Similar Documents at Cook |
---|
Category:Inspection Report Correspondence
MONTHYEARML23117A0062023-04-27027 April 2023 Review of the Spring 2022 Steam Generator Tube Inspections Report IR 05000315/20224022022-07-0505 July 2022 Material Control and Accounting Program Inspection Report 05000315/2022402 and 05000316/2022402 IR 05000315/20214032021-11-17017 November 2021 Security Baseline Inspection Report 05000315/2021403 and 05000316/2021403 IR 05000315/20214012021-10-21021 October 2021 Cyber Security Inspection Report 05000315/2021401 and 05000316/2021401 IR 05000315/20164072016-08-15015 August 2016 Cyber Security Problem and Identification Inspection Report 05000315/2016407; 05000316/2016407 - Cover Letter Only IR 05000315/20164052016-08-12012 August 2016 NRC Security Baseline Inspection Report 05000315/2016405; 05000316/2016405 (Cover Letter Only) IR 05000315/20160042016-07-11011 July 2016 Donald C. Cook Nuclear Power Plant, Unit 2 - Notification of NRC Inspection and Request for Information; Inspection Report 05000315/2016004; 05000316/2016004 ML16193A6542016-07-11011 July 2016 Notification of NRC Inspection and Request for Information; Inspection Report 05000315/2016004; 05000316/2016004 ML16025A0552016-01-22022 January 2016 Ltr. 01/22/16 Donald C. Cook Nuclear Power Plant, Units 1 and 2 - Request for Information for an NRC Pilot Design Bases Inspection on the Implementation of the Environmental Qualification Program Inspection Report 05000315/2016008; 05000316 IR 05000315/20085012009-02-13013 February 2009 IR 05000315-08-501, IR 05000316-08-501, on 12/31/2008, Donald C. Cook Nuclear Power Plant - NRC Emergency Preparedness Annual Inspection Report; NRC Security Annual Inspection Report IR 05000315-08-401, IR 05000316-08-401 ML0808703952008-03-26026 March 2008 IR 05000315-08-003 and 05000316-08-003, on 05/12/2008, D.C. Cook Nuclear Power Plant, TI-166 Request for Information NRC Inspection of Temporary Instruction 2515-166 IR 05000315/20074032007-07-20020 July 2007 IR 05000315-07-403, and IR 05000316-07-403, (Drs), on 06/11/2007 - 06/15/2007, D.C. Cook, Units 1 and 2, Routine Security Baseline Inspection - Cover Letter IR 05000315/20060072007-02-12012 February 2007 IR 05000315-06-007, IR 05000316-06-007, on 10/01/2006-12/31/2006, D. C. Cook Nuclear Power Plant, Units 1 and 2, Evaluation of Changes, Tests, or Experiments, Inservice Inspection Activities ML0210603072002-04-16016 April 2002 IR 05000315/2002-002(DRP), IR 05000316/2002-002(DRP), on 02/09-03/31/2002, Indiana Michigan Power Company, D.C. Cook Nuclear Power Plant, Units 1 and 2. Post Maintenance Testing, Surveillance Testing, Performance Indicator Verification IR 05000315/20010192002-01-23023 January 2002 IR 05000315/2001-019(DRP), IR 05000316/2001-019(DRP), on 11/18-12/29/2001; Indiana Michigan Power Company, D.C. Cook Nuclear Power Plant, Units 1 and 2. Fire Protection, Radiological Environmental and Radioactive Material. Violations Noted 2023-04-27
[Table view] Category:Letter
MONTHYEARIR 05000315/20240032024-10-31031 October 2024 Integrated Inspection Report 05000315/2024003 05000316/2024003 07200072/2024001 and Exercise of Enforcement Discretion AEP-NRC-2024-77, U2C28 Steam Generator Tube Inspection Report2024-10-21021 October 2024 U2C28 Steam Generator Tube Inspection Report AEP-NRC-2024-80, Independent Spent Fuel Storage Installation Registration of Dry Spent Fuel Storage Cask2024-10-15015 October 2024 Independent Spent Fuel Storage Installation Registration of Dry Spent Fuel Storage Cask AEP-NRC-2024-79, Unit 2, Independent Spent Fuel Storage Installation - Registration of Dry Spent Storage Cask2024-09-26026 September 2024 Unit 2, Independent Spent Fuel Storage Installation - Registration of Dry Spent Storage Cask AEP-NRC-2024-78, Reply to a Notice of Violation: EA-24-0472024-09-23023 September 2024 Reply to a Notice of Violation: EA-24-047 05000316/LER-2024-002-01, Manual Reactor Trip Following Rapid Downpower for Steam Leak2024-09-12012 September 2024 Manual Reactor Trip Following Rapid Downpower for Steam Leak IR 05000315/20244022024-09-10010 September 2024 Security Baseline Inspection Report 05000315/2024402 and 05000316/2024402, Independent Spent Fuel Storage Installation Security Inspection Report 07200072/2024401 AEP-NRC-2024-69, Core Operating Limits Report2024-09-0909 September 2024 Core Operating Limits Report IR 05000315/20243012024-09-0505 September 2024 NRC Initial