|
|
Line 17: |
Line 17: |
|
| |
|
| =Text= | | =Text= |
| {{#Wiki_filter: | | {{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE RD. SUITE 210 LISLE, IL 60532-4352 January 22, 2016 Mr. Larry Weber Senior VP and Chief Nuclear Officer Indiana Michigan Power Company Nuclear Generation Group One Cook Place Bridgman, MI 49106 SUBJECT: DONALD. C. COOK NUCLEAR POWER PLANT, UNITS 1 AND 2 - REQUEST FOR INFORMATION FOR AN NRC PILOT DESIGN BASES INSPECTION ON THE IMPLEMENTATION OF THE ENVIRONMENTAL QUALIFICATION PROGRAM INSPECTION REPORT 05000315/2016008; 05000316/2016008 Dear Mr. Weber: On May 9, 2016, the U. S. Nuclear Regulatory Commission (NRC) will begin the pilot program portion of the triennial baseline Design Bases Inspection (DBI) at Donald C. Cook Nuclear Power Plant, Units 1 and 2. This inspection will be performed in accordance with NRC Baseline Inspection Procedure 71111.21N. The inspection will focus on the implementation of the Environmental Qualification (EQ) Program. The EQ components to be reviewed during this baseline inspection will be identified during the in-office preparation week that occurs prior to the first onsite inspection week. The inspection will include a bagman trip to support selection of components and one week of onsite inspection. The inspection team will consist of three NRC inspectors. The current inspection schedule is as follows: Bagman trip onsite week: March 29 - 30, 2016 Inspection onsite week: May 9 - 13, 2016 The team will be preparing for the inspection, mainly during the week of May 2 - 6, 2016, as discussed in the enclosure. Experience with previous baseline design inspections of similar depth and length has shown that this type of inspection is extremely resource intensive, both for the NRC inspectors and the licensee staff. In order to minimize the inspection impact on the site and to ensure a productive inspection for both parties, we have enclosed a request for information needed for the inspection. |
| [[Issue date::January 22, 2016]]
| | L. Weber -2- It is important that all of these documents are up-to-date and complete in order to minimize the number of additional documents requested during the preparation and/or the onsite portions of the inspection. Insofar as possible, this information should be provided electronically to the lead inspector. The information request has been divided into four groups: The first group lists information necessary for our initial inspection scoping activities. This information should be provided to the lead inspector no later than March 1, 2016. By March 15, 2016, the lead inspector will communicate the initial selected set of approximately 12 EQ components. The second group of documents requested is those items needed to support the bagman trip. This set of documents should be available to the lead inspector onsite on March 29, 2016. The third group of documents requested is those items needed to support our in-office preparation activities for the selected set of 6 - 9 EQ components. This set of documents should be provided to the lead inspector at the Regional Office no later than April 27, 2016. During the in-office preparation activities, the team may identify additional information needed to support the inspection. The last group includes the additional information above as well as plant specific reference material. This information should be available to the team onsite on May 9, 2016. It is also requested that corrective action documents and/or questions developed during the inspection be provided to the lead inspector as the documents are generated. The lead inspector for this inspection is Mr. Andrew Dunlop. We understand that our licensing contact for this inspection is Mr. Rick Wynegar of your organization. If there are any questions about the inspection or the material requested in the enclosure, please contact the lead |
| | inspector at (630) 829-9726, or via e-mail at Andrew.Dunlop@nrc.gov. This letter does not contain new or amended information collection requirements subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection requirements were approved by the Office of Management and Budget, Control Number 3150-0011. The NRC may not conduct or sponsor, and a person is not required to respond to, a request for information or an information collection requirement unless the requesting document displays a currently valid Office of Management and Budget Control Number. In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, "Public Inspections, Exemptions, Requests for Withholding," of the NRC's "Rules of Practice," a copy of this letter, its enclosure, and your response (if any) will be available electronically for public inspection in the NRC's Public Document Room or from the Publicly Available Records (PARS) |
| | L. Weber -3- component of the NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). Sincerely, /RA/ |
| | Christine A. Lipa, Chief Engineering Branch 2 Division of Reactor Safety Docket Nos. 50-315; 50-316 License Nos. DPR-58; DPR-74 Enclosure: Request for Information - Design Bases Inspection cc: Distribution via LISTSERV |
| | REQUEST FOR INFORMATION - DESIGN BASES INSPECTION Enclosure Inspection Report: 05000315/2016008; 05000316/2016008 Bagman Dates: March 29 - 30, 2016 Inspection Dates: May 9 - 13, 2016 Inspection Procedure: IP 71111.21N, "Design Bases Inspection" Lead Inspector: Andrew Dunlop, Senior Reactor Engineer, DRS (630) 829-9726 Andrew.Dunlop@nrc.gov I. Information Requested Prior to the Onsite Information Gathering/Bagman Week The following information is requested by March 1, 2016, or sooner, to facilitate inspection preparation. If you have any questions regarding this information, please call the team leader as soon as possible. (Please provide the information electronically in "pdf" files, Excel, or other searchable formats, preferably on some portable electronic media (e.g., CD-ROM, DVD, etc.). The portable electronic media should contain descriptive names, and be indexed and hyperlinked to facilitate ease of use. Information in "lists" should contain enough information to be easily understood by someone who has knowledge of light water reactor technology). 1. Risk-ranking of top 250 components from your site specific probabilistic safety analysis (PSA) sorted by Fussell Vesely Importance. 2. PSA listing of top ten risk-significant systems. 3. Electronic copies of Updated Final Safety Analysis Report, Technical |
| | Specifications, and Technical Specifications Bases. Specifically identify which Updated Final Safety Analysis Report sections address environmental (including seismic) qualification (EQ). 4. NRC Safety Evaluation Report(s) associated with EQ. 5. Identify the various EQ standards (including year, edition, or revision) that the station is committed to. 6. Copy of EQ Design Basis Document, if applicable. 7. Copy of any licensing commitments related to EQ, if applicable. 8. Equipment Qualification Master List (EQML). Specific issues to be identified include: safety classification (safety-related or nonsafety-related), Regulatory Guide 1.97 instrumentation, EQ qualification (e.g. DOR, NUREG 588, 50.49), original or replaced after implementation of 50.49, and plant location. |
