Similar Documents at Cook |
---|
Category:Letter
MONTHYEARIR 05000315/20240032024-10-31031 October 2024 Integrated Inspection Report 05000315/2024003 05000316/2024003 07200072/2024001 and Exercise of Enforcement Discretion AEP-NRC-2024-77, U2C28 Steam Generator Tube Inspection Report2024-10-21021 October 2024 U2C28 Steam Generator Tube Inspection Report AEP-NRC-2024-80, Independent Spent Fuel Storage Installation Registration of Dry Spent Fuel Storage Cask2024-10-15015 October 2024 Independent Spent Fuel Storage Installation Registration of Dry Spent Fuel Storage Cask AEP-NRC-2024-79, Unit 2, Independent Spent Fuel Storage Installation - Registration of Dry Spent Storage Cask2024-09-26026 September 2024 Unit 2, Independent Spent Fuel Storage Installation - Registration of Dry Spent Storage Cask AEP-NRC-2024-78, Reply to a Notice of Violation: EA-24-0472024-09-23023 September 2024 Reply to a Notice of Violation: EA-24-047 05000316/LER-2024-002-01, Manual Reactor Trip Following Rapid Downpower for Steam Leak2024-09-12012 September 2024 Manual Reactor Trip Following Rapid Downpower for Steam Leak IR 05000315/20244022024-09-10010 September 2024 Security Baseline Inspection Report 05000315/2024402 and 05000316/2024402, Independent Spent Fuel Storage Installation Security Inspection Report 07200072/2024401 AEP-NRC-2024-69, Core Operating Limits Report2024-09-0909 September 2024 Core Operating Limits Report IR 05000315/20243012024-09-0505 September 2024 NRC Initial License Examination Report 05000315/2024301 and 05000316/2024301 ML24225A0022024-09-0303 September 2024 Issuance of Amendment Nos. 363 and 344 Revising Technical Specifications Section 3.8.1, AC Sources-Operating, for a One-Time Extension of a Completion Time IR 05000315/20240112024-08-30030 August 2024 NRC Inspection Report 05000315/2024011 and 05000316/2024011 and Notice of Violation AEP-NRC-2024-51, Annual Report of Loss-Of-Coolant Accident Evaluation Model Changes2024-08-28028 August 2024 Annual Report of Loss-Of-Coolant Accident Evaluation Model Changes AEP-NRC-2024-76, Unit 2 - Supplement to License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating2024-08-28028 August 2024 Unit 2 - Supplement to License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating 05000316/LER-2024-003, Plant Shutdown Required by Technical Specifications Due to Reactor Coolant System Identified Leakage2024-08-22022 August 2024 Plant Shutdown Required by Technical Specifications Due to Reactor Coolant System Identified Leakage IR 05000315/20240052024-08-21021 August 2024 Updated Inspection Plan for Donald C. Cook Nuclear Plant, Units 1 and 2 (Report 05000315/2024005 and 05000316/2024005) AEP-NRC-2024-61, Unit 2 - Response to Request for Additional Information for Neutron Flux Instrumentation License Amendment Request2024-08-15015 August 2024 Unit 2 - Response to Request for Additional Information for Neutron Flux Instrumentation License Amendment Request ML24221A2702024-08-0808 August 2024 Unit 2 Independent Spent Fuel Storage Installation - Registration of Dry Spent Fuel Storage Cask AEP-NRC-2024-62, Unit 2, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Cask2024-08-0707 August 2024 Unit 2, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Cask ML24256A1482024-08-0202 August 2024 2024 Post Examination Submittal Letter AEP-NRC-2024-47, Form OAR-1, Owners Activity Report2024-07-30030 July 2024 Form OAR-1, Owners Activity Report ML24169A2142024-07-25025 July 2024 Issuance of Amendment No. 362 Regarding Change to Technical Specification 3.4.12, Low Temperature Overpressure Protection System ML24183A0162024-07-25025 July 2024 Review of Reactor Vessel Material Surveillance