License Examination Report 05000315/2024301 and 05000316/2024301 ML24225A0022024-09-0303 September 2024 Issuance of Amendment Nos. 363 and 344 Revising Technical Specifications Section 3.8.1, AC Sources-Operating, for a One-Time Extension of a Completion Time IR 05000315/20240112024-08-30030 August 2024 NRC Inspection Report 05000315/2024011 and 05000316/2024011 and Notice of Violation AEP-NRC-2024-76, Unit 2 - Supplement to License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating2024-08-28028 August 2024 Unit 2 - Supplement to License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating AEP-NRC-2024-51, Annual Report of Loss-Of-Coolant Accident Evaluation Model Changes2024-08-28028 August 2024 Annual Report of Loss-Of-Coolant Accident Evaluation Model Changes 05000316/LER-2024-003, Plant Shutdown Required by Technical Specifications Due to Reactor Coolant System Identified Leakage2024-08-22022 August 2024 Plant Shutdown Required by Technical Specifications Due to Reactor Coolant System Identified Leakage IR 05000315/20240052024-08-21021 August 2024 Updated Inspection Plan for Donald C. Cook Nuclear Plant, Units 1 and 2 (Report 05000315/2024005 and 05000316/2024005) AEP-NRC-2024-61, Unit 2 - Response to Request for Additional Information for Neutron Flux Instrumentation License Amendment Request2024-08-15015 August 2024 Unit 2 - Response to Request for Additional Information for Neutron Flux Instrumentation License Amendment Request ML24221A2702024-08-0808 August 2024 Unit 2 Independent Spent Fuel Storage Installation - Registration of Dry Spent Fuel Storage Cask AEP-NRC-2024-62, Unit 2, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Cask2024-08-0707 August 2024 Unit 2, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Cask ML24256A1482024-08-0202 August 2024 2024 Post Examination Submittal Letter AEP-NRC-2024-47, Form OAR-1, Owners Activity Report2024-07-30030 July 2024 Form OAR-1, Owners Activity Report ML24183A0162024-07-25025 July 2024 Review of Reactor Vessel Material Surveillance Program Capsule W Technical Report ML24169A2142024-07-25025 July 2024 Issuance of Amendment No. 362 Regarding Change to Technical Specification 3.4.12, Low Temperature Overpressure Protection System IR 05000315/20240022024-07-24024 July 2024 Integrated Inspection Report 05000315/2024002 and 05000316/2024002 05000316/LER-2024-002, Manual Reactor Trip Following Rapid Downpower for Steam Leak2024-07-15015 July 2024 Manual Reactor Trip Following Rapid Downpower for Steam Leak ML24197A1262024-07-15015 July 2024 Unit 2 - Request for Additional Information (RAI) for License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating ML24191A0692024-07-0909 July 2024 Operator Licensing Examination Approval - Donald C. Cook Nuclear Power Plant, July 2024 AEP-NRC-2024-56, Unit 2, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Cask2024-07-0808 July 2024 Unit 2, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Cask AEP-NRC-2024-48, Response to Request for Additional Information (RAI) for License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating2024-07-0202 July 2024 Response to Request for Additional Information (RAI) for License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating ML24176A1012024-06-21021 June 2024 57143-EN 57143 - Paragon Energy Solutions - Update 1 (Final) - 10CFR Part 21 Final Notification: P21-05242024-FN, Rev. 0 AEP-NRC-2024-45, Report Per Technical Specification 5.6.6 for Inoperability of Post Accident Monitoring Neutron Flux Monitoring2024-06-13013 June 2024 Report Per Technical Specification 5.6.6 for Inoperability of Post Accident Monitoring Neutron Flux Monitoring ML24163A0132024-06-12012 June 2024 Request for Information for the NRC Age-Related Degradation Inspection: Inspection Report 05000315/2024012 and 05000316/2024012 ML24159A2522024-05-30030 May 2024 10 CFR 50.71(e) Update and Related Site Change Reports AEP-NRC-2024-23, Core Operating Limits Report2024-05-23023 May 2024 Core Operating Limits Report ML24141A2162024-05-20020 May 2024 —Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection 05000316/LER-2024-001, Reactor Trip Due to Main Turbine Trip from a High-High Thrust Bearing Position Trip2024-05-20020 May 2024 Reactor Trip Due to Main Turbine Trip from a High-High Thrust Bearing Position Trip AEP-NRC-2024-40, Unit 2 - Supplement to License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating2024-05-16016 