| {{#Wiki_filter:. ..:) I -YANKEE ATOMIC ELECTRIC COMPANY 49 Yankee Road, Rowe, Massachusetts 01367 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC' 20555 -0001 Yankee Atomic Electric Company March 5, 2018 BYR 2018-006 10 CFR50.4 10 CFR 50.82(a)(8)(vii) Yankee Nuclear Power Plant Independent Spent Fuel Storage Installation NRC License No. DPR-3 {NRC Docket No. 50-029) | | {{#Wiki_filter:. ..:) I -YANKEE ATOMIC ELECTRIC COMPANY 49 Yankee Road, Rowe, Massachusetts 01367 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC' 20555 -0001 Yankee Atomic Electric Company March 5, 2018 BYR 2018-006 10 CFR50.4 10 CFR 50.82(a)(8)(vii) |
| | Yankee Nuclear Power Plant Independent Spent Fuel Storage Installation NRC License No. DPR-3 {NRC Docket No. 50-029) |
|
| |
|
| ==Subject:== | | ==Subject:== |
| Funding Status Report for Managing Irradiated Fuel and GTCC Waste On February 26, 1992, Yankee Atomic Electric Company (YAEC) informed the USNRC that the Board of Directors of Y AEC had decided to permanently cease operations at the Yankee Nuclear Power Plant and that fuel had been permanently removed from the reactor (Reference 1 ). In accordance with 10 CFR 50.82(a)(2), the certifications in the letter modified the YAEC license to permanently withdraw YAEC's authority to operate the reactor. In 1993, Y AEC commenced decommissioning the power plant. On August 10, 2007, the NRC released most of the formerly licensed land for unrestricted use, shrinking the licensed land to that utilized to support the Independent Spent Fuel Storage Installation (ISFSI) (Reference 2). Presently, Y AEC is storing irradiated fuel and Greater than Class C (GTCC) waste on site until the Department of Energy (DOE) satisfies its contractual obligations to take title and possession of the spent fuel and GTCC waste and remove them from the site. In Attachment 1, YAEC provides the attached Funding Status Report for Managing Irradiated Fuel and GTCC Waste at the Yankee Nuclear Power Plant ISFSI to comply with 1,0 CFR 50.82(a)(8)(vii). This letter contains no regulatory commitments. If you have any questions regarding this letter, please do not hesitate to contact me at (860) 267-6426 x304. | | |
| * Respectfully, Carla M. Pizzella Vice President, Chief Financial Officer, and Treasurer Yankee Atomic Electric Company BYR 2018-006\March 5, 2018\Page 2 | | Funding Status Report for Managing Irradiated Fuel and GTCC Waste On February 26, 1992, Yankee Atomic Electric Company (YAEC) informed the USNRC that the Board of Directors of Y AEC had decided to permanently cease operations at the Yankee Nuclear Power Plant and that fuel had been permanently removed from the reactor (Reference 1 ). In accordance with 10 CFR 50.82(a)(2), |
| | the certifications in the letter modified the YAEC license to permanently withdraw YAEC's authority to operate the reactor. |
| | In 1993, Y AEC commenced decommissioning the power plant. On August 10, 2007, the NRC released most of the formerly licensed land for unrestricted use, shrinking the licensed land to that utilized to support the Independent Spent Fuel Storage Installation (ISFSI) (Reference 2). Presently, Y AEC is storing irradiated fuel and Greater than Class C (GTCC) waste on site until the Department of Energy (DOE) satisfies its contractual obligations to take title and possession of the spent fuel and GTCC waste and remove them from the site. In Attachment 1, YAEC provides the attached Funding Status Report for Managing Irradiated Fuel and GTCC Waste at the Yankee Nuclear Power Plant ISFSI to comply with 1,0 CFR 50.82(a)(8)(vii). |
| | This letter contains no regulatory commitments. |
| | If you have any questions regarding this letter, please do not hesitate to contact me at (860) 267-6426 x304. |
| | * Respectfully, Carla M. Pizzella Vice President, Chief Financial |
| | : Officer, and Treasurer Yankee Atomic Electric Company BYR 2018-006\March 5, 2018\Page 2 |
|
| |
|
| ==Attachment:== | | ==Attachment:== |
Line 26: |
Line 33: |
|
| |
|
| ==References:== | | ==References:== |