Program Capsule W Technical Report IR 05000315/20240022024-07-24024 July 2024 Integrated Inspection Report 05000315/2024002 and 05000316/2024002 ML24197A1262024-07-15015 July 2024 Unit 2 - Request for Additional Information (RAI) for License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating 05000316/LER-2024-002, Manual Reactor Trip Following Rapid Downpower for Steam Leak2024-07-15015 July 2024 Manual Reactor Trip Following Rapid Downpower for Steam Leak ML24191A0692024-07-0909 July 2024 Operator Licensing Examination Approval - Donald C. Cook Nuclear Power Plant, July 2024 AEP-NRC-2024-56, Unit 2, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Cask2024-07-0808 July 2024 Unit 2, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Cask AEP-NRC-2024-48, Response to Request for Additional Information (RAI) for License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating2024-07-0202 July 2024 Response to Request for Additional Information (RAI) for License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating ML24176A1012024-06-21021 June 2024 57143-EN 57143 - Paragon Energy Solutions - Update 1 (Final) - 10CFR Part 21 Final Notification: P21-05242024-FN, Rev. 0 AEP-NRC-2024-45, Report Per Technical Specification 5.6.6 for Inoperability of Post Accident Monitoring Neutron Flux Monitoring2024-06-13013 June 2024 Report Per Technical Specification 5.6.6 for Inoperability of Post Accident Monitoring Neutron Flux Monitoring ML24163A0132024-06-12012 June 2024 Request for Information for the NRC Age-Related Degradation Inspection: Inspection Report 05000315/2024012 and 05000316/2024012 ML24159A2522024-05-30030 May 2024 10 CFR 50.71(e) Update and Related Site Change Reports AEP-NRC-2024-23, Core Operating Limits Report2024-05-23023 May 2024 Core Operating Limits Report ML24141A2162024-05-20020 May 2024 —Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection 05000316/LER-2024-001, Reactor Trip Due to Main Turbine Trip from a High-High Thrust Bearing Position Trip2024-05-20020 May 2024 Reactor Trip Due to Main Turbine Trip from a High-High Thrust Bearing Position Trip AEP-NRC-2024-40, Unit 2 - Supplement to License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating2024-05-16016 May 2024 Unit 2 - Supplement to License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating AEP-NRC-2024-41, Annual Radiological Environmental Operating Report2024-05-15015 May 2024 Annual Radiological Environmental Operating Report IR 05000315/20244012024-05-14014 May 2024 – Security Baseline Inspection Report 05000315/2024401 and 05000316/2024401 IR 05000315/20240012024-05-14014 May 2024 Integrated Inspection Report 05000315/2024001 and 05000316/2024001 AEP-NRC-2024-26, Transmittal of Donald C. Cook Nuclear Plant, Emergency Plan Revision 492024-05-14014 May 2024 Transmittal of Donald C. Cook Nuclear Plant, Emergency Plan Revision 49 AEP-NRC-2024-07, Unit 2 - Transmittal of Report of Changes to the Emergency Plan2024-05-14014 May 2024 Unit 2 - Transmittal of Report of Changes to the Emergency Plan AEP-NRC-2024-24, Form OAR-1, Owners Activity Report2024-05-0707 May 2024 Form OAR-1, Owners Activity Report ML24115A2152024-05-0707 May 2024 LTR: CNP Non-Acceptance with Opportunity TS 3-8-1 ML24256A1472024-05-0606 May 2024 DC Cook 2024 NRC Examination Submittal Letter: Submittal ML24116A0002024-05-0202 May 2024 – Regulatory Audit in Support of Review of the Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors AEP-NRC-2024-35, Response to NRC Regulatory Issue Summary 2024-01 Preparation and Scheduling of Operator Licensing Examinations2024-04-30030 April 2024 Response to NRC Regulatory Issue Summary 2024-01 Preparation and Scheduling