May 2024 Unit 2 - Supplement to License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating AEP-NRC-2024-41, Annual Radiological Environmental Operating Report2024-05-15015 May 2024 Annual Radiological Environmental Operating Report AEP-NRC-2024-26, Transmittal of Donald C. Cook Nuclear Plant, Emergency Plan Revision 492024-05-14014 May 2024 Transmittal of Donald C. Cook Nuclear Plant, Emergency Plan Revision 49 IR 05000315/20244012024-05-14014 May 2024 – Security Baseline Inspection Report 05000315/2024401 and 05000316/2024401 AEP-NRC-2024-07, Unit 2 - Transmittal of Report of Changes to the Emergency Plan2024-05-14014 May 2024 Unit 2 - Transmittal of Report of Changes to the Emergency Plan IR 05000315/20240012024-05-14014 May 2024 Integrated Inspection Report 05000315/2024001 and 05000316/2024001 ML24115A2152024-05-0707 May 2024 LTR: CNP Non-Acceptance with Opportunity TS 3-8-1 AEP-NRC-2024-24, Form OAR-1, Owners Activity Report2024-05-0707 May 2024 Form OAR-1, Owners Activity Report ML24256A1472024-05-0606 May 2024 DC Cook 2024 NRC Examination Submittal Letter: Submittal ML24116A0002024-05-0202 May 2024 – Regulatory Audit in Support of Review of the Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors AEP-NRC-2024-35, Response to NRC Regulatory Issue Summary 2024-01 Preparation and Scheduling of Operator Licensing Examinations2024-04-30030 April 2024 Response to NRC Regulatory Issue Summary 2024-01 Preparation and Scheduling of Operator Licensing Examinations AEP-NRC-2024-28, 2023 Annual Radioactive Effluent Release Report2024-04-29029 April 2024 2023 Annual Radioactive Effluent Release Report AEP-NRC-2024-31, Annual Report of Individual Monitoring2024-04-24024 April 2024 Annual Report of Individual Monitoring AEP-NRC-2024-29, (CNP) Unit 2 - Request for Relief Related to American Society of Mechanical Engineers (ASME) Code Case N-729-6 Supplemental Examination Requirements, ISIR-5-072024-04-0303 April 2024 (CNP) Unit 2 - Request for Relief Related to American Society of Mechanical Engineers (ASME) Code Case N-729-6 Supplemental Examination Requirements, ISIR-5-07 AEP-NRC-2024-02, Unit 2 License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating2024-04-0303 April 2024 Unit 2 License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating 2024-09-09
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML24178A0432024-06-26026 June 2024 NRR E-mail Capture - Final RAI - D.C. Cook 1 & 2 - License Amendment Request Regarding Neutron Flux Instrumentation ML24156A0072024-05-30030 May 2024 NRR E-mail Capture - Final RAI - D.C. Cook Nuclear Plant, Unit Nos. 1 and 2 - License Amendment Request Regarding Reserve Feed Enclosure ML24141A2162024-05-20020 May 2024 —Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection ML23352A3502023-12-19019 December 2023 Dc. Cook Nuclear Power Plant, Units 1 Biennial Licensed Operator Requalification Program Inspection and Request for Information ML23310A1152023-11-0606 November 2023 Notification of the NRC Baseline Inspection and Request for Information, Inspection Report 05000316/2024002 ML22264A1112022-09-21021 September 2022 Notification of Post-Approval Site Inspection for License Renewal - Phase IV; IR 05000315/2023010; 05000316/2023010 and RFI ML22230A4362022-08-19019 August 2022 Licensed Operator Positive Fitness-For-Duty Test ML22049B4532022-02-22022 February 2022 Notification of NRC Baseline Inspection and Request for Information Report 05000315/2022002 ML21307A3352021-11-0303 November 2021 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 and 2 - Final RAI - License Amendment Request Regarding Containment Water Level Instrumentation ML21215A1242021-08-0303 August 2021 Information Request to Support Upcoming Temporary Instruction 2515/194 Inspection; Inspection Report 05000315/2021013; 05000316/2021013 ML21140A3052021-05-20020 May 2021 NRR E-mail Capture - Final RAI - D.C. Cook 1 & 2 - Relief Request ISIR-4-11, Impractical Examinations for the Fourth 10-Year ISI Interval ML21049A2682021-02-16016 February 2021 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit No. 2 - Final RAI - License Amendment Request for One-Time Extension Containment Type a ILRT ML21026A3472021-01-26026 January 2021 NRR E-mail Capture - Final RAI - D.C. Cook 1 & 2 - Relief Request REL-PP2 for Pump and Valve IST Fifth 10-year Interval IR 05000315/20200112020-09-17017 September 2020 Information