| : 1. A. C. Kadak (Y AEC) letter to USNRC, "Permanent Cessation of Power Operations at the Yankee Nuclear Power Station," BYR-92-024, dated February 26, 1992 2. USNRC letter to Yankee Atomic Power Company, "Yankee Nuclear Power Station -Release of Land from Part 50 License," dated August 10, 2007 cc: D. Lew, Acting NRC Region I Administrator R. Powell, Chief, Decommissioning Branch, NRC, Region 1 J. Nguyen, NRC Project Manager J. Giarrusso, Planning, Preparedness & Nuclear Section Chief, MEMA J. Cope-Flanagan, Assistant General Counsel, MDPU J. Rogers, Commonwealth of Massachusetts Office of the Attorney General ATTACHMENT 1 TO BYR 2018-006 FUNDING STATUS REPORT FOR THE MANAGING OF IRRADIATED FUEL AND GTCC WASTE AT THE YANKEE NUCLEAR POWER PLANT INDEPENDENT SPENT FUEL STORAGE INSTALLATION (STATUS AS OF 12/31/2017) to BYR 2018-006 Funding Status Report for the Managing of Irradiated Fuel and GTCC Waste at the Yankee Nuclear Power Plant Independent Spent Fuel Storage Installation (Status as of 12/31/2017) 10 CFR Requirement Response Comment 10 CFR 50.82(a)(8)(vii) Requirements 1. The amount of funds accumulated -$123.5 Yankee Atomic Electric Company (Y AEC) has established an account within its to cover the cost of managing the million ( as of Nuclear Decommissioning Trust (NDT) entitled, "ISFSI Radiological Decom," that irradiated fuel. 12/31/2017) segregates the funds for decommissioning of the Yankee Nuclear Power Plant Independent Spent Fuel Storage Installation (ISFSI) from the larger balance of funds for ongoing management of irradiated fuel and Greater than Class C (GTCC) waste held in the NDT. The market balance represented here as of December 31, 2017 excludes the funds set-aside for decommissioning the ISFSI. 2. The projected cost of managing -$169.1 The current cost estimate for management of spent fuel and Greater than Class C irradiated fuel until title to the million (2018 (GTCC) waste was filed with the Federal Energy Regulatory Commission (FERC) on fuel and possession of the fuel is -2036*) September 30, 2016 and approved by FERC on November 15, 2016. transferred to the Secretary of (In 2017 Energy. dollars) | | : 1. A. C. Kadak (Y AEC) letter to USNRC, "Permanent Cessation of Power Operations at the Yankee Nuclear Power Station," |
| * Currently, the irradiated fuel and GTCC waste are scheduled to be removed from the site by 2035, with decommissioning, license termination, and business closure occurring after that time period. 3. If the funds accumulated do not See Comment The Company has several methods of obtaining additional funds to cover projected cover the projected cost, a plan to costs. obtain additional funds to cover the cost. First, Y AEC may collect funds through its power contracts and amendatory agreements under FERC regulation. The power contracts and the amendatory agreements specify the obligations of the purchasers for the costs of Y AEC, including the ongoing costs of managing irradiated fuel and GTCC waste. Pursuant to these power contracts, Y AEC has the ongoing ability to seek collections from its purchasers for additional funds that may be required to cover these costs. Second, Y AEC has received proceeds from the successful litigation of the first three phases of its breach of contract damages claims against the DOE for failure to begin the removal of spent nuclear fuel (SNF) and GTCC waste from the site in 1998. Y AEC will continue to file claims against the DOE as long as the DOE continues to breach its contract obligations related to SNF and GTCC waste. To that end, in 2017, the Company filed a fourth round of claims (the Phase IV case) against the DOE seeking Page 1 of2 to BYR 2018-006 Funding Status Report for the Managing of Irradiated Fuel and GTCC Waste at the Yankee Nuclear Power Plant Independent Spent Fuel Storage Installation (Status as of 12/31/2017) 10 CFR Requirement Response Comment damages for the years 2013 -2016. The Company cannot predict the timing or the amount it may ultimately be awarded. A YAEC FERC filing approved in June, 2013, implemented a fifteen-year funding mechanism. Until the 2013 FERC filing, the Company had employed a "full funding" assumption in developing funding requirements. The fifteen-year funding mechanism was put in place to incorporate the potential for the receipt of future DOE breach of contract damages as a source of funding. If future damage recovery does not occur, the Company has the ability to apply to FERC for more funding, if necessary. The approved FERC filing also requires Y AEC to provide an informational filing regarding the adequacy of funding if five years pass without receipt of damage awards from litigation with the DOE. Third, Y AEC expects to utilize the investment return on Decommissioning Trust assets to offset future costs. The current assumed rate of investment return, after fees and taxes IS 4.0%. Page 2 of2 (}} | | BYR-92-024, dated February 26, 1992 2. USNRC letter to Yankee Atomic Power Company, "Yankee Nuclear Power Station -Release of Land from Part 50 License," |
| | dated August 10, 2007 cc: D. Lew, Acting NRC Region I Administrator R. Powell, Chief, Decommissioning Branch, NRC, Region 1 J. Nguyen, NRC Project Manager J. Giarrusso, |
| | : Planning, Preparedness |