of Operator Licensing Examinations AEP-NRC-2024-28, 2023 Annual Radioactive Effluent Release Report2024-04-29029 April 2024 2023 Annual Radioactive Effluent Release Report AEP-NRC-2024-31, Annual Report of Individual Monitoring2024-04-24024 April 2024 Annual Report of Individual Monitoring AEP-NRC-2024-02, Unit 2 License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating2024-04-0303 April 2024 Unit 2 License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating AEP-NRC-2024-29, (CNP) Unit 2 - Request for Relief Related to American Society of Mechanical Engineers (ASME) Code Case N-729-6 Supplemental Examination Requirements, ISIR-5-072024-04-0303 April 2024 (CNP) Unit 2 - Request for Relief Related to American Society of Mechanical Engineers (ASME) Code Case N-729-6 Supplemental Examination Requirements, ISIR-5-07 2024-09-09
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML24178A0432024-06-26026 June 2024 NRR E-mail Capture - Final RAI - D.C. Cook 1 & 2 - License Amendment Request Regarding Neutron Flux Instrumentation ML24156A0072024-05-30030 May 2024 NRR E-mail Capture - Final RAI - D.C. Cook Nuclear Plant, Unit Nos. 1 and 2 - License Amendment Request Regarding Reserve Feed Enclosure ML24141A2162024-05-20020 May 2024 —Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection ML23352A3502023-12-19019 December 2023 Dc. Cook Nuclear Power Plant, Units 1 Biennial Licensed Operator Requalification Program Inspection and Request for Information ML23310A1152023-11-0606 November 2023 Notification of the NRC Baseline Inspection and Request for Information, Inspection Report 05000316/2024002 ML22264A1112022-09-21021 September 2022 Notification of Post-Approval Site Inspection for License Renewal - Phase IV; IR 05000315/2023010; 05000316/2023010 and RFI ML22230A4362022-08-19019 August 2022 Licensed Operator Positive Fitness-For-Duty Test ML22049B4532022-02-22022 February 2022 Notification of NRC Baseline Inspection and Request for Information Report 05000315/2022002 ML21307A3352021-11-0303 November 2021 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 and 2 - Final RAI - License Amendment Request Regarding Containment Water Level Instrumentation ML21215A1242021-08-0303 August 2021 Information Request to Support Upcoming Temporary Instruction 2515/194 Inspection; Inspection Report 05000315/2021013; 05000316/2021013 ML21140A3052021-05-20020 May 2021 NRR E-mail Capture - Final RAI - D.C. Cook 1 & 2 - Relief Request ISIR-4-11, Impractical Examinations for the Fourth 10-Year ISI Interval ML21049A2682021-02-16016 February 2021 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit No. 2 - Final RAI - License Amendment Request for One-Time Extension Containment Type a ILRT ML21026A3472021-01-26026 January 2021 NRR E-mail Capture - Final RAI - D.C. Cook 1 & 2 - Relief Request REL-PP2 for Pump and Valve IST Fifth 10-year Interval IR 05000315/20200112020-09-17017 September 2020 Information Request to Support Upcoming Temporary Instruction 2515/194 Inspection; Inspection Report 05000315/2020011; 05000316/2020011 ML20181A4122020-06-29029 June 2020 NRR E-mail Capture - Final RAI - D.C. Cook 1 - One-Time Extension, Containment Type a ILRT Frequency ML20232B4562020-04-27027 April 2020 Request for Supporting Information for the D.C. Cook SPRA Audit Review - Fragility Questions IR 05000315/20200202020-04-10010 April 2020 Units 1 and 2 - Information Request for NRC Triennial Evaluation of Changes, Tests, and Experiments (50.59) Baseline Inspection 05000315/2020020 and 05000316/2020020 ML20232B4432020-03-25025 March 2020 Request for Supporting Information for the D.C. Cook SPRA Audit Review - Plant Response Model Questions