Request to Support Upcoming Temporary Instruction 2515/194 Inspection; Inspection Report 05000315/2020011; 05000316/2020011 ML20181A4122020-06-29029 June 2020 NRR E-mail Capture - Final RAI - D.C. Cook 1 - One-Time Extension, Containment Type a ILRT Frequency ML20232B4562020-04-27027 April 2020 Request for Supporting Information for the D.C. Cook SPRA Audit Review - Fragility Questions IR 05000315/20200202020-04-10010 April 2020 Units 1 and 2 - Information Request for NRC Triennial Evaluation of Changes, Tests, and Experiments (50.59) Baseline Inspection 05000315/2020020 and 05000316/2020020 ML20232B4432020-03-25025 March 2020 Request for Supporting Information for the D.C. Cook SPRA Audit Review - Plant Response Model Questions ML19267A1362019-09-24024 September 2019 NRC Information Request (September 23, 2019) - IP 71111.08 - DC Cook U2 - Documents Selected for Onsite Review (DRS-M.Holmberg) ML19204A0962019-07-23023 July 2019 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 and 2 - Request for Additional Information Related to Unit 2 Leak Before Break Analysis and Deletion of Containment Humidity Monitors for Unit Nos. 1 and 2 ML19211C3032019-07-0303 July 2019 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 & 2 - Request for Additional Information Related to LAR to Address NSAL-15-1 ML19084A0002019-03-20020 March 2019 NRR E-mail Capture - Resubmitted: Draft Request for Additional Information DC Cook Unit 1 - Leak-Before-Break LAR ML19072A1432019-03-12012 March 2019 NRR E-mail Capture - Resubmitted: Draft Request for Additional Information DC Cook Unit 1 - Leak-Before-Break LAR ML19011A3512019-01-11011 January 2019 NRR E-mail Capture - Request for Additional Information DC Cook Unit 1 Leak Before Break Amendment ML18313A0802018-11-0808 November 2018 NRR E-mail Capture - D.C. Cook Units 1 and 2 - RAI for RPV Threads in Flange Alternative ML18263A1542018-09-14014 September 2018 NRR E-mail Capture - D.C. Cook Unit No. 1 - RAI for Leak-Before-Break LAR ML18204A3722018-07-19019 July 2018 NRR E-mail Capture - D.C. Cook Unit No. 1 - RAI for Leak-Before-Break LAR ML18143B6292018-05-29029 May 2018 Dtf. RAI ML18142B5312018-05-29029 May 2018 Request for Additional Information Concerning 2017 Decommissioning Funding Status Report ML18060A0212018-02-28028 February 2018 Enclosurequest for Additional Information (Request for Additional Information Regarding Indiana Michigan Power Company'S Decommissioning Funding Update for Donald C Cook Nuclear Plant Units 1 and 2 ISFSI) ML18043A0092018-02-0909 February 2018 NRR E-mail Capture - DC Cook, Unit 2 - Request for Additional Information Regarding Reactor Vessel Internals Again Management Program ML17304A0102017-11-0101 November 2017 Unit Nos.1 and 2 - Request for Additional Information Regarding Generic Letter 2016-01, Monitoring of Neutron-Absorbing Materials in Spent Fuel Pools (CAC Nos. MF9444 and MF9445; EPID L-2016-LRC-0001) ML17249A7492017-08-28028 August 2017 E-Mail Sent August 28, 2017, Request for Information for Donald C. Cook Nuclear Power Plant, Unit 1 (Part B); Inspection Report 05000315/2017004 (Msh) ML17108A7772017-04-18018 April 2017 17 Donald C. Cook Nuclear Power Plant, Unit 1 - Notification of NRC Baseline Inspection and Request for Information (05000315/2017003; 05000316/2017003) (Msh) ML17068A0652017-03-0808 March 2017 Ltr 03/08/17 Donald C. Cook Nuclear Power Plant, Unit 2 - Information Request for an NRC Post-Approval Site Inspection for License Renewal 05000316/2017009 (Bxj) ML17027A0192017-01-26026 January 2017 NRR E-mail Capture - D.C. Cook Units 1 and 2 - RAI Regarding LAR to Revise TS 5.5.14 (MF8483 and MF8484) ML16211A0152016-08-0101 August 2016 Follow-Up Request for Additional Information Regarding License Amendment Request to Relocate Surveillance Frequencies to Licensee Control IR 05000315/20160042016-07-11011 July 2016 Donald C. Cook Nuclear Power Plant, Unit 2 - Notification of NRC Inspection and Request for Information; Inspection Report 05000315/2016004; 05000316/2016004 ML16193A6542016-07-11011 July 2016 Notification of NRC Inspection and Request for Information; Inspection Report 05000315/2016004; 05000316/2016004 ML16154A1822016-06-0909 June 2016 Request for Additional Information Regarding License Amendment Request to Relocate Surveillance Frequencies to Licensee Control (CAC Nos. MF7114 and MF7115) ML16127A0792016-05-11011 May 2016 Request for Additional Information