| | REQUEST FOR INFORMATION - DESIGN BASES INSPECTION 2 9. List of any installed equipment removed from the EQML and basis for removal. 10. For units that have entered the period of extended operation, if EQ files were reviewed for Aging Management effects of license renewal, identify which EQ files were modified/changed to incorporate appropriate actions for the period of extended operation. Copies of any EQ Aging Management Programs. 11. List or drawings of plant areas that are subjected to EQ, identifying design (limiting) temperature, both normal and accident, high-energy line break, radiation levels, etc. that the associated equipment will have to be qualified to meet EQ. If unit has obtained a power uprate (greater than 5 percent) provide same information pre-update (earliest available if multiple uprates). 12. Site (and corporate if applicable) procedures associated with the 10 CFR 50.49 EQ Program for electrical components. Include procedures for procurement of qualified equipment, maintenance of qualified equipment, modification to |
| | qualified equipment (including equivalency or commercial grade dedication (CGD) programs), and material storage and shelf life controls. 13. List of CGD evaluations performed, for which the dedicated parts have been issued for installation (parts issued for the last 10 years) on EQ applications in the plant. Include CGD evaluation number, name of part, component ID number or description of the component the part was issued to repair, work order, and date issued or installed. 14. List of Condition Reports (CRs) related to the EQ Program or EQ of components for the last 5 years. 15. Current management and engineering organizational chart. II. Information Requested (for the approximate 9 - 12 selected components) to be Available by the Bagman Trip on March 29, 2016. 1. EQ Summary Report for each component/subcomponent. 2. Qualification Maintenance Requirement Sheet (QMRS) or equivalent. 3. List of CRs (corrective action documents) associated with each of the selected |
| | components for the last 5 years. 4. Photos of any component in containment or high-radiation areas, if available. III. Information Requested (for the approximate 6 - 9 selected components) to be Available by April 27, 2016, (will be reviewed by the team in the Regional office |
| | during the week of May 2 - 6, 2016). This information should be separated for each selected component, especially if provided electronically (e.g., folder with component name that includes EQ files, Qualification Test Reports, calculations, CRs, maintenance history, etc.). 1. EQ file, including associated Qualification Test Reports. 2. Vendor manual (electronic copy or availability of hard copy during inspection). |
| | REQUEST FOR INFORMATION - DESIGN BASES INSPECTION 3 3. Preventive maintenance template. 4. Last performed work order (WO) for each associated EQ preventive maintenance. 5. List of corrective maintenance WOs for the last 10 years. Include WO number, date performed, and brief one line description. 6. If repair work (e.g., a motor rewind) was performed under a purchase order, provide copy of the purchase order. 7. Thermal life calculation. 8. Any self-assessments of the EQ Program for the last 3 years. IV. Additional Information to be Provided on May 9, 2016, Onsite 1. During the in-office preparation activities, the team may identify additional information needed to support the inspection. The lead inspector will provide a list of the additional information needed during the week of May 2 - 6, 2016. V. Information Requested to be Provided Throughout the Inspection 1. Copies of any corrective action documents generated as a result of the team's questions or queries during this inspection. 2. Copies of the list of questions submitted by the team members and the status/resolution of the information requested (provide daily during the inspection to each team member). If you have questions regarding the information requested, please contact the lead inspector. |
| | L. Weber -3- component of the NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). Sincerely, /RA/ |
| | Christine A. Lipa, Chief Engineering Branch 2 Division of Reactor Safety Docket Nos. 50-315; 50-316 License Nos. DPR-58; DPR-74 Enclosure: Request for Information - Design Bases Inspection cc: Distribution via LISTSERV DISTRIBUTION: Kimyata MorganButler RidsNrrDorlLpl3-1 Resource RidsNrrPMDCCook Resource RidsNrrDirsIrib Resource Cynthia Pederson |
| | Darrell Roberts Richard Skokowski Allan Barker Carole Ariano Linda Linn |
| | DRPIII DRSIII Jim Clay Carmen Olteanu ADAMS Accession Number ML16025A055 Publicly Available Non-Publicly Available Sensitive Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII RIII NAME CLipa for ADunlop:cl CLipa DATE 01/22/16 01/22/16 OFFICIAL RECORD COPY |
|
| |
|
| Mr. Larry Weber Senior VP and Chief Nuclear Officer Indiana Michigan Power Company Nuclear Generation Group One Cook Place Bridgman, MI 49106
| |
|
| |
| SUBJECT: DONALD. C. COOK NUCLEAR POWER PLANT, UNITS 1 AND 2 - REQUEST FOR INFORMATION FOR AN NRC PILOT DESIGN BASES INSPECTION ON THE IMPLEMENTATION OF THE ENVIRONMENTAL QUALIFICATION PROGRAM INSPECTION REPORT 05000315/2016008; 05000316/2016008
| |
|
| |
| ==Dear Mr. Weber:==
| |
| On May 9, 2016, the U. S. Nuclear Regulatory Commission (NRC) will begin the pilot program portion of the triennial baseline Design Bases Inspection (DBI) at Donald C. Cook Nuclear Power Plant, Units 1 and 2. This inspection will be performed in accordance with NRC Baseline Inspection Procedure 71111.21N. The inspection will focus on the implementation of the Environmental Qualification (EQ) Program. The EQ components to be reviewed during this baseline inspection will be identified during the in-office preparation week that occurs prior to the first onsite inspection week. The inspection will include a bagman trip to support selection of components and one week of onsite inspection. The inspection team will consist of three NRC inspectors. The current inspection schedule is as follows: Bagman trip onsite week: March 29 - 30, 2016 Inspection onsite week: May 9 - 13, 2016 The team will be preparing for the inspection, mainly during the week of May 2 - 6, 2016, as discussed in the enclosure. Experience with previous baseline design inspections of similar depth and length has shown that this type of inspection is extremely resource intensive, both for the NRC inspectors and the licensee staff. In order to minimize the inspection impact on the site and to ensure a productive inspection for both parties, we have enclosed a request for information needed for the inspection. It is important that all of these documents are up-to-date and complete in order to minimize the number of additional documents requested during the preparation and/or the onsite portions of the inspection. Insofar as possible, this information should be provided electronically to the lead inspector. The information request has been divided into four groups: The first group lists information necessary for our initial inspection scoping activities. This information should be provided to the lead inspector no later than March 1, 2016. By March 15, 2016, the lead inspector will communicate the initial selected set of approximately 12 EQ components. The