ML19267A1362019-09-24024 September 2019 NRC Information Request (September 23, 2019) - IP 71111.08 - DC Cook U2 - Documents Selected for Onsite Review (DRS-M.Holmberg) ML19204A0962019-07-23023 July 2019 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 and 2 - Request for Additional Information Related to Unit 2 Leak Before Break Analysis and Deletion of Containment Humidity Monitors for Unit Nos. 1 and 2 ML19211C3032019-07-0303 July 2019 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 & 2 - Request for Additional Information Related to LAR to Address NSAL-15-1 ML19084A0002019-03-20020 March 2019 NRR E-mail Capture - Resubmitted: Draft Request for Additional Information DC Cook Unit 1 - Leak-Before-Break LAR ML19072A1432019-03-12012 March 2019 NRR E-mail Capture - Resubmitted: Draft Request for Additional Information DC Cook Unit 1 - Leak-Before-Break LAR ML19011A3512019-01-11011 January 2019 NRR E-mail Capture - Request for Additional Information DC Cook Unit 1 Leak Before Break Amendment ML18313A0802018-11-0808 November 2018 NRR E-mail Capture - D.C. Cook Units 1 and 2 - RAI for RPV Threads in Flange Alternative ML18263A1542018-09-14014 September 2018 NRR E-mail Capture - D.C. Cook Unit No. 1 - RAI for Leak-Before-Break LAR ML18204A3722018-07-19019 July 2018 NRR E-mail Capture - D.C. Cook Unit No. 1 - RAI for Leak-Before-Break LAR ML18143B6292018-05-29029 May 2018 Dtf. RAI ML18142B5312018-05-29029 May 2018 Request for Additional Information Concerning 2017 Decommissioning Funding Status Report ML18060A0212018-02-28028 February 2018 Enclosurequest for Additional Information (Request for Additional Information Regarding Indiana Michigan Power Company'S Decommissioning Funding Update for Donald C Cook Nuclear Plant Units 1 and 2 ISFSI) ML18043A0092018-02-0909 February 2018 NRR E-mail Capture - DC Cook, Unit 2 - Request for Additional Information Regarding Reactor Vessel Internals Again Management Program ML17304A0102017-11-0101 November 2017 Unit Nos.1 and 2 - Request for Additional Information Regarding Generic Letter 2016-01, Monitoring of Neutron-Absorbing Materials in Spent Fuel Pools (CAC Nos. MF9444 and MF9445; EPID L-2016-LRC-0001) ML17249A7492017-08-28028 August 2017 E-Mail Sent August 28, 2017, Request for Information for Donald C. Cook Nuclear Power Plant, Unit 1 (Part B); Inspection Report 05000315/2017004 (Msh) ML17108A7772017-04-18018 April 2017 17 Donald C. Cook Nuclear Power Plant, Unit 1 - Notification of NRC Baseline Inspection and Request for Information (05000315/2017003; 05000316/2017003) (Msh) ML17068A0652017-03-0808 March 2017 Ltr 03/08/17 Donald C. Cook Nuclear Power Plant, Unit 2 - Information Request for an NRC Post-Approval Site Inspection for License Renewal 05000316/2017009 (Bxj) ML17027A0192017-01-26026 January 2017 NRR E-mail Capture - D.C. Cook Units 1 and 2 - RAI Regarding LAR to Revise TS 5.5.14 (MF8483 and MF8484) ML16211A0152016-08-0101 August 2016 Follow-Up Request for Additional Information Regarding License Amendment Request to Relocate Surveillance Frequencies to Licensee Control IR 05000315/20160042016-07-11011 July 2016 Donald C. Cook Nuclear Power Plant, Unit 2 - Notification of NRC Inspection and Request for Information; Inspection Report 05000315/2016004; 05000316/2016004 ML16193A6542016-07-11011 July 2016 Notification of NRC Inspection and Request for Information; Inspection Report 05000315/2016004; 05000316/2016004 ML16154A1822016-06-0909 June 2016 Request for Additional Information Regarding License Amendment Request to Relocate Surveillance Frequencies to Licensee Control (CAC Nos. MF7114 and MF7115) ML16127A0792016-05-11011 May 2016 Request for Additional Information