL is not appropriate at this

time because the licensee had recently implemented corrective actions and is still

evaluating the effectiveness of corrective actions. The NRC has requested the

licensee respond to the NRCs assessment results and implement appropriate

corrective actions.

INSPECTION RESULTS

10

No findings were identified.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

On October 24, 2022, the inspectors presented the integrated inspection results to Mr.

Anthony Williams and other members of the licensee staff.

On October 31, 2022, the inspector presented the SGRP inspection results to Mr.

Anthony Williams and other members of the licensee staff.

11

DOCUMENTS REVIEWED

Inspection Type Designation Description or Title Revision or

Procedure Date

50001 Miscellaneous 2-PI-CEM-15.0 Watts Bar Chemistry Primary to Secondary Leak Rate (data) 07/11/2022 -

07/17/2022

31814-116-PO Purchase Order - WP3730 Ready Mix Concrete for Dome 03/03/2022

Reinstall

31814-CGDP-001 SGT commercial grade dedication plan for concrete for Revision 1

reinstallation of WBN2 shield building dome following

replacement of SGs

31814-SPEC-C- SGT Specification - Bar Nuclear Plant Unit 2 - Concrete and Revision 5

004 Grout

Work Orders WO 120927614 visual examination record for initial preservice exam of rigid 05/29/2022

supports - SG#3

WO 120931694 visual examination record for initial preservice exam of rigid 05/29/2022

supports - SG#1

WO 120931715 visual examination record for initial preservice exam of rigid 05/28/2022

supports - SG#2

WO 120931760 visual examination record for initial preservice exam of rigid 05/28/2022

supports - SG#4

WO 121321481 Reinstall Hydraulic Tubing and Hoses to SG 2-1 Snubbers 06/08/2022

WO 121879786 0-SI-0-914 Snubber Functional Testing - Unit 2 06/09/2022

WO 122343467 pressure testing of SCV liner after replacement/repairs per 06/24/2022

TI-88.01

WO 122498103 2-SI-68-32 Reactor Coolant System Water Inventory 07/07/2022

Balance

71111.04 Corrective Action CR 1803952 NRC Identified: Error in system 63 Power Checklists 9/21/2022

Documents

Drawings 0-45W700-1 120VAC and 125VDC Vital Plant Control Power System 85

1-47W811-1-ISI Flow Diagram Safety Injection System 85

Procedures 0-SI-0-3 Weekly Log 72

1-SOI-63.01 Safety Injection System 20

1-SOI-63.01 ATT- Safety Injection System Handswitch 0

1H

1-SOI-63.01 ATT- Safety Injection System Power Checklist 9

12

Inspection Type Designation Description or Title Revision or

Procedure Date

1P

1-SOI-63.01 ATT- Safety Injection System Valve Checklist 16

1V

71111.05 Fire Plans Fire Plans WBN-PREFIREPLAN-AUX-0-692-01, Rev. 4/Rev. 3, AUX-0-

692-02, Rev. 3/Rev. 3, AUX-0-692-03, Rev. 8/Rev. 2, AUX-

0-692-04, Rev. 1/Rev. 2

Miscellaneous WBN FHAR, Part Introduction, Table I-1 Summary Compliance Fire Protection 60

1

71111.06 Calculations MDN-000-999- WBN PRA Internal Flooding Analysis Notebook 2

2008-0146

WBN-OSG-4099 Moderate Energy Line Break Flooding Study 16

Drawings 37W201-1 Intake Pumping Station, Mechanical Drawing 9

WBN-46W401-8- Architectural Plan EL 772.0, 782.0, & 786.0 7

AD

Miscellaneous WB-DC-40-31 Evaluating the Effect of Flooding due to Moderate Energy 5

Pipe Failures Inside and Outside Containment

WBN-DC-40-29 Flood Protection Provisions 19

71111.11Q Procedures 1-GO-4 Normal Power Operations 33

71111.13 Miscellaneous eSOMS

Daily risk status sheets

71111.15 Corrective Action Condition Report WBN-1-BD-211-B-B, 6.9KV Shutdown Board 1B-B

Documents 1793858

Miscellaneous 0-15E500-1 Key Diagram Station Aux Power System 85

71111.18 Engineering WBN-2-2022-068- Removal of Unit 2 Loop 1 Tcold2 RTD from scan in Eagle 06/29/2022

Changes 001 21

71111.19 Procedures 2-SI-63-901-B Safety Injection Pump 2 B-B Quarterly Performance Test 9

Work Orders 122517424 Testing of Large 2 Pole Motors-Safety Injection Pump 2B-B 09/06/2022

122517428 Safety Injection Pump 2 B-B, Inspect, Clean, 09/06/2022

Sample/Change Oil

122658395 Safety Injection Pump 2 B-B Quarterly Performance Test 09/06/2022

71111.22 Drawings WBN-2-47W811- Unit 2 Safety Injection System Flow Diagram 85

1-ISI-ISI

Procedures 2-SI-63-901-A Procedure, Safety Injection Pump 2A-A Quarterly 8

Performance Test

13

Inspection Type Designation Description or Title Revision or

Procedure Date

2-SOI-63.01 Safety Injection System 23

Work Orders WO 122610433 Safety Injection Pump 2A-A Quarterly Performance Test 08/31/2022

71152A Calculations MDQ0020742008- Documentation of Design Basis Review, Required 7

0302 Thrust/Torque Calculations and Valve and Actuator

Capability Assessment for Valve 2-FCV-74-009

Corrective Action CR 1763323

Documents

Miscellaneous DS-M18.2.21 Motor Operated Valve Thrust and Torque Calculations 28

S1001032800 Decommitment Package 17-2 3/21/2001

Procedures NPG-SPP-22.300 Corrective Action Program Rev 24

Work Orders 122176385

71153 Procedures 0-SOI-211.02 6.9KV Shutdown Board 1B-B 6

1-GO-4 Normal Power Operation 33

1-SOI-201.03 6.9 KV Unit Board 1C 5

14