second group of documents requested is those items needed to support the bagman trip. This set of documents should be available to the lead inspector onsite on March 29, 2016. The third group of documents requested is those items needed to support our in-office preparation activities for the selected set of 6 - 9 EQ components. This set of documents should be provided to the lead inspector at the Regional Office no later than April 27, 2016. During the in-office preparation activities, the team may identify additional information needed to support the inspection. The last group includes the additional information above as well as plant specific reference material. This information should be available to the team onsite on May 9, 2016. It is also requested that corrective action documents and/or questions developed during the inspection be provided to the lead inspector as the documents are generated. The lead inspector for this inspection is Mr. Andrew Dunlop. We understand that our licensing contact for this inspection is Mr. Rick Wynegar of your organization. If there are any questions about the inspection or the material requested in the enclosure, please contact the lead inspector at (630) 829-9726, or via e-mail at Andrew.Dunlop@nrc.gov. This letter does not contain new or amended information collection requirements subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection requirements were approved by the Office of Management and Budget, Control Number 3150-0011. The NRC may not conduct or sponsor, and a person is not required to respond to, a request for information or an information collection requirement unless the requesting document displays a currently valid Office of Management and Budget Control Number. In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, "Public Inspections, Exemptions, Requests for Withholding," of the NRC's "Rules of Practice," a copy of this letter, its enclosure, and your response (if any) will be available electronically for public inspection in the NRC's Public Document Room or from the Publicly Available Records (PARS) component of the NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
| |
|
| |
| Sincerely,/RA/
| |
| Christine A. Lipa, Chief Engineering Branch 2 Division of Reactor Safety Docket Nos. 50-315; 50-316 License Nos. DPR-58; DPR-74
| |
|
| |
| ===Enclosure:===
| |
| Request for Information - Design Bases Inspection cc: Distribution via LISTSERV REQUEST FOR INFORMATION - DESIGN BASES INSPECTION Enclosure Inspection Report: 05000315/2016008; 05000316/2016008 Bagman Dates: March 29 - 30, 2016 Inspection Dates: May 9 - 13, 2016 Inspection Procedure: IP 71111.21N, "Design Bases Inspection" Lead Inspector: Andrew Dunlop, Senior Reactor Engineer, DRS (630) 829-9726 Andrew.Dunlop@nrc.gov I. Information Requested Prior to the Onsite Information Gathering/Bagman Week The following information is requested by March 1, 2016, or sooner, to facilitate inspection preparation. If you have any questions regarding this information, please call the team leader as soon as possible. (Please provide the information electronically in "pdf" files, Excel, or other searchable formats, preferably on some portable electronic media (e.g., CD-ROM, DVD, etc.). The portable electronic media should contain descriptive names, and be indexed and hyperlinked to facilitate ease of use. Information in "lists" should contain enough information to be easily understood by someone who has knowledge of light water reactor technology). 1. Risk-ranking of top 250 components from your site specific probabilistic safety analysis (PSA) sorted by Fussell Vesely Importance. 2. PSA listing of top ten risk-significant systems. 3. Electronic copies of Updated Final Safety Analysis Report, Technical Specifications, and Technical Specifications Bases. Specifically identify which Updated Final Safety Analysis Report sections address environmental (including seismic) qualification (EQ). 4. NRC Safety Evaluation Report(s) associated with EQ. 5. Identify the various EQ standards (including year, edition, or revision) that the station is committed to. 6. Copy of EQ Design Basis Document, if applicable. 7. Copy of any licensing commitments related to EQ, if applicable. 8. Equipment Qualification Master List (EQML). Specific issues to be identified include: safety classification (safety-related or nonsafety-related), Regulatory Guide 1.97 instrumentation, EQ qualification (e.g. DOR, NUREG 588, 50.49), original or replaced after implementation of 50.49, and plant location.
| |
|
| |
| REQUEST FOR INFORMATION - DESIGN BASES INSPECTION 2 9. List of any installed equipment removed from the EQML and basis for removal. 10. For units that have entered the period of extended operation, if EQ files were reviewed for Aging Management effects of license renewal, identify which EQ files were modified/changed to incorporate appropriate actions for the period of extended operation. Copies of any EQ Aging Management Programs. 11. List or drawings of plant areas that are subjected to EQ, identifying design (limiting) temperature, both normal and accident, high-energy line break, radiation levels, etc. that the associated equipment will have to be qualified to meet EQ. If unit has obtained a power uprate (greater than 5 percent) provide same information pre-update (earliest available if multiple uprates). 12. Site (and corporate if applicable) procedures associated with the 10 CFR 50.49 EQ Program for electrical components. Include procedures for procurement of qualified equipment, maintenance of qualified equipment, modification to qualified equipment (including equivalency or commercial grade dedication (CGD) programs), and material storage and shelf life controls. 13. List of CGD evaluations performed, for which the dedicated parts have been issued for installation (parts issued for the last 10 years) on EQ applications in the plant. Include CGD evaluation number, name of part, component ID number or description of the component the part was issued to repair, work order, and date issued or installed. 14. List of Condition Reports (CRs) related to the EQ Program or EQ of components for the last 5 years. 15. Current management and engineering organizational chart. II. Information Requested (for the approximate 9 - 12 selected components) to be Available by the Bagman Trip on March 29, 2016. 1. EQ Summary Report for each component/subcomponent. 2. Qualification Maintenance Requirement Sheet (QMRS) or equivalent. 3. List of CRs (corrective action documents) associated with each of the selected components for the last 5 years. 4. Photos of any component in containment or high-radiation areas, if available. III. Information Requested (for the approximate 6 - 9 selected components) to be Available by April 27, 2016, (will be reviewed by the team in the Regional office during the week of May 2 - 6, 2016). This information should be separated for each selected component, especially if provided electronically (e.g., folder with component name that includes EQ files, Qualification Test Reports, calculations, CRs, maintenance history, etc.). 1. EQ file, including associated Qualification Test Reports. 2. Vendor manual (electronic copy or availability of hard copy during inspection).