Regarding License Amendment Request to Relocate Surveillance Frequencies to Licensee Control ML16025A0552016-01-22022 January 2016 Ltr. 01/22/16 Donald C. Cook Nuclear Power Plant, Units 1 and 2 - Request for Information for an NRC Pilot Design Bases Inspection on the Implementation of the Environmental Qualification Program Inspection Report 05000315/2016008; 05000316 ML15267A6832015-10-0505 October 2015 Second Request for Additional Information Regarding License Amendment Request to Revise Technical Specification 3.8.1 ML15231A5542015-08-18018 August 2015 Ltr. 08/18/15 Donald C. Cook Nuclear Power Plant, Units 1 and 2 - Request for Information for an NRC Triennial Pilot Baseline Component Design Bases Inspection (Inspection Report 05000315/2015008; 05000316/2015008) (Axd) ML15225A5772015-08-13013 August 2015 Information Request to Support Upcoming Problem Identification and Resolution Inspection at D.C. Cook, Units 1 and 2 ML15163A1672015-06-15015 June 2015 Request for Additional Information Regarding License Amendment Request to Revise Technical Specification 3.8.1 ML15149A3832015-05-28028 May 2015 Information Request to Support NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection (Mxg) ML15119A3392015-05-0505 May 2015 Follow-up Request for Additional Information Concerning the Reactor Vessel Internals Aging Management Program Submittal ML15055A5702015-02-24024 February 2015 Cyber Security RFI Temporary Instruction 2201/004 ML15022A1532015-01-21021 January 2015 Dccook ISI Request for Information 2024-06-26
[Table view] |
Text
August 19, 2022 Kelly J. Ferneau Site Vice President Indiana Michigan Power Company Nuclear Generation Group One Cook Place Bridgman, MI 49106
SUBJECT:
DONALD C. COOK NUCLEAR PLANT LICENSED OPERATOR POSITIVE FITNESS-FOR-DUTY TEST
Dear Kelly Ferneau:
On August 16, 2022, your facility reported to the U.S. Nuclear Regulatory Commission (NRC) via Title 10 of the Code of Federal Regulations (CFR) 26.719 that an NRC-licensed operator tested positive following a fitness-for-duty test administered under 10 CFR 26.31(c) on August 16, 2022, (Event Report 56046). Although we have obtained preliminary information, this letter is a formal request for information pertaining to this occurrence. Within 30 days of the date of this letter, please provide responses to the questions listed in the enclosure. In addition, please provide other records and information on this operators fitness-for-duty that are relevant to this occurrence. If you are unable to meet this deadline, please notify us no later than 15 days from the date of this letter, with the reasons for the delay and a proposed date of submittal.
We request that any personal privacy, proprietary, or safeguards information in your response be contained in a separate enclosure and appropriately marked. The affidavit required by 10 CFR 2.390(b) must accompany your response, where applicable.
You should determine whether the operator meets the requirements of 10 CFR 55.33(a)(1).
You should ensure that: (1) the operator meets the general health requirements of ANSI/ANS-3.4-1983; (2) the operator does not have a disqualifying condition under Section 5.3 of that standard; and (3) documentation describing the designated physicians conclusion that the operator meets the requirements of ANSI/ANS-3.4-1983 is available for review by the NRC.
If a conditional license is requested per 10 CFR 55.25, that condition should be documented on NRC Form 396, Certification of Medical Examination by Facility Licensee, and sent to the U.S. Nuclear Regulatory Commission, ATTN: Regional Administrator, Region III Office, 2443 Warrenville Road, Suite 210, Lisle, IL 60532-4352.