| | & Nuclear Section Chief, MEMA J. Cope-Flanagan, Assistant General Counsel, MDPU J. Rogers, Commonwealth of Massachusetts Office of the Attorney General ATTACHMENT 1 TO BYR 2018-006 FUNDING STATUS REPORT FOR THE MANAGING OF IRRADIATED FUEL AND GTCC WASTE AT THE YANKEE NUCLEAR POWER PLANT INDEPENDENT SPENT FUEL STORAGE INSTALLATION (STATUS AS OF 12/31/2017) |
| | Attachment 1 to BYR 2018-006 Funding Status Report for the Managing of Irradiated Fuel and GTCC Waste at the Yankee Nuclear Power Plant Independent Spent Fuel Storage Installation (Status as of 12/31/2017) 10 CFR Requirement Response Comment 10 CFR 50.82(a)(8)(vii) |
| | Requirements |
| | : 1. The amount of funds accumulated |
| | -$123.5 Yankee Atomic Electric Company (Y AEC) has established an account within its to cover the cost of managing the million ( as of Nuclear Decommissioning Trust (NDT) entitled, "ISFSI Radiological Decom," that irradiated fuel. 12/31/2017) segregates the funds for decommissioning of the Yankee Nuclear Power Plant Independent Spent Fuel Storage Installation (ISFSI) from the larger balance of funds for ongoing management of irradiated fuel and Greater than Class C (GTCC) waste held in the NDT. The market balance represented here as of December 31, 2017 excludes the funds set-aside for decommissioning the ISFSI. 2. The projected cost of managing |
| | -$169.1 The current cost estimate for management of spent fuel and Greater than Class C irradiated fuel until title to the million (2018 (GTCC) waste was filed with the Federal Energy Regulatory Commission (FERC) on fuel and possession of the fuel is -2036*) September 30, 2016 and approved by FERC on November 15, 2016. transferred to the Secretary of (In 2017 Energy. dollars) |
| | * Currently, the irradiated fuel and GTCC waste are scheduled to be removed from the site by 2035, with decommissioning, license termination, and business closure occurring after that time period. 3. If the funds accumulated do not See Comment The Company has several methods of obtaining additional funds to cover projected cover the projected cost, a plan to costs. obtain additional funds to cover the cost. First, Y AEC may collect funds through its power contracts and amendatory agreements under FERC regulation. |
| | The power contracts and the amendatory agreements specify the obligations of the purchasers for the costs of Y AEC, including the ongoing costs of managing irradiated fuel and GTCC waste. Pursuant to these power contracts, Y AEC has the ongoing ability to seek collections from its purchasers for additional funds that may be required to cover these costs. Second, Y AEC has received proceeds from the successful litigation of the first three phases of its breach of contract damages claims against the DOE for failure to begin the removal of spent nuclear fuel (SNF) and GTCC waste from the site in 1998. Y AEC will continue to file claims against the DOE as long as the DOE continues to breach its contract obligations related to SNF and GTCC waste. To that end, in 2017, the Company filed a fourth round of claims (the Phase IV case) against the DOE seeking Page 1 of2 Attachment 1 to BYR 2018-006 Funding Status Report for the Managing of Irradiated Fuel and GTCC Waste at the Yankee Nuclear Power Plant Independent Spent Fuel Storage Installation (Status as of 12/31/2017) 10 CFR Requirement Response Comment damages for the years 2013 -2016. The Company cannot predict the timing or the amount it may ultimately be awarded. |
| | A YAEC FERC filing approved in June, 2013, implemented a fifteen-year funding mechanism. |
| | Until the 2013 FERC filing, the Company had employed a "full funding" assumption in developing funding requirements. |
| | The fifteen-year funding mechanism was put in place to incorporate the potential for the receipt of future DOE breach of contract damages as a source of funding. |
| | If future damage recovery does not occur, the Company has the ability to apply to FERC for more funding, if necessary. |
| | The approved FERC filing also requires Y AEC to provide an informational filing regarding the adequacy of funding if five years pass without receipt of damage awards from litigation with the DOE. Third, Y AEC expects to utilize the investment return on Decommissioning Trust assets to offset future costs. The current assumed rate of investment return, after fees and taxes IS 4.0%. Page 2 of2 (}} |
|
---|
Category:Graphics incl Charts and Tables