| |
|
| |
| REQUEST FOR INFORMATION - DESIGN BASES INSPECTION 3 3. Preventive maintenance template. 4. Last performed work order (WO) for each associated EQ preventive maintenance. 5. List of corrective maintenance WOs for the last 10 years. Include WO number, date performed, and brief one line description. 6. If repair work (e.g., a motor rewind) was performed under a purchase order, provide copy of the purchase order. 7. Thermal life calculation. 8. Any self-assessments of the EQ Program for the last 3 years. IV. Additional Information to be Provided on May 9, 2016, Onsite 1. During the in-office preparation activities, the team may identify additional information needed to support the inspection. The lead inspector will provide a list of the additional information needed during the week of May 2 - 6, 2016. V. Information Requested to be Provided Throughout the Inspection 1. Copies of any corrective action documents generated as a result of the team's questions or queries during this inspection. 2. Copies of the list of questions submitted by the team members and the status/resolution of the information requested (provide daily during the inspection to each team member). If you have questions regarding the information requested, please contact the lead inspector.
| |
| }} | | }} |
Similar Documents at Cook |
---|
Category:Inspection Report Correspondence
MONTHYEARML23117A0062023-04-27027 April 2023 Review of the Spring 2022 Steam Generator Tube Inspections Report IR 05000315/20224022022-07-0505 July 2022 Material Control and Accounting Program Inspection Report 05000315/2022402 and 05000316/2022402 IR 05000315/20214032021-11-17017 November 2021 Security Baseline Inspection Report 05000315/2021403 and 05000316/2021403 IR 05000315/20214012021-10-21021 October 2021 Cyber Security Inspection Report 05000315/2021401 and 05000316/2021401 IR 05000315/20164072016-08-15015 August 2016 Cyber Security Problem and Identification Inspection Report 05000315/2016407; 05000316/2016407 - Cover Letter Only IR 05000315/20164052016-08-12012 August 2016 NRC Security Baseline Inspection Report 05000315/2016405; 05000316/2016405 (Cover Letter Only) IR 05000315/20160042016-07-11011 July 2016 Donald C. Cook Nuclear Power Plant, Unit 2 - Notification of NRC Inspection and Request for Information; Inspection Report 05000315/2016004; 05000316/2016004 ML16193A6542016-07-11011 July 2016 Notification of NRC Inspection and Request for Information; Inspection Report 05000315/2016004; 05000316/2016004 ML16025A0552016-01-22022 January 2016 Ltr. 01/22/16 Donald C. Cook Nuclear Power Plant, Units 1 and 2 - Request for Information for an NRC Pilot Design Bases Inspection on the Implementation of the Environmental Qualification Program Inspection Report 05000315/2016008; 05000316 IR 05000315/20085012009-02-13013 February 2009 IR 05000315-08-501, IR 05000316-08-501, on 12/31/2008, Donald C. Cook Nuclear Power Plant - NRC Emergency Preparedness Annual Inspection Report; NRC Security Annual Inspection Report IR 05000315-08-401, IR 05000316-08-401 ML0808703952008-03-26026 March 2008 IR 05000315-08-003 and 05000316-08-003, on 05/12/2008, D.C. Cook Nuclear Power Plant, TI-166 Request for Information NRC Inspection of Temporary Instruction 2515-166 IR 05000315/20074032007-07-20020 July 2007 IR 05000315-07-403, and IR 05000316-07-403, (Drs), on 06/11/2007 - 06/15/2007, D.C. Cook, Units 1 and 2, Routine Security Baseline Inspection - Cover Letter IR 05000315/20060072007-02-12012 February 2007 IR 05000315-06-007, IR 05000316-06-007, on 10/01/2006-12/31/2006, D. C. Cook Nuclear Power Plant, Units 1 and 2, Evaluation of Changes, Tests, or Experiments, Inservice Inspection Activities ML0210603072002-04-16016 April 2002 IR 05000315/2002-002(DRP), IR 05000316/2002-002(DRP), on 02/09-03/31/2002, Indiana Michigan Power Company, D.C. Cook Nuclear Power Plant, Units 1 and 2. Post Maintenance Testing, Surveillance Testing, Performance Indicator Verification IR 05000315/20010192002-01-23023 January 2002 IR 05000315/2001-019(DRP), IR 05000316/2001-019(DRP), on 11/18-12/29/2001; Indiana Michigan Power Company, D.C. Cook Nuclear Power Plant, Units 1 and 2. Fire Protection, Radiological Environmental and Radioactive Material. Violations Noted 2023-04-27
[Table view] Category:Letter
MONTHYEAR05000316/LER-2024-004, AB Emergency Diesel Generator Inoperable for Longer than Allowed by Technical Specifications2024-11-11011 November 2024 AB Emergency Diesel Generator Inoperable for Longer than Allowed by Technical Specifications IR 05000315/20240032024-10-31031 October 2024 Integrated Inspection Report 05000315/2024003 05000316/2024003 07200072/2024001 and Exercise of Enforcement Discretion AEP-NRC-2024-77, U2C28 Steam Generator Tube Inspection Report2024-10-21021 October 2024 U2C28 Steam Generator Tube Inspection Report AEP-NRC-2024-80, Independent Spent Fuel Storage Installation Registration of Dry Spent Fuel Storage Cask2024-10-15015 October 2024 Independent Spent Fuel Storage Installation Registration of Dry Spent Fuel Storage Cask AEP-NRC-2024-79, Unit 2, Independent Spent Fuel Storage Installation - Registration of Dry Spent Storage Cask2024-09-26026 September 2024 Unit 2, Independent Spent Fuel Storage Installation - Registration of Dry Spent Storage Cask AEP-NRC-2024-78, Reply to a Notice of Violation: EA-24-0472024-09-23023 September 2024 Reply to a Notice of Violation: EA-24-047 05000316/LER-2024-002-01, Manual Reactor Trip Following Rapid Downpower for Steam Leak2024-09-12012 September 2024 Manual Reactor Trip Following Rapid Downpower for Steam Leak IR 05000315/20244022024-09-10010 September 2024 Security Baseline Inspection Report 05000315/2024402 and 05000316/2024402, Independent Spent Fuel Storage Installation Security Inspection Report 07200072/2024401 AEP-NRC-2024-69, Core Operating Limits Report2024-09-0909 September 2024 Core Operating Limits Report IR 05000315/20243012024-09-0505 September 2024 NRC Initial License Examination Report 05000315/2024301 and 05000316/2024301 ML24225A0022024-09-0303 September 2024 Issuance of Amendment Nos. 363 and 344 Revising Technical Specifications Section 3.8.1, AC Sources-Operating, for a One-Time Extension of a Completion Time IR 05000315/20240112024-08-30030 August 2024 NRC Inspection Report 05000315/2024011 and 05000316/2024011 and Notice of Violation AEP-NRC-2024-76, Unit 2 - Supplement to License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating2024-08-28028 