Regarding License Amendment Request to Relocate Surveillance Frequencies to Licensee Control ML16025A0552016-01-22022 January 2016 Ltr. 01/22/16 Donald C. Cook Nuclear Power Plant, Units 1 and 2 - Request for Information for an NRC Pilot Design Bases Inspection on the Implementation of the Environmental Qualification Program Inspection Report 05000315/2016008; 05000316 ML15267A6832015-10-0505 October 2015 Second Request for Additional Information Regarding License Amendment Request to Revise Technical Specification 3.8.1 ML15231A5542015-08-18018 August 2015 Ltr. 08/18/15 Donald C. Cook Nuclear Power Plant, Units 1 and 2 - Request for Information for an NRC Triennial Pilot Baseline Component Design Bases Inspection (Inspection Report 05000315/2015008; 05000316/2015008) (Axd) ML15225A5772015-08-13013 August 2015 Information Request to Support Upcoming Problem Identification and Resolution Inspection at D.C. Cook, Units 1 and 2 ML15163A1672015-06-15015 June 2015 Request for Additional Information Regarding License Amendment Request to Revise Technical Specification 3.8.1 ML15149A3832015-05-28028 May 2015 Information Request to Support NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection (Mxg) ML15119A3392015-05-0505 May 2015 Follow-up Request for Additional Information Concerning the Reactor Vessel Internals Aging Management Program Submittal ML15055A5702015-02-24024 February 2015 Cyber Security RFI Temporary Instruction 2201/004 ML15022A1532015-01-21021 January 2015 Dccook ISI Request for Information 2024-06-26
[Table view] |
See also: IR 05000315/2016004
Text
UNITED STATES
NUCLEAR REGULATORY COMMISSION
REGION III
2443 WARRENVILLE RD. SUITE 210
LISLE, IL 60532-4352
July 11, 2016
Mr. Joel Gebbie
Senior VP and Chief Nuclear Officer
Indiana Michigan Power Company
Nuclear Generation Group
One Cook Place
Bridgman, MI 49106
SUBJECT: DONALD C. COOK NUCLEAR POWER PLANT, UNIT 2 - NOTIFICATION
OF NRC INSPECTION AND REQUEST FOR INFORMATION; INSPECTION
REPORT 05000315/2016004; 05000316/2016004
Dear Mr. Gebbie:
On October 11, 2016, the U. S. Nuclear Regulatory Commission (NRC) will begin the Baseline
Inservice Inspection Procedure 71111.08. This onsite inspection is scheduled to be performed
October 11, 2016, through November 10, 2016.
Experience has shown that this inspection is resource intensive both for the NRC inspector and
your staff. In order to minimize the impact to your onsite resources, and to ensure a productive
inspection for both sides, we have enclosed a request for documents needed for this inspection.
These documents have been divided into two groups.
The first group identifies information necessary to ensure that the inspector is adequately
prepared. The second group identifies the information the inspector will need upon arrival at
the site. It is important that all of these documents are up-to-date, and complete, in order to
minimize the number of additional documents requested during the preparation and/or the
onsite portions of the inspection.
We have discussed the schedule for inspection activities with your staff and understand that our
regulatory contact for this inspection will be Ms. K. Harper, of your organization. If there are any
questions about this inspection or the material requested, please contact the lead inspector
Mr. J. Neurauter at 630-829-9828, or via e-mail at James.Neurauter@nrc.gov.
This letter does not contain new or amended information collection requirements subject
to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information
collection requirements were approved by the Office of Management and Budget, Control
Number 3150-0011. The NRC may not conduct or sponsor, and a person is not required
to respond to, a request for information or an information collection requirement unless the
requesting document displays a currently valid Office of Management and Budget Control
Number.
J. Gebbie -2-
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, Public
Inspections, Exemptions, Requests for Withholding, of the NRC's "Rules of Practice," a copy
of this letter, its enclosure, and your response (if any) will be available electronically for public
inspection in the NRCs Public Document Room or from the Publicly Available Records (PARS)
component of the NRC's Agencywide Documents Access and Management System (ADAMS).
ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html
(the Public Electronic Reading Room).