MONTHYEARML18078A3012018-03-0505 March 2018 Yankee Nuclear Power Plant Independent Spent Fuel Storage Installation - Funding Status Report for Managing Irradiated Fuel and GTCC Waste ML15240A3622015-09-28028 September 2015 Master Report - Tables 1 and 2 ML0629300912006-10-16016 October 2006 OOL-09, Attachment B - Data Quality Assessment Plots and Curves, List of Figures ML0629300932006-10-16016 October 2006 6279 Activity Forms, Portable Instrument Accountability Forms and Source Check Form ML0629700712006-10-0505 October 2006 Yankee Nuclear Power Station - Graphs and Charts, 6264 Activity ML0615304122006-01-25025 January 2006 Report for Analysis of Concrete Samples from the Yankee Nuclear Power Station, Rowe, Massachusetts (Inspection No. 50-029/2005-002) (Rfta No. 06-001) ML0513301302005-02-23023 February 2005 Report for Analysis of a Concrete Sample from the Yankee Nuclear Power Station, Rowe, Massachusetts (Inspection No. 50-029/2004-002) (Rfta No. 05-001) IR 05000029/20040022005-02-23023 February 2005 Report for Analysis of a Concrete Sample from the Yankee Nuclear Power Station, Rowe, Massachusetts (Inspection No. 50-029/2004-002) (Rfta No. 05-001) ML0704004002005-02-21021 February 2005 YNPS-FSS-TBN01-00, Final Status Survey Report, TBN-01-13, Frequency Plot FSS Data Through Calculation of ALARA Action Level ML0704003942005-02-21021 February 2005 YNPS-FSS-TBN01-00, Final Status Survey Report, Volume 3 (Attachment B Through Appendix D) ML0513600812005-02-16016 February 2005 Confirmatory Survey Results for Class 3 Open Land Areas Outside the RCA, Yankee Nuclear Power Station, Rowe, Massachusetts (Docket No. 50-29; Rfta No. 04-007) ML0426801492004-08-0505 August 2004 Calculation for Contaminated Concrete for the License Termination Plan (Ltp) ML0426801462004-08-0505 August 2004 Calculation for Contaminated Concrete for the License Termination Plan (Ltp) ML0426801512004-07-31031 July 2004 Calculation for Contaminated Concrete for the License Termination Plan (Ltp) ML0634804411996-12-0404 December 1996 Attachment B - Data Quality Assessment Plots and Curves 2018-03-05
[Table view] Category:Letter
MONTHYEARML24085A2192024-03-11011 March 2024 Yankee Nuclear Power Station Independent Spent Fuel Storage Installation - Decommissioning Funding Assurance Status Report ML24085A2222024-03-11011 March 2024 Yankee Nuclear Power Plant Independent Spent Fuel Storage Installation - Funding Status Report for Managing Irradiated Fuel and GTCC Waste ML24047A0552024-01-15015 January 2024 Independent Spent Fuel Storage Installation, Formal Announcement of Change in ISFSI Manager ML24057A0212024-01-12012 January 2024 Yankee Nuclear Power Station Independent Spent Fuel Storage Installation - Nuclear Liability Insurance Coverage IR 07200031/20234012023-10-0404 October 2023 Yankee Atomic Electric Company - Independent Spent Fuel Storage Security Inspection Report 07200031/2023401 ML23157A1012023-05-0404 May 2023 Request for Exemption from 10 CFR 50.82(a)(8)(i)(A) and 10 CFR 50.75(h)(2) for the Yankee Nuclear Power Station Independent Spent Fuel Storage Installation ML23130A1562023-04-24024 April 2023 Yankee Nuclear Power Station Independent Spent Fuel Storage Installation, Annual Radioactive Effluent Release Report, Annual Radiological Environmental Operating Report, and Changes to the Off-Site Dose Calculation Manual for 2022 ML23080A1072023-03-0606 March 2023 Yankee Nuclear Power Station Independent Spent Fuel Storage Installation, Decommissioning Funding Assurance Status Report ML23080A1112023-03-0606 March 2023 Yankee Nuclear Power Plant Independent Spent Fuel Storage Installation, Funding Status Report for Managing Irradiated Fuel and GTCC Waste ML22340A4752023-02-24024 February 2023 Closeout Letter to Yankee Atomic Electric Company Regarding 2018 and 2021 Updated DFPs for Yankee Nuclear Power Station ISFSI ML23041A1132023-01-0505 January 2023 Yankee Atomic Electric Company - Report of 10 CFR 72.48 Changes, Tests, and Experiments ML23041A1122023-01-0505 January 2023 Independent Spent Fuel Storage Installation, 10 CFR 50.59 Changes, Tests, and Experiments Report ML22347A2802022-12-21021 December 2022 Yankee Atomic Electric Company - Independent Spent Fuel Storage Installation Security Inspection Plan Dated December 21, 2022 ML22237A0632022-08-0303 August 2022 Yankee Atomic Electric Company - Supplemental Information for the Three-Year Update to the Independent Spent Fuel Storage Installation Decommissioning Funding Plan ML22136A1562022-04-28028 April 2022 Yankee Nuclear Power Station Independent Spent Fuel Storage Installation, Annual Radioactive Effluent Release Report, Annual Radiological Environmental Operating Report, and Changes to the Off-Site Dose Calculation Manual for 2021 ML22119A2112022-04-18018 April 2022 Independent Spent Fuel Storage Installation - Yankee Atomic Electric Company Adoption of NAC-MPC