August 2024 Unit 2 - Supplement to License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating AEP-NRC-2024-51, Annual Report of Loss-Of-Coolant Accident Evaluation Model Changes2024-08-28028 August 2024 Annual Report of Loss-Of-Coolant Accident Evaluation Model Changes 05000316/LER-2024-003, Plant Shutdown Required by Technical Specifications Due to Reactor Coolant System Identified Leakage2024-08-22022 August 2024 Plant Shutdown Required by Technical Specifications Due to Reactor Coolant System Identified Leakage IR 05000315/20240052024-08-21021 August 2024 Updated Inspection Plan for Donald C. Cook Nuclear Plant, Units 1 and 2 (Report 05000315/2024005 and 05000316/2024005) AEP-NRC-2024-61, Unit 2 - Response to Request for Additional Information for Neutron Flux Instrumentation License Amendment Request2024-08-15015 August 2024 Unit 2 - Response to Request for Additional Information for Neutron Flux Instrumentation License Amendment Request ML24221A2702024-08-0808 August 2024 Unit 2 Independent Spent Fuel Storage Installation - Registration of Dry Spent Fuel Storage Cask AEP-NRC-2024-62, Unit 2, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Cask2024-08-0707 August 2024 Unit 2, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Cask ML24256A1482024-08-0202 August 2024 2024 Post Examination Submittal Letter AEP-NRC-2024-47, Form OAR-1, Owners Activity Report2024-07-30030 July 2024 Form OAR-1, Owners Activity Report ML24169A2142024-07-25025 July 2024 Issuance of Amendment No. 362 Regarding Change to Technical Specification 3.4.12, Low Temperature Overpressure Protection System ML24183A0162024-07-25025 July 2024 Review of Reactor Vessel Material Surveillance Program Capsule W Technical Report IR 05000315/20240022024-07-24024 July 2024 Integrated Inspection Report 05000315/2024002 and 05000316/2024002 05000316/LER-2024-002, Manual Reactor Trip Following Rapid Downpower for Steam Leak2024-07-15015 July 2024 Manual Reactor Trip Following Rapid Downpower for Steam Leak ML24197A1262024-07-15015 July 2024 Unit 2 - Request for Additional Information (RAI) for License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating ML24191A0692024-07-0909 July 2024 Operator Licensing Examination Approval - Donald C. Cook Nuclear Power Plant, July 2024 AEP-NRC-2024-56, Unit 2, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Cask2024-07-0808 July 2024 Unit 2, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Cask AEP-NRC-2024-48, Response to Request for Additional Information (RAI) for License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating2024-07-0202 July 2024 Response to Request for Additional Information (RAI) for License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating ML24176A1012024-06-21021 June 2024 57143-EN 57143 - Paragon Energy Solutions - Update 1 (Final) - 10CFR Part 21 Final Notification: P21-05242024-FN, Rev. 0 AEP-NRC-2024-45, Report Per Technical Specification 5.6.6 for Inoperability of Post Accident Monitoring Neutron Flux Monitoring2024-06-13013 June 2024 Report Per Technical Specification 5.6.6 for Inoperability of Post Accident Monitoring Neutron Flux Monitoring ML24163A0132024-06-12012 June 2024 Request for Information for the NRC Age-Related Degradation Inspection: Inspection Report 05000315/2024012 and 05000316/2024012 ML24159A2522024-05-30030 May 2024 10 CFR 50.71(e) Update and Related Site Change Reports AEP-NRC-2024-23, Core Operating Limits Report2024-05-23023 May 2024 Core Operating Limits Report ML24141A2162024-05-20020 May 2024 —Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection 05000316/LER-2024-001, Reactor Trip Due to Main Turbine Trip from a High-High Thrust Bearing Position Trip2024-05-20020 May 2024 Reactor Trip Due to Main Turbine Trip from a High-High Thrust Bearing Position Trip AEP-NRC-2024-40, Unit 2 - Supplement to License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating2024-05-16016 May 2024 Unit 2 - Supplement to License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating AEP-NRC-2024-41, Annual Radiological Environmental Operating Report2024-05-15015 May 2024 Annual Radiological Environmental Operating Report AEP-NRC-2024-26, Transmittal of Donald C. Cook Nuclear Plant, Emergency Plan Revision 492024-05-14014 May 2024 Transmittal of Donald C. Cook Nuclear Plant, Emergency Plan Revision 49 AEP-NRC-2024-07, Unit 2 - Transmittal of Report of Changes to the Emergency Plan2024-05-14014 May 2024 Unit 2 - Transmittal of Report of Changes to the Emergency Plan IR 05000315/20240012024-05-14014 May 2024 Integrated Inspection Report 05000315/2024001 and 05000316/2024001 IR 05000315/20244012024-05-14014 May 2024 – Security Baseline Inspection Report 05000315/2024401 and 05000316/2024401 AEP-NRC-2024-24, Form OAR-1, Owners Activity Report2024-05-0707 May 2024 Form OAR-1, Owners Activity Report ML24115A2152024-05-0707 May 2024 LTR: CNP Non-Acceptance with Opportunity TS 3-8-1 ML24256A1472024-05-0606 May 2024 DC Cook 2024 NRC Examination Submittal Letter: Submittal ML24116A0002024-05-0202 May 2024 – Regulatory Audit in Support of Review of the Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors AEP-NRC-2024-35, Response to NRC Regulatory Issue Summary 2024-01 Preparation and Scheduling of Operator Licensing Examinations2024-04-30030 April 2024 Response to NRC Regulatory Issue Summary 2024-01 Preparation and Scheduling of Operator Licensing Examinations AEP-NRC-2024-28, 2023 Annual Radioactive Effluent Release Report2024-04-29029 April 2024 2023 Annual Radioactive Effluent Release Report AEP-NRC-2024-31, Annual Report of Individual Monitoring2024-04-24024 April 2024 Annual Report of Individual Monitoring AEP-NRC-2024-02, Unit 2 License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating2024-04-0303 April 2024 Unit 2 License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating 2024-09-09