If you determine that the operator no longer meets the medical qualifications described in 10 CFR 55.33(a)(1), then, in accordance with 10 CFR 55.25, you must notify the NRC, in writing, of the operators permanent incapacitation. For example, you must notify the NRC if you determine, based on your employee assistance program in consultation with your designated physician, that the operator can no longer meet the medical criteria of ANSI/ANS-3.4-1983.
K. Ferneau 2 The NRC will evaluate the information in your reply to this letter to determine if further action is warranted pursuant to 10 CFR Part 50 or Part 55. The information supplied will be maintained in NRC Privacy Systems of Records-16 and will be subject to the Privacy Act.
Please provide a copy of this letter, as well as your response to this letter, to the operator.
If you are unwilling to provide this information to the operator for any reason, the NRC will provide the information to the operator when it is available as part of the operators docket file.
If you have any questions concerning this matter, please contact Patricia J. Pelke, Chief, Operations Branch, 630-829-9868. The requested information should be sent to the attention of Patricia J. Pelke at the NRC Region III Office, 2443 Warrenville Road, Suite 210, Lisle, IL 60532-4352. Your cooperation is appreciated.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS). ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely, Signed by Atack, Sabrina on 08/19/22 Sabrina Atack, Acting Director Division of Reactor Safety Docket Nos. 50-315; 50-316 License Nos. DPR-58; DPR-74
Enclosure:
Fitness-for-Duty Request for Additional Information cc: Distribution w/encl via ListServ D. Emery, Training Manager
K. Ferneau 3 Letter to Kelly Ferneau from Sabrina Atack dated August 19, 2022.
SUBJECT:
DONALD C. COOK NUCLEAR PLANT LICENSED OPERATOR POSITIVE FITNESS-FOR-DUTY TEST Distribution w/encl:
John Giessner Mohammed Shuaibi Sabrina Atack Jamie Heisserer Jason Kozal Diana Betancourt-Roldan Kenneth Lambert Laura Kozak Lauren Nist Patricia Pelke Randal Baker Colleen Schmidt ADAMS Accession Number: ML22230A436 OFFICE RIII/DRS RIII/DRS RIII/DRP RIII/EICS RIII/DRS NAME RBaker:jw PPelke LKozak DBetancourt- SAtack Roldan DATE 08/18/22 08/18/22 08/18/22 08/19/22 08/19/22 OFFICIAL RECORD COPY
Fitness-for-Duty Request for Additional Information Donald C. Cook Nuclear Plant is requested to provide the following information concerning the fitness-for-duty occurrence (Title 10 of the Code of Federal Regulations (10 CFR) Part 26.719) reported on August 16, 2022, regarding the involved licensed operator:
- 1. Name, Docket Number, and responsibilities of the operator.
- 2. A summary of the operators entire fitness-for-duty testing history.
Please include the dates and times the operator was tested, the reasons for the tests (i.e., random, for-cause, or follow-up), the results of the tests, including quantification, and the dates that any tests were confirmed positive.
- 3. Whether the operator used, sold, or possessed illegal drugs. If so, please provide the details of the circumstances surrounding such use, sale, or possession.
OR Whether the operator consumed alcoholic beverages within the protected area. If so, please provide the details of the circumstances surrounding such consumption.
- 4. Whether the operator was at the controls or supervising licensed activities while under the influence of illegal drugs or alcohol. If so, please provide the details of the operators performance of licensed duties while under the influence.
- 5. Whether the operator fulfilled a position that was required to meet minimum licensed operating staffing requirements (fire brigade, emergency plan operations, etc.) while under the influence.
- 6. Whether the operator was involved in procedural errors related to this occurrence. If so, please provide the details of the procedural errors and the consequences of the errors.
- 7. The extent to which you reviewed the operators past work history, both on the day of the occurrence and prior to August 16, 2022.
- 8. Your intentions with regard to the operators resumption of duties under the 10 CFR Part 50 and Part 55 licenses, including your plans for follow-up testing.
Enclosure