System, Amendment 8 Certificate of Compliance and Canister Registration ML22089A1002022-03-14014 March 2022 Yankee Nuclear Power Plant Independent Spent Fuel Storage Installation - Funding Status Report for Managing Irradiated Fuel and GTCC Waste ML22082A1232022-03-14014 March 2022 Yankee Nuclear Power Station Independent Spent Fuel Storage Installation, Decommissioning Funding Assurance Status Report ML22011A1292022-01-31031 January 2022 Yankee Atomic Electric Company- Independent Spent Fuel Storage Installation Security Inspection Plan ML22038A2062022-01-20020 January 2022 Yankee Nuclear Power Station Independent Spent Fuel Storage Installation - Nuclear Liability Insurance Coverage ML22038A1982022-01-20020 January 2022 Yankee Nuclear Power Station Independent Spent Fuel Storage Installation - Property Insurance Coverage ML22010A0122022-01-10010 January 2022 Yankee Atomic Electric Company - Three-Year Update to the Independent Spent Fuel Storage Installation Decommissioning Funding Plan IR 05000029/20210012021-10-29029 October 2021 Yankee Atomic Electric Company - NRC Independent Spent Fuel Storage Installation Inspection Report 07200031/2021001 and 0500029/2021001 ML21287A0362021-10-0404 October 2021 Biennial Update to the Yankee Nuclear Power Station Final Safety Analysis Report ML21291A1602021-10-0404 October 2021 Yankee Nuclear Power Station Independent Spent Fuel Storage Installation, Biennial Update of the Yaec Quality Assurance Program ML21287A1012021-10-0404 October 2021 Yankee Atomic Electric Company - Yankee Nuclear Power Station Independent Spent Fuel Storage Installation, Biennial Update to the Yankee Nuclear Power Station License Termination Plan ML21189A0502021-06-0101 June 2021 Independent Spent Fuel Storage Installation, Formal Announcement of Change in ISFSI Manager ML21062A2472021-04-0707 April 2021 Close-out Letter - Yankee Rowe ISFSI DFP ML21105A7382021-03-0202 March 2021 Yankee Nuclear Power Station Independent Sperit Fuel Storage Installation - Decommissioning Funding Assurance Status Report ML21077A1682021-03-0202 March 2021 Yankee Nuclear Power Plant Independent Spent Fuel Storage Installation - Funding Status Report for Managing Irradiated Fuel and GTCC Waste ML21042A1452021-01-27027 January 2021 Yankee Nuclear Power Station Independent Spent Fuel Storage Installation - Property Insurance Coverage ML21042A9812021-01-27027 January 2021 Yankee Nuclear Power Station Independent Spent Fuel Storage Installation - Nuclear Liability Insurance Coverage ML21028A0632021-01-26026 January 2021 M210211: Welcome Letter to W. Norton ML20167A3032020-07-10010 July 2020 Letter - Ynps Exemption 190502, Rev 0 ML20167A3022020-07-0202 July 2020 FRN - Ynps Exemption 190502, Rev 0 ML20162A1282020-06-23023 June 2020 Issuance of Temporary Exemption from 10 CFR Part 73, Appendix B, for Yankee Rowe ISFSI (COVID-19) ML20160A0402020-05-20020 May 2020 BYR 2020-014 - Yaec Letter BYR 2020-014 Temporary Exemption - Annual Physical Requirement ML20087J6642020-03-16016 March 2020 Yankee Nuclear Power Independent Spent Fuel Storage Installation - Funding Status Report for Managing Irradiated Fuel and GTCC Waste ML20108F5362020-03-12012 March 2020 Yankee Nuclear Power Station Independent Spent Fuel Storage Installation - Decommissioning Funding Assurance Status Report ML20054B6392020-02-0606 February 2020 Independent Spent Fuel Storage Installation - Formal Announcement of Change in ISFSI Manager ML20015A4942020-01-15015 January 2020 Yankee Atomic Power Company - Independent Spent Fuel Storage Installation Security Inspection Plan ML20013F6882019-12-17017 December 2019 Independent Spent Fuel Storage Installation - Formal Announcement of Change in Isfsj Manager ML19295E1062019-10-0202 October 2019 Biennial Update of the Yankee Atomic Electric Company Quality Assurance Program (Rev. 39) for the Yankee Rowe ISFSI ML19165A0262019-06-0505 June 2019 Independent Spent Fuel Storage Installation - Formal Announcement of Change in ISFSI Manager ML19176A0752019-05-0202 May 2019 Independent Spent Fuel Storage Installation - Request for Exemption from Certain Requirements of 10 CFR 72.212 and 10 CFR 72.214 ML19121A4202019-04-23023 April 2019 Yankee Nuclear Power Station Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report, Annual Radiological Environmental Operating Report, and Changes to the Off-Site Dose Calculation Manual for 2018 ML18354A7382018-12-10010 December 2018 Yankee Nuclear Power Station Independent Spent Fuel Storage Installation - Three-Year Update to the Decommissioning Funding Plan IR 05000029/20180012018-05-30030 May 2018 Yankee Atomic Electric Company, Rowe, Massachusetts Site - NRC Independent Spent Fuel Storage Installation Report Nos. 07200031/2018001 and 05000029/2018001 IR 07200031/20184012018-05-17017 May 2018 Inspection Report 07200031/2018401, on May 17, 2018, Yankee Atomic Electric Company - ISFSI Security Inspection Report 07200031/2018401 - (Cover Letter Only) ML18136A5552018-04-10010 April 2018 Yankee Nuclear Power Station, and Independent Spent Fuel Storage Installation - Annual Radioactive Effluent Release Report, Annual Radiological Environmental Operating Report, and Changes to the Off-Site Dose Calculation Manual for 2017 2024-03-11