Sincerely,
/RA/
James E. Neurauter, Senior Reactor Inspector
Engineering Branch 1
Division of Reactor Safety
Docket Nos. 50-315; 50-316
License Nos. DPR-58; DPR-74
Enclosure:
Baseline Inservice Inspection Document Request
cc: Distribution via LISTSERV
BASELINE INSERVICE INSPECTION DOCUMENT REQUEST
Inspection Report: 05000315/2016004; 05000316/2016004
Inspection Dates: October 11, 2016, through November 10, 2016
Inspection Procedures: IP 71111-08, Inservice Inspection
Lead Inspector: James Neurauter, DRS
630-829-9828
James.Neurauter@nrc.gov
I. Information for the In-Office Preparation Week
The following information is requested as an (electronic copy CD ROM if possible) by
September 26, 2016, to facilitate the selection of specific items that will be reviewed
during the onsite inspection week. The inspector will select specific items from the
information requested below and a list of additional documents needed onsite from your
staff. We request that the specific items selected from the lists be available and ready
for review on the first day of inspection. The following information is applicable to Unit 2
unless otherwise indicated. If you have any questions regarding this information, please
call the inspector as soon as possible.
1. For the upcoming outage, a detailed schedule and description of:
a. Non-Destructive Examinations (NDEs) planned for Class 1 and 2 Systems
and containment, performed as part of your American Society of Mechanical
Engineers (ASME) Code Inservice Inspection (ISI) Program (include edition
and addenda of Code committed to), and NDEs planned for other systems
performed as part of a Risk-Informed ISI Program, or other augmented
inspection programs (e.g., ASME Code Case N-770-1 examination of dissimilar
metal welds and examinations to meet an industry initiative). For each weld
examination, include the weld identification number, description of weld
(component name), category, class, type of exam and procedure number,
and date of examination;
b. Reactor vessel upper head examinations required by Title 10 of the Code of
Federal Regulations (CFR), Part 50.55a(g)(6)(ii)(D) and Code Case N-729-1;
c. Steam generator (SG) tube inspection and repair activities for the upcoming
outage or SG secondary side examinations1;
d. Welding on Code Class 1, 2, or 3 components; and
e. Baffle-former bolt examinations performed in accordance with the D.C. Cook
Nuclear Plant, Units 1 and 2, Reactor Vessel Internals Aging Management
Program.
1
Note 1- If no SG examinations are planned for this outage, please confirm when the next SG examination will occur
and no further information is required for the items identified above requesting SG related information.
Enclosure
BASELINE INSERVICE INSPECTION DOCUMENT REQUEST
2. A copy of the NDE procedures and welding procedures used to perform the activities
identified in Item A.1 (including NDE calibration and flaw characterization/sizing
procedures and Welding Procedure Qualification Records). For ultrasonic
examination procedures qualified in accordance with Appendix VIII, of Section XI
of the ASME Code, provide documentation supporting the procedure qualification
(e.g., the [Electric Power Research Institute] EPRI performance demonstration
qualification summary sheets).
3. A copy of ASME Section XI, Code Relief Requests applicable to the examinations
identified in Item A.1. This would include the U.S. Nuclear Regulatory Commission
(NRC)-approved Relief Request for implementing a Risk-Informed ISI Program
(if applicable).
4. A copy of the 10-year ISI Program showing those required exams scheduled to be
performed this outage, and those which have been completed.
5. A list identifying NDE reports (ultrasonic, radiography, magnetic particle, or dye
penetrant), which have identified relevant indications on Code Class 1 and 2
Systems since the beginning of the last refueling outage.
6. List with short description of the welds in Code Class 1 and 2 Systems, which have
been fabricated due to component repair/replacement activities since the beginning
of the last refueling outage and identify the system, weld number, and reference
applicable documentation (e.g., NIS-2 forms with definitions of system and
component acronyms).
7. If reactor vessel weld examinations required by the ASME Code are scheduled to
occur during the inspection period, provide a detailed description of the welds to be
examined, and the extent of the planned examination.
8. List with description of ISI and SG-related issues such as piping or SG tube
degradation or damage (e.g., cracks, wall thinning, wear, microbiologically induced
corrosion) or errors identified during piping/SG tube examinations that have been
entered into your corrective action system since the beginning of the last refueling
outage. Also, include a list of corrective action records associated with foreign
material introduced/identified in the reactor vessel, primary coolant system, SG
or feed systems since the beginning of the last refueling outage.
9. Copy of any Title 10 CFR Part 21 reports applicable to your structures systems
or components within the scope of Section XI of the ASME Code that have been
identified since the beginning of the last refueling outage.
10. Copy of SG history documentation given to vendors performing eddy current (ET)
testing of the SGs during the upcoming outage1.