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML24178A0432024-06-26026 June 2024 NRR E-mail Capture - Final RAI - D.C. Cook 1 & 2 - License Amendment Request Regarding Neutron Flux Instrumentation ML24156A0072024-05-30030 May 2024 NRR E-mail Capture - Final RAI - D.C. Cook Nuclear Plant, Unit Nos. 1 and 2 - License Amendment Request Regarding Reserve Feed Enclosure ML24141A2162024-05-20020 May 2024 —Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection ML23352A3502023-12-19019 December 2023 Dc. Cook Nuclear Power Plant, Units 1 Biennial Licensed Operator Requalification Program Inspection and Request for Information ML23310A1152023-11-0606 November 2023 Notification of the NRC Baseline Inspection and Request for Information, Inspection Report 05000316/2024002 ML22264A1112022-09-21021 September 2022 Notification of Post-Approval Site Inspection for License Renewal - Phase IV; IR 05000315/2023010; 05000316/2023010 and RFI ML22230A4362022-08-19019 August 2022 Licensed Operator Positive Fitness-For-Duty Test ML22049B4532022-02-22022 February 2022 Notification of NRC Baseline Inspection and Request for Information Report 05000315/2022002 ML21307A3352021-11-0303 November 2021 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 and 2 - Final RAI - License Amendment Request Regarding Containment Water Level Instrumentation ML21215A1242021-08-0303 August 2021 Information Request to Support Upcoming Temporary Instruction 2515/194 Inspection; Inspection Report 05000315/2021013; 05000316/2021013 ML21140A3052021-05-20020 May 2021 NRR E-mail Capture - Final RAI - D.C. Cook 1 & 2 - Relief Request ISIR-4-11, Impractical Examinations for the Fourth 10-Year ISI Interval ML21049A2682021-02-16016 February 2021 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit No. 2 - Final RAI - License Amendment Request for One-Time Extension Containment Type a ILRT ML21026A3472021-01-26026 January 2021 NRR E-mail Capture - Final RAI - D.C. Cook 1 & 2 - Relief Request REL-PP2 for Pump and Valve IST Fifth 10-year Interval IR 05000315/20200112020-09-17017 September 2020 Information Request to Support Upcoming Temporary Instruction 2515/194 Inspection; Inspection Report 05000315/2020011; 05000316/2020011 ML20181A4122020-06-29029 June 2020 NRR E-mail Capture - Final RAI - D.C. Cook 1 - One-Time Extension, Containment Type a ILRT Frequency ML20232B4562020-04-27027 April 2020 Request for Supporting Information for the D.C. Cook SPRA Audit Review - Fragility Questions IR 05000315/20200202020-04-10010 April 2020 Units 1 and 2 - Information Request for NRC Triennial Evaluation of Changes, Tests, and Experiments (50.59) Baseline Inspection 05000315/2020020 and 05000316/2020020 ML20232B4432020-03-25025 March 2020 Request for Supporting Information for the D.C. Cook SPRA Audit Review - Plant Response Model Questions ML19267A1362019-09-24024 September 2019 NRC Information Request (September 23, 2019) - IP 71111.08 - DC Cook U2 - Documents Selected for Onsite Review (DRS-M.Holmberg) ML19204A0962019-07-23023 July 2019 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 and 2 - Request for Additional Information Related to Unit 2 Leak Before Break Analysis and Deletion of Containment Humidity Monitors for Unit Nos. 1 and 2 ML19211C3032019-07-0303 July 2019 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 & 2 - Request for Additional Information Related to LAR to Address NSAL-15-1 ML19084A0002019-03-20020 March 2019 NRR E-mail Capture - Resubmitted: Draft Request for Additional Information DC Cook Unit 1 - Leak-Before-Break LAR ML19072A1432019-03-12012 March 2019 NRR E-mail Capture - Resubmitted: Draft Request for Additional Information DC Cook Unit 1 - Leak-Before-Break LAR ML19011A3512019-01-11011 January 2019 NRR E-mail Capture - Request for Additional Information DC Cook Unit 1 Leak Before Break Amendment ML18313A0802018-11-0808 November 2018 NRR E-mail Capture - D.C. Cook Units 1 and 2 - RAI for RPV Threads in Flange Alternative ML18263A1542018-09-14014 September 2018 NRR E-mail Capture - D.C. Cook Unit No. 1 - RAI for Leak-Before-Break LAR ML18204A3722018-07-19019 July 2018 NRR E-mail Capture - D.C. Cook Unit No. 1 - RAI for Leak-Before-Break LAR ML18143B6292018-05-29029 May 2018 Dtf. RAI ML18142B5312018-05-29029 May 2018 Request for Additional Information Concerning 2017 Decommissioning Funding Status Report ML18060A0212018-02-28028 February 2018 Enclosurequest for Additional Information (Request for Additional Information Regarding Indiana Michigan Power Company'S Decommissioning Funding Update for Donald C Cook Nuclear Plant Units 1 and 2 ISFSI) ML18043A0092018-02-0909 February 2018 NRR E-mail Capture - DC Cook, Unit 2 - Request for Additional Information Regarding Reactor Vessel Internals Again Management Program ML17304A0102017-11-0101 November 2017 Unit Nos.1 and 2 - Request for Additional Information Regarding Generic Letter 2016-01, Monitoring of Neutron-Absorbing Materials in Spent Fuel Pools (CAC Nos. MF9444 and MF9445; EPID L-2016-LRC-0001) ML17249A7492017-08-28028 August 2017 E-Mail Sent August 28, 2017, Request for Information for Donald C. Cook Nuclear Power Plant, Unit 1 (Part B); Inspection Report 05000315/2017004 (Msh) ML17108A7772017-04-18018 April 2017 17 Donald C. Cook Nuclear Power Plant, Unit 1 - Notification of NRC Baseline Inspection and Request for Information (05000315/2017003; 05000316/2017003) (Msh) ML17068A0652017-03-0808 March 2017 Ltr 03/08/17 Donald C. Cook Nuclear Power Plant, Unit 2 - Information Request for an NRC Post-Approval Site Inspection for License Renewal 05000316/2017009 (Bxj) ML17027A0192017-01-26026 January 2017 NRR E-mail Capture - D.C. Cook Units 1 and 2 - RAI Regarding LAR to Revise TS 5.5.14 (MF8483 and MF8484) ML16211A0152016-08-0101 August 2016 Follow-Up Request for Additional Information Regarding License Amendment Request to Relocate Surveillance Frequencies to Licensee Control IR 05000315/20160042016-07-11011 July 2016 Donald C. Cook Nuclear Power Plant, Unit 2 - Notification of NRC Inspection and Request for Information; Inspection Report 05000315/2016004; 05000316/2016004 ML16193A6542016-07-11011 July 2016 Notification of NRC Inspection and Request for Information; Inspection Report 05000315/2016004; 05000316/2016004 ML16154A1822016-06-0909 June 2016 Request for Additional Information Regarding License Amendment Request to Relocate Surveillance Frequencies to Licensee Control (CAC Nos. MF7114 and MF7115) ML16127A0792016-05-11011 May 2016 Request for Additional Information Regarding License Amendment Request to Relocate Surveillance Frequencies to Licensee Control ML16025A0552016-01-22022 January 2016 Ltr. 01/22/16 Donald C. Cook Nuclear Power Plant, Units 1 and 2 - Request for Information for an NRC Pilot Design Bases Inspection on the Implementation of the Environmental Qualification Program Inspection Report 05000315/2016008; 05000316 ML15267A6832015-10-0505 October 2015 Second Request for Additional Information Regarding License Amendment Request to Revise Technical Specification 3.8.1 