[Table view] Category:Status Report
MONTHYEARML23080A1112023-03-0606 March 2023 Yankee Nuclear Power Plant Independent Spent Fuel Storage Installation, Funding Status Report for Managing Irradiated Fuel and GTCC Waste ML23080A1072023-03-0606 March 2023 Yankee Nuclear Power Station Independent Spent Fuel Storage Installation, Decommissioning Funding Assurance Status Report ML22082A1232022-03-14014 March 2022 Yankee Nuclear Power Station Independent Spent Fuel Storage Installation, Decommissioning Funding Assurance Status Report ML22089A1002022-03-14014 March 2022 Yankee Nuclear Power Plant Independent Spent Fuel Storage Installation - Funding Status Report for Managing Irradiated Fuel and GTCC Waste ML21077A1682021-03-0202 March 2021 Yankee Nuclear Power Plant Independent Spent Fuel Storage Installation - Funding Status Report for Managing Irradiated Fuel and GTCC Waste ML20087J6642020-03-16016 March 2020 Yankee Nuclear Power Independent Spent Fuel Storage Installation - Funding Status Report for Managing Irradiated Fuel and GTCC Waste ML19116A0502019-03-12012 March 2019 Yankee Nuclear Power Station Independent Spent Fuel Storage Installation Decommissioning Funding Assurance Status Report ML18075A3252018-03-0505 March 2018 Yankee Nuclear Power Station Independent Spent Fuel Storage Installation - Decommissioning Funding Assurance Status Report ML18078A3012018-03-0505 March 2018 Yankee Nuclear Power Plant Independent Spent Fuel Storage Installation - Funding Status Report for Managing Irradiated Fuel and GTCC Waste ML17090A4112017-03-0909 March 2017 Yankee Nuclear Power Plant Independent Spent Fuel Storage Installation - Funding Status Report for Managing Irradiated Fuel and GTCC Waste ML17094A7342017-03-0909 March 2017 Yankee Nuclear Power Station Independent Spent Fuel Storage Installation - Decommissioning Funding Assurance Status Report ML16096A3652016-03-21021 March 2016 Yankee ISFSI - Funding Status Report for Managing Irradiated Fuel and GTCC Waste ML16076A2742016-03-0909 March 2016 Yankee Nuclear Power Station Independent Spent Fuel Storage Installation - Decommissioning Funding Assurance Status Report ML15065A1382015-02-10010 February 2015 Yankee ISFSI - Funding Status Report for Managing Irradiated Fuel and GTCC Waste ML14085A0192014-03-11011 March 2014 Funding Status Report for Managing Irradiated Fuel and GTCC Waste ML14085A0172014-03-11011 March 2014 Yankee - Decommissioning Funding Assurance Status Report ML13094A1162013-03-25025 March 2013 Yankee Nuclear Power Station Independent Spent Fuel Storage Installation, Decommissioning Funding Assurance Status Report ML13092A1432013-03-19019 March 2013 Yankee Nuclear Power Station Independent Spent Fuel Storage Installation, Funding Status Report for Managing Irradiated Fuel and GTCC Waste ML1210706332012-03-27027 March 2012 Redacted - Yankee, Decommissioning Funding Assurance Status Report - 10CFR 50.75 ML1108101152011-03-15015 March 2011 Yankee, Decommissioning Funding Assurance Status Report ML1029403622010-11-12012 November 2010 October 2010 10 CFR 2.206 Monthly Status Report: Enclosures ML0908301902009-03-16016 March 2009 Yankee Atomic Electric Company - Decommissioning Funding Assurance Status Report - 10CFR 50.75 ML0629300822006-10-13013 October 2006 Yankee Nuclear Power Station Final Status Survey Report, Report No. YNPS-FSS-OOL-09-00 ML0629700152006-10-0505 October 2006 Yankee Nuclear Power Station - Final Status Survey Report YNPS-FSS-OOL-07-00 ML0629700512006-10-0303 October 2006 Yankee Nuclear Power Station - Final Status Survey Report, YNPS-FSS-NOL-05-00 ML0701605402006-09-26026 September 2006 Yankee Nuclear Power Station Final Status Survey Report, YNPS-FSS-OOL-13-00 ML0701605442006-09-21021 September 2006 Yankee Nuclear Power Station Final Status Survey Report, YNPS-FSS-SVC-01-00 ML0701605222006-09-18018 September 2006 Yankee Nuclear Power Station Final Status Survey Report, YNPS-FSS-OOL-16 ML0701604902006-09-0707 September 2006 Yankee Nuclear Power Station Final Status Survey Report, YNPS-FSS-AUX-02 ML0701605412006-08-31031 August 2006 Yankee