11. Copy of procedure containing screening criteria used for selecting tubes for in-situ
pressure testing and the procedure to be used for in-situ pressure testing1.
1 Note 1- If no SG examinations are planned for this outage, please confirm when the next SG examination will occur
and no further information is required for the items identified above requesting SG related information.
2
BASELINE INSERVICE INSPECTION DOCUMENT REQUEST
12. Copy of previous outage SG tube operational assessment completed following ET
of the SGs1.
13. Copy of the document defining the planned SG ET scope (e.g., 100 percent of
unrepaired tubes with bobbin probe and 20 percent sample of hot leg expansion
transition regions with rotating probe) and identify the scope expansion criteria,
which will be applied. Also identify and describe any deviations in this scope or
expansion criteria from the EPRI Guidelines1.
14. Copy of the document describing the ET acquisition equipment to be applied
including ET probe types. Also identify the extent of planned tube examination
coverage with each probe type (e.g., rotating probe - 0.080 inches, 0.115 inches
pancake coils, and mid-range + point coil applied at the top-of-tube-sheet plus
3 inches to minus 12 inches) 1.
15. Provide procedures with guidance/instructions for identifying (e.g., physically locating
the tubes that require repair) and plugging SG tubes1.
16. Identify and quantify any SG tube leakage experienced during the previous operating
cycle. Also provide documentation identifying which SG was leaking and corrective
actions completed or planned for this condition.
17. Copy of current calculations for EDY, and RIY as defined in Code Case N-729-1 that
establish the volumetric and visual examination frequency for the reactor vessel
head and J-groove welds.
18. Point of contact information (name and site number) for the following activities:
a. ISI - Site and vendor leads
b. Boric Acid Inspections and Evaluations
c. Reactor Vessel Head Inspection - Site and vendor leads
d. SG Inspection - Site and vendor leads
e. Baffle-former bolt examinations - Site and vendor leads
II. Onsite Information to be Provided to the Inspector on the First Day of the
Inspection (e.g., Following the Entrance Meeting). Please Provide Hard Copies
(e.g., Paper Records) of the Following Documents.
1. For welds selected by the inspector from Item A.1.d and A.6 above, provide copies
of the following documents:
a. Document of the weld number and location (e.g., system, train, branch);
b. Document with a detail of the weld construction (e.g., drawing);
1 Note 1- If no SG examinations are planned for this outage, please confirm when the next SG examination will occur
and no further information is required for the items identified above requesting SG related information.
3
BASELINE INSERVICE INSPECTION DOCUMENT REQUEST
c. Applicable Code Edition and Addenda for construction of the weldment
(e.g., B31.1 or ASME Section III);
d. Applicable Code Edition and Addenda for weld procedure (WP) qualification;
e. Applicable WPs and weld data sheets used to fabricate the welds;
f. Copies of procedure qualification records supporting the WPs;
g. Copies of welders performance qualification records;
h. Copies of mechanical test reports identified in the procedure qualification
records above;
i. Copies of the non-conformance reports for the selected welds;
j. Access to radiographs and equipment to view radiographs of the selected
welds; and
k. Copies of the pre-service examination records for the selected welds.
2. For the ISI-related corrective action issues selected by the inspector from Item A.8
above, provide a copy of the corrective actions and supporting documentation.
3. For the NDE reports with relevant indications on Code Class 1 and 2 Systems
selected by the inspector from Item A.5 above, provide a copy of the examination
records and associated corrective action documents. Updated schedules for
Item A.1 (including schedule showing contingency repair plans if available).
4. Copy of the procedures which govern the scope, equipment used, and
implementation of the inspections required to identify boric acid leakage from
systems and components above the vessel head.
5. Copy of:
a. Engineering evaluations/assessments of boric acid related deposits and
associated wastage or corrosion for safety significant components; and
b. Corrective action records for coolant leakage including boric acid deposits on
safety-related components identified since the beginning of the last refueling
outage.
6. Copy of the plant procedures used to perform inspections to identify reactor coolant
system leaks or boric acid deposits and the procedures for resolution of leaks or
boric acid deposits.
7. Fabrication Drawings (D size) of the reactor vessel welds (including vessel head
J-groove welds) if any are to be examined during the outage. Also provide any
drawings used by NDE vendors to locate these welds.
8. Copy of the documents which demonstrate that the procedures to be used for
volumetric examination of the reactor vessel head penetration J-groove welds were
qualified by a blind demonstration test in accordance with 10 CFR 50.55a(g)(6)(ii)(D).
4
BASELINE INSERVICE INSPECTION DOCUMENT REQUEST
9. Copy of volumetric, surface and visual examination records for the prior inspection of
the reactor vessel head and head penetration J-groove welds.