ML15231A5542015-08-18018 August 2015 Ltr. 08/18/15 Donald C. Cook Nuclear Power Plant, Units 1 and 2 - Request for Information for an NRC Triennial Pilot Baseline Component Design Bases Inspection (Inspection Report 05000315/2015008; 05000316/2015008) (Axd) ML15225A5772015-08-13013 August 2015 Information Request to Support Upcoming Problem Identification and Resolution Inspection at D.C. Cook, Units 1 and 2 ML15163A1672015-06-15015 June 2015 Request for Additional Information Regarding License Amendment Request to Revise Technical Specification 3.8.1 ML15149A3832015-05-28028 May 2015 Information Request to Support NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection (Mxg) ML15119A3392015-05-0505 May 2015 Follow-up Request for Additional Information Concerning the Reactor Vessel Internals Aging Management Program Submittal ML15055A5702015-02-24024 February 2015 Cyber Security RFI Temporary Instruction 2201/004 ML15022A1532015-01-21021 January 2015 Dccook ISI Request for Information 2024-06-26
[Table view] |
See also: IR 05000315/2016008
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE RD. SUITE 210 LISLE, IL 60532-4352 January 22, 2016 Mr. Larry Weber Senior VP and Chief Nuclear Officer Indiana Michigan Power Company Nuclear Generation Group One Cook Place Bridgman, MI 49106 SUBJECT: DONALD. C. COOK NUCLEAR POWER PLANT, UNITS 1 AND 2 - REQUEST FOR INFORMATION FOR AN NRC PILOT DESIGN BASES INSPECTION ON THE IMPLEMENTATION OF THE ENVIRONMENTAL QUALIFICATION PROGRAM INSPECTION REPORT 05000315/2016008; 05000316/2016008 Dear Mr. Weber: On May 9, 2016, the U. S. Nuclear Regulatory Commission (NRC) will begin the pilot program portion of the triennial baseline Design Bases Inspection (DBI) at Donald C. Cook Nuclear Power Plant, Units 1 and 2. This inspection will be performed in accordance with NRC Baseline Inspection Procedure 71111.21N. The inspection will focus on the implementation of the Environmental Qualification (EQ) Program. The EQ components to be reviewed during this baseline inspection will be identified during the in-office preparation week that occurs prior to the first onsite inspection week. The inspection will include a bagman trip to support selection of components and one week of onsite inspection. The inspection team will consist of three NRC inspectors. The current inspection schedule is as follows: Bagman trip onsite week: March 29 - 30, 2016 Inspection onsite week: May 9 - 13, 2016 The team will be preparing for the inspection, mainly during the week of May 2 - 6, 2016, as discussed in the enclosure. Experience with previous baseline design inspections of similar depth and length has shown that this type of inspection is extremely resource intensive, both for the NRC inspectors and the licensee staff. In order to minimize the inspection impact on the site and to ensure a productive inspection for both parties, we have enclosed a request for information needed for the inspection.
L. Weber -2- It is important that all of these documents are up-to-date and complete in order to minimize the number of additional documents requested during the preparation and/or the onsite portions of the inspection. Insofar as possible, this information should be provided electronically to the lead inspector. The information request has been divided into four groups: The first group lists information necessary for our initial inspection scoping activities. This information should be provided to the lead inspector no later than March 1, 2016. By March 15, 2016, the lead inspector will communicate the initial selected set of approximately 12 EQ components. The second group of documents requested is those items needed to support the bagman trip. This set of documents should be available to the lead inspector onsite on March 29, 2016. The third group of documents requested is those items needed to support our in-office preparation activities for the selected set of 6 - 9 EQ components. This set of documents should be provided to the lead inspector at the Regional Office no later than April 27, 2016. During the in-office preparation activities, the team may identify additional information needed to support the inspection. The last group includes the additional information above as well as plant specific reference material. This information should be available to the team onsite on May 9, 2016. It is also requested that corrective action documents and/or questions developed during the inspection be provided to the lead inspector as the documents are generated. The lead inspector for this inspection is Mr. Andrew Dunlop. We understand that our licensing contact for this inspection is Mr. Rick Wynegar of your organization. If there are any questions about the inspection or the material requested in the enclosure, please contact the lead
inspector at (630) 829-9726, or via e-mail at Andrew.Dunlop@nrc.gov. This letter does not contain new or amended information collection requirements subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection requirements were approved by the Office of Management and Budget, Control Number 3150-0011. The NRC may not conduct or sponsor, and a person is not required to respond to, a request for information or an information collection requirement unless the requesting document displays a currently valid Office of Management and Budget Control Number. In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, "Public Inspections, Exemptions, Requests for Withholding," of the NRC's "Rules of Practice," a copy of this letter, its enclosure, and your response (if any) will be available electronically for public inspection in the NRC's Public Document Room or from the Publicly Available Records (PARS)
L. Weber -3- component of the NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). Sincerely, /RA/
Christine A. Lipa, Chief Engineering Branch 2 Division of Reactor Safety Docket Nos. 50-315; 50-316 License Nos. DPR-58; DPR-74 Enclosure: Request for Information - Design Bases Inspection cc: Distribution via LISTSERV