Nuclear Power Station Final Status Survey Report, YNPS-FSS-NOL-04-00 ML0701605372006-08-28028 August 2006 Yankee Nuclear Power Station Final Status Survey Report, YNPS-FSS-BRT-01-00 ML0629300832006-07-13013 July 2006 Yankee Nuclear Power Station, YNPS-FSSP-OOL0901-00, Final Status Survey Planning Worksheets ML0704701242006-05-11011 May 2006 Yankee Nuclear Power Station - Submittal of YNPS-FSS-AUX01-00 and YNS-FSS-NSY12-00, the Final Status Survey Reports for Survey Areas AUX-01 and NSY-12, Respectively ML0704701302006-05-11011 May 2006 Submittal of YNPS-FSS-AUX0I-00 and YNS-FSS-NSY12-00, Final Status Survey Reports for Survey Areas AUX-01 and NSY-12, Respectively ML0704701212006-04-17017 April 2006 Submittal of Yankee Nuclear Power Station, Final Status Survey Report for Area WST-01 ML0613202062006-02-15015 February 2006 E-mail from D. Croulet of Entergy to Various, Regarding Monitoring Well Status - February 15, 2006-0600 ML0701601242005-11-0909 November 2005 YNPS-FSS-OOL-03-00, Appendix D, Generic ALARA Evaluation Comparison Worksheet. ML0701601132005-11-0909 November 2005 YNPS-FSS-OOL-03-00, Appendix a, Final Status Survey Planning Worksheets. ML0629300892005-11-0404 November 2005 YA-REPT-00-018-05, Rev 0, Use of In-Situ Gamma Spectrum Analysis to Perform Elevated Measurement Comparisons in Support of Final Status Surveys ML0630704972005-08-29029 August 2005 Yankee - Final Status Survey Planning Worksheets, YNPS-FSSP-NOL-06, RSS Footprint within the West Lower RCA Yard- Central ML0633402552005-08-0909 August 2005 Yankee Nuclear Power Station, Final Status Survey Planning Worksheet ML0629700172005-07-18018 July 2005 Yankee Nuclear Power Station - Final Status Survey Planning Worksheet ML0509603032005-03-30030 March 2005 Evaluation Biennial Summary Report for 2003 / 2004 ML0704003942005-02-21021 February 2005 YNPS-FSS-TBN01-00, Final Status Survey Report, Volume 3 (Attachment B Through Appendix D) ML0704004002005-02-21021 February 2005 YNPS-FSS-TBN01-00, Final Status Survey Report, TBN-01-13, Frequency Plot FSS Data Through Calculation of ALARA Action Level ML0634806042005-01-18018 January 2005 YA-REPT-00-003-05, Generic ALARA Review for Final Status Survey of Soil at Ynps ML0701601202005-01-18018 January 2005 YNPS-FSS-OOL-03-00, Appendix C, YA-REPT-00-003-05, Generic ALARA Review for Final Status Survey of Soil at Ynps. ML0700305252004-11-0303 November 2004 Yankee Final Status Survey Report, Appendix a - YNPS-FSSP-OOL-08, Final Status Survey Planning Worksheets ML0701601162004-10-0707 October 2004 YNPS-FSS-OOL-03-00, Appendix B, YA-REPT-00-015-04, Instrument Efficiency Determination for Use in Minimum Detectable Concentration Calculations in Support of the Final Status Survey at Yankee Rowe. ML0716700042004-06-0404 June 2004 Site Characterization Status Report, Yankee Nuclear Power Station Site Closure Project, Rowe, Massachusetts 2023-03-06
[Table view] |
Text
. ..:) I -YANKEE ATOMIC ELECTRIC COMPANY 49 Yankee Road, Rowe, Massachusetts 01367 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC' 20555 -0001 Yankee Atomic Electric Company March 5, 2018 BYR 2018-006 10 CFR50.4 10 CFR 50.82(a)(8)(vii)
Yankee Nuclear Power Plant Independent Spent Fuel Storage Installation NRC License No. DPR-3 {NRC Docket No.50-029)
Subject:
Funding Status Report for Managing Irradiated Fuel and GTCC Waste On February 26, 1992, Yankee Atomic Electric Company (YAEC) informed the USNRC that the Board of Directors of Y AEC had decided to permanently cease operations at the Yankee Nuclear Power Plant and that fuel had been permanently removed from the reactor (Reference 1 ). In accordance with 10 CFR 50.82(a)(2),
the certifications in the letter modified the YAEC license to permanently withdraw YAEC's authority to operate the reactor.
In 1993, Y AEC commenced decommissioning the power plant. On August 10, 2007, the NRC released most of the formerly licensed land for unrestricted use, shrinking the licensed land to that utilized to support the Independent Spent Fuel Storage Installation (ISFSI) (Reference 2). Presently, Y AEC is storing irradiated fuel and Greater than Class C (GTCC) waste on site until the Department of Energy (DOE) satisfies its contractual obligations to take title and possession of the spent fuel and GTCC waste and remove them from the site. In Attachment 1, YAEC provides the attached Funding Status Report for Managing Irradiated Fuel and GTCC Waste at the Yankee Nuclear Power Plant ISFSI to comply with 1,0 CFR 50.82(a)(8)(vii).
This letter contains no regulatory commitments.
If you have any questions regarding this letter, please do not hesitate to contact me at (860) 267-6426 x304.