10. Provide a copy of the EPRI Examination Technique Specification Sheets and vendor
documents, which support qualification of the ET probes to be used during the
upcoming SG tube inspections1.
11. Provide a copy of the guidance to be followed if a loose part or foreign material is
identified in the SGs1.
12. Identify the types of SG tube repair processes which will be implemented for
defective SG tubes (including any NRC reviews/evaluation/approval of this repair
process). Provide the flaw depth sizing criteria to be applied for ET indications
identified in the SG tubes1.
13. Copy of document describing actions to be taken if a new SG tube degradation
mechanism is identified1.
14. Provide document which defines the scope of SG secondary side examinations
(if any are planned) and identify site specific operational history related to
degradation of SG secondary side components (if any).
15. Provide procedures with guidance/instructions for identifying (e.g., physically locating
the tubes that require repair) and plugging SG tubes1.
16. Provide procedures for baffle-former bolt NDE performed in accordance with
the D.C. Cook Nuclear Plant, Units 1 and 2, Reactor Vessel Internals Aging
Management Program including associated vendor procedures and ultrasonic and
visual examination qualification documents for the vendor procedures.
17. Provide degraded/missing baffle bolt/repair/replacement plans; vendor documents
that establish acceptance criteria for minimum acceptable baffle bolt patterns; and
drawings associated with reactor internal areas to be inspected during the outage.
18. Provide a copy of Unit 1 records related to degraded or missing baffle bolts including
site acceptance criteria used to allow continued operation with the identified
degraded or missing fasteners.
19. Provide copies of the following standards at the onsite NRC inspection location for
the duration of the inspection:
a. Sections V, IX, and XI of the ASME Code with Editions applicable to the
ISI Program and the Repair/Replacement Program;
b. Copy of the performance demonstration initiative (PDI) generic procedures
with the latest applicable revisions that support site qualified ultrasonic
examination of piping welds and components (e.g., PDI-UT-1, PDI-UT-2,
PDI-UT-3, PDI-UT-10 etc.);
1 Note 1- If no SG examinations are planned for this outage, please confirm when the next SG examination will occur
and no further information is required for the items identified above requesting SG related information.
5
BASELINE INSERVICE INSPECTION DOCUMENT REQUEST
c. EPRI and industry standards referenced in the site procedures used to
perform the SG tube ET examination, which includes EPRI documents:
TR-107621-R1, Steam Generator Integrity Assessment Guidelines,
TR-107620-R1, Steam Generator In-Situ Pressure Test Guidelines,
SG Management Program: Steam Generator Integrity Assessment Guidelines,
Part 10, and 1003138, Pressurized Water Reactor Steam Generator
Examination Guidelines1;
d. EPRI and industry standards referenced in the site procedures used to perform
baffle-former bolt ultrasonic and visual examination, which includes: MRP-227-A,
Pressurized Water Reactor Internals Inspection and Evaluation Guidelines,
MRP-228, Materials Reliability Program: Inspection Standard for PWR
Internals, and WCAP-17096, Reactor Internals Acceptance Criteria
Methodology and Data Requirements; and
e. Boric Acid Corrosion Guidebook Revision 1 - EPRI Technical Report 1000975.
20. Provide training (e.g., Scaffolding, Fall Protection, foreign material exclusion)
if required to access the NDEs selected by the inspector for observation.
If you have questions regarding the information requested, please contact the lead inspector.
6
J. Gebbie -2-
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, Public
Inspections, Exemptions, Requests for Withholding, of the NRC's "Rules of Practice," a copy
of this letter, its enclosure, and your response (if any) will be available electronically for public
inspection in the NRCs Public Document Room or from the Publicly Available Records (PARS)
component of the NRC's Agencywide Documents Access and Management System (ADAMS).
ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html
(the Public Electronic Reading Room).
Sincerely,
/RA/
James E. Neurauter, Senior Reactor Inspector
Engineering Branch 1
Division of Reactor Safety
Docket Nos. 50-315; 50-316
License Nos. DPR-58; DPR-74
Enclosure:
Baseline Inservice Inspection Document Request
cc: Distribution via LISTSERV
DISTRIBUTION:
Jeremy Bowen
RidsNrrDorlLpl3-1 Resource
RidsNrrPMDCCook Resource
RidsNrrDirsIrib Resource
Cynthia Pederson
Darrell Roberts
Richard Skokowski
Allan Barker
Carole Ariano
Linda Linn
DRPIII
DRSIII
ADAMS Accession Number ML16193A654
Publicly Available Non-Publicly Available Sensitive Non-Sensitive
To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy
OFFICE RIII RIII RIII RIII
NAME JNeurauter:
DATE 07/11/16
OFFICIAL RECORD COPY