REQUEST FOR INFORMATION - DESIGN BASES INSPECTION Enclosure Inspection Report: 05000315/2016008; 05000316/2016008 Bagman Dates: March 29 - 30, 2016 Inspection Dates: May 9 - 13, 2016 Inspection Procedure: IP 71111.21N, "Design Bases Inspection" Lead Inspector: Andrew Dunlop, Senior Reactor Engineer, DRS (630) 829-9726 Andrew.Dunlop@nrc.gov I. Information Requested Prior to the Onsite Information Gathering/Bagman Week The following information is requested by March 1, 2016, or sooner, to facilitate inspection preparation. If you have any questions regarding this information, please call the team leader as soon as possible. (Please provide the information electronically in "pdf" files, Excel, or other searchable formats, preferably on some portable electronic media (e.g., CD-ROM, DVD, etc.). The portable electronic media should contain descriptive names, and be indexed and hyperlinked to facilitate ease of use. Information in "lists" should contain enough information to be easily understood by someone who has knowledge of light water reactor technology). 1. Risk-ranking of top 250 components from your site specific probabilistic safety analysis (PSA) sorted by Fussell Vesely Importance. 2. PSA listing of top ten risk-significant systems. 3. Electronic copies of Updated Final Safety Analysis Report, Technical
Specifications, and Technical Specifications Bases. Specifically identify which Updated Final Safety Analysis Report sections address environmental (including seismic) qualification (EQ). 4. NRC Safety Evaluation Report(s) associated with EQ. 5. Identify the various EQ standards (including year, edition, or revision) that the station is committed to. 6. Copy of EQ Design Basis Document, if applicable. 7. Copy of any licensing commitments related to EQ, if applicable. 8. Equipment Qualification Master List (EQML). Specific issues to be identified include: safety classification (safety-related or nonsafety-related), Regulatory Guide 1.97 instrumentation, EQ qualification (e.g. DOR, NUREG 588, 50.49), original or replaced after implementation of 50.49, and plant location.
REQUEST FOR INFORMATION - DESIGN BASES INSPECTION 2 9. List of any installed equipment removed from the EQML and basis for removal. 10. For units that have entered the period of extended operation, if EQ files were reviewed for Aging Management effects of license renewal, identify which EQ files were modified/changed to incorporate appropriate actions for the period of extended operation. Copies of any EQ Aging Management Programs. 11. List or drawings of plant areas that are subjected to EQ, identifying design (limiting) temperature, both normal and accident, high-energy line break, radiation levels, etc. that the associated equipment will have to be qualified to meet EQ. If unit has obtained a power uprate (greater than 5 percent) provide same information pre-update (earliest available if multiple uprates). 12. Site (and corporate if applicable) procedures associated with the 10 CFR 50.49 EQ Program for electrical components. Include procedures for procurement of qualified equipment, maintenance of qualified equipment, modification to
qualified equipment (including equivalency or commercial grade dedication (CGD) programs), and material storage and shelf life controls. 13. List of CGD evaluations performed, for which the dedicated parts have been issued for installation (parts issued for the last 10 years) on EQ applications in the plant. Include CGD evaluation number, name of part, component ID number or description of the component the part was issued to repair, work order, and date issued or installed. 14. List of Condition Reports (CRs) related to the EQ Program or EQ of components for the last 5 years. 15. Current management and engineering organizational chart. II. Information Requested (for the approximate 9 - 12 selected components) to be Available by the Bagman Trip on March 29, 2016. 1. EQ Summary Report for each component/subcomponent. 2. Qualification Maintenance Requirement Sheet (QMRS) or equivalent. 3. List of CRs (corrective action documents) associated with each of the selected
components for the last 5 years. 4. Photos of any component in containment or high-radiation areas, if available. III. Information Requested (for the approximate 6 - 9 selected components) to be Available by April 27, 2016, (will be reviewed by the team in the Regional office
during the week of May 2 - 6, 2016). This information should be separated for each selected component, especially if provided electronically (e.g., folder with component name that includes EQ files, Qualification Test Reports, calculations, CRs, maintenance history, etc.). 1. EQ file, including associated Qualification Test Reports. 2. Vendor manual (electronic copy or availability of hard copy during inspection).
REQUEST FOR INFORMATION - DESIGN BASES INSPECTION 3 3. Preventive maintenance template. 4. Last performed work order (WO) for each associated EQ preventive maintenance. 5. List of corrective maintenance WOs for the last 10 years. Include WO number, date performed, and brief one line description. 6. If repair work (e.g., a motor rewind) was performed under a purchase order, provide copy of the purchase order. 7. Thermal life calculation. 8. Any self-assessments of the EQ Program for the last 3 years. IV. Additional Information to be Provided on May 9, 2016, Onsite 1. During the in-office preparation activities, the team may identify additional information needed to support the inspection. The lead inspector will provide a list of the additional information needed during the week of May 2 - 6, 2016. V. Information Requested to be Provided Throughout the Inspection 1. Copies of any corrective action documents generated as a result of the team's questions or queries during this inspection. 2. Copies of the list of questions submitted by the team members and the status/resolution of the information requested (provide daily during the inspection to each team member). If you have questions regarding the information requested, please contact the lead inspector.
L. Weber -3- component of the NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). Sincerely, /RA/
Christine A. Lipa, Chief Engineering Branch 2 Division of Reactor Safety Docket Nos. 50-315; 50-316 License Nos. DPR-58; DPR-74 Enclosure: Request for Information - Design Bases Inspection cc: Distribution via LISTSERV DISTRIBUTION: Kimyata MorganButler RidsNrrDorlLpl3-1 Resource RidsNrrPMDCCook Resource RidsNrrDirsIrib Resource Cynthia Pederson
Darrell Roberts Richard Skokowski Allan Barker Carole Ariano Linda Linn
DRPIII DRSIII Jim Clay Carmen Olteanu ADAMS Accession Number ML16025A055 Publicly Available Non-Publicly Available Sensitive Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII RIII NAME CLipa for ADunlop:cl CLipa DATE 01/22/16 01/22/16 OFFICIAL RECORD COPY