- Respectfully, Carla M. Pizzella Vice President, Chief Financial
- Officer, and Treasurer Yankee Atomic Electric Company BYR 2018-006\March 5, 2018\Page 2
Attachment:
- 1. Funding Status Report for Managing Irradiated Fuel and GTCC Waste at the Yankee Nuclear Power Plant Independent Spent Fuel Storage Installation (Status as of 12/31/2017)
References:
- 1. A. C. Kadak (Y AEC) letter to USNRC, "Permanent Cessation of Power Operations at the Yankee Nuclear Power Station,"
BYR-92-024, dated February 26, 1992 2. USNRC letter to Yankee Atomic Power Company, "Yankee Nuclear Power Station -Release of Land from Part 50 License,"
dated August 10, 2007 cc: D. Lew, Acting NRC Region I Administrator R. Powell, Chief, Decommissioning Branch, NRC, Region 1 J. Nguyen, NRC Project Manager J. Giarrusso,
- Planning, Preparedness
& Nuclear Section Chief, MEMA J. Cope-Flanagan, Assistant General Counsel, MDPU J. Rogers, Commonwealth of Massachusetts Office of the Attorney General ATTACHMENT 1 TO BYR 2018-006 FUNDING STATUS REPORT FOR THE MANAGING OF IRRADIATED FUEL AND GTCC WASTE AT THE YANKEE NUCLEAR POWER PLANT INDEPENDENT SPENT FUEL STORAGE INSTALLATION (STATUS AS OF 12/31/2017)
Attachment 1 to BYR 2018-006 Funding Status Report for the Managing of Irradiated Fuel and GTCC Waste at the Yankee Nuclear Power Plant Independent Spent Fuel Storage Installation (Status as of 12/31/2017) 10 CFR Requirement Response Comment 10 CFR 50.82(a)(8)(vii)
Requirements
- 1. The amount of funds accumulated
-$123.5 Yankee Atomic Electric Company (Y AEC) has established an account within its to cover the cost of managing the million ( as of Nuclear Decommissioning Trust (NDT) entitled, "ISFSI Radiological Decom," that irradiated fuel. 12/31/2017) segregates the funds for decommissioning of the Yankee Nuclear Power Plant Independent Spent Fuel Storage Installation (ISFSI) from the larger balance of funds for ongoing management of irradiated fuel and Greater than Class C (GTCC) waste held in the NDT. The market balance represented here as of December 31, 2017 excludes the funds set-aside for decommissioning the ISFSI. 2. The projected cost of managing
-$169.1 The current cost estimate for management of spent fuel and Greater than Class C irradiated fuel until title to the million (2018 (GTCC) waste was filed with the Federal Energy Regulatory Commission (FERC) on fuel and possession of the fuel is -2036*) September 30, 2016 and approved by FERC on November 15, 2016. transferred to the Secretary of (In 2017 Energy. dollars)
- Currently, the irradiated fuel and GTCC waste are scheduled to be removed from the site by 2035, with decommissioning, license termination, and business closure occurring after that time period. 3. If the funds accumulated do not See Comment The Company has several methods of obtaining additional funds to cover projected cover the projected cost, a plan to costs. obtain additional funds to cover the cost. First, Y AEC may collect funds through its power contracts and amendatory agreements under FERC regulation.
The power contracts and the amendatory agreements specify the obligations of the purchasers for the costs of Y AEC, including the ongoing costs of managing irradiated fuel and GTCC waste. Pursuant to these power contracts, Y AEC has the ongoing ability to seek collections from its purchasers for additional funds that may be required to cover these costs. Second, Y AEC has received proceeds from the successful litigation of the first three phases of its breach of contract damages claims against the DOE for failure to begin the removal of spent nuclear fuel (SNF) and GTCC waste from the site in 1998. Y AEC will continue to file claims against the DOE as long as the DOE continues to breach its contract obligations related to SNF and GTCC waste. To that end, in 2017, the Company filed a fourth round of claims (the Phase IV case) against the DOE seeking Page 1 of2 Attachment 1 to BYR 2018-006 Funding Status Report for the Managing of Irradiated Fuel and GTCC Waste at the Yankee Nuclear Power Plant Independent Spent Fuel Storage Installation (Status as of 12/31/2017) 10 CFR Requirement Response Comment damages for the years 2013 -2016. The Company cannot predict the timing or the amount it may ultimately be awarded.
A YAEC FERC filing approved in June, 2013, implemented a fifteen-year funding mechanism.
Until the 2013 FERC filing, the Company had employed a "full funding" assumption in developing funding requirements.
The fifteen-year funding mechanism was put in place to incorporate the potential for the receipt of future DOE breach of contract damages as a source of funding.
If future damage recovery does not occur, the Company has the ability to apply to FERC for more funding, if necessary.
The approved FERC filing also requires Y AEC to provide an informational filing regarding the adequacy of funding if five years pass without receipt of damage awards from litigation with the DOE. Third, Y AEC expects to utilize the investment return on Decommissioning Trust assets to offset future costs. The current assumed rate of investment return, after fees and taxes IS 4.0%. Page 2 of2 (